A deep foundation pit splicing prefabricated pile inclinometer tube installation structure and use method thereof

Through the installation structure of prefabricated pile inclined pipe splicing in-depth foundation pit, the coordination of the limiting mechanism and the placement of pipe fittings is used to solve the problems of floating and verticality deviation of the inclined pipe in the subway station foundation pit enclosing pile inclined pipe in construction, achieving more accurate The installation and monitoring data ensures construction safety and quality.

CN111236331BActive Publication Date: 2024-11-15SHANGHAI CIVIL ENG GRP CO LTD OF CREC +1
View PDF 3 Cites 0 Cited by

Patent Information

Application Number
CN202010175380.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-03-13
Publication Date
2024-11-15
Estimated Expiration
2040-03-13

AI Technical Summary

Technical Problem

The inclined pipes of existing subway station foundation pits are prone to floating and verticality deviation during construction, and the interfaces are misaligned when splicing prefabricated piles, which cannot accurately reflect the displacement changes of piles, affecting the accuracy of monitoring data and construction safety.

Method used

The installation structure of the inclined pipe of deep foundation pit splicing prefabricated piles includes the upper and lower prefabricated piles, placement grooves, limiting mechanisms and adjustable sleeves. The stability and verticality of the inclined pipe are ensured through the threaded steel bar layer and fixed slurry. , use the limiting mechanism and placement pipe fittings for precise installation.

Benefits of technology

The installation accuracy and stability of the inclined measuring pipe is improved, the data inaccuracy problems in traditional construction methods are avoided, construction safety and quality are ensured, and the accuracy of subsequent monitoring data is improved.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN111236331B_ABST
    Figure CN111236331B_ABST
Patent Text Reader

Abstract

The present invention relates to an inclinometer tube installation structure, specifically, an inclinometer tube installation structure for splicing precast piles in a deep foundation pit and a method for using the same, wherein the inclinometer tube installation structure comprises an upper placement groove arranged on an upper pile body and a lower placement groove arranged on a lower pile body; the upper placement groove and the lower placement groove constitute a pipe placement channel for placing the inclinometer tube. The present invention discloses an inclinometer tube installation structure for splicing precast piles in a deep foundation pit; through the cooperation of a limiting mechanism and a placement pipe, the accuracy and stability of the inclinometer tube installation can be well guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to an inclinometer tube installation structure, in particular to an inclinometer tube installation structure for splicing prefabricated piles in a deep foundation pit and a use method thereof. Background Art

[0002] In subway station projects, some stations use prefabricated piles for foundation pit retaining piles. When the foundation pit is deep, the pile body cannot be installed in one go and needs to be spliced ​​together. During deep foundation pit excavation, it is necessary to monitor the retaining pile body, install inclinometers, observe the dynamic changes of the surrounding area and the foundation pit during excavation, monitor the foundation pit excavation construction, and ensure the safety of the foundation pit excavation construction.

[0003] At present, most of the inclinometer pipes for retaining piles in subway stations at home and abroad are pre-buried and cast-in-place constructed.

[0004] This process can easily cause the inclinometer tube to float and have verticality deviations during construction, and cannot more accurately reflect the displacement changes of the pile body during the monitoring process; a few subway station foundation pit retaining piles are composed of prefabricated piles, and the inclinometer tube cannot be pre-buried and formed in one go, and needs to be completed in sections and segments, which can easily cause the interface to be misaligned during the burial process and cannot be used normally.

[0005] Therefore, in order to avoid the above problems, a new inclinometer tube installation structure and method are now needed. Summary of the invention

[0006] The purpose of the present invention is to overcome the deficiencies of the prior art and provide an inclinometer pipe installation structure based on spliced ​​prefabricated piles.

[0007] In order to achieve the above object, the technical solution adopted by the present invention is:

[0008] A deep foundation pit splicing precast pile inclinometer tube installation structure, the splicing precast pile includes an upper precast pile and a lower precast pile, the upper precast pile includes an upper pile body, the lower precast pile includes a lower pile body, the upper pile body and the lower pile body are arranged oppositely; the inclinometer tube installation structure includes an upper placement groove arranged on the upper pile body and a lower placement groove arranged on the lower pile body; the upper placement groove and the lower placement groove constitute a pipe placement channel for placing the inclinometer tube; the pipe placement channel of the present invention

[0009] A pipe placement passage is provided with a pipe placement passage for placing an inclinometer pipe.

[0010] A threaded steel bar layer is arranged around the periphery of the placed pipe fittings to ensure the stability of the placed pipe fittings.

[0011] The placing pipe is poured with fixing slurry after the oblique side pipe is inserted.

[0012] The inclinometer tube installation structure also includes a limiting mechanism for positioning the inclinometer tube; the limiting mechanism is arranged at the upper end of the upper pile body; the limiting mechanism includes a connecting frame, the interior of the connecting frame is hollow, and the inclinometer tube is connected to the interior of the connecting frame; the lower end of the connecting frame is connected to the upper end surface of the upper pile body.

[0013] A hanging hook for hanging the inclinometer tube is provided on the inner side of the connecting frame; the hanging hook is arranged at the center position of the connecting frame.

[0014] The hanging hook is connected to the inclinometer tube through a connecting mechanism, the connecting structure comprises a protective cover connected to the inclinometer tube, and the inclinometer tube is connected to the hanging hook through the protective cover.

[0015] An adjustable sleeve for adjusting the position of the inclinometer tube for placing the pipe fitting is provided at one end of the inclinometer tube close to the protective cover.

[0016] The inclinometer pipe installation structure also includes a blocking cover for blocking the placed pipe fittings.

[0017] A method for using a deep foundation pit splicing prefabricated pile inclinometer tube installation structure, the method comprising the following steps:

[0018] Step 1: At the center of the upper pile body and the lower pile body where the steel bars have been tied, use the threaded steel bar layer to fix the pipe fittings to form a rigid component, and seal the bottom of the pipe fittings set in the upper placement groove;

[0019] Step 2: hoist the upper pile body with the steel bars tied. Before hoisting the upper pile body, open the plugging cover at the bottom of the pipe fitting in the upper pile body. During hoisting, the upper pile body is required to be hoisted above the corresponding lower pile body so that the upper pile body and the lower pile body form an integral structure. Adjust the positions of the upper pile body and the lower pile body so that the entire structure of the spliced ​​prefabricated pile is in the vertical direction.

[0020] Step 3: After the upper precast pile and the lower precast pile are spliced ​​and reinforced, fill mortar liquid is injected into the upper precast pile and the lower precast pile. After the curing strength is qualified, the inclinometer tube is inserted into the pre-buried pipe fittings of the spliced ​​precast piles, and the limit mechanism is installed;

[0021] Step 4: The limit mechanism is installed on the top of the upper prefabricated pile, and the bottom of the limit mechanism is connected to the upper pile body with screws; the connecting frame in the limit mechanism is connected to the inclinometer tube through a hanging hook; the limit mechanism hangs the inclinometer tube in the connecting frame to adjust the verticality of the inclinometer tube, and after the inclinometer tube is stable; adjust the adjustable sleeve in the limit mechanism to fix the inclinometer tube;

[0022] Step 5: After the inclinometer tube is placed, inject mortar into the placed pipe. After the injected mortar is solidified, remove the limit mechanism to complete the installation of the inclinometer tube.

[0023] The advantages of the present invention are:

[0024] The invention discloses an inclinometer tube installation structure for splicing prefabricated piles in a deep foundation pit; the accuracy and stability of the inclinometer tube installation can be well guaranteed through the cooperation of a limiting mechanism and a placed pipe fitting; in addition, the invention adopts offline prefabrication and on-site installation of the inclinometer tube for splicing prefabricated piles, which is beneficial to the verticality and elevation control of the inclinometer tube, and avoids the problem of inaccurate measurement data caused by one-time pile body forming deformation in the traditional construction method; in addition, the invention can ensure the safety and quality of construction through a new construction process, improve the accuracy of subsequent measurement and monitoring data, and better monitor and guide on-site construction. BRIEF DESCRIPTION OF THE DRAWINGS

[0025] The following is a brief description of the contents expressed in the drawings of the present invention and the symbols in the drawings:

[0026] Figure 1 It is a cross-sectional view of the present invention.

[0027] Figure 2 It is a horizontal cross-sectional view of the upper prefabricated pile of the present invention.

[0028] Figure 3 It is a top view of the present invention.

[0029] Figure 4 It is a structural schematic diagram of the connection frame in the present invention.

[0030] Figure 5 It is a schematic diagram of the structure when the inclinometer tube and the protective cover are connected in the present invention.

[0031] The marks in the above figure are:

[0032] 1. Limiting mechanism, 2. Protective cover, 3. Inclinometer tube, 4. Placement of pipe fittings, 5. Upper precast piles, 6. Lower precast piles, 7. Fixing slurry, 8. Threaded steel bar layer, 9. Adjustable sleeve. DETAILED DESCRIPTION

[0033] The specific implementation of the present invention will be further explained in detail below by describing the optimal embodiment with reference to the accompanying drawings.

[0034] A deep foundation pit spliced ​​precast pile inclinometer tube 3 installation structure, the spliced ​​precast pile includes an upper precast pile 5 and a lower precast pile 6, the upper precast pile 5 includes an upper pile body, the lower precast pile 6 includes a lower pile body, and the upper pile body and the lower pile body are arranged relatively to each other; the inclinometer tube 3 installation structure includes an upper placement groove arranged on the upper pile body and a lower placement groove arranged on the lower pile body; the upper placement groove and the lower placement groove constitute a pipe placement channel for placing the inclinometer tube 3; the present invention can facilitate the placement of the inclinometer tube 3 and subsequent positioning through the setting of the pipeline placement channel; in addition, the precast piles of the present invention adopt a splicing connection method, which can facilitate actual processing.

[0035] Preferably, a placement pipe fitting 4 for placing the inclinometer tube 3 is provided in the pipe fitting placement channel of the present invention; the setting of the placement pipe fitting 4 plays a certain limiting role, and at the same time plays a certain protective role, and also facilitates the subsequent pouring of fixing slurry, and plays the role of a mold, which can facilitate the fixed limitation of the inclinometer tube 3; as a greater optimization, the placement pipe fitting 4 in the present invention can be a PVC pipe fitting.

[0036] Preferably, the periphery of the placed pipe fitting 4 described in the present invention is surrounded by a threaded steel bar layer 8 for ensuring the stability of the placed pipe fitting 4; the threaded steel bar layer 8 is arranged around the placed pipe fitting 4; it can play a good limiting role; in addition, because the threaded steel bar layer 8 of the present invention has a threaded layer on the outside, it can perform friction limiting on the placed pipe fitting 4 to ensure the stability of the placed pipe fitting 4; in addition, as a greater optimization, the periphery of the placed pipe fitting 4 in the present invention is provided with multiple layers of threaded steel bar layers 8; the threaded steel bar layers 8 are distributed along the longitudinal direction; each threaded steel bar layer 8 is supported by overlapping multiple single threaded steel bars; each threaded steel bar layer 8 is in a tic-tac-toe shape in a top view, so that each threaded steel bar layer 8 has a hole in the middle, which can better ensure the installation stability of the placed pipe fitting 4.

[0037] Preferably, the placement pipe fitting 4 of the present invention is poured with fixing slurry 7 after the inclined side pipe is inserted; the material of the fixing slurry 7 can be set as needed. In addition, the present invention can fix the inclinometer tube 3 placed in the placement pipe fitting 4 by setting the fixing slurry 7.

[0038] Preferably, the inclinometer tube 3 installation structure of the present invention further includes a limiting mechanism 1 for positioning the inclinometer tube 3; the limiting mechanism 1 is arranged at the upper end of the upper pile body; the limiting mechanism 1 includes a connecting frame, the interior of the connecting frame is hollow, and the inclinometer tube 3 is connected to the interior of the connecting frame; the lower end of the connecting frame is connected to the upper end surface of the upper pile body; the setting of the connecting frame provides a hanging foundation for the inclinometer tube 3, which is conducive to ensuring the verticality of the inclinometer tube 3; it also facilitates the subsequent adjustment of the position of the inclinometer tube 3 by the adjustable sleeve; the connecting frame disclosed in the present invention is assembled by splicing steel bars, and the simplest structure is shown in the accompanying drawings; it can include four columns, the upper ends of the four columns are connected by four horizontal columns, and the lower end of each column is connected to a transverse flange 92, and the transverse flange is provided with a threaded hole, and the transverse flange is connected to the upper pile body by bolts; of course, the connecting frame also includes other reinforcement beams or bridge beams 93 as needed to facilitate the subsequent setting of hanging hooks.

[0039] Preferably, a hanging hook 1-1 for hanging the inclinometer tube 3 is provided on the inner side of the connecting frame in the present invention; the hanging hook 1-1 is arranged at the center position of the connecting frame; the arrangement of the hanging hook 1-1 facilitates the hanging of the inclinometer tube 3; that is, it facilitates the initial positioning of the inclinometer tube 3.

[0040] Preferably, the hanging hook described in the present invention is connected to the inclinometer tube 3 through a connecting mechanism, and the connecting structure includes a protective cover 2 connected to the inclinometer tube 3; the protective cover is a cylindrical cover formed by injection molding of a plastic material; when in use, the protective cover is sleeved on the end of the inclinometer tube, and the protective cover is connected to the inclinometer tube through a waterproof tape 21; when connected, one side of the waterproof tape 21 is connected to the end of the protective cover, and the other side is connected to the inclinometer tube. Such a connection method can not only ensure the connection between the protective cover and the inclinometer tube, but also facilitate subsequent disassembly; as a greater optimization, the end of the protective cover described in the present invention is provided with a hanging hole, and the protective cover is connected to the hanging hook through the hanging hole; the inclinometer tube 3 is connected to the hanging hook through the protective cover 2; the present invention facilitates the connection between the hanging hook and the inclinometer tube 3 through the setting of the connecting mechanism, and at the same time, through the setting of the protective cover 2, the end of the inclinometer tube 3 can be protected. As a greater optimization, protective covers 2 are provided at both ends of the inclinometer tube 3, which can provide greater protection for the inclinometer tube 3.

[0041] Preferably, the inclinometer tube 3 described in the present invention is provided with an adjustable sleeve at one end close to the protective cover 2 for adjusting the position of the inclinometer tube 3 in placing the pipe fitting 4; the adjustable sleeve of the present invention can be a clamp, which is connected to the inclinometer tube, and the clamp is connected to the connecting frame through the steel column 91; the inclinometer tube can be fixed by the setting of the clamp, that is, the adjustable sleeve, to prevent the inclinometer tube 3 from floating up during the grouting process; as a greater optimization, the clamp in the present invention is made of two semicircular iron rings, and the two semicircular iron rings are connected by bolts; the two semicircular iron ring structures constituting the adjustable sleeve are docked and clamped on the inclinometer tube 3; the inclinometer tube is fixed by reinforcing the bolts on the adjustable sleeve, to prevent the inclinometer tube 3 from floating up during the grouting process.

[0042] Preferably, the inclinometer tube 3 installation structure of the present invention also includes a sealing cover for sealing the placed pipe 4; the sealing cover can be used to ensure the neatness of the placed pipe 4 and reduce the probability of foreign matter appearing in the placed pipe 4 before the prefabricated piles are spliced.

[0043] In addition to the above statements, the following is a discussion in conjunction with specific embodiments:

[0044] The present invention provides an installation structure for a deep foundation pit splicing prefabricated pile inclinometer tube 3;

[0045] The whole structure includes an upper prefabricated pile 5, a lower prefabricated pile 6, a limit mechanism 1, an inclinometer tube 3, and a placement pipe 4. The placement pipe 4 is made of PVC pipes, threaded steel bars, and adjustable sleeves in actual use.

[0046] When in use, the limiting mechanism 1 and the adjustable clamping sleeve are prefabricated and installed, and the threaded steel bar and the placement pipe 4 are prefabricated to form an integral component.

[0047] The inclinometer tube 3 is inserted into the placement pipe fitting 4, corresponding to the center of the limiting mechanism 1. The limiting mechanism 1 suspends the inclinometer tube 3 and fixes it with an adjustable sleeve to adjust the verticality and elevation of the inclinometer tube 3. After the inclinometer tube 3 is placed in the placement pipe fitting 4, grouting is injected into the placement pipe fitting 4 to better ensure the stability of the placement of the inclinometer tube 3.

[0048] During the specific construction:

[0049] The steps include:

[0050] Step 1: At the center of the upper pile body and the lower pile body where the steel bars have been tied, use the threaded steel bar layer 8 to fix the placement pipe 4 to form a rigid component, and seal the bottom of the placement pipe 4 set in the upper placement groove;

[0051] Step 2: hoist the upper pile body with the steel bars tied. Before hoisting the upper pile body, open the plugging cover at the bottom of the pipe fitting 4 in the upper pile body. During hoisting, the upper pile body is required to be hoisted above the corresponding lower pile body so that the upper pile body and the lower pile body form an integral structure, and adjust the positions of the upper pile body and the lower pile body so that the entire structure of the spliced ​​prefabricated pile is in the vertical direction;

[0052] Step 3: After the upper precast pile 5 and the lower precast pile 6 are spliced ​​and reinforced, the mortar is injected into the upper precast pile 5 and the lower precast pile 6. After the curing strength is qualified, the inclinometer tube 3 is inserted into the pre-buried pipe fitting 4 of the spliced ​​precast pile, and the limit mechanism 1 is installed;

[0053] Step 4: The limiting mechanism 1 is installed on the top of the upper prefabricated pile 5, and the bottom of the limiting mechanism 1 is connected to the upper pile body with screws; the connecting frame in the limiting mechanism 1 is connected to the inclinometer tube 3 through a hanging hook; the limiting mechanism 1 hangs the inclinometer tube 3 in the connecting frame to adjust the verticality of the inclinometer tube 3, and after the inclinometer tube 3 is stable; adjust the adjustable sleeve in the limiting mechanism 1 to fix the inclinometer tube 3;

[0054] Step 5: After the inclinometer tube 3 is placed, mortar is injected into the placement pipe 4. After the injected mortar is solidified, the limiting mechanism 1 is removed to complete the installation of the inclinometer tube 3.

[0055] In step 4, the bottom of the limit mechanism 1 is fixed with expansion screws, and the bottom of the hanging inclinometer tube 3 is separated from the bottom of the placement pipe 4, that is, the inclinometer tube 3 is in a vertical suspended state; during the specific operation, the inclinometer tube 3 is filled with water, and the inclinometer tube is in a vertical state through the action of gravity, so that the inclinometer tube can be relatively straight as a whole, thereby improving the accuracy of the monitoring data.

[0056] Through the implementation of the above method, the present invention can improve the accuracy of subsequent monitoring data and ensure construction safety while ensuring the quality of the project.

[0057] The characteristics of the installation structure of the prefabricated pile inclinometer tube 3 for deep foundation pit of subway station of the present invention are:

[0058] Prefabricated components are provided, including an inclinometer tube 3, a limiting mechanism 1, and pre-buried pipe fittings 4, namely PVC pipe fittings; an integral component is formed by limiting grouting reinforcement; and the inclinometer tube 3 is reinforced with mortar.

[0059] A large-diameter PVC pipe is pre-buried vertically upward in the center of each precast pile, corresponding to the lower center of the limiting mechanism 1, and a small-diameter inclinometer pipe 3 is inserted in the center of the PVC pipe to form a ring-shaped pipe hole, and reinforcing slurry is injected into the outer ring channel.

[0060] At the center of the pile body of each prefabricated pile, corresponding to the position of the PVC pipe in each prefabricated component, a threaded steel bar is provided to limit the PVC pipe. The inclinometer tube 3 is inserted into the PVC pipe and corrected and reinforced by a limiting mechanism 1 arranged on the top of the upper pile body; and the inclinometer tube 3 is fastened and fixed by grouting the placed pipe fitting 4.

[0061] Obviously, the specific implementation of the present invention is not limited to the above-mentioned methods. As long as various non-substantial improvements are made using the method concept and technical solution of the present invention, they are all within the protection scope of the present invention.

Claims

1. A deep foundation pit splicing precast pile inclinometer tube installation structure, the splicing precast pile comprises an upper precast pile and a lower precast pile, the upper precast pile comprises an upper pile body, the lower precast pile comprises a lower pile body, the upper pile body and the lower pile body are arranged opposite to each other; characterized in that: The inclinometer pipe installation structure comprises an upper placement groove arranged on the upper pile body and a lower placement groove arranged on the lower pile body; the upper placement groove and the lower placement groove constitute a pipe placement channel for placing the inclinometer pipe; The pipe fitting placement channel is provided with a pipe fitting for placing the inclinometer pipe; The inclinometer tube installation structure also includes a limiting mechanism for positioning the inclinometer tube; the limiting mechanism is arranged at the upper end of the upper pile body; the limiting mechanism includes a connecting frame, the interior of the connecting frame is hollow, and the inclinometer tube is connected to the interior of the connecting frame; the lower end of the connecting frame is connected to the upper end surface of the upper pile body; A hanging hook for hanging the inclinometer tube is provided on the inner side of the connecting frame; the hanging hook is arranged at the center position of the connecting frame; The hanging hook is connected to the inclinometer tube through a connecting mechanism, the connecting mechanism includes a protective cover connected to the inclinometer tube, and the inclinometer tube is connected to the hanging hook through the protective cover; The protective cover is a cylindrical cover made of plastic injection molding. When in use, the protective cover is put on the end of the inclinometer tube, and the protective cover is connected to the inclinometer tube through a waterproof tape. When connected, one side of the waterproof tape is connected to the end of the protective cover, and the other side is connected to the inclinometer tube. An adjustable clamping sleeve for adjusting the position of the inclinometer tube at which the pipe fitting is placed is provided at one end of the inclinometer tube close to the protective cover; the adjustable clamping sleeve is a clamp; The clamp is connected to the connection frame through the steel bar column; A threaded steel bar layer is arranged around the periphery of the placed pipe fittings to ensure the stability of the placed pipe fittings; the threaded steel bar layer is in a tic-tac-toe shape when viewed from above.

2. The inclinometer tube installation structure for splicing prefabricated piles in a deep foundation pit according to claim 1 is characterized in that: The placing pipe is filled with fixing slurry after the inclinometer pipe is inserted.

3. A deep foundation pit splicing prefabricated pile inclinometer tube installation structure according to any one of claims 1-2, characterized in that: The inclinometer pipe installation structure also includes a blocking cover for blocking the placed pipe fittings.

4. A method for using a deep foundation pit splicing prefabricated pile inclinometer tube installation structure according to any one of claims 1 to 3, characterized in that: The method of use comprises the following steps: Step 1: At the center of the upper pile body and the lower pile body where the steel bars have been tied, use the threaded steel bar layer to fix the pipe fittings to form a rigid component, and seal the bottom of the pipe fittings set in the upper placement groove; Step 2: hoist the upper pile body with the steel bars tied. Before hoisting the upper pile body, open the plugging cover at the bottom of the pipe fitting in the upper pile body. During hoisting, the upper pile body is required to be hoisted above the corresponding lower pile body so that the upper pile body and the lower pile body form an integral structure. Adjust the positions of the upper pile body and the lower pile body so that the entire structure of the spliced ​​prefabricated pile is in the vertical direction. Step 3: After the upper precast pile and the lower precast pile are spliced ​​and reinforced, fill mortar liquid is injected into the upper precast pile and the lower precast pile. After the curing strength is qualified, the inclinometer tube is inserted into the pre-buried pipe fittings of the spliced ​​precast piles, and the limit mechanism is installed; Step 4: The limit mechanism is installed on the top of the upper prefabricated pile, and the bottom of the limit mechanism is connected to the upper pile body with screws; the connecting frame in the limit mechanism is connected to the inclinometer tube through a hanging hook; the limit mechanism hangs the inclinometer tube in the connecting frame to adjust the verticality of the inclinometer tube, and after the inclinometer tube is stable; adjust the adjustable sleeve in the limit mechanism to fix the inclinometer tube; Step 5: After the inclinometer tube is placed, inject mortar into the placed pipe. After the injected mortar is solidified, remove the limit mechanism to complete the installation of the inclinometer tube.

Citation Information

Patent Citations

  • Monitoring method for perpendicularity of steel pipe pile

    CN106592654A

  • Mechanical device for mounting inclinometer tubes and mounting method of inclinometer tubes

    CN107938638A

  • Mounting structure of inclinometer pipe of deep foundation pit spliced precast pile

    CN212405274U