Calculation method and system for pavement engineering quantity of typical intersection

By obtaining the geometric characteristic index of the intersection and deriving the calculation formula, combined with VBA development tools, the accuracy and efficiency of the intersection project volume calculation in the existing technology are solved, and high-precision and high-efficiency calculation of the intersection pavement project volume is achieved.

CN118965544APending Publication Date: 2024-11-15TIANJIN MUNICIPAL ENGINEERING DESIGN & RESEARCH INSTITUTE CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411198766.5
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-29
Publication Date
2024-11-15

AI Technical Summary

Technical Problem

The prior art has insufficient accuracy and complexity in formulas when calculating the engineering volume of road intersections, resulting in problems of deviation in calculation results and low efficiency.

Method used

By obtaining indicators that characterize the geometric characteristics of the intersection, an accurate calculation formula for the intersection pavement is derived, and a VBA development tool is used to create an intersection engineering calculation system to simplify the interface and improve the calculation efficiency.

Benefits of technology

High-precision engineering volume calculation for intersections without partitions is realized, which reduces the work complexity of designers and improves calculation efficiency. It is suitable for complex road projects at multiple intersections and reduces calculation errors.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118965544A_ABST
    Figure CN118965544A_ABST
Patent Text Reader

Abstract

The invention discloses a typical intersection pavement engineering quantity calculation method and system, and the calculation method comprises the steps: S1, obtaining indexes representing the geometric characteristics of an intersection, including a general index, a roadway index and a road red line index; s2, constructing an intersection pavement engineering quantity calculation model; comprising the steps of solving the area of an upper layer of an intersection roadway, the area surrounded by intersection road red lines and the length of curbs; s3, constructing an engineering quantity calculation model of each structural layer of the pavement; comprising solving the area of each structural layer of the roadway pavement and the area of each structural layer of the sidewalk pavement. According to the method, the key indexes representing the geometric characteristics of the intersection are extracted and utilized for the typical separation-zone-free cross intersection in actual engineering. By accurately calculating the area of each structural layer of the roadway and the sidewalk and the length of the curb, the problem that the accuracy is insufficient when a traditional calculation method is used for processing a complex intersection is solved, and therefore it is ensured that the calculation result is highly matched with the actual construction requirement.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the field of road engineering design, and in particular to a method and system for calculating the engineering quantity of a typical intersection pavement. Background Art

[0002] In the field of road engineering design, compiling a pavement engineering quantity table is a common task for designers. The pavement engineering quantity table compiled by designers mainly includes the area of ​​each pavement structure layer of the carriageway and sidewalk, the length of the side curb, and the area of ​​geosynthetics (anti-seepage geotextile, fiberglass grid) used for pavement construction and overlap. The compiled pavement engineering quantity table can facilitate relevant professionals to perform calculations related to engineering costs and compile a bill of quantities, which serves as an important basis for measurement and payment during engineering bidding, tendering and implementation.

[0003] When the road engineering quantity is classified according to the road line shape, it is mainly composed of the engineering quantity of the straight line, curve section, and intersection section of the road. The calculation of the engineering quantity of the intersection section is relatively complicated due to its complex geometric form. When designers compile the pavement engineering quantity table, they mainly use two methods to calculate the engineering quantity. The first method is to use the calculation formula. This calculation method currently has the following two problems:

[0004] 1. Lack of accuracy: For roads with intersections, the existing calculation formula cannot accurately calculate the engineering volume of road intersections, resulting in a deviation between the calculated pavement engineering volume and the actual amount.

[0005] 2. The formulas are complex and lack practicality: When designers use EXCEL tables to edit formulas, the formulas are complex, resulting in a messy interface and making it difficult to apply and promote.

[0006] The second method is to use AutoCAD software to circle the road outline in the road plan, count the road surface area and curb length, and calculate the road surface engineering volume.

[0007] This calculation method is relatively accurate, but it takes a lot of time when encountering road projects with many intersections. If the drawings are subsequently modified, the road contour needs to be re-circled and calculated, which is time-consuming, labor-intensive and inefficient. Summary of the invention

[0008] The purpose of the present invention is to overcome the deficiencies in the prior art and to provide a method and system for calculating the pavement engineering quantities of a typical intersection. For a typical intersection without a dividing strip, an accurate calculation formula for the pavement engineering quantities of the intersection is derived by capturing indicators that characterize the characteristics of the intersection, and a VBA development tool is used to create an intersection engineering quantity calculation system. The system meets the accuracy of the calculation and has a simple interface. It can greatly improve the work efficiency of designers and is worthy of application and promotion.

[0009] The objective of the present invention is achieved through the following technical solutions:

[0010] A calculation method for typical intersection pavement engineering quantity, applicable to cross-shaped road intersections without dividing strips, and the road red line corner type of the intersection is symmetrical cutting angle, including:

[0011] S1. Obtaining indicators representing geometric features of the intersection, including general indicators, lane indicators, and road redline indicators;

[0012] S2. Construct a calculation model for the intersection pavement engineering quantity; including the solution of the intersection road surface area, the intersection road red line area and the curb length;

[0013] S3. Construct a calculation model for the engineering quantity of each structural layer of the road surface; including the solution of the area of ​​each structural layer of the road surface for vehicles and the area of ​​each structural layer of the road surface for pedestrians.

[0014] 11. The method for calculating the typical intersection pavement engineering quantity according to claim 1, characterized in that, in step S1, the general indicators include the vertical road length L1, the horizontal road length L2 and the centerline angle α of the intersecting roads;

[0015] The lane indicators include vertical lane width W1, transverse lane width W2, lane corner small guide circle radius R1, and lane corner large guide circle radius R2;

[0016] The road red line indicators include the vertical road red line width W1′, the horizontal road red line width W2′, the road red line small cut angle length K1, the road red line large cut angle length K2, the road red line small cut angle arc radius r1, and the road red line large cut angle arc radius r2.

[0017] Furthermore, in step S2, the surface area S of the intersection roadway C for:

[0018] S C =S1+S2 (1)

[0019] S1 is the area of ​​the intersection excluding the shaded part of the corner, and S2 is the sum of the areas of the shaded parts of the corners;

[0020] S1=L2×W2+(L1-X)×W1 (2)

[0021] X=W2 / sinα (3)

[0022] Substituting (3) into (2), we get:

[0023]

[0024] Among them, L1 is the vertical road length, L2 is the horizontal road length, W1 is the vertical lane width, W2 is the horizontal lane width; α is the angle between the center lines of the intersecting roads; the area of ​​S2 is composed of two With 2 The area of ​​R1 and R2 is composed of and To solve:

[0025]

[0026] Substituting (6) into (5), we get:

[0027]

[0028] Similarly:

[0029]

[0030]

[0031] Substituting (9) into (8), we get:

[0032]

[0033] From this we can get:

[0034]

[0035] The areas of S1 and S2 are calculated respectively. Substituting equations (4) and (11) into equation (1), we get:

[0036]

[0037] Formula (12) is the formula for calculating the surface area of ​​the carriageway at a typical intersection.

[0038] Further, in step S2,

[0039] Assume that the length of the small cut angle of the intersection road red line and the length of the large cut angle of the intersection road red line are K1 and K2 respectively, that is, calculate the area S enclosed by the intersection road red line H for:

[0040] S H =S1′+S2′ (13)

[0041] S1′ is the area of ​​the intersection excluding the shaded part of the corner, and S2′ is the sum of the areas of the shaded parts of the corners. The solution method for S1′ is the same as that for S1, see formula (14):

[0042]

[0043] S2′ is regarded as the shadow area corresponding to the radius of the small cut-angle arc of the road red line r1 and the radius of the large cut-angle arc of the road red line r2, which contains 2 With 2 Now calculate the shaded area S corresponding to r1 and r2 respectively r1 , S r2 To solve:

[0044]

[0045] Substituting (16) into (15), we obtain:

[0046]

[0047] Substituting (19) into (18), we obtain:

[0048]

[0049] Get the area of ​​S2′:

[0050]

[0051] The areas of S1′ and S2′ are calculated respectively. Substituting equations (14) and (21) into (13), we get:

[0052]

[0053] According to formula (22), the area enclosed by the intersection road red line can be calculated.

[0054] Further, in step S2, the types of curbstones on the road surface of the intersection include type A curbstones and type B curbstones, wherein the type A curbstones are located at the outer edge of the roadway of the intersection, and the type B curbstones are located at the outer edge of the sidewalk of the intersection;

[0055] (1) Length of Type A curbstone L A for:

[0056] L A =2×(L1+L2)-2×(m1+m2)-4×(x1+x2)+2×(c R1 +c R2 ) (twenty three)

[0057]

[0058] Wherein, L1 is the vertical road length, L2 is the horizontal road length, W1 is the vertical road width, W2 is the horizontal road width; α is the angle between the center lines of the intersecting roads; R1 and r2 are the small guide circle radius of the road corner and the large guide circle radius of the road corner;

[0059] Substituting (24)-(26) into (23), we obtain

[0060]

[0061] (2) Length of Type B curbstone L B for:

[0062] L B =2×(L1+L2)-2×(m1+m2)-4×(r1+r2)+2×(K1+K2) (28)

[0063] Substituting formula (24) into (28), we get:

[0064]

[0065] Among them, K1 and K2 are the small angle cut length and large angle cut length of the road red line at the intersection respectively.

[0066] Furthermore, in step S3, the area of ​​each structural layer of the road surface includes the area of ​​the upper layer, the area of ​​the middle layer, the area of ​​the lower layer, the area of ​​the upper base layer, the area of ​​the lower base layer and the area of ​​the bottom base layer; the upper layer area S of the intersection road surface C Obtained from step S2;

[0067] The area of ​​the middle surface layer is: S c +(S d2 / H c2 )×L A / 100;S d2 is the equivalent area of ​​the edge of the mid-surface layer, H c2 is the thickness of the middle surface layer; L A is the length of type A curb; S d2 =W d2 ×H d2 , W d2 , H d2 are the edge width and edge thickness of the mid-surface layer, respectively;

[0068] The area of ​​the lower layer is: S c +(S d3 / H c3 )×L A / 100;S d3 is the equivalent area of ​​the lower layer edge, H c3 is the thickness of the lower layer; S d3 =W d3 ×H d3 , W d3 , H d3 are the edge width and edge thickness of the lower layer, respectively;

[0069] The area of ​​the upper base is: S c +(Sd4 / H c4 )×L A / 100;S d4 is the equivalent area of ​​the upper base edge, H c4 is the thickness of the upper base layer; S d4 =W d4 ×H d4 , W d4 , H d4 are the edge width and edge thickness of the upper base layer respectively;

[0070] The area of ​​the lower base is: S c +(S d5 / H c5 )×L A / 100;S d5 is the equivalent area of ​​the lower base edge, H c5 is the thickness of the lower base; S d5 =W d5 ×H d5 , W d5 , H d5 are the edge width and edge thickness of the lower base layer respectively;

[0071] The base area is: S c +(S d6 / H c6 )×L A / 100;S d6 is the equivalent area of ​​the base layer edge, H c6 is the thickness of the base layer; S d6 =W d6 ×H d6 , W d6 , H d6 They are the edge width and edge thickness of the base layer respectively.

[0072] Furthermore, in step S3, the sidewalk surface area s R is the area enclosed by the intersection road red line s H The surface area of ​​the intersection roadway s C The difference, that is

[0073] s R =S H -S C (30)

[0074] The area of ​​the floor below the sidewalk is: s R +(s d2 / h R2 )×L B / 100;L B is the length of type B curbstone, S d2is the equivalent area of ​​the sidewalk surface edge, H R2 is the thickness of the layer below the sidewalk;

[0075] The area of ​​the base layer on the sidewalk is: S R +(S d3 / H R3 )×L B / 100;S d3 is the equivalent area of ​​the upper base edge of the sidewalk, H R3 is the thickness of the base layer on the sidewalk;

[0076] The area of ​​the sidewalk subbase is: S R +(S d4 / H R4 )×L B / 100;S d4 is the equivalent area of ​​the sidewalk subbase edge, H R4 is the thickness of the sidewalk subbase;

[0077] Where S d2 , S d3 , S d4 Obtained in combination with the edge structure of the specific drawing.

[0078] The present invention also provides a calculation system for typical intersection pavement engineering quantities, based on the calculation method for typical intersection pavement engineering quantities, comprising:

[0079] A login module, used to log into the computing system;

[0080] An input module, used for inputting intersection geometric characteristic indicators, including general indicators, lane indicators and road red line indicators;

[0081] The general indicators include the vertical road length L1, the horizontal road length L2 and the angle α between the center lines of the intersecting roads;

[0082] The lane indicators include vertical lane width W1, horizontal lane width W2, lane corner small guide circle radius R1, lane corner large guide circle radius R2;

[0083] The road red line indicators include the vertical road red line width W1′, the horizontal road red line width W2′, the road red line small cut angle length K1, the road red line large cut angle length K2, the road red line small cut angle arc radius r1, and the road red line large cut angle arc radius r2;

[0084] A calculation module is used to calculate the area of ​​each structural layer of the road surface, the area of ​​each structural layer of the sidewalk surface and the length of the curb;

[0085] Output module outputs calculation results and realizes the calculation of typical intersection pavement engineering quantities.

[0086] The present invention also provides an electronic device, comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, wherein the processor implements the steps of the method for calculating the typical intersection pavement engineering quantity when executing the program.

[0087] The present invention also provides a computer-readable storage medium on which a computer program is stored. When the computer program is executed by a processor, the steps of the method for calculating the typical intersection pavement engineering quantity are implemented.

[0088] Compared with the prior art, the technical solution of the present invention has the following beneficial effects:

[0089] 1. High-precision engineering quantity calculation: This invention extracts and utilizes key indicators that characterize the geometric characteristics of intersections, such as road length, carriageway width, corner guide radius, etc., for common undivided intersections in actual projects, and provides a set of accurate engineering quantity calculation formulas. These formulas can accurately calculate the area of ​​each structural layer of the carriageway and sidewalk and the length of the curb, solving the problem of insufficient accuracy of traditional calculation methods when dealing with complex intersections, thereby ensuring that the calculation results are highly consistent with actual construction requirements. This method can be widely applied to most intersections in actual road projects and has strong practicality.

[0090] 2. Easy operation and intuitive system: Based on the precise calculation method, the present invention uses VBA development tools to produce an integrated calculation system. The system interface is concise and easy to operate, and can quickly and intuitively complete the calculation of intersection pavement engineering quantities, greatly reducing the complexity of the designer's work. Through this system, designers can easily input data and immediately obtain accurate calculation results, avoiding calculation errors caused by complex formulas and manual operations in traditional methods. And the visualization of the calculation is realized, which can realize the rapid solution of pavement engineering quantities.

[0091] 3. Greatly improve work efficiency: Compared with the traditional AutoCAD software method of calculating road contours, the system of the present invention can process complex road projects containing multiple intersections in a short time without spending a lot of time on manual circle drawing and area statistics; at the same time, the system can quickly calculate the engineering quantity after the road drawings are updated, which greatly improves work efficiency and is particularly suitable for the design needs of large-scale engineering projects.

[0092] 4. Wide applicability and promotion value: The calculation method and system of the present invention are not only highly versatile and can be applied to the engineering design of various cross-shaped road intersections without dividing strips, but also highly adaptable and can handle intersections with different intersection angles. Due to its high accuracy, simple operation and strong adaptability, the system has a wide range of application prospects and can be popularized and promoted in the field of road engineering design, promoting the improvement of the overall calculation accuracy and efficiency of the industry.

[0093] 5. Project cost and management support: Through the precise calculation system of the present invention, designers can quickly generate accurate engineering quantity data, providing reliable data support for subsequent project cost budgeting, bidding, project implementation and acceptance. At the same time, the use of this system can also reduce the risks and errors caused by calculation deviations in the process of project management, and help achieve refined management.

[0094] 6. Saving of manpower and resources: With the system of the present invention, designers no longer need to repeatedly perform complex manual calculations and operations, so they can devote more energy to other design work. This not only saves a lot of manpower, but also reduces the consumption of physical resources such as paper, reflecting the green and environmentally friendly design concept. BRIEF DESCRIPTION OF THE DRAWINGS

[0095] Figure 1 It is a precise calculation method and system flow chart of the typical intersection pavement engineering quantity;

[0096] Figure 2 This is a typical intersection diagram (without a dividing strip);

[0097] Figure 3 It is the geometric characteristic index of the intersection lane;

[0098] Figure 4 It is the geometric characteristic index of the intersection road red line;

[0099] Figure 5 It is a schematic diagram for deducing the upper surface area of ​​the roadway at the intersection;

[0100] Figure 6 YesS R1 (Shaded area) Solution diagram;

[0101] Figure 7 YesS R2 (Shaded area) Solution diagram;

[0102] Figure 8 It is a schematic diagram of the secant line at the intersection of the circle and the two side lines;

[0103] Fig. 9 This is a schematic diagram for solving the red line area of ​​the intersection road;

[0104] Fig.10 YesS r1 Solution diagram;

[0105] Fig.11 YesS r2 Solution diagram;

[0106] Fig.12 This is a schematic diagram of type A and type B curbstones at an intersection;

[0107] Fig.13 This is a schematic diagram for solving the length of type A curb;

[0108] Fig.14 This is a schematic diagram for solving the length of the A4 curb;

[0109] Fig.15 It is a schematic diagram of the road surface structure;

[0110] Fig.16 It is a schematic diagram of the sidewalk pavement structure;

[0111] Fig.17 It is the input and output of the characteristic index of the intersection lane and road red line;

[0112] Fig.18 It is the intersection road surface structure index input and result output;

[0113] Fig.19 It is the input and output of the intersection sidewalk pavement structure index;

[0114] Fig. 20 It is the interface for inputting and calculating the characteristic indexes of the intersection lane and red line pavement;

[0115] Fig.21 It is the engineering quantity calculation interface for the road surface structure layer of the intersection;

[0116] Fig. 22 It is the engineering quantity calculation interface of the intersection sidewalk pavement structure layer;

[0117] Fig.23 It is a schematic diagram of the geometric indicators of the engineering example intersection (unit: m);

[0118] Fig.24 is a schematic diagram of the road pavement edge structure of the engineering example (unit: cm);

[0119] Fig.25 It is the input and calculation results of the characteristic indexes of the intersection lane and red line pavement;

[0120] Fig.26 It is the calculation result of the engineering quantity of the road surface structure layer of the intersection;

[0121] Fig. 27 It is the calculation result of the engineering quantity of the structural layer of the pedestrian pavement at the intersection;

[0122] Fig.28 It is the statistical result of the area and length encircled by AutoCAD software. DETAILED DESCRIPTION

[0123] The present invention will be further described in detail below in conjunction with the accompanying drawings and specific embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0124] like Figure 1 As shown, this embodiment first proposes a method for accurately calculating the engineering quantity of the pavement of a typical intersection, analyzes the geometric characteristics of a typical intersection, obtains the geometric characteristic indicators of the intersection, and then derives the engineering quantity calculation formula for the carriageway and the road red line, and obtains the engineering quantity calculation formula including the key indicators such as the carriageway, the surface area of ​​the sidewalk, and the curb length. Then, by inputting the relevant parameters of the carriageway and sidewalk structure layers, the engineering quantity results of each pavement structure layer of the carriageway and the sidewalk can be solved.

[0125] Then use VBA development tools to make the above engineering quantity calculation method into an accurate calculation system for intersection engineering quantity, which can easily and quickly input intersection-related index data and output engineering quantity calculation results. This system can be widely used in intersections without dividing strips in actual projects. While meeting the accuracy of engineering quantity, it also improves the work efficiency of designers. The details are as follows: 1. Accurate calculation method for typical intersection pavement engineering quantity:

[0126] S1. Obtain indicators that characterize the geometric features of the intersection:

[0127] The common road intersections in actual projects are mainly four-way intersections, such as Figure 2 , in the process of designing road intersections, its specific geometric forms and characteristics can be found:

[0128] 1. The outer side of the carriageway is the sidewalk, and the outer edge of the sidewalk is the road red line.

[0129] 2. The outline of the intersection surrounded by the road red line is similar to that of the carriageway, but the corner treatment at the intersection of the road sidelines is different. The inner corner of the sidewalk uses an arc, and the outer corner uses the secant of the circle guided by the corner extension line.

[0130] 3. In addition to being vertical, the center lines of two intersecting roads often intersect at a certain angle.

[0131] 4. The radius of the corner guide circles on the opposite sides of the intersection lanes is equal, and the radius of the corner arcs on the opposite sides of the intersection road red line is equal [1, 2] .

[0132] By analyzing the geometric form of the typical road intersection without a dividing strip, the relevant indicators characterizing its geometric characteristics were obtained and used for the precise calculation of the subsequent intersection pavement engineering quantity.

[0133] like Figure 3 , 4 As shown in Figure 2, the characteristics of the roadway at the intersection and the road surrounded by the red line show that the geometric characteristics of the roadway at the intersection are mainly determined by seven indicators: Figure 3 ): vertical road lane length L1, vertical lane width W1, transverse road length L2, transverse lane width W2, angle α between the center lines of the intersecting roads, guide radius R1 and R2 (R1≤R2) at the corner of the lane edge. The geometric characteristics of the road surrounded by the red line of the intersection are determined by 9 indicators ( Figure 4 ): In addition to the length L1 of the vertical road lane, the length L2 of the horizontal road, and the angle α of the centerline of the intersecting road, it also includes the vertical and horizontal road red line widths W1′ and W2′, the road red line angle lengths K1 and K2 (K1≤K2), and the road red line angle arc radii r1 and r2 (r1≤r2). The obtained characteristic indicators are summarized in Table 1:

[0134] Table 1 Summary of intersection characteristic indicators

[0135]

[0136]

[0137] The above indicators can be used to describe the geometric characteristics of typical intersections in actual projects, and the pavement engineering volume of the intersection can be accurately calculated later.

[0138] S2. Construct intersection pavement engineering quantity calculation model:

[0139] According to the experience of engineering quantity calculation, solving the surface area of ​​the intersection roadway, the area enclosed by the road red line and the length of the curb are the core of calculating the intersection pavement engineering quantity. Subsequently, the area of ​​the remaining structural layers of the intersection roadway and sidewalk can be solved based on it. Therefore, using the above indicators that characterize the geometric characteristics of the intersection, the accurate calculation formulas for the surface area of ​​the roadway, the road red line area and the length of the curb of a typical intersection are derived.

[0140] S201. Derivation of the surface area of ​​the roadway at the intersection:

[0141] like Figure 5 , the surface area of ​​the intersection roadway S C for:

[0142] S C =S1+S2 (1)

[0143] S1 is the area of ​​the intersection excluding the shaded part of the corner, and S2 is the sum of the areas of the shaded parts of the corners.

[0144] S1=L2×W2+(L1-X)×W1 (2)

[0145] X=w2 / sinα (3)

[0146] Substituting (3) into (2), we get:

[0147]

[0148] The area of ​​S2 consists of two With 2 The area of ​​the shaded parts corresponding to R1 and R2 is calculated. and Solution:

[0149] Figure 6 (Shaded area) Solution diagram

[0150]

[0151] Substituting (6) into (5), we get:

[0152]

[0153] Figure 7 (Shaded area) Solution diagram

[0154]

[0155] Substituting (9) into (8), we get:

[0156]

[0157] From this we can get:

[0158]

[0159] The areas of S1 and S2 are calculated respectively. Substituting equations (4) and (11) into equation (1), we get:

[0160]

[0161] Formula (12) is the formula for accurately calculating the surface area of ​​the carriageway at a typical intersection.

[0162] S202. Derivation of the area enclosed by the red line of the intersection:

[0163] The intersection outline enclosed by the road red line is similar to the roadway, but the corner is not an arc, but a secant line between the intersection of the extended lines of the corner and the intersection of the two side lines, that is, the tangent line, such as Figure 8 shown.

[0164] Assume that the intersection road red line cut angle lengths are K1 and K2 (the small cut angle length is K1, the large cut angle length is K2), such as Fig. 9 , the intersection area corresponding to the road red line can be calculated.

[0165] The area enclosed by the red line of the intersection road S H :

[0166] S H =S1′+S2′ (13)

[0167] S1′ is the area of ​​the intersection excluding the shaded part of the corner, and S2′ is the sum of the areas of the shaded parts of the corners. The solution method for S1′ is the same as that for S1, see formula (14):

[0168]

[0169] S2′ is regarded as the shaded area corresponding to the radius r1 and r2 of the road red line cutting arc, which contains 2 With 2 Now calculate the area of ​​the shaded parts corresponding to r1 and r2 respectively. and Solution:

[0170] Fig.10 S r1 Solution diagram

[0171]

[0172] Substituting (16) into (15), we obtain:

[0173]

[0174] Fig.11 S r2 Solution diagram

[0175]

[0176] Substituting (19) into (18), we obtain:

[0177]

[0178] Get the area of ​​S2′:

[0179]

[0180] The areas of S1′ and S2′ are calculated respectively. Substituting equations (14) and (21) into (13), we get:

[0181]

[0182] S203. Solution for the exact length of the curb:

[0183] Fig.12 The figure is a schematic diagram of type A and type B curbs at the intersection. The above indicators can also be used to accurately solve the lengths of type A and type B curbs at the intersection, where type A curbs are located at the outer edge of the intersection's carriageway and type B curbs are located at the outer edge of the intersection's sidewalk.

[0184] (1) Calculation of the length of type A curb:

[0185] like Fig.13 , the length of type A curbstone is L A for:

[0186] L A =2×(L1+L2)-2×(m1+m2)-4×(x1+x2)+2×(c R1 +c R2 ) (twenty three)

[0187]

[0188] Substituting (24)-(26) into (23), we obtain

[0189]

[0190] (2) Solution for the length of type B curbstone:

[0191] like Fig.14 , the length of type B curbstone is L B for:

[0192] L B =2×(L1+L2)-2×(m1+m2)-4×(r1+r2)+2×(K1+K2) (28)

[0193] Substituting formula (24) into (28), we get:

[0194]

[0195] S3. Construct the engineering quantity calculation model for each structural layer of the pavement:

[0196] The above-mentioned intersection road surface area S of the typical intersection has been accurately calculated C (surface area of ​​the road surface), the area enclosed by the red line of the intersection road S H , Type A curb length LA The length of the B-type curbstone is L B There are four key engineering quantity indicators, based on which other engineering quantities are solved.

[0197] S301. Calculate the area of ​​each structural layer of the road surface:

[0198] Combination Fig.15 The road surface structure and the area formula of each structural layer of the road surface are shown in Table 2:

[0199] Table 2 Area formula of each structural layer of the road surface

[0200]

[0201] Note: 1. The area of ​​the upper layer has been solved in the previous article, so there is no need to calculate the edge; 2. In actual situations, there is generally no edge structural change between the middle and lower layers of the road surface. 3. Equivalent area S d =W d ×H d , H c , W d With H d Show your opinion Fig.15 .

[0202] S302. Calculate the area of ​​each structural layer of the sidewalk pavement:

[0203] Depend on Figure 2 It can be seen that the surface area of ​​the sidewalk S R is the road red line area S H The surface area of ​​the roadway S C The difference, that is:

[0204] S R =S H -S C (30)

[0205] Combination Fig.16 The structure of the sidewalk pavement and the area formula of each structural layer of the sidewalk pavement are shown in the following table:

[0206] Table 3 Area formula of each structural layer of the sidewalk pavement

[0207]

[0208] Note: Equivalent sidewalk area S d It needs to be calculated in combination with the edge structure of the specific drawing. See the example for the specific method. Fig.16 :

[0209] S d2 =0 S d3 =-S a S d4 =Sc -S b (31)

[0210] The above calculation content solves the main engineering quantities of the pavement engineering quantity table through precise calculation formulas, and then the VBA development tool can be used to develop the engineering quantity calculation system.

[0211] 2. Development of an Accurate Calculation System for Intersection Pavement Engineering Quantities

[0212] Based on the solution principle and derivation of the above intersection calculation formula, the proposed intersection precise calculation formula is transformed into a system program to achieve visualization and operability, and improve the accuracy and work efficiency of calculating engineering quantities. The "Intersection Pavement Engineering Quantity Precision Calculation System" was designed and developed using Microsoft Excel's VBA development tool. The system can accurately calculate the pavement engineering quantity of typical road intersections. The interface is simple and easy to understand, and the operation is simple, which can greatly improve the work efficiency of road designers.

[0213] (1) Introduction to VBA development tools:

[0214] The development tool used in this system is Visual Basic For Application (VBA). VBA is a macro language of VisualBasic and a programming language for performing common automation (OLE) tasks in its desktop applications. It can be mainly used to expand the application functions of Windows, especially Microsoft Office software. VBA is developed based on VisualBasic and has a similar language structure to VB. VBA does not have its own independent working environment, it must be attached to a main application. VBA is specifically used in various Office applications, such as Word, Excel, Access, etc. In Access, modules can be written through VBA to meet specific needs. [3-5] .

[0215] This embodiment uses the VBA development tool in Microsoft Excel, using Excel as a platform for developing a computing system, and can apply all existing functions in Excel, including data processing, chart drawing, database links, built-in functions, etc.

[0216] (2) Design of the calculation system flowchart:

[0217] The program flowchart design of this system is mainly divided into three parts. The first part is to input the geometric characteristic indicators of the intersection carriageway and the road red line, and output four key engineering quantity indicators: the upper surface area of ​​the intersection carriageway, the area surrounded by the road red line, and the length of type A and type B curbs. The second and third parts are based on this, inputting key parameters such as the thickness of each structural layer of the carriageway and the sidewalk, the equivalent width, thickness, area of ​​the edge, etc., and outputting the area of ​​each pavement layer structure to complete the system's accurate calculation of the basic engineering quantity of the road intersection. The three program flowcharts are shown in Figure 17-19 :

[0218] (3) Main functions of the computing system:

[0219] a. Login interface design

[0220] First, you need to design the system's login interface, which is implemented by inserting a form in VBA. It requires entering a "user name" and "password", and clicking "Login" and "Logout" to enter and exit the program respectively.

[0221] b. Data Entry

[0222] Insert a text box in the form as a medium for data entry. The source input data is saved in Excel. Then double-click the form, enter the relevant code, call the workbook and cell in Excel, and enter the data into the Excel workbook by entering it in the form.

[0223] c. Result output

[0224] The specific data processing and calculation process are all carried out in Excel. The data input into Excel is calculated and processed to obtain the calculation results, and the results are visualized through the "ListView" control in the form. The results in Excel are called programmatically and displayed on the ListView control.

[0225] (4) Main functions of system development and application:

[0226] a.MsgBox function

[0227] The MsgBox function is mainly used in the login interface of the program to display whether the program login is successful or not, and whether the password is correct or not. This function can be used to display a message box, wait for the user to click a button, and then perform related operations based on the button clicked by the user.

[0228] The complete syntax structure of MsgBox is MsgBox(prompt[,buttons][,title][,helpfile,context]). This program mainly uses its prompt required items.

[0229] b.Cells function

[0230] The Cells function in VBA is mainly used for data entry in this program. The input value of the form text box is passed to the cell of the Excel workbook through the Cells function to realize data entry. The composition of the Cells syntax is: Cells (number of rows, number of columns), the number of rows and columns are both integer values, such as: Cells (1,1) represents the first row and the first column, that is, cell A1, which is the same as the cell referred to by Range (A1) in VBA, and can also be written as Cells (1, A).

[0231] c.ListSubitems collection

[0232] The ListSubitems collection is mainly used in the data visualization output of the ListView control in this program. Unlike SubItems, ListSubitems can directly add a row when adding a row object, and then assign a value to each added row by adding a row to the row object.

[0233] (5) System interface introduction:

[0234] (501). Login interface:

[0235] In the login interface that pops up, enter your username and password and click "Login" to enter the system. If the username and password are incorrect, a "Wrong Password" prompt box will pop up.

[0236] (502). Input and calculation of intersection lane and red line pavement characteristic indicators:

[0237] After logging in successfully, you can enter the "Intersection Lane and Red Line Pavement Characteristic Index Input and Calculation" interface. Fig. 20 , you can input the characteristic indicators of the intersection lane and red line, output the area of ​​the intersection lane surface and road red line, the length of type A and type B curbs and the area of ​​the sidewalk surface, and click "Next Page" to enter the next interface.

[0238] (503). Calculation of the engineering quantity of the road surface structure layer at the intersection:

[0239] Based on the above operations, the engineering quantity calculation of the road surface structure layer of the intersection is carried out. Fig.21 , input the length of the A-type curb, the thickness of each structural layer of the roadway, and the width and thickness of the edge, and you can output the area of ​​each structural layer of the roadway. Click "Next Page" to enter the next interface.

[0240] (504). Calculation of engineering quantities of the structural layer of the pedestrian pavement at the intersection

[0241] Then calculate the engineering quantity of the pedestrian pavement structure layer at the intersection, see Fig. 22 , input the length of type B curb, the thickness of each structural layer of the sidewalk, and the equivalent area of ​​the edge, and you can output the area of ​​each structural layer of the sidewalk.

[0242] After completing the above operations, the calculation of the typical intersection pavement engineering quantity is completed.

[0243] Preferably, the calculation of the engineering quantity of the intersection of a road project in a certain area is taken as an example to carry out the specific practical application of the "typical intersection engineering quantity accurate calculation system" and verify the accuracy of the results. The road grade is an urban branch road, the road red line width is 18m, and the design speed is 30km / h. The schematic diagram of the intersection geometry index annotation of the road is as follows Fig.23 : The schematic diagram of the road edge structure of this branch road is as follows: Fig.24 As shown:

[0244] according to Fig.23 The labeling information of the feature index values ​​that need to be entered are summarized in Table 4:

[0245] Table 4 Summary of input information for calculating system characteristic index values

[0246]

[0247]

[0248] Input the index values ​​in the table into the "Typical Intersection Engineering Quantity Accurate Calculation System", click "Output 1" and "Output 2", as shown in the figure below. Fig.25 :

[0249] The output shows that the upper surface area of ​​the intersection road is 1253.938m 2 The length of the A-type curb is 182.265m; the red line area of ​​the intersection is 1908.250m 2 , the length of type B curb is 154.000m; the sidewalk area is 654.312m 2 .

[0250] Click "Next Page" to enter the next calculation interface and calculate the engineering quantity of the road surface structure layer of the intersection. It is known that the length of type A curb is 182.265m. Fig.24 The input information of each structural layer of the carriageway is as follows:

[0251] Table 5 Input information of each structural layer of the carriageway

[0252]

[0253] Input the above information into the system interface and click "Output 1" to get the area of ​​each structural layer of the carriageway. Fig.26 As shown: The results of the area of ​​each structural layer are shown in Table 6:

[0254] Table 6 Area results of each structural layer of the carriageway

[0255]

[0256] Click "Next Page" to enter the next calculation interface and calculate the engineering quantity of the pedestrian pavement structure layer at the intersection. It is known that the length of the B-type curb is 154.000m. Fig.24 The input information of each structural layer of the sidewalk is shown in Table 7:

[0257] Table 7 Input information of each structural layer of the sidewalk

[0258]

[0259] Input the above information into the system interface and click "Output" to get the area of ​​each structural layer of the carriageway. Fig. 27 The results of the area of ​​each structural layer are shown in Table 8:

[0260] Table 8 Area of ​​each structural layer of the sidewalk

[0261]

[0262] Finally, the accuracy of the calculation results is checked:

[0263] The key to the accuracy of the calculation results of this calculation system is to verify the four indicators of the surface area of ​​the intersection roadway, the intersection red line area, and the length of type A and type B curbs. Now use AutoCAD software to circle the road outline to calculate the area and length to verify the accuracy of the results obtained by the system. The statistical results of the area and length circled by AutoCAD software are shown in Fig.28 :Comparison of the calculation results of the calculation system with the statistical results obtained by AutoCAD software is shown in Table 9:

[0264] Table 9 Comparison and difference of calculation results

[0265]

[0266] As can be seen from the table, the calculation results of this calculation system are very close to the statistical results of the AutoCAD encircling method. The difference percentage is used to compare the difference in the results. The maximum difference percentage of length is 0.032%, and the maximum difference percentage of area is 0.016%, both of which are within the range of allowable errors in engineering quantity calculation. Therefore, this system has high calculation accuracy and practicality, and can be applied and promoted.

[0267] Preferably, the embodiment of the present application also provides a specific implementation of an electronic device capable of implementing all steps in the method for calculating the typical intersection pavement engineering quantity in the above embodiment, and the electronic device specifically includes the following contents:

[0268] Processor, memory, communications interface and bus;

[0269] Among them, the processor, memory, and communication interface communicate with each other through the bus; the communication interface is used to realize information transmission between related devices such as server-side devices, metering devices, and user-side devices.

[0270] The processor is used to call the computer program in the memory, and when the processor executes the computer program, all the steps in the method for calculating the typical intersection pavement engineering quantity in the above embodiment are implemented.

[0271] An embodiment of the present application also provides a computer-readable storage medium capable of implementing all steps in the method for calculating the typical intersection pavement engineering quantity in the above-mentioned embodiment. A computer program is stored on the computer-readable storage medium, and when the computer program is executed by a processor, all steps in the method for calculating the typical intersection pavement engineering quantity in the above-mentioned embodiment are implemented.

[0272] Each embodiment in this specification is described in a progressive manner, and the same or similar parts between the embodiments can be referred to each other, and each embodiment focuses on the differences from other embodiments. In particular, for the hardware + program embodiment, since it is basically similar to the method embodiment, the description is relatively simple, and the relevant parts can be referred to the partial description of the method embodiment.

[0273] The above is a description of a specific embodiment of the specification. Other embodiments are within the scope of the appended claims. In some cases, the actions or steps recorded in the claims can be performed in an order different from that in the embodiments and still achieve the desired results. In addition, the processes depicted in the drawings do not necessarily require the specific order or continuous order shown to achieve the desired results. In some embodiments, multitasking and parallel processing are also possible or may be advantageous.

[0274] Although the present application provides method operation steps such as embodiments or flow charts, more or fewer operation steps may be included based on conventional or non-creative labor. The order of steps listed in the embodiments is only one way of executing the order of many steps and does not represent the only execution order. When the actual device or client product is executed, it can be executed in the order of the method shown in the embodiments or the drawings or in parallel (for example, in a parallel processor or multi-threaded processing environment).

[0275] Those skilled in the art will appreciate that embodiments of the present invention may be provided as methods, systems, or computer program products. Therefore, the present invention may take the form of a complete hardware embodiment, a complete software embodiment, or an embodiment combining software and hardware. Moreover, the present invention may take the form of a computer program product implemented on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) containing computer-usable program code.

[0276] These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing device to operate in a specific manner, so that the instructions stored in the computer-readable memory produce an article of manufacture comprising an instruction device, which implements the process Figure 1 A process or multiple processes and / or boxes Figure 1 A function specified in one or more boxes.

[0277] These computer program instructions can also be loaded onto a computer or other programmable data processing device so that a series of operating steps are executed on the computer or other programmable device to produce a computer-implemented process, thereby providing instructions for implementing the process. Figure 1 A process or multiple processes and / or boxes Figure 1 A step that specifies a function in one or more boxes.

[0278] The present invention is not limited to the embodiments described above. The above description of the specific embodiments is intended to describe and illustrate the technical solution of the present invention. The above specific embodiments are merely illustrative and not restrictive. Without departing from the scope of the present invention and the scope of protection of the claims, a person of ordinary skill in the art can also make many forms of specific changes under the guidance of the present invention, which all fall within the scope of protection of the present invention.

[0279] References:

[0280] [1]. Jing Chunguang, Wang Dianhai. Analysis and treatment of mixed traffic conflicts at typical intersections[J]. China Civil Engineering Journal, 2004, 37(6):97-100.DOI:10.3321 / j.issn:1000-131X.2004.06.018.

[0281] [2]. Xiao Yefeng. Study on channelization design of several typical intersections of urban roads[J]. Urban Roads, Bridges and Flood Control, 2016(7):273-277.DOI:10.16799 / j.cnki.csdqyfh.2016.07.082.

[0282] [3]. Hao Sheng. Key technologies for target mix ratio and gradation control of asphalt mixture[D]. Heilongjiang: Harbin Institute of Technology, 2022.

[0283] [4]. Wang Yinyu. Design and implementation of rapid test automation based on VBA[J]. Wireless Internet Technology, 2023, 20(17): 70-74. DOI: 10.3969 / j.issn.1672-6944.2023.17.020.

[0284] [5]. Li Weize, Liu Baozhen. Research on laboratory review database system based on VBA[J]. Market Supervision and Quality Technology Research, 2023(4):44-47. DOI:10.3969 / j.issn.1674-5981.2023.04.011.

Claims

1. A method for calculating the pavement engineering quantity of a typical intersection, characterized in that: Applicable to cross-shaped road intersections without dividing strips, and the road red line corner type of the intersection is symmetrical cutting angle, including: S1. Obtaining indicators representing geometric features of the intersection, including general indicators, lane indicators, and road redline indicators; S2. Construct a calculation model for the intersection pavement engineering quantity; including the solution of the intersection road surface area, the intersection road red line area and the curb length; S3. Construct a calculation model for the engineering quantity of each structural layer of the road surface; including the solution of the area of ​​each structural layer of the road surface for vehicles and the area of ​​each structural layer of the road surface for pedestrians.

2. The method for calculating the typical intersection pavement engineering quantity according to claim 1 is characterized in that: In step S1, the general indicators include the vertical road length L1, the horizontal road length L2 and the angle α between the center lines of the intersecting roads; The lane indicators include vertical lane width W1, transverse lane width W2, lane corner small guide circle radius R1, and lane corner large guide circle radius R2; The road red line indicators include the vertical road red line width W1′, the horizontal road red line width W′2, the road red line small cut angle length K1, the road red line large cut angle length K2, the road red line small cut angle arc radius r1, and the road red line large cut angle arc radius r2.

3. The method for calculating the typical intersection pavement engineering quantity according to claim 1 is characterized in that: In step S2, the surface area of ​​the intersection roadway S C for: S C =S1+S2 (1) S1 is the area of ​​the intersection excluding the shaded part of the corner, and S2 is the sum of the areas of the shaded parts of the corners; S1=L2×W2+(L1-X)×W1 (2) X=W2 / sinα (3) Substituting (3) into (2), we get: Among them, L1 is the vertical road length, L2 is the horizontal road length, W1 is the vertical lane width, W2 is the horizontal lane width; α is the angle between the center lines of the intersecting roads; the area of ​​S2 is composed of two With 2 The area of ​​R1 and R2 is composed of and To solve: Substituting (6) into (5), we get: Similarly: Substituting (9) into (8), we get: From this we can get: The areas of S1 and S2 are calculated respectively. Substituting equations (4) and (11) into equation (1), we get: Formula (12) is the formula for calculating the surface area of ​​the carriageway at a typical intersection.

4. The method for calculating the typical intersection pavement engineering quantity according to claim 3 is characterized in that: In step S2, Assume that the length of the small cut angle of the intersection road red line and the length of the large cut angle of the intersection road red line are K1 and K2 respectively, that is, calculate the area S enclosed by the intersection road red line H for: S H =S1′+S2′ (13) S1′ is the area of ​​the intersection excluding the shaded part of the corner, and S2′ is the sum of the areas of the shaded parts of the corners. The solution method for S1′ is the same as that for S1, see formula (14): S2′ is regarded as the shadow area corresponding to the radius of the small cut-angle arc of the road red line r1 and the radius of the large cut-angle arc of the road red line r2, which contains 2 With 2 S r2 , now calculate the shaded area S corresponding to r1 and r2 respectively r1 , S r2 To solve: Substituting (16) into (15), we obtain: Substituting (19) into (18), we obtain: Get the area of ​​S2′: The areas of S1′ and S2′ are calculated respectively. Substituting equations (14) and (21) into (13), we get: According to formula (22), the area enclosed by the intersection road red line can be calculated.

5. The method for calculating the typical intersection pavement engineering quantity according to claim 1 is characterized in that: In step S2, the types of curbstones on the road surface of the intersection include type A curbstones and type B curbstones, wherein the type A curbstones are located at the outer edge of the roadway of the intersection, and the type B curbstones are located at the outer edge of the sidewalk of the intersection; (1) Length of Type A curbstone L A for: L A =2×(L1+L2)-2×(m1+m2)-4×(x1+x2)+2×(c R1 +c R2 ) (23) Wherein, L1 is the vertical road length, L2 is the horizontal road length, W1 is the vertical road width, W2 is the horizontal road width; α is the angle between the center lines of the intersecting roads; R1 and R2 are the small guide circle radius of the road corner and the large guide circle radius of the road corner; Substituting (24)-(26) into (23), we obtain (2) Length of Type B curbstone L B for: <h2 style=";text-align:left;direction:ltr">L<h2 style=";text-align:left;direction:ltr"> B <h2 style=";text-align:left;direction:ltr"> = 2×(L1+L2)-2×(m1+m2)-4×(r1+r2)+2×(K1+K2) (28) Substituting formula (24) into (28), we get: Among them, K1 and K2 are the small angle cut length and large angle cut length of the road red line at the intersection respectively.

6. The method for calculating the typical intersection pavement engineering quantity according to claim 3 is characterized in that: In step S3, the area of ​​each structural layer of the road surface includes the upper layer area, the middle layer area, the lower layer area, the upper base layer area, the lower base layer area and the bottom base layer area; the upper layer area S of the intersection road surface C Obtained from step S2; The area of ​​the middle surface layer is: S c +(S d2 / H c2 )×L A / 100;S d2 is the equivalent area of ​​the edge of the mid-surface layer, H c2 is the thickness of the middle surface layer; L A is the length of type A curb; S d2 =W d2 ×H d2 , W d2 , H d2 are the edge width and edge thickness of the mid-surface layer, respectively; The area of ​​the lower layer is: S c +(S d3 / H c3 )×L A / 100;S d3 is the equivalent area of ​​the lower layer edge, H c3 is the thickness of the lower layer; S d3 =W d3 ×H d3 , W d3 , H d3 are the edge width and edge thickness of the lower layer, respectively; The area of ​​the upper base is: S c +(S d4 / H c4 )×L A / 100;S d4 is the equivalent area of ​​the upper base edge, H c4 is the thickness of the upper base layer; S d4 =W d4 ×H d4 , W d4 , H d4 are the edge width and edge thickness of the upper base layer respectively; The area of ​​the lower base is: S c +(S d5 / H c5 )×L A / 100;S d5 is the equivalent area of ​​the lower base edge, H c5 is the thickness of the lower base; S d5 =W d5 ×H d5 , W d5 , H d5 are the edge width and edge thickness of the lower base layer respectively; The base area is: S c +(S d6 / H c6 )×L A / 100;S d6 is the equivalent area of ​​the base layer edge, H c6 is the thickness of the base layer; S d6 =W d6 ×H d6 , W d6 , H d6 They are the edge width and edge thickness of the base layer respectively.

7. The method for calculating the typical intersection pavement engineering quantity according to claim 3 is characterized in that: In step S3, the sidewalk surface area S R is the area S enclosed by the red line of the intersection H The surface area of ​​the intersection roadway S C The difference, that is S R =S H -S C (30) The area of ​​the floor below the sidewalk is: S R +(S d2 / H R2 )×L B / 100;L B is the length of type B curbstone, S d2 is the equivalent area of ​​the sidewalk surface edge, H R2 is the thickness of the layer below the sidewalk; The area of ​​the base layer on the sidewalk is: S R +(S d3 / H R3 )×L B / 100;S d3 is the equivalent area of ​​the upper base edge of the sidewalk, H R3 is the thickness of the base layer on the sidewalk; The area of ​​the sidewalk subbase is: S R +(S d4 / H R4 )×L B / 100;S d4 is the equivalent area of ​​the sidewalk subbase edge, H R4 is the thickness of the sidewalk subbase; Where S d2 , S d3 , S d4 Obtained in combination with the edge structure of the specific drawing.

8. A typical intersection pavement engineering quantity calculation system, based on the typical intersection pavement engineering quantity calculation method according to any one of claims 1 to 7, characterized in that: include: A login module, used to log into the computing system; An input module, used for inputting intersection geometric characteristic indicators, including general indicators, lane indicators and road red line indicators; The general indicators include the vertical road length L1, the horizontal road length L2 and the angle α between the center lines of the intersecting roads; The lane indicators include vertical lane width W1, horizontal lane width W2, lane corner small guide circle radius R1, lane corner large guide circle radius R2; The road red line indicators include the vertical road red line width W1′, the horizontal road red line width W′2, the road red line small cut angle length K1, the road red line large cut angle length K2, the road red line small cut angle arc radius r1, and the road red line large cut angle arc radius r2; A calculation module is used to calculate the area of ​​each structural layer of the road surface, the area of ​​each structural layer of the sidewalk surface and the length of the curb; Output module outputs calculation results and realizes the calculation of typical intersection pavement engineering quantities.

9. An electronic device comprising a memory, a processor, and a computer program stored in the memory and executable on the processor, characterized in that: When the processor executes the program, the steps of the method for calculating the typical intersection pavement engineering quantity as described in any one of claims 1 to 7 are implemented.

10. A computer-readable storage medium having a computer program stored thereon, characterized in that: When the computer program is executed by a processor, the steps of the method for calculating the typical intersection pavement engineering quantity as described in any one of claims 1 to 7 are implemented.