Large carbon dioxide tank and construction method
Through the methods of segmented production and total segment assembly, the problem of plant space and equipment resource limitations in the manufacturing process of large-scale carbon dioxide canisters is solved, efficient production and assembly is achieved, production costs are reduced and efficiency is improved.
Patent Information
- Application Number
- CN202411115384.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-08-14
- Publication Date
- 2024-11-15
AI Technical Summary
During the manufacturing process, large carbon dioxide canisters are limited by factory space and equipment resources, making it difficult to produce and assemble efficiently, resulting in high production costs.
The method of segmented production and total segment assembly is adopted, and large-scale carbon dioxide canisters are gradually assembled through manual arc welding and stress-removing heat treatment, and large-scale assembly is carried out in the field, using resources within the span to reduce plant space and equipment restrictions.
It effectively reduces production costs, improves production efficiency, and can use plant resources more reasonably, achieving efficient manufacturing of large carbon dioxide tanks.
Smart Images

Figure CN118959840A_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of liquid tank construction, and in particular relates to a large carbon dioxide tank and a construction method thereof. Background Art
[0002] In recent years, as the global temperature rises, climate change is having a lasting and profound impact on the world. Therefore, the goal is to control the increase in global average temperature to within 2 degrees Celsius compared with the pre-industrial period. Under the condition that it is impossible to completely abandon fossil energy, CCS technology is the key technical means and bottom-line technical guarantee to achieve the temperature control goal. At the same time, with the operation of the European carbon trading market, carbon dioxide has become a tradable commodity. The development of the LCO2 shipping market will greatly increase the transportation and trading volume of LCO2. As the core equipment of LCO2 ships, carbon dioxide liquid tanks have been favored by the market. The material P690QL2, which was used for carbon dioxide tanks for the first time, also has relatively mature performance. The welding materials matched with steel have been fully verified and quantitatively produced. A lot of research has been conducted on the production and manufacturing process, and experience has been accumulated in the manufacture of P690QL1 materials on liquid tanks. Summary of the invention
[0003] The purpose of the present invention is to provide a large carbon dioxide tank and a construction method, to prove the feasibility of using high-strength P690QL2 on C-type carbon dioxide tanks, and at the same time reduce the restrictions on the operation of large carbon dioxide tanks caused by the size of the factory space. It is not limited by the lifting capacity of the factory and the size of the heat treatment furnace space, so that site and equipment resources can be reasonably allocated and used to solve the problems raised in the above background technology.
[0004] To achieve the above object, the present invention provides the following technical solution: a large carbon dioxide tank, which is composed of a stern head, nine middle cylinder sections, a bow head, a top air chamber component and a bottom liquid collecting well component; wherein
[0005] The stern head and bow head are composed of twelve petals and six top circle segments;
[0006] The barrel section is composed of four barrel section plates;
[0007] The air chamber components are composed of a dish-shaped head, an air chamber cone and a lower cylinder section of the air chamber;
[0008] The liquid collecting well is composed of a liquid collecting well cover and a liquid collecting well shaft section;
[0009] The stern head and the barrel section constitute the A total section, at least two barrel sections constitute the BC total section, and the bow head and the barrel section constitute the D total section.
[0010] Preferably, the A total section is composed of a spherical stern head and cylindrical barrel sections A1 and A2.
[0011] Preferably, the total section B is composed of a pair of cylindrical sections B1, B2, and B3.
[0012] Preferably, the C total section is composed of a pair of cylindrical sections C1, C2, and C3.
[0013] Preferably, the D total section is composed of a spherical bow head and a cylindrical barrel section D1.
[0014] The present invention also discloses a method for constructing a large carbon dioxide tank, including a carbon dioxide tank, which specifically includes the following steps:
[0015] Step 1: Construct the main sections A, B, C, D and the air chamber and liquid collecting well components, and include the following steps:
[0016] S1, assemble and weld the cylinder section, accessories and head on the tire frame in the workshop. All welding is done by manual arc welding. Preheating before welding and post-heating after welding are required according to the corresponding WPS;
[0017] S2, determine the outsourcing manufacturer of the gas chamber and liquid collecting well head, and carry out outsourcing production and processing;
[0018] S3, assemble according to the general block diagram: the stern head, A1 cylinder section, A2 cylinder section are assembled into the closure general block A; B1 cylinder section, B2 cylinder section, B3 cylinder section are assembled into the closure general block B; C1 cylinder section, C2 cylinder section, C3 cylinder section are assembled into the closure general block C; cylinder section D1 and bow head are assembled into the closure general block D; all girth welds are preheated before welding and post-heated after welding according to the corresponding WPS;
[0019] S4, conduct nondestructive testing on the longitudinal circumferential welds of all the segments. After passing the test, install the pre-welded parts of each segment. After completion, transport the segment to the field.
[0020] Step 2: Perform stress relief heat treatment on the large closing section A, section B, section C, section D, the air chamber and the liquid collecting well components respectively:
[0021] S1, hoist the main section into the heat treatment furnace, put in the corresponding test plate according to the requirements of the list and install and connect the thermocouple;
[0022] S2, heating, heating and heat preservation according to the heat treatment process, air cooling after the heat preservation time is reached, pay attention to the changes in the heat treatment curve during the process, and strictly follow the requirements of the process documents. Specifically, the furnace temperature does not exceed 200℃ when entering the furnace, the heating rate is 300-340℃ / h, the insulation temperature is 550-570℃, the insulation time is 1-1.2min per millimeter of steel plate thickness, calculated according to the maximum plate thickness, and the cooling method is air cooling;
[0023] S3, according to the requirements of classification society regulations, non-destructive testing of the longitudinal circumferential seams of the total section shall be carried out after the cooling time reaches 72 hours;
[0024] Step 3: Complete the closing of the entire tank on the large closing frame and install the escalator platform inside the tank:
[0025] S1, first hoist the qualified closing section A onto the large closing frame, and at the same time install the tank ladder platform into section A;
[0026] S2, then hoist the qualified closing segments B, C, and D to the large closing frame for reasonable assembly;
[0027] S3, after acceptance, the large closure seam shall be welded according to WPS. The welding process shall be well controlled. The weld preheating temperature is 140-180℃. When welding begins, the steel plate surface temperature must be greater than 140℃. The weld post-heating temperature is 250-300℃, and the post-heating holding time is 2 hours.
[0028] S4: After passing the inspection, the large closing seam is subjected to stress relief heat treatment according to the heat treatment process, and the large closing seam is subjected to non-destructive testing again after cooling for 72 hours;
[0029] Step 4: Complete the assembly of the air chamber nozzle, and open holes on the tank to install the air chamber and liquid collecting well assembly:
[0030] S1, assemble the nozzle parts on the horizontal platform using the air chamber nozzle tooling, weld them according to the WPS requirements, and conduct non-destructive testing after the welding is completed and polished;
[0031] S2, positioning and marking on the tank body, opening the gas chamber and liquid collecting well installation opening;
[0032] S3, according to the process guidance, pre-install the air chamber assembly to mark out the margin of the upper opening of the air chamber lower cylinder section, leaving a margin of 10mm, that is, the height of the upper opening of the air chamber lower cylinder section from the center line of the tank bottom is theoretically +10mm, cut the margin of the upper opening of the air chamber lower cylinder section, re-planed and beveled the upper opening of the air chamber lower cylinder section, and then assembled it, and installed the air chamber components. The liquid collecting well will be installed after the internal parts in the tank are installed;
[0033] Step 5: Install the piping and outfitting parts. After the overall assembly is completed, install the main wood blocks:
[0034] S1, locate and install pipe supports, outfitting parts, etc. according to the markings in the drawing;
[0035] S2, after the whole tank is assembled and inspected, install the main wood block according to the wood block pasting process instruction;
[0036] Step 6: Tie down the frame and transfer the special platform for water pressure test to conduct water pressure test:
[0037] S1, after the wood block is cured, the carbon dioxide tank is hoisted onto the saddle bracket;
[0038] S2, tie according to the process requirements, and transport the carbon dioxide tank to the dedicated hydraulic platform by the module trolley; the details are as follows
[0039] ①. Lay soft pine wood between the saddle and the tank block. The tank block must not come into contact with the saddle;
[0040] ②. H-shaped steel is used to connect the saddles, and X-shaped steel is used to strengthen the connection in the middle;
[0041] ③. The two sides of the saddle and the anti-floating ribs of the liquid tank are firmly connected by 7-shaped connecting plates;
[0042] S3, install hydraulic blind plate, safety valve, pressure gauge and other supporting components, and conduct hydraulic pressure test according to hydraulic pressure process requirements;
[0043] Step 7: Sandblast the inside and outside of the carbon dioxide tank and move it to the wind and rain shed for insulation work:
[0044] S1, after the water pressure test is passed, the carbon dioxide tank is moved to the sandblasting room and the inner and outer surfaces of the tank are sandblasted;
[0045] S2, move the carbon dioxide tank into the awning, set up the scaffolding and perform the spray insulation operation according to the insulation construction process;
[0046] Step 8: Comprehensively inspect, clean, seal, and tie up the CO2 tank for shipment:
[0047] S1, after the insulation construction is completed, the inside and outside of the tank are fully inspected and the remaining parts are installed;
[0048] S2, after comprehensive inspection and repair of the inside and outside of the CO2 tank, clean it according to the process documents;
[0049] The specific process documents are as follows:
[0050] ①. Empty all the accumulated water in the tank and use high-pressure water to flush the tank pipeline; after the treatment, cover all the pipe openings with 2 layers of protective cloth to ensure that sandblasting or foreign objects will not enter and cause contamination;
[0051] ②. Use a dryer to dehumidify the air and remove rust and polish the inside of the tank;
[0052] ③. After the dust settles, blow away the dust on the surface of the three-proof cloth and vacuum the bottom;
[0053] ④. Use compressed air to purge the pipeline to ensure that it is unobstructed and clean;
[0054] ⑤. Use a sticky roller to remove dust from the tank body and platform; the tank should always be filled with dry air to ensure that the humidity inside the tank meets the standard;
[0055] It should be noted that all personnel entering the liquid tank should wear airtight gloves and shoe covers to prevent rust caused by sweat;
[0056] S3, fill the cabin with nitrogen and seal it according to the process requirements;
[0057] S4. Tie the CO2 tank to the saddle securely according to the tying diagram and ship on time.
[0058] Preferably, when implementing S1 of step one, the longitudinal seams of the cylinder sections are preheated according to the process regulations before being assembled, and positioning welding is performed after reaching the preheating temperature requirement. Due to the characteristics of high-strength steel such as P690QL2, at least two positioning welds are required, with the lengths of both ends not less than 400 mm and the middle length not less than 250 mm, otherwise it is easy to crack. The weld needs to be preheated before formal welding. Due to the characteristics of P690QL2 high-strength steel, the preheating temperature requires a relative temperature, so the weld is heated by a double-sided heating plate.
[0059] Preferably, when implementing S3 of step one, the entire carbon dioxide liquid tank is divided into four sections, which are manufactured in the bay. The A section of the stern head is lifted and turned over by a combination of a shaft hoist and a lifting lug; the sections B and C are lifted and turned over by arranging them on the inner side of the upper opening and the outer side of the lower opening of the sections; the D section of the bow head is lifted and turned over by arranging lifting lugs on the outer side of the head and the cylinder respectively.
[0060] Compared with the prior art, the present invention has the following beneficial effects:
[0061] In the present invention, the segments and the whole sections are manufactured within the span, and the independent whole sections are assembled in the outside field, thereby reducing the restriction of the plant space size on the operation of large towers, and is not limited by the lifting capacity of the plant and the size of the heat treatment furnace space. The resources within the plant can be used more reasonably, and the production cost of the enterprise is greatly reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0062] Figure 1 It is a structural schematic diagram of the present invention;
[0063] Figure 2 It is a schematic diagram of the structure of each general section of the present invention;
[0064] Figure 3 A state diagram of a general section of step 2 of the present invention;
[0065] Figure 4 It is a state diagram of step three of the present invention.
[0066] In the figure:
[0067] 1. Stern head cover; 2. Bow head cover;
[0068] 3. Air chamber components; 31. Disc-shaped head; 32. Air chamber cone; 33. Air chamber lower cylinder section;
[0069] 4. Liquid collecting well; 41. Liquid collecting well cap; 42. Liquid collecting well shaft section. DETAILED DESCRIPTION
[0070] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0071] See also Figures 1 to 4 The present invention provides a technical solution: a large carbon dioxide tank, which is composed of a stern head 1, nine middle cylinder sections, a bow head 2, a top air chamber component 3 and a bottom liquid collecting well 4; wherein
[0072] The stern head 1 and the bow head 2 are composed of twelve petals and six top circle segments;
[0073] The barrel section is composed of four barrel section plates;
[0074] The air chamber component 3 is composed of a dish-shaped head 31, an air chamber cone 32 and an air chamber lower cylinder section 33;
[0075] The liquid collecting well 4 is composed of a liquid collecting well cover 41 and a liquid collecting well section 42;
[0076] The stern head 1 and the cylinder segment constitute the A total section, at least two cylinder segments constitute the BC total section, and the bow head 2 and the cylinder segment constitute the D total section.
[0077] In this embodiment, preferably, the A total section is composed of a spherical stern head 1 and cylindrical barrel sections A1 and A2.
[0078] In this embodiment, preferably, the total section B is composed of a pair of cylindrical sections B1, B2, and B3.
[0079] In this embodiment, preferably, the total section C is composed of a pair of cylindrical sections C1, C2, and C3.
[0080] In this embodiment, preferably, the D section is composed of a spherical bow head 2 and a cylindrical barrel section D1.
[0081] The present invention also discloses a method for constructing a large carbon dioxide tank, including a carbon dioxide tank, which specifically includes the following steps:
[0082] Step 1: construct the four components of the total sections A, B, C, D and the air chamber and liquid collecting well, and include the following steps:
[0083] S1, assemble and weld the cylinder section, accessories and head on the tire frame in the workshop. All welding is done by manual arc welding. Preheating before welding and post-heating after welding are required according to the corresponding WPS;
[0084] S2, determine the outsourcing manufacturer of the gas chamber and the liquid collecting well 4 heads, and carry out outsourcing production and processing;
[0085] S3, assemble according to the general section drawing: stern head 1, A1 cylinder section, A2 cylinder section are assembled into the combined general section A; B1 cylinder section, B2 cylinder section, B3 cylinder section are assembled into the combined general section B; C1 cylinder section, C2 cylinder section, C3 cylinder section are assembled into the combined general section C; cylinder section D1 and bow head 2 are assembled into the combined general section D; all girth welds are preheated before welding and post-heated after welding according to the corresponding WPS;
[0086] S4, conduct nondestructive testing on the longitudinal circumferential welds of all the segments. After passing the test, install the pre-welded parts of each segment. After completion, transport the segment to the field.
[0087] Step 2: Perform stress relief heat treatment on the four components of the large closing section A, section B, section C, section D, the air chamber and the liquid collecting well respectively:
[0088] S1, hoist the main section into the heat treatment furnace, put in the corresponding test plate according to the requirements of the list and install and connect the thermocouple;
[0089] S2, heating, heating and heat preservation according to the heat treatment process, air cooling after the heat preservation time is reached, pay attention to the changes in the heat treatment curve during the process, and strictly follow the requirements of the process documents. Specifically, the furnace temperature does not exceed 200℃ when entering the furnace, the heating rate is 300-340℃ / h, the insulation temperature is 550-570℃, the insulation time is 1-1.2min per millimeter of steel plate thickness, calculated according to the maximum plate thickness, and the cooling method is air cooling;
[0090] S3, according to the requirements of classification society regulations, non-destructive testing of the longitudinal circumferential seams of the total section shall be carried out after the cooling time reaches 72 hours;
[0091] Step 3: Complete the closing of the entire tank on the large closing frame and install the escalator platform inside the tank:
[0092] S1, first hoist the qualified closing section A onto the large closing frame, and at the same time install the tank ladder platform into section A;
[0093] S2, then hoist the qualified closing segments B, C, and D to the large closing frame for reasonable assembly;
[0094] S3, after acceptance, the large closure seam shall be welded according to WPS. The welding process shall be well controlled. The weld preheating temperature is 140-180℃. When welding begins, the steel plate surface temperature must be greater than 140℃. The weld post-heating temperature is 250-300℃, and the post-heating holding time is 2 hours.
[0095] S4: After passing the inspection, the large closing seam is subjected to stress relief heat treatment according to the heat treatment process, and the large closing seam is subjected to non-destructive testing again after cooling for 72 hours;
[0096] Step 4: Complete the assembly of the air chamber nozzle, and open holes on the tank to install the air chamber and liquid collecting well 4 components:
[0097] S1, assemble the nozzle parts on the horizontal platform using the air chamber nozzle tooling, weld them according to the WPS requirements, and conduct non-destructive testing after the welding is completed and polished;
[0098] S2, positioning and marking on the tank body, opening the gas chamber and the liquid collecting well 4 for installation;
[0099] S3, according to the process guidance, pre-assemble the air chamber assembly to mark the margin of the upper opening of the lower cylinder section of the air chamber, leaving a margin of 10mm, that is, the height of the upper opening of the lower cylinder section of the air chamber from the center line of the tank bottom is theoretically +10mm, cut the margin of the upper opening of the lower cylinder section of the air chamber, re-planed and beveled the upper opening of the lower cylinder section of the air chamber, and then assembled, and installed the air chamber component 3, and the liquid collecting well 4 will be installed after the installation of the internal parts in the tank is completed;
[0100] Step 5: Install the piping and outfitting parts. After the overall assembly is completed, install the main wood blocks:
[0101] S1, locate and install pipe supports, outfitting parts, etc. according to the markings in the drawing;
[0102] S2, after the whole tank is assembled and inspected, install the main wood block according to the wood block pasting process instruction; the details are as follows:
[0103] ①. The construction party should be careful not to lose or damage the wood blocks during the installation process;
[0104] ②. The wooden blocks at the fixed and sliding supports are glued to the corresponding positions of the tank body and fixed with flat steel;
[0105] ③. Before applying glue to the liquid tank, the rust, oil stains and other debris on the contact surface must be cleaned and kept dry;
[0106] ④. Apply the uniformly stirred adhesive (JM-98) to the liquid tank within 2 hours. The gaps between the wood block and the shell and the support plate, and between the wood blocks must be filled with glue without any gaps. The wood blocks must be tapped firmly after being glued to the tank body, and the unevenness of the surface and side of adjacent wood blocks must be ≤2mm;
[0107] ⑤. After gluing, the wood blocks are tied and tightened with steel wire ropes. The wood blocks can be loosened about 24 hours after the glue solidifies. After the steel wire ropes are loosened, the wood blocks need to be fixed with flat steel tie rods. The flat steel tie rods must be removed mechanically when the liquid tanks are loaded on board.
[0108] ⑥. If there are any unevenness at the joints of the wood blocks, they must be polished and smoothed;
[0109] Step 6: Tie down the frame and transfer the special platform for water pressure test to conduct water pressure test:
[0110] S1, after the wood block is cured, the carbon dioxide tank is hoisted onto the saddle bracket;
[0111] S2, tie according to the process requirements, and transport the carbon dioxide tank to the dedicated hydraulic platform by the module trolley; the details are as follows
[0112] ①. Lay soft pine wood between the saddle and the tank block. The tank block must not come into contact with the saddle;
[0113] ②. H-shaped steel is used to connect the saddles, and X-shaped steel is used to strengthen the connection in the middle;
[0114] ③. The two sides of the saddle and the anti-floating ribs of the liquid tank are firmly connected by 7-shaped connecting plates;
[0115] S3, install hydraulic blind plate, safety valve, pressure gauge and other supporting components, and conduct hydraulic pressure test according to hydraulic process requirements; the specific process requirements are as follows:
[0116] ①. Confirm the position of the liquid tank on the hydraulic support and check all measuring equipment;
[0117] ②. Add water when all the air chamber ports are open;
[0118] ③. Before closing the air chamber pipe opening, continue to add water at a smaller water volume to allow the water to overflow, so as to release the residual air in the pipe system and the corners of the tank;
[0119] ④. Seal all air chamber openings with blind flanges and temporary sealing rings;
[0120] ⑤. Use a pressure pump to gradually pressurize the fuel tank to (0.5 times the test pressure), maintain the pressure for 10 minutes, and the maximum pressurization rate is 0.3 bar / minute;
[0121] ⑥ During the pressure holding time, all welds should be checked for tightness, and the outer surface of the tank should be kept dry and free of moisture and condensed water, and the temperature and pressure values should be recorded at the same time;
[0122] ⑦. Use a pressure pump to gradually pressurize the fuel tank to the test pressure, maintain the pressure for the time required by the specification, and the maximum pressurization rate is 0.3 bar / minute. At the same time, check and record;
[0123] ⑧. Reduce pressure to design pressure and maintain design pressure for 10 minutes. The maximum rate of pressure reduction is 0.3 bar / minute. Check and record at the same time.
[0124] ⑨. Reduce the pressure to 0 and start draining. When draining, make sure to open enough pipe openings to prevent negative pressure from forming in the tank;
[0125] Step 7: Sandblast the inside and outside of the carbon dioxide tank and move it to the wind and rain shed for insulation work:
[0126] S1, after the water pressure test is passed, the carbon dioxide tank is moved to the sandblasting room and the inner and outer surfaces of the tank are sandblasted;
[0127] S2, move the carbon dioxide tank into the awning, set up the scaffolding and perform the spray insulation operation according to the insulation construction process;
[0128] Step 8: Comprehensively inspect, clean, seal, and tie up the CO2 tank for shipment:
[0129] S1, after the insulation construction is completed, the inside and outside of the tank are fully inspected and the remaining parts are installed;
[0130] S2, after comprehensive inspection and repair of the inside and outside of the CO2 tank, clean it according to the process documents;
[0131] The specific process documents are as follows:
[0132] ①. Empty all the accumulated water in the tank and use high-pressure water to flush the tank pipeline; after the treatment, cover all the pipe openings with 2 layers of protective cloth to ensure that sandblasting or foreign objects will not enter and cause contamination;
[0133] ②. Use a dryer to dehumidify the air and remove rust and polish the tank;
[0134] ③. After the dust settles, blow away the dust on the surface of the three-proof cloth and vacuum the bottom;
[0135] ④. Use compressed air to purge the pipeline to ensure that it is unobstructed and clean;
[0136] ⑤. Use a sticky roller to remove dust from the tank body and platform; the tank should always be filled with dry air to ensure that the humidity inside the tank meets the standard;
[0137] It should be noted that all personnel entering the liquid tank should wear airtight gloves and shoe covers to prevent rust caused by sweat;
[0138] S3, fill the cabin with nitrogen and seal it according to the process requirements;
[0139] S4. Tie the CO2 tank to the saddle securely according to the tying diagram and ship on time.
[0140] In this embodiment, preferably, when implementing S1 of step one, the longitudinal seams of the cylinder sections are preheated according to the process regulations before being assembled, and positioning welding is performed after reaching the preheating temperature requirement. Due to the characteristics of high-strength steel such as P690QL2, at least two positioning welds are required, with the lengths of both ends not less than 400 mm and the middle length not less than 250 mm, otherwise it is easy to crack. The weld needs to be preheated before formal welding. Due to the characteristics of P690QL2 high-strength steel, the preheating temperature requires a relative temperature, so the weld is heated by a double-sided heating plate.
[0141] In this embodiment, preferably, when implementing S3 of step one, the entire carbon dioxide liquid tank is divided into four main sections, which are manufactured in the bay. The main section A of the stern head 1 is lifted and turned over by a combination of an axle hoist and a lifting lug; the main sections B and C are lifted and turned over by arrangements on the inner side of the upper opening and the outer side of the lower opening of the main sections; the main section D of the bow head 2 is lifted and turned over by respectively arranging lifting lugs on the outside of the head and the cylinder.
[0142] Although embodiments of the present invention have been shown and described (see the above detailed description for details), it will be appreciated by those skilled in the art that various changes, modifications, substitutions and variations may be made to these embodiments without departing from the principles and spirit of the present invention, and the scope of the present invention is defined by the appended claims and their equivalents.
Claims
1. A large carbon dioxide tank, characterized in that: The carbon dioxide liquid tank is composed of a stern head (1), nine middle cylinder sections, a bow head (2), a top air chamber component (3) and a bottom liquid collecting well (4); wherein The stern head (1) and the bow head (2) are composed of twelve petals and six top circle segments; The barrel section is composed of four barrel section plates; The air chamber component (3) is composed of a dish-shaped head (31), an air chamber cone (32) and an air chamber lower cylinder section (33); The liquid collecting well (4) is composed of a liquid collecting well sealing head (41) and a liquid collecting well shaft section (42); The stern head (1) and the barrel section form a total section A, at least two barrel sections form a total section BC, and the bow head (2) and the barrel section form a total section D.
2. A large carbon dioxide tank according to claim 1, characterized in that: The A total section is composed of a spherical stern head (1) and cylindrical barrel sections A1 and A2.
3. A large carbon dioxide tank according to claim 1, characterized in that: The B total section is composed of cylindrical sections B1, B2, and B3.
4. A large carbon dioxide tank according to claim 1, characterized in that: The C total section is composed of cylindrical sections C1, C2, and C3.
5. A large carbon dioxide tank according to claim 1, characterized in that: The D total section is composed of a spherical bow head (2) and a cylindrical barrel section D1.
6. A method for constructing a large carbon dioxide tank, comprising the carbon dioxide tank according to any one of claims 1 to 5, characterized in that: The specific steps include: Step 1: construct the overall sections A, B, C, D and the air chamber and liquid collecting well (4) components, and includes the following steps: S1, assemble and weld the cylinder section, accessories and head on the tire frame in the workshop. All welding is done by manual arc welding. Preheating before welding and post-heating after welding are required according to the corresponding WPS; S2, determine the outsourcing manufacturer of the gas chamber and liquid collecting well (4) end caps and carry out outsourcing production and processing; S3, assemble according to the block diagram: the stern head (1), A1 cylinder section, A2 cylinder section are assembled into the assembled block A; the B1 cylinder section, B2 cylinder section, B3 cylinder section are assembled into the assembled block B; the C1 cylinder section, C2 cylinder section, C3 cylinder section are assembled into the assembled block C; the cylinder section D1 and the bow head (2) are assembled into the assembled block D; all girth welds are preheated before welding and post-heated after welding according to the corresponding WPS; S4, conduct nondestructive testing on the longitudinal circumferential welds of all the segments. After passing the test, install the pre-welded parts of each segment. After completion, transport the segment to the field. Step 2: Perform stress relief heat treatment on the large closing section A, section B, section C, section D, the air chamber and the liquid collecting well (4) components respectively: S1, hoist the main section into the heat treatment furnace, put in the corresponding test plate according to the requirements of the list and install and connect the thermocouple; S2, heating, heating and heat preservation according to the heat treatment process, air cooling after the heat preservation time is reached, paying attention to the changes of the heat treatment curve during the process, and strictly following the requirements of the process documents; S3, according to the requirements of classification society regulations, non-destructive testing of the longitudinal circumferential seams of the total section shall be carried out after the cooling time reaches 72 hours; Step 3: Complete the closing of the entire tank on the large closing frame and install the escalator platform inside the tank: S1, first hoist the qualified closing section A onto the large closing frame, and at the same time install the tank ladder platform into section A; S2, then hoist the qualified closing segments B, C, and D to the large closing frame for reasonable assembly; S3, after acceptance, weld the large closing seam according to WPS, and the welding process must be well controlled; S4: After passing the inspection, the large closing seam is subjected to stress relief heat treatment according to the heat treatment process, and the large closing seam is subjected to non-destructive testing again after cooling for 72 hours; Step 4: Complete the assembly of the air chamber nozzle, and open a hole on the tank body to install the air chamber and liquid collecting well (4) components: S1, assemble the nozzle parts on the horizontal platform using the air chamber nozzle tooling, weld them according to the WPS requirements, and conduct non-destructive testing after the welding is completed and polished; S2, positioning and marking the tank body, and opening the gas chamber and the liquid collecting well (4) for installation; S3, according to the process guidance, the pre-installed air chamber assembly is marked out with a margin of 10mm on the upper opening of the air chamber lower cylinder section, that is, the height of the upper opening of the air chamber lower cylinder section from the center line of the tank bottom is theoretically +10mm, the margin of the upper opening of the air chamber lower cylinder section is cut, the upper opening of the air chamber lower cylinder section is re-planed and beveled, and then assembled, and the air chamber component (3) is installed. The liquid collecting well (4) is installed after the internal parts in the tank are installed; Step 5: Install the piping and outfitting parts. After the overall assembly is completed, install the main wood blocks: S1, locate and install pipe supports, outfitting parts, etc. according to the markings in the drawing; S2, after the whole tank is assembled and inspected, install the main wood block according to the wood block pasting process instruction; Step 6: Tie down the frame and transfer the special platform for water pressure test to conduct water pressure test: S1, after the wood block is cured, the carbon dioxide tank is hoisted onto the saddle bracket; S2, lashing is performed according to the process requirements, and the CO2 tank is transferred to the dedicated hydraulic platform by the module trolley; S3, install hydraulic blind plate, safety valve, pressure gauge and other supporting components, and conduct hydraulic pressure test according to hydraulic pressure process requirements; Step 7: Sandblast the inside and outside of the carbon dioxide tank and move it to the wind and rain shed for insulation work: S1, after the water pressure test is passed, the carbon dioxide tank is moved to the sandblasting room and the inner and outer surfaces of the tank are sandblasted; S2, move the carbon dioxide tank into the awning, set up the scaffolding and perform the spray insulation operation according to the insulation construction process; Step 8: Comprehensively inspect, clean, seal, and tie up the CO2 tank for shipment: S1, after the insulation construction is completed, the inside and outside of the tank are fully inspected and the remaining parts are installed; S2, after comprehensive inspection and repair of the inside and outside of the CO2 tank, clean it according to the process documents; S3, fill the cabin with nitrogen and seal it according to the process requirements; S4. Tie the CO2 tank to the saddle securely according to the tying diagram and ship on time.
7. The method for constructing a large carbon dioxide tank according to claim 6, characterized in that: When implementing S1 of step 1, the longitudinal seams of the cylinder sections are preheated according to the process requirements before being assembled, and positioning welding is performed after the preheating temperature requirement is reached.
8. The method for constructing a large carbon dioxide tank according to claim 6, characterized in that: When implementing S3 of step 1, the entire carbon dioxide liquid tank is divided into four sections and manufactured in the bay. The A section of the stern head (1) is lifted and turned over by a combination of a shaft hanger and a lifting lug; the B section and the C section are lifted and turned over by arranging the inside of the upper opening and the outside of the lower opening of the section; the D section of the bow head (2) is lifted and turned over by arranging the lifting lugs on the outside of the head and the cylinder respectively.
Citation Information
Patent Citations
Liquefied natural gas shipborne dual-body storage tank and manufacturing method thereof
CN110356512A
Large tower and construction method
CN116025213A
Construction process of C-shaped three-body tank independent liquid cargo tank
CN116750160A
Manufacturing process of marine ammonia fuel tank
CN117961436A
Cargo tank for low-pressure liquid carbon dioxide ship
CN220749812U