Combined square hoop for hoisting prefabricated pier column of bridge

CN224740650UActive Publication Date: 2026-09-11NANJING FORESTRY UNIV
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202521982148.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-15
Publication Date
2026-09-11
Estimated Expiration
2035-09-15

AI Technical Summary

Technical Problem

已有试验结果表明,当埋深不足0.8m时,在约40t的荷载下便可能产生裂缝破坏;随着埋深增加至1.0m和1.2m,承载力有所提高,分别可达46t和51t,但总体安全储备依然不足

Benefits of technology

[0011]本实用新型通过上述结构设计实现了以下有益效果:采用L形抱箍板拼装方式,保证了装置的安装简便性和适应性,能够根据不同截面尺寸的墩柱进行定制;通过牛腿面板、加强肋板、垫块与竖向连接钢筋的多点连接设计,使得受力更加均匀,避免局部失稳;竖向钢筋与底部工字钢托架的端板连接方式,确保了竖向荷载传递的可靠性;整体装置为组合式结构,可方便拆卸与重复利用,显著降低了施工成本,提高了桥梁施工的效率与安全水平。

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224740650U_ABST
    Figure CN224740650U_ABST
Patent Text Reader

Abstract

The utility model relates to a combined square hoop for hoisting bridge prefabricated pier column, which comprises L-shaped hoop plates, bracket vertical plates, bracket face plates, reinforcing rib plates, cushion blocks, vertical connecting steel bars, end plates, I-beam brackets, high-strength bolts and lifting lugs that can be assembled and connected. The bracket face plates comprise second bracket face plates and bottom bracket face plates that are respectively welded to the upper and lower ends of the bracket vertical plates. The device adopts four L-shaped hoop plates, the bottom bracket face plates are connected with the vertical steel bars through the cushion blocks, the end plates are welded to the lower ends of the vertical connecting steel bars, the end plates are connected with the bottom I-beam brackets through the high-strength bolts, and independent lifting lugs are arranged on the second bracket face plates for hoisting. Through the above structure, the utility model provides reliable structural safety and anti-sliding stability in the hoisting operation of the bridge pier column, and the construction process is simple and easy to operate.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model relates to the field of bridge construction technology, specifically to the field of bridge structure reinforcement and construction auxiliary equipment, and is a clamp-type hoisting device suitable for precast bridge piers. Background Technology

[0002] In the existing construction of precast bridge piers, the commonly used lifting point methods mainly include pre-embedded steel bar lifting rings, pre-embedded steel strand lifting rings, reserved lifting holes, and pre-embedded lifting lugs. While these methods can meet the lifting requirements to a certain extent, they all have varying degrees of safety hazards and limitations. For example, pre-embedded steel bar lifting rings and pre-embedded steel strand lifting rings need to be embedded together with the pier concrete pouring, which is complex to construct. Furthermore, during the lifting process, the stress is concentrated in a localized area of ​​concrete, which can easily lead to cracking or spalling problems, especially when lifting large-tonnage piers.

[0003] Existing research, engineering experience, and standards indicate that the load-bearing capacity of steel strand lifting rings is significantly affected by the burial depth and working conditions. During conventional vertical lifting, to ensure safety, the working stress of the steel strand is typically controlled within a reasonable range of the material's design strength, generally not exceeding approximately 350 MPa. However, in more complex stress conditions such as flipping operations, this control value needs to be further reduced, usually not exceeding 280 MPa, and the number of such flipping operations should not be excessive, typically limited to three times or less. On the other hand, the burial depth of the lifting ring also directly affects its ultimate bearing capacity. Existing test results show that when the burial depth is less than 0.8 m, cracking failure may occur under a load of approximately 40 t. As the burial depth increases to 1.0 m and 1.2 m, the bearing capacity improves, reaching 46 t and 51 t respectively, but the overall safety reserve remains insufficient. Therefore, traditional steel strand lifting rings have low bearing capacity, limited reliability, and restricted operating conditions when lifting large-tonnage bridge piers, making it difficult to meet engineering requirements.

[0004] Furthermore, both pre-drilled lifting holes and pre-embedded lifting lugs have limitations. The former requires repair of the holes after lifting, affecting the overall durability and appearance quality of the component; the latter can obstruct the local reinforcement arrangement and may cause fatigue cracking due to long-term load. These problems make traditional lifting point methods unsuitable for the current demand for rapid and safe lifting of large-tonnage bridge piers.

[0005] Therefore, there is an urgent need for a bridge precast pier hoisting device that is structurally sound, uniformly stressed, can ensure safe hoisting, and is reusable, in order to address the shortcomings of existing technologies. Utility Model Content

[0006] To address the aforementioned problems, this utility model provides a combined square clamp hoisting device for precast bridge piers. By setting a cross-shaped I-beam bracket at the bottom of the clamp structure and connecting it with the upper clamp structure using vertical connecting steel bars, the anti-slip stability and safety of the clamp device are improved.

[0007] To achieve the above objectives, the present invention adopts the following technical solution: The device mainly includes four mutually symmetrical L-shaped clamping plates. Corbel vertical plates are welded on both sides of the L-shaped clamping plates. Bolt holes are provided on the corbel vertical plates, and they are connected by high-strength bolts to form a complete square clamping structure. In addition, corbel panels and reinforcing ribs are welded to the outside of the L-shaped clamping plates to improve the overall rigidity and load-bearing capacity. The corbel panels are separated from the vertical connecting steel bars by spacers and are fixedly connected by high-strength bolts, so that the vertical steel bars and the clamping structure form an integrated load-bearing structure.

[0008] Furthermore, an end plate is welded to the lower end of the vertical connecting steel bar, and the end plate is reliably connected to the bottom I-beam bracket by high-strength bolts, with the I-beam bracket serving as the load-bearing foundation. Through the above connection method, an integrated force-bearing system is formed by the cooperation of the clamps, vertical steel bars, end plates, and brackets, thereby ensuring the stability and safety of the hoisting process.

[0009] Furthermore, this device features independently manufactured lifting lugs at the top of the square clamp. These lugs are welded from thick steel plates and are specifically designed for connection with lifting slings during hoisting operations. This avoids localized stress concentration or weld damage caused by directly hoisting the clamp itself. The lifting lugs are independently designed and reliably strong, ensuring long-term stable use during repeated hoisting operations.

[0010] Furthermore, the reinforcing ribs are evenly distributed along the circumference of the L-shaped clamp plate and are vertically welded to the outer side of the L-shaped clamp plate to enhance the overall rigidity of the clamp, and all reinforcing ribs are welded to the L-shaped clamp plate.

[0011] This utility model achieves the following beneficial effects through the above structural design: the L-shaped clamp plate assembly method ensures the ease of installation and adaptability of the device, and can be customized according to piers with different cross-sectional dimensions; the multi-point connection design of the corbel panel, reinforcing ribs, pads and vertical connecting steel bars makes the stress more uniform and avoids local instability; the connection method between the vertical steel bars and the end plate of the bottom I-beam bracket ensures the reliability of vertical load transfer; the overall device is a modular structure, which can be easily disassembled and reused, significantly reducing construction costs and improving the efficiency and safety level of bridge construction. Attached Figure Description

[0012] To more clearly illustrate the technical solutions in the embodiments of this application or the prior art, the drawings used in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some examples recorded in this utility model. For those skilled in the art, other drawings can be obtained based on these drawings.

[0013] Figure 1 This is a schematic diagram of the overall structure of the combined square clamp hoisting device of this utility model, which shows the four L-shaped clamp plates assembled into a square closed structure, as well as the schematic positions of the upper lifting lug and the lower cross I-beam bracket;

[0014] Figure 2 This is a partially enlarged view of a single L-shaped clamp plate and its reinforcing structure in this utility model.

[0015] Figure 3 This is a schematic diagram showing the connection between the vertical connecting steel bars and the upper clamp structure and the lower I-beam bracket in this utility model.

[0016] Explanation of reference numerals in the attached figures:

[0017] In the attached diagram, 1 is an L-shaped clamp plate, 2 is a corbel vertical plate, 3 is a corbel panel, 4 is a reinforcing rib plate, 5 is a pad block, 6 is a vertical connecting steel bar, 7 is an end plate, 8 is an I-beam bracket, 9 is a high-strength bolt, 10 is a lifting lug, 31 is a second corbel panel, and 32 is a bottom corbel panel. Detailed Implementation

[0018] This utility model proposes a combined square clamp for hoisting bridge piers. Its overall structure consists of multiple steel structural components and connectors, mainly including an L-shaped clamp plate 1, a corbel vertical plate 2, a corbel panel 3, reinforcing ribs 4, pads 5, vertical connecting steel bars 6, end plates 7, I-beam brackets 8, high-strength bolts 9, and lifting lugs 10. The components are reliably connected through a combination of welding and bolting, thus providing a stable force path and reliable constraint during the hoisting of bridge piers. The design of the entire device not only considers load-bearing capacity but also the operability of on-site installation and hoisting operations, as well as the convenience of later disassembly and reuse.

[0019] The square clamp structure is the core component of this device, assembled from four L-shaped clamp plates 1. Each L-shaped clamp plate 1 has corbel vertical plates 2 welded to both ends. Bolt holes are provided on the corbel vertical plates 2, and corbel face plates 3 are welded to them and the L-shaped clamp plates 1. When the four L-shaped clamp plates 1 are arranged around the pier, they are connected and secured by several sets of high-strength bolts 9, forming a closed rectangular frame structure. To ensure the reliability of the connections, the bolt holes are symmetrically arranged, and local strength is enhanced by reinforcing ribs 4. The thickness of the L-shaped clamp plates 1 is typically between 20 and 30 mm, and can be customized according to the pier cross-sectional dimensions. Their inner surfaces are polished and treated with anti-slip material. Reinforcing ribs 4 are welded to the outer side of the L-shaped clamp plates 1 to improve overall rigidity.

[0020] The vertical connecting steel bar 6 is a longitudinal load-bearing member. Its upper end is welded to the pad 5 and fixed to the bottom bracket panel 32 by high-strength bolts 9, while the lower end is welded to the end plate 7, thus forming a complete mechanical transmission path in the vertical direction. The diameter of the vertical connecting steel bar 6 is designed according to the weight of the precast pier and the hoisting conditions, and HRB400 grade steel bars with a diameter of 25-40mm are usually selected to ensure sufficient tensile strength. The connection between the lower end and the end plate 7 is a full weld, and the weld is a circumferential weld with a weld height of not less than 8mm to ensure that it can withstand the maximum axial tensile force generated during hoisting. The end plate 7 is a rectangular or square steel plate with a thickness of generally 20-30mm. Several bolt holes are opened on the surface, and the arrangement can be symmetrical to facilitate the connection with the I-beam bracket 8 by high-strength bolts 9.

[0021] The I-beam bracket 8 is a crucial load-bearing component at the bottom of the device. It consists of two I-beams arranged crosswise and welded together at the center point to form a cross-shaped structure. The type of I-beam is selected based on the load requirements, with common specifications ranging from I20 to I40. The two I-beams are fully welded at the intersection to prevent buckling or cracking. The end plate 7 is connected to the I-beam bracket 8 using high-strength bolts 9. The bolt holes are located on the upper flange of the I-beam and arranged in a double row to ensure that the connection between the end plate 7 and the I-beam bracket 8 can transmit vertical tensile force without causing eccentricity or shear failure.

[0022] Lifting lugs 10 are welded to the second bracket panels on the two opposite sides of the top of the square clamp. The lifting lugs 10 are made of high-strength steel plate. The shape of the lifting lugs 10 can be U-shaped or annular, with lifting point holes inside for easy connection to the crane wire rope or lifting hook. The design of the lifting lugs 10 is independent of the clamp body's load-bearing structure, enabling them to bear the entire lifting load independently during hoisting, thus avoiding localized damage caused by concentrated stress on the clamp body. The strength of the lifting lugs 10 has been verified to meet the safety requirements of multiple hoisting operations.

[0023] The installation sequence of this device is as follows: First, install square clamps on the upper part of the precast pier column, then assemble four L-shaped clamp plates 1 in sequence and tighten them with high-strength bolts 9 to ensure that the square clamps 1 are tightly fitted to the outer surface of the pier column. Then, using the lifting lugs 10 connected to the crane's wire rope, slowly lift the precast pier column as a whole, leaving installation space at its bottom. After the precast pier column is lifted to a certain height, install the I-beam bracket 8 at its bottom and fix it to the I-beam bracket 8 with bolts through the end plates 7. At this time, the upper end of the vertical connecting steel bar 6 is fixed to the clamp 1 through the corbel panel 3, and the lower end is fixed to the I-beam bracket 8 through the end plates 7, forming a force transmission system that coordinates the upper and lower forces, ensuring that the weight of the pier column is evenly distributed and reliably transmitted, thereby guaranteeing the safety and stability of the lifting process.

[0024] After the hoisting construction is completed, the device can be easily disassembled. The disassembly sequence is as follows: First, loosen the high-strength bolts 9 between the end plate 7 and the I-beam bracket 8 to separate the vertical connecting steel bar 6 from the I-beam bracket 8; then remove the high-strength bolts 9 between the vertical connecting steel bar 6 and the corbel panel 3, and remove the shims 5 to completely detach the vertical connecting steel bar 6; finally, loosen the high-strength bolts 9 on the corbel vertical plate 2 in sequence, and remove the four L-shaped clamp plates 1 one by one to complete the disassembly of the entire device.

[0025] This utility model is not limited to the specific embodiments described above. For those skilled in the art, any equivalent modifications and substitutions to this utility model are also within its scope. Therefore, all equivalent changes and modifications made without departing from the spirit and scope of this utility model should be covered within its scope.

Claims

1. A combined square clamp for hoisting precast bridge piers, comprising an L-shaped clamp plate (1) and vertical connecting steel bars (6), characterized in that, Each L-shaped clamp plate (1) has a corbel vertical plate (2) welded to both ends. The corbel vertical plate (2) has bolt holes. During assembly, the L-shaped clamp plate (1) is fixed in the bolt holes of the corbel vertical plate (2) by high-strength bolts (9), thereby fastening the four L-shaped clamp plates (1) into a whole closed square clamp structure. Corbel panels (3) and reinforcing ribs (4) are welded to the outside of the L-shaped clamp plate (1). The vertical connecting steel bars (6) are welded to the pads (5). On the corbel panel (3), a pad (5) is provided between the corbel panel (3) and the vertical connecting steel bar (6), and the bottom corbel panel (32), the pad (5) and the vertical connecting steel bar (6) are fixedly connected by high-strength bolts (9); the lower end of the vertical connecting steel bar (6) is welded with an end plate (7), and the end plate (7) is connected to the bottom I-beam bracket (8) by high-strength bolts (9); the second corbel panel (31) of the square clamp is provided with a lifting lug (10) for lifting.

2. The combination square clamp according to claim 1, wherein, A second bracket panel (31) is welded to the upper part of the bracket vertical plate (2), and lifting lugs (10) are welded on the two opposite second bracket panels (31). The lifting lugs (10) are made of thick steel plate.

3. The combination square clamp of claim 1, wherein, The bottom bracket panel (32) and the pad block (5) are both made of steel plate. The bottom bracket panel (32) is welded to the L-shaped clamp plate (1) and the bracket vertical plate (2).

4. The combined square clamp according to claim 1, characterized in that, The upper end of the vertical connecting steel bar (6) is welded and fixed on the pad (5), and the lower end is welded with an end plate (7). The end plate (7) is connected to the I-beam bracket (8) by high-strength bolts (9).

5. The combined square clamp according to claim 1, characterized in that, The I-beam bracket (8) is formed by welding two I-beams together to form a cross-shaped structure.

6. The combined square clamp according to claim 1, characterized in that, The reinforcing ribs (4) are evenly distributed around the L-shaped clamp plate (1) and are vertically welded to the outer side of the L-shaped clamp plate to enhance the overall rigidity of the clamp. All reinforcing ribs (4) are welded to the L-shaped clamp plate (1).

7. The combination square tube as claimed in claim 1, wherein: The device uses high-strength bolts (9) as the main fasteners. The installation sequence is as follows: first, install the upper square clamp structure on the upper part of the precast pier and connect it with the crane lifting tool to lift the precast pier to a certain height; then install the I-beam bracket (8) and fix it to the end plate (7) with high-strength bolts (9).