Installation structure of operation and maintenance channel on color steel tile with trapezoidal skeleton line
By designing the installation structure of the operation and maintenance channel on the color steel tile and using the method of fixing the support beams and clamps on the bone line, the problem of staff trampling and damaging the solar panels during disassembly and assembly and maintenance is solved, and the stability and load-bearing capacity are improved.
Patent Information
- Application Number
- CN202420526377.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-03-18
- Publication Date
- 2025-03-14
- Estimated Expiration
- 2034-03-18
AI Technical Summary
On the color steel tiles laid on large areas of solar panels, staff are prone to trampling and damaging the solar panels during disassembly and assembly and repair, and the stability and load-bearing capacity of the prior art are insufficient when installing operation and maintenance channels.
An installation structure for the operation and maintenance channel is designed on the color steel tiles of the trapezoidal bone line. Through a plurality of support beams and clamps arranged side by side and spaced apart, the support beam is fixedly connected to the bone lines of the color steel tiles through the clamps. A through groove and hollow hole are provided on the upper side of the operation and maintenance channel for drainage.
The installation operation and maintenance channel is realized on color steel tile, which is convenient for disassembly and assembly and maintenance of solar panels, avoiding trampling and damage. At the same time, the installation stability and reliability are improved by utilizing the stiffness and load-bearing capacity of the bone line.
Smart Images

Figure CN222614708U_ABST
Abstract
Description
Technical Field
[0001] The utility model belongs to the technical field of installing an operation and maintenance channel on a color steel tile, in particular to an installation structure of an operation and maintenance channel on a color steel tile with a trapezoidal skeleton. Background Art
[0002] When building factories on a large scale, people prefer to use color steel plates to reduce costs. In order to save energy, solar panels are laid on the color steel roofs, that is, on color steel tiles. Due to the large laying area of solar panels, it is easy for workers to step on them and cause damage to other solar panels during maintenance, disassembly and replacement of solar panels. Utility Model Content
[0003] In view of this, the utility model aims to overcome the shortcomings of the above-mentioned problems in the prior art and proposes an installation structure of an operation and maintenance channel on the colored steel tiles of the trapezoidal skeleton.
[0004] In order to achieve the above object, the technical solution of the utility model is implemented as follows:
[0005] A mounting structure for an operation and maintenance channel on a color steel tile of a trapezoidal skeleton line, comprising a plurality of support beams arranged side by side and at intervals, the operation and maintenance channel being fixedly connected to the upper sides of the plurality of support beams, and clamping members being fixedly connected to both ends of the bottom of each support beam, the clamping member comprising a lap joint and an inverted L-shaped supporting member located on the upper side of the lap joint, the lap joint being lap-fixed on the corresponding skeleton line on the upper side of the color steel tile, and the two ends of the support beam being fixedly connected to the upper sides of the corresponding supporting members.
[0006] Furthermore, two clamping pieces at the bottom of each support beam are overlapped and fixed on the same bone line.
[0007] Furthermore, the cross-section of the bone wire is a trapezoidal structure, the lower end of the overlapping part is opened, and the shape and size are consistent with the shape and size of the cross-section of the bone wire, and it is fixed together with the corresponding bone wire through multiple first drill screws on the overlapping horizontal section on the upper side of the overlapping part, the supporting part is fixed at the middle or edge of the overlapping horizontal section, and the supporting beam is fixed together with the supporting horizontal section on the upper side of the supporting part through the second drill screw.
[0008] Furthermore, the overlapping portion and the supporting portion are an integrally formed structure.
[0009] Furthermore, each support beam is fixedly connected to the operation and maintenance channel through a plurality of third drill tail screws.
[0010] Furthermore, a plurality of through grooves are provided on the upper side of the operation and maintenance channel along the width direction, and a plurality of hollow holes are provided in each through groove.
[0011] Compared with the prior art, the utility model has the following advantages:
[0012] The installation structure of the operation and maintenance channel on the color steel tile of the trapezoidal skeleton line described in the utility model installs the operation and maintenance channel on the color steel tile, which is convenient for disassembly, assembly and maintenance of the solar panels installed on the color steel tile without stepping on the solar panels to avoid damage to the solar panels. In addition, since the support beam for installing the operation and maintenance channel is fixed to the skeleton line on the color steel tile by a clamp, that is to say, when the staff walks on the operation and maintenance channel, the skeleton line is the main stress point. It is more reliable to utilize the stiffness and bearing capacity of the skeleton line than directly stepping on the color steel tile to bear the stress. BRIEF DESCRIPTION OF THE DRAWINGS
[0013] The accompanying drawings constituting a part of the present invention are used to provide a further understanding of the present invention. The illustrative embodiments of the present invention and their descriptions are used to explain the present invention and do not constitute an improper limitation on the present invention. In the accompanying drawings:
[0014] Figure 1 This is a schematic diagram of the installation structure of the operation and maintenance channel described in an embodiment of the utility model on the colored steel tile of the trapezoidal skeleton;
[0015] Figure 2 This is a schematic diagram of the structure of the clamping member and the support beam installed on the color steel tile according to the embodiment of the utility model;
[0016] Figure 3 This is a schematic diagram of the structure of the clamping member according to an embodiment of the utility model;
[0017] Figure 4 This is another structural schematic diagram of the clamping member described in an embodiment of the utility model.
[0018] Description of reference numerals:
[0019] 1. Color steel tile; 11. Skeleton line; 2. Clamp; 21. Overlap part; 211. Overlap horizontal section; 22. Support part; 221. Support horizontal section; 3. Support beam; 4. Operation and maintenance channel; 41. Through groove; 42. Hollow hole; 5. First drill thread; 6. Second drill thread; 7. Third drill thread. DETAILED DESCRIPTION
[0020] It should be noted that, in the absence of conflict, the embodiments of the present invention and the features in the embodiments can be combined with each other.
[0021] In the description of the present utility model, it should be understood that the terms "center", "longitudinal", "lateral", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside" and the like indicate positions or positional relationships based on the positions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present utility model and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as a limitation on the present utility model. In addition, the terms "first", "second", etc. are only used for descriptive purposes, and cannot be understood as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Therefore, features defined as "first", "second", etc. may explicitly or implicitly include one or more of the features. In the description of the present utility model, unless otherwise specified, "multiple" means two or more.
[0022] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installation", "connection" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be an indirect connection through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood by specific circumstances.
[0023] The present invention will be described in detail below with reference to the accompanying drawings and in combination with embodiments.
[0024] As shown in the figure, an installation structure of an operation and maintenance channel on a color steel tile with a trapezoidal skeleton line includes a plurality of support beams 3 arranged side by side and at intervals, an operation and maintenance channel 4 is fixedly connected to the upper side of the plurality of support beams 3, and a clamping member 2 is fixedly connected at both ends of the bottom of each support beam 3, the clamping member 2 includes a lap portion 21 and an inverted L-shaped support portion 22 located on the upper side of the lap portion 21, the lap portion 21 is lap-fixed on the corresponding skeleton line 11 on the upper side of the color steel tile 1, and the two ends of the support beam 3 are fixedly connected to the upper side of the corresponding support portion 22. In this embodiment, the operation and maintenance channel 4 is installed on the color steel tile 1, which is convenient for disassembly, assembly and maintenance of the solar panel installed on the color steel tile 1, without stepping on the solar panel to avoid damage to the solar panel, and because the support beam 3 on which the operation and maintenance channel 4 is installed is fixed to the bone wire 11 on the color steel tile 1 through the clamp 2, that is, when the staff walks on the operation and maintenance channel 4, the bone wire 11 is the main force-bearing point, and the use of the rigidity and bearing capacity of the bone wire 11 is more reliable than directly stepping on the color steel tile 1. And if the operation and maintenance channel 4 is directly fixed on the color steel tile 1 by laying the drill tail wire, since the color steel tile 1 and the operation and maintenance channel 4 are both thin, it will cause unstable installation and poor bearing capacity. Therefore, the operation and maintenance channel is supported and fixed by the support beam 3 with greater rigidity, which can effectively improve the reliability of the operation and maintenance channel 4.
[0025] The two clamps 2 at the bottom of each support beam 3 are overlapped and fixed on the same bone line 11, ensuring that the support beam 3 is parallel to the bone line 11. On the one hand, it is convenient for installation and the installation is regular, which is suitable for installing operation and maintenance channels 4 of different widths and convenient for adjusting the distance between the two clamps 2. On the other hand, it also effectively utilizes the stiffness and bearing capacity of the bone line 11 to ensure the stability of the operation and maintenance channel 4 installed on the color steel tile 1.
[0026] The cross section of the bone wire 11 is a trapezoidal structure, the lower end of the overlap portion 21 is open, and the shape and size are consistent with the cross section shape and size of the bone wire 11, and the overlap horizontal section 211 on the upper side of the overlap portion 21 is fixedly connected to the corresponding bone wire 11 through a plurality of first drill screws 5, the support portion 22 is fixedly connected to the middle or edge of the overlap horizontal section 211, and the support beam 3 is fixedly connected to the support horizontal section 221 on the upper side of the support portion 22 through the second drill screw 6. In this embodiment, the clamp 2 is fixedly connected to the bone wire 11 by two drill screws.
[0027] The overlapping portion 21 and the supporting portion 22 are an integrally formed structure, which enhances the overall strength of the clamping member 2 .
[0028] Each support beam 3 is fixedly connected to the operation and maintenance channel 4 via a plurality of third drill threads 7 , so that the operation and maintenance channel 4 is fixedly connected to the plurality of support beams 3 .
[0029] A plurality of through grooves 41 are provided along the width direction on the upper side of the operation and maintenance channel 4, and a plurality of hollow holes 42 are provided in each through groove 41 for drainage. In this embodiment, the hollow holes 42 correspond to the positions between two adjacent skeleton lines 11, avoiding being directly provided at the corresponding positions of the skeleton lines 11, that is, provided at the support beam 3, which cannot effectively drain water.
[0030] The working process of this embodiment is as follows:
[0031] The operation and maintenance channel 4 is laid on the color steel tile 1 on which the solar panel is laid through the clamping piece 2 and the support beam 3, so as to facilitate the disassembly and maintenance of the solar panel installed on the color steel tile 1, without stepping on the solar panel to avoid damaging the solar panel. During installation, the clamping piece 2 is first fixed to the corresponding bone line 11 through the first drill thread 5, and then the two ends of the support beam 3 are fixed to the corresponding two clamping pieces 2 through the second drill thread 6, and finally the operation and maintenance channel 4 is laid on the upper side of multiple support beams 3, and fixed to the support beam 3 through the third drill thread 7.
[0032] The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention should be included in the protection scope of the present invention.
Claims
1. An installation structure of an operation and maintenance channel on a colored steel tile of a trapezoidal skeleton, characterized in that: It includes multiple support beams arranged side by side and at intervals, and an operation and maintenance channel is fixedly connected to the upper side of the multiple support beams. Clamps are fixedly connected at both ends of the bottom of each support beam. The clamps include a lap joint and an inverted L-shaped support portion located on the upper side of the lap joint. The lap joint is lap-fixed on the corresponding bone line on the upper side of the color steel tile, and both ends of the support beam are fixedly connected to the upper side of the corresponding support portion.
2. The installation structure of the operation and maintenance channel on the colored steel tile of the trapezoidal skeleton according to claim 1 is characterized by: The two clamping pieces at the bottom of each supporting beam are overlapped and fixed on the same bone line.
3. The installation structure of the operation and maintenance channel on the colored steel tile of the trapezoidal skeleton according to claim 1 is characterized by: The cross-section of the bone wire is a trapezoidal structure, and the lower end of the overlapping part is open, and the shape and size are consistent with the shape and size of the cross-section of the bone wire. It is fixed together with the corresponding bone wire through multiple first drill screws on the overlapping horizontal section on the upper side of the overlapping part, and the support part is fixed at the middle or edge of the overlapping horizontal section. The support beam is fixed together with the supporting horizontal section on the upper side of the support part through the second drill screw.
4. The installation structure of the operation and maintenance channel on the colored steel tile of the trapezoidal skeleton according to claim 3 is characterized by: The overlapping part and the supporting part are an integrally formed structure.
5. The installation structure of the operation and maintenance channel on the colored steel tile of the trapezoidal skeleton according to claim 1 is characterized by: Each support beam is fixedly connected to the operation and maintenance channel through a plurality of third drill tail screws.
6. The installation structure of the operation and maintenance channel on the colored steel tile of the trapezoidal skeleton according to claim 1 is characterized by: A plurality of through slots are provided along the width direction on the upper side of the operation and maintenance channel, and a plurality of hollow holes are provided in each through slot.