Placing device for RH dip pipe ring bricks

By designing a placement device for RH impregnated pipe ring bricks, including booms and support mechanisms, the problem of difficulty in placement of ring bricks is solved, and the rapid and stable placement of ring bricks is achieved, reducing labor intensity and improving work efficiency .

CN222498325UActive Publication Date: 2025-02-18LUOYANG LIER REFRACTORY MATERIAL
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202421225406.5
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-31
Publication Date
2025-02-18
Estimated Expiration
2034-05-31

AI Technical Summary

Technical Problem

During the casting and forming process of RH impregnated pipes, it is difficult to place the ring bricks, and the commonly used outer clamping tools are difficult to put into the steel barrel, resulting in unstable entanglement of the rope and easy to slip. It is time-consuming and labor-intensive to untie the ring bricks, affecting work efficiency.

Method used

A placement device for RH impregnated tube ring bricks is designed, including a boom and a support mechanism, which consists of a support block, a first electric push rod, a fixing block and a pallet, and the pallet is controlled by the first electric push rod. The telescopic support the bottom of the ring brick and provides friction through the guide wheel to ensure stable placement of the ring brick.

Benefits of technology

By supporting the bottom of the ring brick and using the combination of electric push rods and guide wheels, the device achieves rapid and stable placement of the ring bricks, reduces the labor intensity of workers, improves work efficiency, and avoids the ring bricks being affected during the placement process risk of loss.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222498325U_ABST
    Figure CN222498325U_ABST
Patent Text Reader

Abstract

The utility model discloses a placing device for RH dip pipe ring bricks, which comprises a hanging rod, a hanging ring is arranged at the upper end of the hanging rod, at least two supporting mechanisms for supporting the bottoms of the ring bricks are arranged at the lower end of the hanging rod, and each supporting mechanism comprises a supporting block, a first electric push rod, a first fixing block, a second fixing block and a supporting plate. The supporting block is fixed to the lower end of the outer side face of the hanging rod, a cavity is formed in the supporting block, the supporting plate is located in the supporting block and can transversely move in the supporting block, a strip-shaped hole is formed in the upper end of the supporting block, the second fixing block is fixed to one end of the upper surface of the supporting plate, and the second fixing block penetrates through the strip-shaped hole. The first fixing block is arranged on the upper surface of the supporting block, the first electric push rod is arranged between the first fixing block and the second fixing block, and the placing device for the RH dip pipe ring bricks can conveniently place the ring bricks, reduce the labor intensity of workers and improve the working efficiency.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of RH impregnated pipe production, in particular to a placement device for RH impregnated pipe ring bricks. Background Art

[0002] RH refining furnace is a smelting equipment in the hot processing industry. It is mostly used for final deoxidation and alloying of molten steel in ferrous metallurgy. It has a wide application market in the metallurgical field. The immersion tube is an important component of the RH refining furnace. The RH immersion tube is composed of ring bricks, self-flowing materials, steel bladder and castable materials from the inside to the outside.

[0003] During casting, the ring bricks that have been ground and bonded need to be placed inside the steel bladder. Since the distance between the ring bricks and the steel bladder is between 20 and 30 mm, it is difficult to put the ring bricks into the steel bladder after the commonly used outer clamping tools clamp the outer side of the ring bricks. Therefore, the ring bricks are fixed and placed in the steel bladder by a crane and a rope. However, the rope is wrapped around the outside of the steel bladder, which is not only easy to slip off, but also very troublesome to untie after the ring bricks are placed. It is time-consuming and labor-intensive, affecting work efficiency. Summary of the invention

[0004] The technical problem to be solved by the utility model is to overcome the existing defects and provide a placement device for RH immersion pipe ring bricks, which can facilitate the placement of ring bricks, reduce the labor intensity of workers, improve work efficiency, and effectively solve the problems in the background technology.

[0005] To achieve the above objectives, the utility model provides the following technical solutions: a placement device for RH impregnation tube ring bricks, comprising a hanger, a hanger ring is provided at the upper end of the hanger, and at least two support mechanisms for supporting the bottom of the ring bricks are provided at the lower end of the hanger.

[0006] As a preferred technical solution of the utility model, the support mechanism includes a support block, a first electric push rod, a first fixed block, a second fixed block and a support plate, the support block is fixed to the lower end of the outer side surface of the suspension rod, the interior of the support block is a cavity, the support plate is located in the support block and can move laterally in the support block, a strip hole is provided at the upper end of the support block, the second fixed block is fixed to one end of the upper surface of the support plate, the second fixed block passes through the strip hole, the first fixed block is provided on the upper surface of the support block, and the first electric push rod is provided between the first fixed block and the second fixed block.

[0007] As a preferred technical solution of the utility model, the number of the supporting mechanisms is four, and the four supporting mechanisms are evenly distributed on the outer side surface of the lower end of the suspension rod.

[0008] As a preferred technical solution of the utility model, a guiding mechanism is symmetrically arranged on the outer side surface of the suspension rod, and the guiding mechanism is located above the supporting mechanism. The guiding mechanism includes a second electric push rod, a U-shaped frame and a guide wheel. The second electric push rod is fixed to the outer side surface of the suspension rod, and the U-shaped frame is connected to the telescopic end of the second electric push rod. The guide wheel is located in the U-shaped frame, and the two end surfaces of the guide wheel are rotatably connected to the U-shaped frame through a pin shaft.

[0009] As a preferred technical solution of the present utility model, the contact surface between the fixed end of the second electric push rod and the suspension rod is a plane.

[0010] As a preferred technical solution of the utility model, the outer side surface of the guide wheel is covered with rubber.

[0011] Compared with the prior art, the beneficial effects of the utility model are as follows: the placement device for RH impregnation tube ring bricks is reasonably designed and ingeniously conceived. A supporting mechanism is arranged at the lower end of the suspension rod, and the bottom of the ring brick is supported by a support plate when the ring brick is placed. When the ring brick is about to contact the mold base, the support plate is retracted by the first electric push rod. At this time, the ring brick falls on the mold base, and the ring brick is placed in the steel sleeve, which saves time and effort and greatly improves work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 It is a schematic diagram of the structure of the utility model;

[0013] Figure 2 This is the front view of the utility model;

[0014] Figure 3 It is a top view of the utility model.

[0015] In the figure: 1 suspension rod, 2 suspension ring, 3 support mechanism, 31 support block, 32 first fixed block, 33 first electric push rod, 34 strip hole, 35 second fixed block, 36 support plate, 4 guide mechanism, 41 second electric push rod, 42 U-shaped frame, 43 guide wheel, 44 plane. DETAILED DESCRIPTION

[0016] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments (for the convenience of description and understanding, the following is a schematic diagram of the present invention). Figure 2 Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work belong to the scope of protection of the present invention.

[0017] See also Figure 1-3The utility model provides a technical solution: a device for placing RH impregnation tube ring bricks, comprising a suspension rod 1, a suspension ring 2 is arranged at the upper end of the suspension rod 1, the suspension ring 2 is connected to a hook on a crane, a support mechanism 3 for supporting the bottom of the ring brick is arranged at the lower end of the suspension rod 1, the support mechanism 3 comprises a support block 31, a first electric push rod 33, a first fixed block 32, a second fixed block 35 and a support plate 36, the support block 31 is fixed to the lower end of the outer side surface of the suspension rod 1, the interior of the support block 31 is a cavity, the support plate 36 is located in the support block 31 and can move laterally in the support block 31 A strip hole 34 is provided at the upper end of the support block 31, and the second fixing block 35 is fixed to one end of the upper surface of the support plate 36. The second fixing block 35 passes through the strip hole 34. The first fixing block 32 is provided on the upper surface of the support block 31. The first electric push rod 33 is provided between the first fixing block 32 and the second fixing block 35. The telescopic end of the first electric push rod 33 is connected to the second fixing block 35. The extension and retraction of the support plate 36 are controlled by the first electric push rod 33 to realize the support and detachment of the ring brick, which is convenient for workers to operate. The support plate 36 does not exceed 10mm outside the ring brick.

[0018] In order to improve the support stability of the ring bricks, the number of the support mechanisms 3 is four, and the four support mechanisms 3 are evenly distributed on the outer side surface of the lower end of the suspension rod 1.

[0019] Furthermore, in order to facilitate the detachment of the support plate 36 and to prevent the ring bricks from suddenly falling and causing certain damage after the support plate 36 detaches from the support for the ring bricks, four guiding mechanisms 4 are symmetrically arranged on the outer side of the suspension rod 1. The four guiding mechanisms 4 are arranged in two layers, each layer has two guiding mechanisms 4 and are symmetrically arranged on the outer side of the suspension rod 1. The guiding mechanisms 4 are located above the supporting mechanism 3. The guiding mechanisms 4 include a second electric push rod 41, a U-shaped frame 42 and a guide wheel 43. The second electric push rod 41 is fixed to the outer side of the suspension rod 1, and the U-shaped frame 42 is connected to the telescopic end of the second electric push rod 41. The guide wheel 43 is located in the U-shaped frame 42, and the two end surfaces of the guide wheel 43 are rotatably connected to the U-shaped frame 42 through a pin shaft. Before the support plate 36 is retracted, the guide wheel 43 is controlled by the second electric push rod 41 to extend and contact the inner wall of the ring brick and provide appropriate pressure. After the support plate 36 is retracted, it slowly slides down under the gravity of the ring brick itself.

[0020] The input ends of the first electric push rod 33 and the second electric push rod 41 are both electrically connected to the output end of the external control switch.

[0021] In order to facilitate the installation of the second electric push rod 41 , the contact surface between the fixed end of the second electric push rod 41 and the suspension rod 1 is a plane 44 .

[0022] In order to increase the friction between the guide wheel 43 and the inner wall of the ring brick so that the ring brick can fall slowly, the outer side surface of the guide wheel 43 is covered with rubber.

[0023] When in use: it is connected to the lifting ring 1 through the crane hook, the lifting rod 2 is located in the ring brick, and the supporting mechanism 3 is located below the ring brick. At this time, the first electric push rod 33 is started, and the support plate 36 is extended. At this time, the support plate 36 is located directly below the lower end surface of the ring brick. The crane raises the lifting rod 1, and the four support plates 36 hold up the ring brick. Then the crane moves to the top of the steel sleeve and lowers the ring brick into the steel sleeve. When the support block 31 is about to contact the mold base, the second electric push rod 41 is started to make the guide wheel 43 extend and contact the inner wall of the ring brick to provide a certain friction force. Then the first electric push rod 33 is retracted to retract the support plate 36. Under the action of gravity, the ring brick slowly falls along the guide wheel 43 to the mold base, completing the placement process of the ring brick.

[0024] The utility model can quickly place the ring bricks into the steel sleeve, reduce the labor intensity of workers and improve work efficiency; by arranging the guide wheel 43, it is convenient to buffer the ring bricks when they fall, avoid damage to the ring bricks, and improve the convenience of use.

[0025] Although the embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to the embodiments without departing from the principles and spirit of the present invention, and that the scope of the present invention is defined by the appended claims and their equivalents.

Claims

1. A device for placing RH impregnated pipe ring bricks, comprising a suspension rod (1), wherein the upper end of the suspension rod (1) is provided with a suspension ring (2), characterized in that: The lower end of the suspension rod (1) is provided with at least two supporting mechanisms (3) for supporting the bottom of the ring brick.

2. A device for placing RH impregnated pipe ring bricks according to claim 1, characterized in that: The support mechanism (3) comprises a support block (31), a first electric push rod (33), a first fixed block (32), a second fixed block (35) and a support plate (36); the support block (31) is fixed to the lower end of the outer side surface of the suspension rod (1); the interior of the support block (31) is a cavity; the support plate (36) is located in the support block (31) and can move laterally in the support block (31); a strip hole (34) is provided at the upper end of the support block (31); the second fixed block (35) is fixed to one end of the upper surface of the support plate (36); the second fixed block (35) passes through the strip hole (34); the first fixed block (32) is arranged on the upper surface of the support block (31); and the first electric push rod (33) is arranged between the first fixed block (32) and the second fixed block (35).

3. The device for placing RH impregnated pipe ring bricks according to claim 1, characterized in that: The number of the supporting mechanisms (3) is four, and the four supporting mechanisms (3) are evenly distributed on the outer side surface of the lower end of the suspension rod (1).

4. The device for placing RH impregnated pipe ring bricks according to claim 1, characterized in that: The outer side surface of the suspension rod (1) is symmetrically provided with a guide mechanism (4), and the guide mechanism (4) is located above the support mechanism (3). The guide mechanism (4) includes a second electric push rod (41), a U-shaped frame (42) and a guide wheel (43). The second electric push rod (41) is fixed to the outer side surface of the suspension rod (1), and the U-shaped frame (42) is connected to the telescopic end of the second electric push rod (41). The guide wheel (43) is located in the U-shaped frame (42), and the two end surfaces of the guide wheel (43) are rotatably connected to the U-shaped frame (42) through a pin shaft.

5. A device for placing RH impregnated pipe ring bricks according to claim 4, characterized in that: The contact surface between the fixed end of the second electric push rod (41) and the suspension rod (1) is a plane (44).

6. A device for placing RH impregnated pipe ring bricks according to claim 4, characterized in that: The outer side surface of the guide wheel (43) is covered with rubber.