A spray liquid replacement device for the primary cooler of a coking plant

By designing a spray liquid replacement device for the primary cooler of a coking plant, and utilizing a tar-ammonia-water separation tank and a PLC controller to achieve automated management of the spray liquid, the problems of spray liquid quality degradation and equipment blockage were solved, thereby improving cooling effect and operating efficiency.

CN224949694UActive Publication Date: 2026-11-10SHANDONG YANKUANG INT COKING CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202522027860.0
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2025-09-22
Publication Date
2026-11-10
Estimated Expiration
2035-09-22

AI Technical Summary

Technical Problem

After prolonged use, the quality of the spray fluid used in the primary cooler of a coking plant deteriorates, resulting in poor spraying effect. Heavy oil impurities deposited at the bottom of the tank increase the resistance of the primary cooler, affecting the cooling effect and potentially clogging the equipment. Traditional cleaning methods are cumbersome and inefficient.

Method used

A spray liquid replacement device for the primary cooler of a coking plant was designed, including a tar-ammonia-water separation tank, a spray liquid tank, a tar pump, an overflow baffle, and a PLC controller. The device achieves sedimentation, replenishment, purging, and rinsing of the spray liquid through automated control, preventing impurities from depositing and improving the quality of the spray liquid.

Benefits of technology

It effectively removes heavy oil impurities deposited at the bottom of the spray tank, prevents equipment blockage, improves cooling effect, and enhances operating efficiency through automated control.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN224949694U_ABST
    Figure CN224949694U_ABST
Patent Text Reader

Abstract

This utility model belongs to the technical field of coking production equipment, and particularly relates to a spray liquid replacement device for a primary cooler in a coking plant. It includes a tar-ammonia-water separation tank, which is sequentially connected by pipes to a spray liquid tank, a tar pump, and a tar-ammonia-water pre-separator. The spray liquid tank is divided into a settling chamber and an overflow chamber by an overflow baffle. The settling chamber is connected to a return pipe, and the overflow chamber is connected to the spray pump. The output end of the tar pump is connected to a steam pipeline. This utility model can extract heavy oil impurities deposited at the bottom of the spray liquid tank and reuse them in the workshop production, thereby preventing heavy oil impurities from increasing the resistance of the primary cooler, affecting the cooling effect, or even clogging the equipment.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] This utility model belongs to the technical field of coking production equipment, and in particular relates to a spray liquid replacement device for the primary cooler of a coking plant. Background Technology

[0002] In coking plants, the spraying fluid used in the primary cooler is recycled. The spraying fluid in the tank is pumped to the primary cooler for spraying and cooling. The fluid in the primary cooler, carrying impurities, then returns to the tank, forming a cycle. Prolonged circulation degrades the quality of the spraying fluid, affecting spraying efficiency. Heavy oil and other impurities easily settle at the bottom of the tank; spraying these into the primary cooler increases its resistance, affecting cooling performance and potentially clogging the equipment. Traditional methods to ensure spraying fluid quality involve continuously replenishing the fluid and periodically cleaning the sediment from the tank bottom, a cumbersome and inefficient process. Summary of the Invention

[0003] The purpose of this invention is to provide a spray liquid replacement device for the primary cooler of a coking plant, so as to solve the problems existing in the prior art.

[0004] The technical solution adopted by this utility model to solve its technical problem is:

[0005] A spray liquid replacement device for a primary cooler in a coking plant includes a tar-ammonia-water separation tank. The tar-ammonia-water separation tank is sequentially connected by pipes to a spray liquid tank, a tar pump, and a tar-ammonia-water pre-separator. The spray liquid tank is divided into a settling chamber and an overflow chamber by an overflow baffle. The settling chamber is connected to a return pipe, and the overflow chamber is connected by pipes to the spray pump. The output end of the tar pump is connected to a steam pipeline.

[0006] Furthermore, there is a gap between the top of the overflow baffle and the inner wall of the spray tank, and the settling chamber and the overflow chamber are connected through the gap. The settling chamber and the overflow chamber are respectively equipped with level gauges.

[0007] Furthermore, the pipeline connection of the tar-ammonia-water separation tank is located in its separation layer. The tar-ammonia-water separation tank is connected to the top of the overflow chamber of the spray liquid tank through a pipeline, and a replenishment valve is installed on the pipeline connecting to the overflow chamber.

[0008] Furthermore, the return pipe is connected to the top of the settling chamber, the spray pump is connected to the bottom of the overflow chamber, and a spray liquid valve is installed on the pipe at the input end of the spray pump.

[0009] Furthermore, a heavy oil valve and a purge valve are installed on the inlet and outlet pipes of the tar pump, respectively.

[0010] Furthermore, the steam pipeline is connected in parallel to the pipelines at both ends of the purge valve. Steam valve one is installed on the pipeline of the purge valve near the tar pump, and steam valve two is installed on the pipeline of the purge valve near the tar ammonia pre-separator.

[0011] Furthermore, flow meters are installed on the installation pipe of the replenishment valve, the return pipe, and the pipe at the output end of the spray pump.

[0012] Furthermore, the tar pump, spray pump, replenishment valve, heavy oil valve, purge valve, steam valve one, steam valve two, level gauge, and flow meter are all electrically connected to a PLC controller.

[0013] This utility model has the following beneficial effects:

[0014] 1. This utility model can extract heavy oil impurities deposited at the bottom of the spray tank and use them in the workshop production, thereby preventing heavy oil impurities from increasing the resistance of the primary cooler, affecting the cooling effect, or even clogging the equipment.

[0015] 2. Use steam to flush relevant pipes, pumps, and valves in a timely manner to prevent residual impurities from accumulating and causing blockages.

[0016] 3. By using PLC controllers for automated control, the level of automation can be improved, thereby increasing control efficiency. Attached Figure Description

[0017] Figure 1 This is a schematic diagram of the structure of this utility model.

[0018] The components include: 1. Tar-ammonia water separation tank; 2. Spray liquid tank; 3. Tar pump; 4. Tar-ammonia water pre-separator; 5. Overflow baffle; 6. Settling chamber; 7. Overflow chamber; 8. Return pipe; 9. Spray pump; 10. Steam pipeline; 11. Make-up valve; 12. Spray liquid valve; 13. Heavy oil valve; 14. Purge valve; 15. Steam valve one; 16. Steam valve two; 17. Level gauge; 18. Pipeline; 19. Flow meter. Detailed Implementation

[0019] To make the objectives, technical solutions, and advantages of this utility model clearer, the following detailed description is provided in conjunction with specific embodiments and accompanying drawings. It should be understood that the specific embodiments described herein are merely illustrative of the utility model and are not intended to limit the scope of the utility model.

[0020] like Figure 1 As shown, a spray liquid replacement device for a coking plant's primary cooler includes a tar-ammonia-water separation tank 1. The tar-ammonia-water separation tank 1 is sequentially connected by pipes to a spray liquid tank 2, a tar pump 3, and a tar-ammonia-water pre-separator 4. The spray liquid tank 2 is divided into a settling chamber 6 and an overflow chamber 7 by an overflow baffle 5. The settling chamber 6 is connected to a return pipe 8, and the overflow chamber 7 is connected by pipes to a spray pump 9. The output end of the tar pump 3 is connected to a steam pipe 10. The tar-ammonia-water separation tank 1, the spray liquid tank 2, and the tar-ammonia-water pre-separator 4 are all existing equipment in the workshop.

[0021] There is a gap between the top of the overflow baffle 5 and the inner wall of the spray tank 2. The settling chamber 6 and the overflow chamber 7 are connected through the gap. The settling chamber 6 and the overflow chamber 7 are respectively equipped with level gauges 17.

[0022] The pipeline connection of the tar-ammonia-water separation tank 1 is located in its separation layer. The tar-ammonia-water separation tank 1 is a sedimentation separation device, and the separation layer is the upper light liquid with fewer impurities. The tar-ammonia-water separation tank 1 is connected to the top of the overflow chamber 7 of the spray liquid tank 2 through a pipeline, and a replenishment valve 11 is installed on the pipeline connecting to the overflow chamber 7.

[0023] The return pipe 8 is connected to the top of the settling chamber 6, the spray pump 9 is connected to the bottom of the overflow chamber 7, and the spray liquid valve 12 is installed on the pipe at the input end of the spray pump 9.

[0024] Heavy oil valve 13 and purge valve 14 are respectively installed on the input and output pipes of tar pump 3.

[0025] Steam pipeline 10 is connected in parallel to the pipelines at both ends of purge valve 14. Steam valve 15 is installed on the pipeline of purge valve 14 near tar pump 3, and steam valve 26 is installed on the pipeline of purge valve 14 near tar ammonia pre-separator 4.

[0026] Flow meters 19 are installed on the installation pipe 18 of the replenishment valve 11, the return pipe 8, and the pipe 18 at the output end of the spray pump 9.

[0027] The tar pump 3, spray pump 9, replenishment valve 11, heavy oil valve 13, purging valve 14, steam valve one 15, steam valve two 16, level gauge 17, and flow meter 19 are all electrically connected to a PLC controller.

[0028] The working principle of this utility model is as follows:

[0029] The standard value (lower than the overflow baffle height), the lower limit value (minimum value of circulating liquid volume) of the liquid level in the settling chamber 6 and the upper and lower limit values ​​of the liquid level in the overflow chamber 7 are set on the PLC controller (not shown in the figure). During normal operation, the spray liquid in the spray tank 2 is input into the primary cooler for spraying and cooling through the spray liquid valve 12 and the spray pump 9. The spray liquid in the primary cooler carries impurities and returns to the settling chamber 6 of the spray tank 2 through the return pipe 8. After the impurities settle in the settling chamber 6, the upper light liquid overflows into the overflow chamber 7 through the overflow baffle 5, and is then input into the primary cooler for spraying through the spray pump 9, thus forming a cycle. During this process, the liquid level in the overflow chamber 7 is always maintained within the set upper and lower limits. When the liquid level is lower than the lower limit, it indicates that the sprayed liquid is insufficient, resulting in a low liquid level in the settling chamber 6, which cannot overflow into the overflow chamber 7. At this time, the replenishment valve 11 is opened to replenish the sprayed liquid that has been separated by settling in the tar ammonia water separation tank 1 into the overflow chamber 7, thereby replenishing the liquid. When the liquid level in the overflow chamber 7 is higher than the upper limit, the replenishment valve 11 is closed to stop replenishing the liquid.

[0030] Based on experience, the time interval for pumping heavy oil from the bottom of the spray tank 2 is set on the PLC controller (e.g., pumping once every 5 days). When pumping begins, tar pump 3, heavy oil valve 13, and purge valve 14 are turned on. The heavy oil at the bottom of the spray tank 2 is pumped to the tar-ammonia pre-separator 4 for pre-separation, so that it can be used for workshop production. The pumping and purging times are set. After a certain pumping time, tar pump 3 and purge valve 14 are turned off, and steam valve 15 and steam valve 26 are turned on for purging. The steam blows the heavy oil impurities remaining in the pipeline and tar pump 3 into the spray tank 2 and tar-ammonia pre-separator 4. After the purging time is reached, heavy oil valve 13, steam valve 15, and steam valve 2 are turned off to stop purging.

[0031] After the pumping and purging are completed, the liquid level in the settling chamber 6 may fall below the lower limit. This indicates that the amount of spray liquid in the spray tank 2 is insufficient to reach the minimum circulating volume of the spray liquid. In this case, it is necessary to quickly and massively replenish the spray tank 2. This has a higher priority than stopping the replenishment when the liquid level in the overflow chamber 7 exceeds the upper limit. That is, the replenishment valve 11 is continuously opened to continuously replenish the overflow chamber 7. When the liquid level in the overflow chamber 7 gradually rises and reaches the upper limit of the liquid level gauge 17 in the overflow chamber 7, the replenishment valve 11 is not closed but replenishment continues until it overflows from the overflow baffle 5 into the settling chamber 6 (reverse overflow replenishment). After the liquid level in the settling chamber 6 continues to rise to the standard value, the replenishment valve 11 is closed. This operation requires first determining that the liquid level in the settling chamber 6 is below the lower limit and that pumping and purging have been completed (e.g., by determining that tar pump 3, heavy oil valve 13, purging valve 14, steam valve 15, and steam valve 26 are all closed). Only when both conditions are met can the backflow replenishment be performed.

[0032] The replenishing valve 11 can be equipped with a flow regulating valve. Based on the required spray volume of the primary cooler per unit time (e.g., 160 m³ / h) and the return flow rate of the return pipe 8 (e.g., 150 m³ / h), a difference (10 m³ / h) is calculated. This difference causes the replenishing valve 11 to open to a certain degree, ensuring the replenishment volume is slightly greater than the difference (e.g., 11 m³ / h). This allows the replenishing valve 11 to slowly replenish the spray volume, thus avoiding frequent opening and closing of the replenishing valve 11. When the liquid level in the settling chamber 6 falls below the lower limit and a large amount of liquid needs to be rapidly replenished into the spray tank 2, the replenishing valve 11 is fully opened for replenishment.

[0033] In addition, when equipment malfunctions such as leakage of the primary cooler spray liquid occur, the liquid level in settling chamber 6 may also fall below the lower limit. An alarm can be electrically connected to the PLC controller to issue a warning when the liquid level in settling chamber 6 falls below the lower limit, thereby reminding the staff.

[0034] The above embodiments are merely descriptions of preferred embodiments of the present invention and are not intended to limit the concept and scope of the present invention. Various modifications and improvements made to the technical solutions of the present invention by those skilled in the art without departing from the design concept of the present invention should fall within the protection scope of the present invention.

[0035] The technologies, shapes, and structures not described in detail in this utility model are all known technologies.

Claims

1. A device for replacing sprayed liquid in the primary cooler of a coking plant, characterized in that, The system includes a tar-ammonia water separation tank, which is connected in sequence by pipes to a spray liquid tank, a tar pump, and a tar-ammonia water pre-separator. The spray liquid tank is divided into a settling chamber and an overflow chamber by an overflow baffle. The settling chamber is connected to a return pipe, and the overflow chamber is connected to a spray pump. The output end of the tar pump is connected to a steam pipeline.

2. The coking plant primary cooler spray liquid replacement device according to claim 1, characterized in that, There is a gap between the top of the overflow baffle and the inner wall of the spray tank. The settling chamber and the overflow chamber are connected through the gap. The settling chamber and the overflow chamber are respectively equipped with level gauges.

3. The coking plant primary cooler spray liquid replacement device according to claim 2, characterized in that, The pipeline connection of the tar-ammonia water separation tank is located in its separation layer. The tar-ammonia water separation tank is connected to the top of the overflow chamber of the spray liquid tank through a pipeline, and a replenishment valve is installed on the pipeline connected to the overflow chamber.

4. The coking plant primary cooler spray liquid replacement device according to claim 3, characterized in that, The return pipe is connected to the top of the settling chamber, the spray pump is connected to the bottom of the overflow chamber, and a spray liquid valve is installed on the pipe at the input end of the spray pump.

5. The coking plant primary cooler spray liquid replacement device according to claim 4, characterized in that, The tar pump is equipped with a heavy oil valve and a purge valve on the inlet and outlet pipes, respectively.

6. The coking plant primary cooler spray liquid replacement device according to claim 5, characterized in that, The steam pipeline is connected to the pipes at both ends of the purge valve. Steam valve one is installed on the pipe near the tar pump end of the purge valve, and steam valve two is installed on the pipe near the tar ammonia pre-separator end of the purge valve.

7. The coking plant primary cooler spray liquid replacement device according to claim 6, characterized in that, Flow meters are installed on the installation pipe of the replenishment valve, the return pipe, and the pipe at the output end of the spray pump.

8. The coking plant primary cooler spray liquid replacement device according to claim 7, characterized in that, The tar pump, spray pump, replenishment valve, heavy oil valve, purge valve, steam valve one, steam valve two, level gauge, and flow meter are all electrically connected to a PLC controller.