Multipurpose safe side-protecting and top-protecting anchor rod trolley and using method thereof
By designing a multi-purpose safety guard and roof anchor rod trolley, the three-dimensional support of the tunnel side support and roof plate is achieved by using the combination of split guard plates and oil cylinders, the problem of incomplete support in the existing technology is solved and the excavation operation is improved The safety and efficiency of the anchor excavator ensure parallel operation between the anchor bolt trolley.
Patent Information
- Application Number
- CN202411090048.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-09
- Publication Date
- 2024-11-12
AI Technical Summary
During the excavation process of coal mine tunnels, it is difficult for the existing technology to effectively support the side and roof plates of the tunnels, resulting in safety hazards such as sheet and roofing. The anchor excavator and anchor trolley cannot achieve parallel operation of the anchor rods, which increases the number of Security risks.
A multi-purpose safety guard and top anchor rod trolley is designed, using a combination of split guard plate, oil cylinder, reducer motor and jack. The reducer motor drives the cylinder rotation and jack sliding to achieve the extension of the guard plate and Move to form temporary support in three-dimensional space, and install extension plates and anchor libraries in the guard plate to improve support flexibility and efficiency.
It realizes stable temporary support for the side and roof of the tunnel, prevents the sheet and roof, improves the safety and efficiency of excavation operations, ensures parallel operation between the anchor machine and the anchor trolley, and reduces the labor intensity of workers. And improve the excavation speed and safety guarantee.
Smart Images

Figure CN118933936A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of coal mine tunnel anchor bolt mechanical supporting equipment, and in particular to a multi-purpose safety side and top protection anchor bolt trolley and a use method thereof. Background Art
[0002] With the development of rapid tunneling technology in coal mines, a process mode of rapid tunneling with an anchor trolley behind the tunnel boring machine has been formed. When using a bolter for tunneling, the anchor rods of the tunnel side are driven into three anchor rods in the high side of the tunnel by the bolter, and then the anchor rod trolley drives the anchor rods of the low side. The empty side up to 2m in the middle is supported by only one anchor rod, which is not only easy to cause side spalling and cause safety hazards, but also the bolter and the anchor trolley cannot achieve parallel operation of side anchor support due to the different number of anchor rods. When using a fully-equipped tunnel boring machine for tunneling, the fully-equipped tunnel boring machine usually cuts and then the anchor trolley goes to the empty top and empty side area to carry out top anchor and side anchor support operations. There is a lack of temporary support for the roof and side, and the safety risk is extremely high. Summary of the invention
[0003] The purpose of the present invention is to provide a multi-purpose safety wall and roof protection anchor trolley and its use method, which can form temporary support for the side walls and roof of coal mine tunnels, eliminate safety hazards such as wall spalling and roof collapse, and realize parallel operation of the side wall anchor support of the channel by the digging machine and the anchor trolley.
[0004] The technical solution of the present invention is a multi-purpose safety side guard and top guard anchor trolley, comprising a trolley body, a split side guard plate, a cylinder, a reduction motor, and a jack. The split side guard plate comprises a first side guard plate and a second side guard plate, and the first side guard plate and the second side guard plate each have two plates, which are arranged on both sides of the front of the trolley body from front to back; the cylinder comprises a first cylinder and a second cylinder, which are respectively arranged on the inner sides of the first side guard plate and the second side guard plate; the reduction motor is fixedly connected to the bottom rotating shaft of the first cylinder, and the rotation of the reduction motor drives the first cylinder and the first side guard plate to rotate 0-90 degrees around the bottom rotating shaft of the first cylinder, and the first cylinder is extended to push the first side guard plate to the side wall and top plate of the tunnel; the jack is arranged at one end of the bottom slide groove of the second cylinder, and the jack drives the second cylinder and the second side guard plate to slide back and forth along both sides of the trolley body, and the second cylinder is extended to push the second side guard plate to the side wall of the tunnel.
[0005] Preferably, two first oil cylinders are arranged on the inner side of each of the first guard plates; and two second oil cylinders are arranged on the inner side of each of the second guard plates.
[0006] Preferably, the first guard plate contains a first extension plate, and a first hydraulic cylinder for driving the first extension plate to be extended and retracted is arranged in the first guard plate; the second guard plate contains a second extension plate, and a second hydraulic cylinder for driving the second extension plate to be extended and retracted is arranged in the second guard plate.
[0007] Preferably, it also includes a wall-mounted anchor rod warehouse and an anchor net hook. The wall-mounted anchor rod warehouse is cylindrical in shape with one end open, and is suspended in the middle groove on the inner side of the second side guard plate on one side of the mining side by relying on an S-shaped bracket; the anchor net hook is installed in the middle groove on the inner side of the second side guard plate on one side of the coal pillar.
[0008] Preferably, the split side guard plate is made of plastic steel.
[0009] A method for using a multi-purpose safety anchor trolley for protecting side and top, comprising the following steps: 1) When the bolt trolley starts to follow the tunnel boring machine to carry out the excavation cycle and start the bolt operation, the reduction motor rotates, driving the first oil cylinder to rotate, turning the first guard plate to be parallel to the tunnel roof, and the first oil cylinder extends to push the first guard plate to the tunnel roof to support the tunnel roof. At the same time, the jack pushes the second oil cylinder to slide forward, moving the second guard plate to the position of the original first guard plate, and the second oil cylinder extends to push the second guard plate to the side of the tunnel. The second guard plate and the first guard plate form a three-dimensional temporary support; when the bolt trolley starts to follow the anchor excavator to carry out the excavation cycle and start the side bolt operation, the first oil cylinder and the second oil cylinder extend to push the first guard plate and the second guard plate to the side of the tunnel to support the high wall and form a temporary support. 2) After the temporary support is formed, the bolting operation begins; 3) After the anchor bolt operation of the side part is completed, the first oil cylinder and the second oil cylinder are shortened to separate the first side guard plate and the second side guard plate from the top plate or the side part; 4) The anchor trolley enters the next excavation anchor operation cycle.
[0010] Preferably, when a tunnel requires a larger support area, the first hydraulic cylinder in the first guard plate extends to push the first extension plate to extend, or the second hydraulic cylinder in the second guard plate extends to push the second extension plate to extend, providing a larger support area and strength.
[0011] Compared with the prior art, the present invention has at least the following beneficial effects: (1) When the anchor trolley of the present invention cooperates with the anchor miner to advance, the front wall guard plate of the anchor trolley supports the side wall of the tunnel to form a stable temporary support. When the anchor miner and the anchor trolley drive the anchor rods into the side wall, it is ensured that the anchor miner and the anchor trolley only need to drive two anchor rods, one on the high side and one on the low side, respectively, to achieve zero-space parallel operation of the side wall anchor rods, effectively prevent the occurrence of side wall spalling, improve the side wall anchor rod operation efficiency, and increase the tunnel excavation speed.
[0012] (2) When the anchor trolley of the present invention cooperates with the tunnel boring machine for excavation, the front wall guard plate of the anchor trolley supports the top plate and side walls of the tunnel to form a three-dimensional temporary support, which can reduce the time of the top and side walls of the anchor support and improve the safety of the anchor support operation during the tunnel boring machine excavation. At the same time, under the protection of the temporary support, the single-cycle operation length of the tunnel boring machine can be effectively increased.
[0013] (3) The split side guard plate is arranged on the anchor trolley of the present invention, which can meet the needs of anchor support when the anchor digging machine and the fully-mechanized excavator are excavating in the coal mine tunnel, and has high flexibility and adaptability.
[0014] (4) An anchor rod warehouse and hanging cat net are set up on the inner side of the guard plate, which can facilitate operators to take anchor rods and anchor nets during anchor support. There is no need to carry them from a long distance, which can reduce the labor intensity of workers and improve the efficiency of cat rod support.
[0015] (5) The extension plate included in the side guard plate can meet the complex support process in coal mines and flexibly adapt to the support space.
[0016] (6) The side guard plates support the side walls and roof of the tunnel to prevent falling coal and gangue, and provide a safe passage between the anchor trolley and the side walls of the tunnel for the working personnel such as the anchor drill driver, material transport personnel and anchor bolting personnel, thereby improving the safety of the working personnel on the excavation working face. BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1 A schematic diagram of the structure of the present invention; Figure 2 The present invention uses a state diagram; Figure 3 A schematic diagram of an extension plate of a side guard plate of the present invention; Figure 4 Schematic diagram of installation of the wall-mounted anchor bar warehouse of the present invention; Figure 5 Schematic diagram of the installation of the anchor net hook of the present invention; In the figure: 1. trolley body, 2. split guard plate, 2-1. first guard plate, 2-1-1. first extension plate, 2-2. second guard plate, 2-2-1. second extension plate, 3. cylinder, 3-1. first cylinder, 3-2. second cylinder, 4. wall-mounted anchor rod warehouse, 5. anchor rod hook, 6. rotating device 7. sliding device, 8. first hydraulic cylinder, 9. second hydraulic cylinder. DETAILED DESCRIPTION
[0018] Combined with Figure 1-5 The present invention is further described clearly and completely with preferred embodiments as follows: like Figure 1 , Figure 2As shown, the present invention is a multi-purpose safety guard and top anchor trolley, including a trolley body 1, a split guard plate 2, a cylinder 3, a reduction motor 6, and a jack 7. The split guard plate 2 includes a first guard plate 2-1 and a second guard plate 2-2. The first guard plate 2-1 and the second guard plate 2-2 each have two plates, which are sequentially arranged on both sides of the front of the trolley body 1 from front to back; the cylinder 3 includes a first cylinder 3-1 and a second cylinder 3-2, which are respectively arranged on the inner sides of the first guard plate 2-1 and the second guard plate 2-2; the reduction motor 6 and The first oil cylinder 3-1 is fixedly connected with the bottom shaft, and the reduction motor 6 rotates to drive the first oil cylinder 3-1 and the first guard plate 2-1 to rotate 0-90 degrees around the bottom shaft of the first oil cylinder 3-1. The first oil cylinder 3-1 is extended to push the first guard plate 2-1 to the side wall and top plate of the tunnel. The jack 7 is set at one end of the bottom slide of the second oil cylinder 3-2. The jack 7 drives the second oil cylinder 3-2 and the second guard plate 2-2 to slide forward and backward along the two sides of the trolley body 1. The second oil cylinder 3-2 is extended to push the second guard plate 2-2 to the side wall of the tunnel. The first guard plate 2-1 and the second guard plate 2-2 support the side wall or top plate of the tunnel, forming a temporary support at the tunnel head, chamber or cut-eye to prevent the side wall or roof from falling.
[0019] like Figure 3 As shown, the first guard plate 2-1 includes a first extension plate 2-1-1, and a first hydraulic cylinder 8 for driving the first extension plate 2-1-1 to extend and retract is arranged in the first guard plate 2-1. The second guard plate 2-2 includes a second extension plate 2-2-1, and a second hydraulic cylinder 9 for driving the second extension plate 2-2-1 to extend and retract is arranged in the second guard plate 2-2, thereby providing a larger supporting area and strength.
[0020] like Figure 4 , Figure 5 As shown, the present invention also provides a wall-mounted anchor rod warehouse 4 and an anchor net hook 5. The wall-mounted anchor rod warehouse 4 is cylindrical, with one end open, and is suspended on the inner middle groove of the second side guard plate 2-2 on the side of the mining side by relying on an S-shaped bracket, for placing anchor rods; the anchor net hook 5 is installed on the inner middle groove of the second side guard plate 2-2 on the side of the coal pillar side. It is used to hang the anchor net to be used, which is very convenient for workers to take the anchor net to carry out support operations, greatly improving the support operation efficiency and excavation speed.
[0021] The sidewall of the mining refers to the unmined coal seam area behind the working face during mining. This area will be affected by the mining of the working face during the mining process, and geological disasters such as roof fall and sidewall spalling may occur. Therefore, the management of the sidewall of the mining is crucial to the safe operation of the mine. The coal pillar refers to a piece of coal body retained between the goaf and the roadway in order to support the roof of the goaf and prevent surface collapse during coal mining. The sidewall of the coal pillar is the contact area between the coal pillar and the sidewall of the roadway. In this area, due to the pressure of water accumulation in the goaf and the influence of geological structure, seepage and other problems often occur, posing a threat to the stability and safety of the roadway.
[0022] Due to the narrow tunnel and the obstruction of large equipment in front (anchor digging machine, anchor trolley, self-moving machine tail), the material transport vehicle can usually only transport anchor rods, anchor nets and other support items to the back of the self-moving machine tail, and then transport the materials forward manually. However, this location is nearly 100m away from the location of the previous support construction. It takes an hour to transport the above support items, which takes up normal excavation time. Therefore, it is particularly important to set up an airborne anchor warehouse and anchor net warehouse in the present invention, which can greatly improve the support efficiency and excavation speed. In one excavation operation cycle, the anchor trolley of the present invention can cooperate with the excavation equipment to excavate 21 meters / shift, while the traditional anchor trolley can only excavate 17 meters / shift.
[0023] The split side guard plate is made of plastic steel.
[0024] A method for using a multi-purpose safety side and top anchor trolley comprises the following steps: 1) When the bolting trolley starts to follow the tunnel boring machine to perform the excavation cycle and start the bolting operation, the reduction motor 6 rotates, driving the first oil cylinder 3-1 to rotate, turning the first side guard plate 2-1 to be parallel to the tunnel roof, the first oil cylinder 3-1 extends to push the first side guard plate 2-1 to the tunnel roof to support the tunnel roof, and at the same time, the jack 7 pushes the second oil cylinder 3-2 to slide forward, moving the second side guard plate 2-2 to the position of the original first side guard plate 2-1, the second oil cylinder 3-2 extends to push the second side guard plate 2-2 to the side of the tunnel, and the second side guard plate 2-2 and the first side guard plate 2-1 form a three-dimensional temporary support; when the bolting trolley starts to follow the anchor excavator to perform the excavation cycle and start the side bolting operation, the first oil cylinder 3-1 and the second oil cylinder 3-2 extend to push the first side guard plate 2-1 and the second side guard plate 2-2 to the side of the tunnel to support the high side and form a temporary support; 2) After the temporary support is formed, the bolting operation begins; 3) After the bolting operation of the side part is completed, the first oil cylinder 3-1 and the second oil cylinder 3-2 are shortened to separate the first side guard plate (2-1) and the second side guard plate 2-2 from the top plate or the side part; 4) The anchor trolley enters the next excavation anchor operation cycle.
[0025] When cooperating with the tunnel boring machine in excavation, the split plastic-steel side guard plate installed on the front of the anchor trolley provides stable temporary support for the roof and side of the tunnel when the anchor trolley is carrying out support operations on the roof and side of the tunnel, which significantly reduces the time of the top and side of the anchor support, and significantly improves the safety of the anchor support operation during the excavation of the tunnel boring machine. At the same time, under the protection of temporary support, the single-cycle operation length of the tunnel boring machine can be effectively increased.
[0026] When cooperating with the anchor drill to excavate, the plastic steel wall guard plate installed on the front of the anchor trolley provides stable temporary support for the side walls of the tunnel when the anchor drill and the anchor trolley drive into the wall anchors. This ensures that the anchor drill and the anchor trolley only need to drive two anchors, one on the high wall and one on the low wall, respectively, to achieve parallel operation of the wall anchors with zero empty walls, effectively preventing the occurrence of wall spalling, improving the operating efficiency of the wall anchors, and improving the efficiency of tunnel excavation while improving safety.
[0027] The present invention can realize adaptation to different excavation equipment, can meet the needs of anchor support when the anchor digging machine and the fully-mechanized excavator are excavating coal mine tunnels, and has high flexibility and adaptability.
[0028] When a larger support area is needed in a tunnel, the first hydraulic cylinder 8 in the first side guard plate 2-1 of the present invention extends to push the first extension plate 2-1-1 to extend, or the second hydraulic cylinder 9 in the second side guard plate 2-2 extends to push the second extension plate 2-2-1 to extend, providing a larger support area and strength. The extension plate included in the side guard plate can meet the complex support process in coal mines and flexibly adapt to the support space.
[0029] In addition to the above embodiments, the present invention may also have other implementation modes; any technical solutions formed by equivalent replacement or equivalent transformation shall fall within the protection scope required by the present invention.
Claims
1. A multi-purpose safety side and top anchor trolley, comprising a trolley body (1), characterized in that: The trolley body (1) also includes a split guard plate (2), a cylinder (3), a reduction motor (6), and a jack (7). The split guard plate (2) includes a first guard plate (2-1) and a second guard plate (2-2). The first guard plate (2-1) and the second guard plate (2-2) each include two plates, which are arranged on both sides of the front of the trolley body (1) in sequence from front to back. The cylinder (3) includes a first cylinder (3-1) and a second cylinder (3-2), which are arranged on the inner sides of the first guard plate (2-1) and the second guard plate (2-2) respectively. The reduction motor (6) and the bottom of the first cylinder (3-1) are connected to each other. The first oil cylinder (3-1) and the first guard plate (2-1) are fixedly connected to the rotating shaft at the bottom of the trolley body (1), and the reduction motor (6) rotates to drive the first oil cylinder (3-1) and the first guard plate (2-1) to rotate 0-90 degrees around the rotating shaft at the bottom of the first oil cylinder (3-1), and the first oil cylinder (3-1) extends to push the first guard plate (2-1) to the side wall and the top plate of the lane; the jack (7) is arranged at one end of the sliding groove at the bottom of the second oil cylinder (3-2), and the jack (7) drives the second oil cylinder (3-2) and the second guard plate (2-2) to slide forward and backward along the two sides of the trolley body (1), and the second oil cylinder (3-2) extends to push the second guard plate (2-2) to the side wall of the lane.
2. A multi-purpose safety side and top protection anchor trolley according to claim 1, characterized in that: Two first oil cylinders (3-1) are arranged on the inner side of each of the first side guard plates (2-1); and two second oil cylinders (3-2) are arranged on the inner side of each of the second side guard plates (2-2).
3. The multi-purpose safety side and top protection anchor trolley according to claim 1 is characterized in that: The first guard plate (2-1) contains a first extension plate (2-1-1), and a first hydraulic cylinder (8) is arranged in the first guard plate (2-1) for driving the first extension plate (2-1-1) to extend and retract. The second guard plate (2-2) contains a second extension plate (2-2-1), and a second hydraulic cylinder (9) is arranged in the second guard plate (2-2) for driving the second extension plate (2-2-1) to extend and retract.
4. The multi-purpose safety side and top protection anchor trolley according to claim 1 is characterized in that: It also comprises a wall-mounted anchor rod warehouse (4) and an anchor net hook (5); the wall-mounted anchor rod warehouse (4) is cylindrical, one end of which is open, and is suspended on the inner middle groove of the second side guard plate (2-2) on the side of the mining side by relying on an S-shaped bracket; the anchor net hook (5) is installed on the inner middle groove of the second side guard plate (2-2) on the side of the coal pillar.
5. The multi-purpose safety side and top protection anchor trolley according to claim 1 is characterized in that: The split side guard plate (2) is made of plastic steel.
6. A method for using a multi-purpose safety side and top anchor trolley, characterized in that: The steps include: 1) When the bolting trolley starts to follow the tunnel boring machine to perform the excavation operation cycle and starts the bolting operation, the reduction motor (6) rotates, driving the first oil cylinder (3-1) to rotate, turning the first guard plate (2-1) to be parallel to the tunnel roof, and the first oil cylinder (3-1) extends to push the first guard plate (2-1) to the tunnel roof to support the tunnel roof. At the same time, the jack (7) pushes the second oil cylinder (3-2) to slide forward, moving the second guard plate (2-2) to the original first guard plate (2- 1), the second oil cylinder (3-2) extends to push the second side guard plate (2-2) to the side of the tunnel, and the second side guard plate (2-2) and the first side guard plate (2-1) form a three-dimensional temporary support; when the bolting trolley starts to follow the bolting machine to perform excavation cycle operation and starts the side bolting operation, the first oil cylinder (3-1) and the second oil cylinder (3-2) extend to push the first side guard plate (2-1) and the second side guard plate (2-2) to the side of the tunnel, support the high wall, and form a temporary support; 2) After the temporary support is formed, the bolting operation begins; 3) After the bolting operation of the side part is completed, the first oil cylinder (3-1) and the second oil cylinder (3-2) are shortened to separate the first side guard plate (2-1) and the second side guard plate (2-2) from the top plate or the side part; 4) The anchor trolley enters the next excavation anchor operation cycle.
7. The method for using the multi-purpose safety side and top anchor trolley according to claim 6 or 7, characterized in that: When a tunnel needs a larger support area, the first hydraulic cylinder (8) in the first side guard plate (2-1) is extended to push the first extension plate (2-1-1) to extend, or the second hydraulic cylinder (9) in the second side guard plate (2-2) is extended to push the second extension plate (2-2-1) to extend, thereby providing a larger support area and strength.