Grouting device for post-grouting construction of pile foundation
By designing a grouting device with upper and lower limit sealing plates and a grout groove, and using elastic parts to drive the inner casing to slide, it is possible to block the backflow of cement slurry and reliably open the valve port, thus solving the problem of backflow of cement slurry in the existing technology. and the problem that the valve port cannot be opened to ensure the grouting quality and pile foundation bearing capacity.
Patent Information
- Application Number
- CN202410807570.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-06-21
- Publication Date
- 2024-09-27
AI Technical Summary
During the grouting construction behind the existing pile foundation, the cement slurry backflow was not completely blocked, resulting in insufficient grouting volume and affecting the bearing capacity of the pile foundation. The one-way valve structure was easily affected by the solidified cement and was difficult to open, resulting in grouting failure.
A grouting device including an outer casing, an inner casing, elastic parts and a valve core is designed. Through the fixed upper and lower limit sealing plates and grout groove structure, the elastic parts are used to drive the inner casing to slide to ensure the first row of grout. The holes are closed when not pressurized, and the second row of slurry holes are channeled when pressurized, achieving effective blocking of cement slurry backflow and reliable opening of the valve port.
It effectively blocks the backflow of cement slurry, reduces the risk of the valve not opening, ensures grouting quality, simplifies the structure, reduces production costs, ensures that the pile foundation bearing capacity meets the requirements, and supports multiple uses.
Smart Images

Figure CN118704467A
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of building construction, and in particular relates to a grouting device for post-grouting construction of pile foundation. Background Art
[0002] Post-grouting of pile foundation means that after a certain period of time, the grouting pipeline reserved in the pile body is used to inject cement-based slurry into the ground at the side and end of the pile through the grouting device through the ground pressure system. The pressure slurry fills, penetrates, compacts, replaces and consolidates the mud skin around the pile, the pile end and the nearby soil around the pile. By changing the physical and mechanical properties of the soil and the boundary conditions between the pile and the soil, the bearing capacity of the pile is improved and the settlement of the pile foundation is reduced.
[0003] The pipelines pre-buried for post-grouting of pile foundation are usually grouting steel pipes. Multiple grouting holes are opened at the bottom of the grouting steel pipes. The grouting steel pipes are lowered into the pile hole together with the steel cage, and then the hole is cleaned and poured according to the bored pile process. In order to prevent the cement slurry from entering the grouting steel pipe through the grouting holes during the pouring of bored piles, the prior art generally blocks the reflux of cement slurry by wrapping waterproof tape around the grouting holes. In this way, there is a risk that the waterproof tape is easily damaged and fails during the lowering, hole cleaning and pouring process. The failure of the waterproof tape will cause the cement slurry to flow back and block the grouting steel pipe, making it impossible to carry out post-grouting, or the grouting volume cannot be guaranteed, so that the bearing capacity of the pile foundation cannot meet the requirements. In some other related technologies, the backflow of cement slurry is blocked by setting a one-way valve at each grouting hole. Although the backflow of cement slurry can be effectively blocked, the existing one-way valve structure is basically in the form of opening outward under pressure. Since the outside of the grouting hole is often wrapped with solidified cement slurry, it is easy for the grouting one-way valve to be difficult to open, which may also easily lead to the grouting volume not being guaranteed, so that the bearing capacity of the pile foundation cannot meet the requirements.
[0004] Therefore, there is an urgent need to provide a new grouting device for post-grouting construction of pile foundation, which is required to be able to effectively block the backflow of cement slurry in the pile hole; at the same time, it can reduce the risk of the valve port of the grouting device failing to open and ensure the grouting quality; at the same time, it can help to simplify the structure and reduce the production cost. Summary of the invention
[0005] In view of this, the purpose of the present invention is to provide a grouting device for post-grouting construction of pile foundation, which can effectively block the backflow of cement slurry in the pile hole; at the same time, it can reduce the risk of the valve body structure not being able to open the valve port, thereby ensuring the grouting quality; at the same time, it can help to simplify the structure and reduce the production cost.
[0006] To achieve the above-mentioned purpose, the present invention provides the following technical solutions: a grouting device for post-grouting construction of pile foundation, comprising a grouting pipe and a grouting valve arranged at the bottom of the grouting pipe, the grouting valve comprising: an outer sleeve fixedly arranged at the bottom of the grouting pipe, the upper and lower ends of the outer sleeve are respectively fixedly provided with an upper limit sealing plate and a lower limit sealing plate, and the side wall of the outer sleeve is provided with a first row of slurry holes near the middle; an inner sleeve, the inner sleeve is sleeved inside the outer sleeve in a manner that it can be driven to slide along the length direction of the outer sleeve, and the inner sleeve can be limited by the upper limit sealing plate and the lower limit sealing plate respectively after sliding upward and downward, and the side wall of the inner sleeve is provided with a first row of slurry holes near the middle; A second row of slurry holes is provided at the upper position. When the inner sleeve is in the upper limit sealing plate position, the lower part of the inner sleeve closes the first row of slurry holes. When the inner sleeve is in the lower limit sealing plate position, the second row of slurry holes is connected with the first row of slurry holes. An elastic member is built into the outer sleeve and is used to drive the inner sleeve to abut against the upper limit sealing plate. A slurry hole is provided on the upper limit sealing plate, and the top of the inner sleeve is sealed. A valve core is fixed to the lower limit sealing plate and extends upward to pass through the top of the inner sleeve, and a slurry groove is provided near the middle of the valve core. The slurry groove allows the slurry hole to be connected with the second row of slurry holes when the inner sleeve is in the lower limit sealing plate position.
[0007] Furthermore, the elastic member is a compression spring, and the compression spring is sleeved on the valve core.
[0008] Furthermore, the slurry passage groove is an annular groove arranged along the circumference of the valve core.
[0009] Furthermore, a threaded connection section extending upward is provided at the top end of the outer sleeve, and the threaded connection section is threadedly connected to the grouting pipe.
[0010] Furthermore, the valve core and the lower limit sealing plate are an integrated structure, and the lower limit sealing plate is threadedly connected to the outer sleeve.
[0011] Furthermore, the first row of pulp holes is evenly distributed in a plurality along the circumference of the outer casing.
[0012] Furthermore, the second row of slurry holes is evenly distributed in a plurality along the circumferential direction of the inner casing, and the second row of slurry holes is waist-shaped holes arranged along the axial direction of the inner casing.
[0013] Furthermore, two sealing rings I are arranged at intervals on the lower portion of the outer circumferential surface of the inner sleeve, and when the inner sleeve is in the upper limit sealing position, the two sealing rings I are respectively located at the upper and lower ends of the first row of slurry holes.
[0014] Furthermore, a sealing ring II is provided on the top end surface of the inner sleeve to surround the slurry passage hole, and a sealing ring III is provided at the through-fitting portion between the valve core and the inner sleeve.
[0015] Furthermore, it also includes a metal filter screen which is coated on the outer sleeve and shields the first row of pulp holes.
[0016] The beneficial effects of the present invention are as follows:
[0017] The grouting device for post-grouting construction of pile foundation provided by the present invention can effectively block the backflow of cement slurry in the pile hole; at the same time, it can reduce the risk of the valve body structure valve port not being able to open, and ensure the grouting quality; at the same time, it can be helpful to simplify the structure and reduce the manufacturing cost; specifically, under the action of the elastic member, it can be ensured that when grouting is not pressurized, the first row of slurry holes on the outer sleeve are always in a closed state, that is, the first row of slurry holes can only be opened from the inside of the outer sleeve, and the grouting construction in the pile hole will not flow back into the outer sleeve, the structure is reliable, and is less affected by the external construction environment of the first row of slurry holes; because the inner sleeve slides inside the outer sleeve, it is not affected by the solidified concrete outside the first row of slurry holes when moving, and it only needs to overcome the resistance of the set elastic member when moving. , high controllability, can effectively reduce the risk of the valve body structure valve port not being able to open, ensure the grouting quality, and then ensure that the pile foundation bearing capacity meets the requirements; of course, on the other hand, since the first row of slurry holes is reliably blocked when not grouting, the external cement slurry will not flow back to the bottom of the outer casing, which will not affect the movement of the inner casing; in this structure, only an inner casing and a valve core matching structure are used to realize the on-off control of the first row of slurry holes and the slurry holes, the structure is simple, and it is conducive to reducing the production cost; of course, the grouting device can also be used multiple times in the same post-grouting construction process, only after grouting, the grouting valve and the grouting pipe After the grouting, the slurry inside the grouting device needs to be cleaned with clean water before the slurry solidifies.
[0018] Other advantages, objectives and features of the present invention will be described in the following description to some extent, and to some extent, will be obvious to those skilled in the art based on the following examination and study, or can be taught from the practice of the present invention. The objectives and other advantages of the present invention can be realized and obtained through the following description. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 This is a schematic cross-sectional view of the overall structure of the present invention when no grouting is performed.
[0020] Figure 2 The cross-sectional schematic diagram of the grouting valve part during grouting of the present invention is
[0021] Figure 3 Schematic diagram of the explosion structure of the grouting valve part of the present invention
[0022] Figure markings: 1-outer casing; 101-first row of slurry holes; 102-threaded connection section; 2-upper limit sealing plate; 201-slurry hole; 3-lower limit sealing plate; 4-inner casing; 401-second row of slurry holes; 5-elastic member; 6-valve core; 601-slurry groove; 601a-bevel; 7-sealing ring I; 8-sealing ring II; 9-sealing ring III; 10-metal filter; 11-grouting pipe. DETAILED DESCRIPTION
[0023] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0024] It should be noted that the up and down direction in the following text refers to the vertical direction of the pile hole when in use.
[0025] See also Figure 1-3 This embodiment discloses a grouting device for post-grouting construction of pile foundation, comprising a grouting pipe 11 and a grouting valve arranged at the bottom of the grouting pipe 11, wherein the grouting valve comprises:
[0026] An outer sleeve 1 is fixedly arranged at the bottom of the grouting pipe 11, and an upper limit sealing plate 2 and a lower limit sealing plate 3 are respectively fixedly arranged at the upper and lower ends of the outer sleeve 1, and a first row of slurry holes 101 is arranged near the middle of the side wall of the outer sleeve 1. Specifically, the outer sleeve 1 is preferably made of steel pipe, and the upper limit sealing plate 2 and the lower limit sealing plate 3 can be welded and fixed to the outer sleeve 1. The "sealing plate" refers to closing the corresponding ends. The first row of slurry holes 101 are preferably arranged in a plurality along the circumference of the outer sleeve 1. The outer sleeve 1 can be welded and fixed to the grouting pipe 11, and the outer sleeve 1 can also be an integral structure with the grouting pipe 11. The grouting pipe 11 can be a plurality of steel pipes spliced together;
[0027] An inner casing 4, wherein the inner casing 4 is sleeved inside the outer casing 1 in a manner that it can be driven to slide along the length direction of the outer casing 1, and after the inner casing 1 slides upward and downward, it can be respectively limited by the upper limit sealing plate 2 and the lower limit sealing plate 3. A second row of slurry holes 401 is provided near the upper part of the side wall of the inner casing 4. When the inner casing 4 is at the upper limit sealing plate 2 position, the lower part of the inner casing 1 closes the first row of slurry holes 101. When the inner casing 4 is at the lower limit sealing plate 3 position, the second row of slurry holes 401 is connected with the first row of slurry holes 101. Here, the inner casing 4 is preferably made of a steel pipe;
[0028] The elastic member 5 is built into the outer sleeve 1 and is used to drive the inner sleeve 4 to abut against the upper limit sealing plate 2. The upper limit sealing plate 2 is provided with a slurry hole 201. The top of the inner sleeve 4 is sealed. Specifically, the elastic member 5 is a compression spring. The two ends of the compression spring are respectively correspondingly abutted against the top of the inner sleeve 4 and the lower limit sealing plate 3. The top of the inner sleeve 4 is sealed by a sealing plate which is an integral structure with the inner sleeve 4. During grouting, the grouting pressure overcomes the elastic force of the elastic member 5 to drive the inner sleeve 4 to move downward;
[0029] The valve core 6 is fixedly mounted on the lower limit sealing plate 3 and extends upward to penetrate the top of the inner sleeve 4, and a slurry groove 601 is provided near the middle of the valve core 6. The slurry groove 601 is used to connect the slurry holes 201 with the second row of slurry holes 401 when the inner sleeve 4 is at the position of the lower limit sealing plate 3. Specifically, the valve core 6 and the lower limit sealing plate 3 are preferably an integral structure. It can be understood that the part where the valve core 6 is connected to the top of the inner sleeve 4 is a movable connection, that is, it does not affect the up and down movement of the inner sleeve 4. It is preferably a sliding sealing connection here. The slurry groove 601 is preferably an annular groove. When the inner sleeve 4 moves to the position of the slurry groove 601, the cement slurry flowing out of the slurry hole 201 can flow to the lower part of the inner sleeve 4 through the slurry groove 601, and then flow to the second row of slurry holes 401. The valve core 6 is preferably an iron core.
[0030] In the above structural design, under the action of the elastic member 5, it can be ensured that when there is no pressurized grouting, the first row of grout holes 101 on the outer sleeve 1 is always in a closed state, that is, the first row of grout holes 101 can only be opened from the inside of the outer sleeve 1, and the grouting in the pile hole will not flow back into the outer sleeve 1. The structure is reliable and is less affected by the external construction environment of the first row of grout holes 101. Since the inner sleeve 4 slides inside the outer sleeve 1, it is not affected by the solidified concrete outside the first row of grout holes 101 when moving. When moving, it only needs to overcome the set resistance of the elastic member 5. It has high controllability, can effectively reduce the risk of the valve body structure valve port not being able to open, and ensure the quality of grouting. Of course, on the other hand, since the first row of slurry holes 101 are reliably blocked when not grouting, the external cement slurry will not flow back to the bottom of the outer casing 1, which will not affect the movement of the inner casing 4; in this structure, only the matching structure of the inner casing 4 and the valve core 6 is adopted to realize the on-off control of the first row of slurry holes 101 and the slurry holes 201, which has a simple structure and is conducive to reducing the production cost; of course, the grouting device can also be used multiple times in the same post-grouting construction process, and it only needs to use clean water to clean the slurry in the device before the slurry solidifies after grouting.
[0031] In this embodiment, the elastic member 5 is a compression spring, and the compression spring is sleeved on the valve core 6. The compression spring has good elasticity, which is beneficial to providing sufficient movement stroke for the inner sleeve 4. The compression spring is sleeved on the valve core 6, and the valve core 6 is used to complete the movement guidance of the compression spring, thereby ensuring the smoothness of the movement and further simplifying the installation structure.
[0032] In this embodiment, the slurry passage groove 601 is an annular groove arranged along the circumference of the valve core 6. The annular groove is simple to process and is conducive to forming the largest slurry passage channel between the valve core 6; in addition, the annular groove here has bevels 601a at both axial ends to transition to the side wall surface of the valve core 6. By designing the bevel transition structure, it is helpful to reduce the sticking of the inner sleeve 4 during movement, and of course it is also conducive to forming a larger slurry passage channel, and at the same time it is conducive to improving the structural strength of the valve core 6.
[0033] In this embodiment, the top of the outer sleeve 1 is provided with an upwardly extending threaded connection section 102, and the threaded connection section 102 is threadedly connected to the grouting pipe 11; this structural design facilitates on-site assembly of the outer sleeve 1 and the grouting pipe 11 and improves assembly efficiency.
[0034] In this embodiment, the valve core 6 and the lower limit sealing plate 3 are an integral structure, and the lower limit sealing plate 3 is threadedly connected to the outer sleeve 1; the structure is simple, which is convenient for processing and manufacturing, and is convenient for on-site assembly, reducing hot work construction.
[0035] In this embodiment, the first row of grouting holes 101 are evenly distributed in a plurality along the circumference of the outer casing 1 , and are arranged in a plurality along the circumference, which is conducive to discharging the grouting liquid to a plurality of places, and further improves the quality of the post-grouting construction.
[0036] In this embodiment, the second row of pulp holes 401 are evenly distributed in a plurality along the circumference of the inner sleeve 4, and the second row of pulp holes 401 are waist-shaped holes arranged axially along the inner sleeve 4; this structural design is beneficial to reducing the impact of manufacturing tolerances while ensuring the use function, and further reducing the production cost. The structural design of the waist-shaped holes allows a certain axial and circumferential misalignment, and can also ensure the connectivity between the second row of pulp holes 401 and the first row of pulp holes 101.
[0037] In the present embodiment, two sealing rings Ⅰ7 are provided at intervals at the lower position on the outer circumferential surface of the inner casing 4, and the two sealing rings Ⅰ7 are respectively located at the upper and lower ends of the first row of slurry holes 101 when the inner casing 4 is in the upper limit sealing plate 3 position; specifically, the sealing rings Ⅰ7 here are all O-type sealing rings, and the installation of O-type sealing rings is a prior art, such as opening an installation groove on the inner casing 4 to complete the installation of the sealing ring, which will not be repeated here; by providing two sealing rings Ⅰ, the sealing performance of the fitting part between the inner casing 4 and the outer casing 1 can be further improved, and water seepage in the pile hole can be prevented from entering the inner part of the outer casing 1 and affecting the overall success rate of valve opening.
[0038] In this embodiment, the top end surface of the inner sleeve 4 is provided with a sealing ring II8 surrounding the slurry hole 201, and the through-fitting portion of the valve core 6 and the inner sleeve 4 is provided with a sealing ring III9; the design of the sealing ring II8 and the sealing ring III9 is conducive to further improving the sealing performance of the inner sleeve 4 and the upper limit sealing plate 3, as well as the through-fitting portion of the valve core 6 and the inner sleeve 4, thereby preventing water from seeping into the outer sleeve 1 from the grouting pipe and affecting the overall success rate of valve opening.
[0039] In this embodiment, it also includes a metal filter 10 that is coated on the outer sleeve 1 and blocks the first row of pulp holes 101; here, the metal filter 10 can be fixed to the outer wall of the outer sleeve 1 by welding or the like; by setting up the metal filter 10, large particles of stone and the like can be prevented from getting stuck in the first row of pulp holes 101 during use and affecting the sliding of the inner sleeve 4, thereby further improving the protection and reliability of use; the metal filter 10 has high durability and reliability.
[0040] Although the present invention has been described in detail with reference to preferred embodiments, those skilled in the art should understand that the technical solutions of the present invention may be modified or replaced by equivalents without departing from the purpose and scope of the technical solutions of the present invention, which should be included in the scope of the claims of the present invention.
Claims
1. A grouting device for post-grouting construction of pile foundation, characterized in that: The invention comprises a grouting pipe (11) and a grouting valve arranged at the bottom of the grouting pipe (11), wherein the grouting valve comprises: An outer sleeve (1) is fixedly mounted at the bottom of the grouting pipe (11), an upper limit sealing plate (2) and a lower limit sealing plate (3) are fixedly mounted at the upper and lower ends of the outer sleeve (1), and a first row of grout holes (101) is disposed at the middle of the side wall of the outer sleeve (1); An inner sleeve (4), wherein the inner sleeve (4) is sleeved inside the outer sleeve (1) in a manner that it can be driven to slide along the length direction of the outer sleeve (1), and after the inner sleeve (1) slides upward and downward, it can be respectively limited by the upper limit sealing plate (2) and the lower limit sealing plate (3), and a second row of pulp holes (401) is provided at the upper part of the side wall of the inner sleeve (4); when the inner sleeve (4) is in the position of the upper limit sealing plate (2), the lower part of the inner sleeve (1) closes the first row of pulp holes (101); when the inner sleeve (4) is in the position of the lower limit sealing plate (3), the second row of pulp holes (401) is connected to the first row of pulp holes (101); An elastic member (5) is built into the outer sleeve (1) and is used to drive the inner sleeve (4) to abut against the upper limit sealing plate (2), wherein the upper limit sealing plate (2) is provided with a slurry hole (201), and the top of the inner sleeve (4) is sealed; The valve core (6) is fixedly mounted on the lower limit sealing plate (3) and extends upward to penetrate the top of the inner sleeve (4). A slurry passage groove (601) is provided near the middle of the valve core (6). The slurry passage groove (601) enables the slurry passage hole (201) to be connected with the second row of slurry holes (401) when the inner sleeve (4) is in the position of the lower limit sealing plate (3).
2. The grouting device for post-grouting construction of pile foundation according to claim 1, characterized in that: The elastic member (5) is a compression spring, and the compression spring is sheathed on the valve core (6).
3. The grouting device for post-grouting construction of pile foundation according to claim 2, characterized in that: The slurry passage groove (601) is an annular groove arranged along the circumference of the valve core (6).
4. The grouting device for post-grouting construction of pile foundation according to claim 2, characterized in that: The top end of the outer sleeve (1) is provided with a threaded connection section (102) extending upward, and the threaded connection section (102) is threadedly connected to the grouting pipe (11).
5. The grouting device for post-grouting construction of pile foundation according to claim 4, characterized in that: The valve core (6) and the lower limit sealing plate (3) are an integrated structure, and the lower limit sealing plate (3) is threadedly connected to the outer sleeve (1).
6. The grouting device for post-grouting construction of pile foundation according to claim 1, characterized in that: The first row of pulp holes (101) is evenly distributed in a plurality along the circumference of the outer casing (1).
7. The grouting device for post-grouting construction of pile foundation according to claim 6, characterized in that: The second row of pulp holes (401) is evenly distributed in a plurality along the circumference of the inner sleeve (4), and the second row of pulp holes (401) are waist-shaped holes arranged axially along the inner sleeve (4).
8. The grouting device for post-grouting construction of pile foundation according to claim 1, characterized in that: Two sealing rings I (7) are arranged at intervals at the lower part of the outer peripheral surface of the inner sleeve (4), and when the inner sleeve (4) is in the upper limit sealing plate (3) position, the two sealing rings I (7) are respectively located at the upper and lower ends of the first row of pulp holes (101).
9. The grouting device for post-grouting construction of pile foundation according to claim 8, characterized in that: The top end surface of the inner sleeve (4) is provided with a sealing ring II (8) surrounding the slurry passage hole (201), and the through-fitting portion between the valve core (6) and the inner sleeve (4) is provided with a sealing ring III (9).
10. The grouting device for post-grouting construction of pile foundation according to claim 1, characterized in that: It also includes a metal filter screen (10) which is disposed on the outer sleeve (1) and covers the first row of pulp holes (101).
Citation Information
Cited By
Grouting device of cast-in-place pile foundation and construction method of cast-in-place pile
CN122082435A