Bidirectional anchoring plate retaining wall and construction method thereof
By adopting bidirectional anchoring plate structure and anchor rod design in retaining walls, the problem of insufficient stability of traditional retaining walls under complex conditions is solved, higher structural stability and safety are achieved, and construction costs are reduced and material usage.
Patent Information
- Application Number
- CN202411318474.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-20
- Publication Date
- 2024-11-22
- Estimated Expiration
- Not applicable · inactive patent
AI Technical Summary
Traditional retaining walls are difficult to construct, costly, and lack stability under complex terrain and geological conditions, and lack effective active constraint mechanisms, which leads to easy displacement and deformation when subjected to large horizontal loads, affecting their normal use function and Security.
Using a bidirectional anchor plate retaining wall structure, a bidirectional anchor is formed by providing a reserved hole on the column by using the outer end anchor assembly and the inner end anchor assembly connected to both ends of the anchor to form a bidirectional anchoring, providing balance and Strong anchoring force enhances structural stability and safety, and designs the bending part of the anti-filter layer and anchor rod through geowoven bags to improve anchoring effect and construction efficiency.
Effectively resist external forces in different directions, enhance structural stability and safety, reduce the risks of deformation and damage, is suitable for various engineering scenarios and geological conditions, reduce material usage and construction costs, and improve project quality.
Smart Images

Figure CN118997216A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of retaining walls, and in particular to a bidirectional anchor plate retaining wall and a construction method thereof. Background Art
[0002] As a common retaining structure, retaining walls are widely used in roads, railways, water conservancy projects, etc. to maintain soil stability and prevent slope collapse. Traditional retaining wall forms, such as gravity retaining walls and cantilever retaining walls, have many limitations under certain engineering conditions.
[0003] With the continuous development of engineering construction, the performance requirements for retaining walls are increasing. Under complex terrain and geological conditions, traditional retaining walls may face problems such as difficult construction, high cost, and insufficient stability. For example, in soft soil foundations or high fill sections, gravity retaining walls require a large amount of masonry materials, which not only increases the cost of the project, but also requires a high bearing capacity of the foundation; when the cantilever retaining wall is high, the internal force of the cantilever section is large, which can easily lead to structural cracking and damage. When resisting soil pressure, existing retaining wall structures can only rely on their own gravity or structural strength, and lack an effective active constraint mechanism. This makes it easy for retaining walls to displace and deform when subjected to large horizontal loads, affecting their normal use function and safety.
[0004] Therefore, in order to overcome the shortcomings of traditional retaining walls, researching and developing a new retaining wall structure and construction method thereof to meet the higher requirements for retaining wall performance in engineering construction is an issue that technical personnel in this field urgently need to solve. Summary of the invention
[0005] In order to overcome the shortcomings of traditional retaining walls and meet higher requirements for retaining wall performance in engineering construction, the present application provides a bidirectional anchor plate retaining wall and a construction method thereof.
[0006] The present application provides a bidirectional anchor plate retaining wall and a construction method thereof, which adopts the following technical solutions: First aspect A two-way anchor plate retaining wall comprises a base arranged along the bottom of an original slope, the top of the base is fixedly connected to equidistantly distributed columns, a filter layer and a fill layer are arranged in sequence on the side of the columns facing the original slope, a reserved hole is opened on the column in the direction of the original slope, an anchor rod is movably inserted in the reserved hole, an outer end anchoring assembly is arranged at one end of the anchor rod close to the column, the outer end anchoring assembly is fixedly arranged on the column, and an inner end anchoring assembly is arranged at one end of the anchor rod away from the column, the inner end anchoring assembly is fixedly arranged inside the intersection of the fill layer and the original slope, and a wall panel is arranged between the columns.
[0007] By adopting the above technical solution, the outer end anchoring assembly and the inner end anchoring assembly connected to the two ends of the anchor rod can form a bidirectional anchoring between the column and the original slope, which can not only provide a balanced and strong anchoring force, but also effectively resist the external forces from different directions, greatly enhance the stability and safety of the structure, and reduce the risk of deformation or damage caused by uneven force. It can also be flexibly applied to various engineering scenarios and geological conditions, and can play an excellent anchoring effect whether in hard rock layers or soft foundation environments. At the same time, bidirectional anchoring can also reduce the use of materials, simplify the construction process, and thus reduce the overall cost of the project.
[0008] Furthermore, the filter layer is constructed by packing gravel in geotextile bags in a backfilling manner, and the thickness of the filter layer is 40 cm to 60 cm.
[0009] By adopting the above technical solution, geotextile woven bags are used to pack gravel in piles for backfilling within a width of 40cm to 60cm behind the retaining wall, which can not only ensure that the gravel will not be lost from the drainage holes, but also prevent the quality of the gravel layer from getting out of control due to interference between the backfill behind the wall and the gravel layer.
[0010] Furthermore, a bending portion is provided in the middle of the anchor rod, and both ends of the anchor rod are coaxially arranged straight portions. A rotating portion is provided at one end of the anchor rod close to the column, and a concrete solid platform is cast inside the fill layer corresponding to the bending portion.
[0011] By adopting the above technical scheme, the anchor rod can be rotated by using the rotating part during the construction process. Rotating the anchor rod can not only connect and fix the anchor rod with the outer end anchor assembly and the inner end anchor assembly, but also stir the concrete when pouring the concrete fixing platform, thereby ensuring the connection strength between the concrete fixing platform and the anchor rod, and increasing the stability of the anchor rod in the working process. The design of the bending part is also conducive to increasing the extensibility of the anchor rod, which is conducive to ensuring the anchoring effect.
[0012] Furthermore, the outer end anchoring assembly includes a first pad, a first mounting hole is provided at the center of the first pad, the anchor rod is inserted into the first mounting hole, a first anchor sleeve is fixedly connected to the side of the first pad away from the column, a first internal thread is provided on the inner side of the first anchor sleeve, a first external thread is provided on the outer side of the anchor rod corresponding to the first internal thread, and an anchor head is provided on the outer end of the anchor rod corresponding to the shape of the first pad.
[0013] By adopting the above technical solution, the strong friction and bite force generated by the first internal thread and the first external thread can be used to tightly and firmly connect the anchor rod and the first anchor sleeve together, and the installation can be quickly completed through a simple rotation operation, which is conducive to simplifying the construction process and improving work efficiency. During the construction process, the connection length and position can be accurately fine-tuned by flexibly rotating the thread, so that the anchoring system can better adapt to various complex and changing situations.
[0014] Furthermore, the inner end anchoring assembly includes an anchoring plate, a second mounting hole is formed in the center of the anchoring plate, the anchor rod is passed through the second mounting hole, a second anchoring sleeve is fixedly connected to the side of the anchoring plate away from the column, a second internal thread is formed on the inner side surface of the second anchoring sleeve, and a second external thread is formed on the outer side surface of the anchor rod corresponding to the second internal thread.
[0015] By adopting the above technical solution, the strong friction and bite force generated by the second internal thread and the second external thread can be used to tightly and firmly connect the anchor rod and the second anchor sleeve together, and the installation can be quickly completed through a simple rotation operation, which is conducive to simplifying the construction process and improving work efficiency. During the construction process, the connection length and position can be accurately fine-tuned by flexibly rotating the thread, so that the anchoring system can better adapt to various complex and changing situations.
[0016] Furthermore, a mounting groove is provided on the side of the column corresponding to the wall panel, and a plurality of drainage holes are provided on the wall panel.
[0017] By adopting the above technical solution, the mounting groove can be used to increase the stability of the connection between the column and the wall panel, and the drainage holes provided on the wall panel can discharge the accumulated water inside the wall panel during later use.
[0018] Second aspect A construction method for a two-way anchor plate retaining wall, characterized by comprising the following steps: S1. Construction preparation, including familiarizing yourself with construction drawings, conducting on-site surveys, and preparing materials and equipment required for construction; S2. excavating a retaining wall foundation pit along the bottom of the original slope according to the design requirements, tying steel bars and installing formwork on the retaining wall foundation pit, and pouring concrete to complete the construction of the base; S3, tying steel bars and installing templates on the upper surface of the base according to the design requirements of the column, installing hollow tubes according to the positions of the reserved holes, and then pouring concrete to complete the construction of the column; S4, tying steel bars and installing formwork on the upper surface of the base according to the design requirements of the wall panel, installing drain pipes according to the positions of the drain holes, and then pouring concrete to complete the construction of the wall panel; S5, laying the filter layer and the fill layer layer by layer, and compacting the fill layer. When the height of the filter layer and the fill layer is close to the height of the hollow pipe, reversely excavate the intersection of the fill layer and the original slope to install the inner end anchor assembly; S6, passing the anchor rod through the hollow tube, and connecting one end of the anchor rod close to the column to the outer anchor assembly, and connecting one end of the anchor rod away from the column to the inner anchor assembly; S7, repeating steps S4 to S6, and then pouring a concrete anchor pier at the outer end of the anchor rod corresponding to the first pad outside to form an anchor head, thereby completing the construction of the retaining wall.
[0019] By adopting the above technical solution, compared with the traditional technology of prefabricating the columns, the columns and the base are constructed by pouring on site, which can not only better adapt to the terrain and geological conditions of the site, but also ensure the construction quality and enhance the integrity of the structure. Due to the complexity and uncertainty of the construction site, the method of pouring the columns and base on site can be adjusted and optimized according to the actual situation to ensure that the columns and base fit the foundation better, thereby improving the stability and bearing capacity of the structure. At the same time, the fill layer is compacted layer by layer, which can effectively ensure the compaction effect of the fill layer.
[0020] Furthermore, S5 includes excavating a first installation pit for installing an inner end anchor assembly at an end of the anchor rod away from the column, corresponding to the intersection of the fill layer and the original slope, and placing the inner end anchor assembly inside the installation pit.
[0021] By adopting the above technical solution, the construction method of reversely excavating the first installation pit after compaction and then installing the inner end anchoring assembly can improve the firmness of the installed inner end anchoring assembly.
[0022] Furthermore, the S6 includes excavating a second installation pit in the opposite direction on the compacted fill layer corresponding to the middle of the anchor rod, and supporting temporary retaining templates inside the first installation pit and the second installation pit.
[0023] By adopting the above technical scheme, the middle part of the anchor rod can be temporarily suspended during the construction process by utilizing the second installation pit, and by supporting temporary retaining formwork inside the first installation pit and the second installation pit, soil blocks can be prevented from falling into the first installation pit or the second installation pit during the compaction of the soil layer. The first installation pit and the second installation pit can be used to set an installation and fixing structure on the outside of the middle part of the anchor rod and the outside of the inner end anchor assembly for reinforced fixation, thereby further improving the firmness of the anchor rod and the inner end anchor assembly during use.
[0024] Furthermore, when the height of the filter layer and the fill layer is close to the top of the temporary retaining formwork, the temporary retaining formwork is removed, and concrete is poured inside the first installation pit and the second installation pit. At the same time, a rotating tool is used to repeatedly rotate the anchor rod in forward and reverse directions for multiple times, and finally the anchor rod is rotated to the designed installation position.
[0025] By adopting the above technical solution, concrete is poured inside the first installation pit and the second installation pit, and the anchor rod and the inner end anchor assembly can be fixed with concrete, which effectively solves the problem that the backfill soil around the anchor rod and the inner end anchor assembly is difficult to compact, which is beneficial to improving the overall project quality.
[0026] The beneficial effects achieved include at least the following: 1. This application can form a bidirectional anchoring between the column and the original slope by using the outer end anchoring assembly and the inner end anchoring assembly connected to the two ends of the anchor rod, which can not only provide a balanced and strong anchoring force, effectively resist the external forces from different directions, greatly enhance the stability and safety of the structure, and reduce the risk of deformation or damage caused by uneven force. It can also be flexibly applied to various engineering scenarios and geological conditions, and can play an excellent anchoring effect in both hard rock layers and soft foundation environments.
[0027] 2. The present application can rotate the anchor rod during the construction process by utilizing the rotating part. Rotating the anchor rod can not only connect and fix the anchor rod with the outer end anchor assembly and the inner end anchor assembly, but also stir the concrete when pouring the concrete fixing platform, thereby ensuring the connection strength between the concrete fixing platform and the anchor rod, and increasing the stability of the anchor rod during the working process. The design of the bending part is also conducive to increasing the extensibility of the anchor rod, which is conducive to ensuring the anchoring effect.
[0028] 3. This application constructs the columns and the base by pouring on site, which can not only better adapt to the terrain and geological conditions of the site, but also ensure the construction quality and enhance the integrity of the structure. Due to the complexity and uncertainty of the construction site, the method of pouring columns and bases on site can be adjusted and optimized according to the actual situation to ensure that the columns and bases are more closely fitted to the foundation, thereby improving the stability and bearing capacity of the structure.
[0029] 4. The present application pours concrete inside the first installation pit and the second installation pit, and can use concrete to fix the anchor rod and the inner end anchor assembly, effectively solving the problem that the backfill soil around the anchor rod and the inner end anchor assembly is difficult to compact, which is beneficial to improving the overall project quality. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the overall structure of Example 1 of the present application.
[0031] Figure 2 It is a schematic diagram of the anchor rod structure of Example 1 of the present application.
[0032] Figure 3 It is a schematic diagram of the structural decomposition of the outer end anchoring assembly of Example 1 of the present application.
[0033] Figure 4 It is a schematic diagram of the structural decomposition of the inner end anchoring assembly of Example 1 of the present application.
[0034] Figure 5 It is a schematic diagram of the wall panel installation structure of Example 1 of the present application.
[0035] Figure 6 It is a schematic diagram of the overall structure of Example 2 of the present application.
[0036] Description of reference numerals: 100, base; 101, column; 102, reserved hole; 103, anchor rod; 1031, bending portion; 1032, straight portion; 1033, rotating portion; 200, filter layer; 300, fill layer; 301, concrete fixing platform; 400, outer end anchoring assembly; 401, first pad; 402, first mounting hole; 403, first anchor sleeve; 404, first internal thread; 405 , first external thread; 406, anchor head; 500, inner end anchor assembly; 501, anchor plate; 502, second mounting hole; 503, second anchor sleeve; 504, second internal thread; 505, second external thread; 600, wall panel; 601, mounting groove; 602, drain hole; 700, hollow pipe; 701, first mounting pit; 702, second mounting pit; 800, original slope; 900, expansion joint. DETAILED DESCRIPTION
[0037] The following is combined with Figure 1-6 This application is described in further detail.
[0038] In the description of the present application, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance.
[0039] In the description of this application, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.
[0040] The embodiment of the present application discloses a bidirectional anchor plate retaining wall and a construction method thereof.
[0041] Please refer to Figure 1 In one embodiment of the present application, a bidirectional anchor plate retaining wall includes a base 100, which is arranged in sections along the bottom of the original slope 800, and the top of the base 100 is fixedly connected with equidistantly distributed columns 101, wall panels 600 are arranged between the columns 101 on the same section of the base 100, and expansion joints 900 are arranged between adjacent columns 101 on two sections of the base 100.
[0042] In a specific embodiment of the present application, asphalt hemp is embedded in the expansion joint 900. The asphalt hemp can effectively prevent moisture from penetrating into the retaining wall through the expansion joint 900, effectively ensuring the stability and durability of the retaining wall structure; it can also adapt to the expansion and deformation of the expansion joint 900 caused by various factors (such as temperature changes and load effects), avoiding cracks or damage that may be caused by material rigidity, and when the structure is subjected to vibration or impact, the asphalt hemp can exert good shock-absorbing and buffering performance, significantly reducing the degree of damage to the expansion joint and surrounding structures.
[0043] Please refer to Figure 1In one embodiment of the present application, a filter layer 200 and a fill layer 300 are sequentially arranged on the side of the column 101 facing the original slope 800, a reserved hole 102 is opened on the column 101 in the direction facing the original slope 800, an anchor rod 103 is movably inserted inside the reserved hole 102, an outer end anchoring assembly 400 is provided at one end of the anchor rod 103 close to the column 101, and the outer end anchoring assembly 400 is fixedly arranged on the column 101, and an inner end anchoring assembly 500 is provided at one end of the anchor rod 103 away from the column 101, and the inner end anchoring assembly 500 is fixedly arranged inside the connection between the fill layer 300 and the original slope 800. The outer anchor assembly 400 and the inner anchor assembly 500 connected to the two ends of the anchor rod 103 can form a two-way anchor between the column 101 and the original slope 800, which can not only provide a balanced and powerful anchoring force, but also effectively resist the external forces from different directions, greatly enhance the stability and safety of the structure, and reduce the risk of deformation or damage caused by uneven force. Moreover, it can be flexibly applied to various engineering scenarios and geological conditions, and can play an excellent anchoring effect whether in hard rock layers or soft foundation environments. At the same time, two-way anchoring can also reduce the use of materials, simplify the construction process, and thus reduce the overall cost of the project.
[0044] In a specific embodiment of the present application, the filter layer 200 is constructed by stacking and backfilling gravel in geotextile bags. The thickness of the filter layer 200 is 40 cm to 60 cm. Preferably, the thickness of the filter layer 200 is 50 cm. Geotextile bags are used to pack gravel and backfill the gravel within a width of 50 cm behind the retaining wall. This ensures that the gravel will not be lost from the drainage holes and that the quality of the gravel layer will not be out of control due to interference between the backfill behind the wall and the gravel layer.
[0045] Please refer to Figure 1 and Figure 2 In one embodiment of the present application, the anchor rod 103 is made of fine-rolled threaded steel bars, and a bending portion 1031 is provided in the middle of the anchor rod 103. The two ends of the anchor rod 103 are coaxially arranged straight portions 1032, and a rotating portion 1033 is provided at one end of the anchor rod 103 close to the column 101. The shape of the rotating portion 1033 is set to be a regular hexagonal prism matching the socket wrench, and the maximum diameter of the regular hexagonal prism is smaller than the diameter of the anchor rod 103, so that the rotating portion 1033 can be easily passed through the reserved hole 102, so as to facilitate the installation of the anchor rod 103 during the construction process, and during the installation process, the anchor rod 103 can be rotated by connecting the rotating portion 1033 with the socket wrench, thereby adjusting the installation state between the anchor rod 103 and the outer end anchor assembly 400 and the inner end anchor assembly 500, and ensuring that the anchor rod 103 is fixedly connected to the outer end anchor assembly 400 and the inner end anchor assembly 500.
[0046] Please refer to Figure 1 and Figure 2 In one embodiment of the present application, a concrete fixing platform 301 is cast inside the fill layer 300 corresponding to the bent portion 1031. When casting the concrete fixing platform 301, by rotating the anchor rod 103, the bent portion 1031 on the anchor rod 103 will stir the concrete, ensuring the connection strength between the concrete fixing platform 301 and the anchor rod 103, thereby increasing the stability of the anchor rod 103 during the working process, and the design of the bent portion 1031 is also conducive to increasing the extensibility of the anchor rod 103, which is conducive to ensuring the anchoring effect.
[0047] Please refer to Figure 2 and Figure 3 In one embodiment of the present application, the outer end anchoring assembly 400 includes a first pad 401, and the first pad 401 is made of Q235B steel plate specified in "Carbon Structural Steel" GB / T700-2006. A first mounting hole 402 is provided at the center of the first pad 401, and the anchor rod 103 is inserted into the first mounting hole 402. A first anchor sleeve 403 is fixedly connected to the side of the first pad 401 away from the column 101, and a first internal thread 404 is provided on the inner side of the first anchor sleeve 403. A first external thread 405 is provided on the outer side of the anchor rod 103 corresponding to the first internal thread 404, and an anchor head 406 is provided at the outer end of the anchor rod 103 corresponding to the shape of the first pad 401. The first internal thread 404 and the first external thread 405 can be used to tightly and firmly connect the anchor rod 103 and the first anchor sleeve 403 together, and the installation can be quickly completed through a simple rotation operation, which is conducive to simplifying the construction process and improving work efficiency. During the construction process, the connection length and position can be accurately fine-tuned by flexibly rotating the thread, so that the anchoring system can better adapt to various complex and changeable situations.
[0048] Please refer to Figure 2 and Figure 4 In one embodiment of the present application, the inner end anchoring assembly 500 includes an anchoring plate 501, a second mounting hole 502 is provided at the center of the anchoring plate 501, the anchor rod 103 is inserted into the second mounting hole 502, a second anchoring sleeve 503 is fixedly connected to the side of the anchoring plate 501 away from the column 101, a second internal thread 504 is provided on the inner side of the second anchoring sleeve 503, and a second external thread 505 is provided on the outer side of the anchor rod 103 corresponding to the second internal thread 504. The anchor rod 103 and the second anchoring sleeve 503 can be tightly and firmly connected together through the second internal thread 504 and the second external thread 505, and the installation can be quickly completed by a simple rotation operation, which is conducive to simplifying the construction process and improving work efficiency. The connection length and position can also be accurately fine-tuned by flexibly rotating the thread during the construction process, so that the anchoring system can better adapt to various complex and changeable situations.
[0049] Please refer to Figure 1 and Figure 5 In one embodiment of the present application, a mounting groove 601 is provided on the side of the column 101 corresponding to the wall panel 600, and a plurality of drainage holes 602 are provided on the wall panel 600. The mounting groove 601 can increase the stability of the connection between the column 101 and the wall panel 600, and the drainage holes 602 provided on the wall panel 600 can drain the accumulated water inside the wall panel 600 during the later use.
[0050] Please refer to Figure 1 and Figure 6 In one embodiment of the present application, a construction method of a bidirectional anchor plate retaining wall comprises the following steps: S1. Construction preparation, including familiarizing with construction drawings, conducting on-site inspections, and preparing materials and equipment required for construction. Check the quality of anchor rods 103 one by one, and do a good job of rust prevention. First, apply anti-rust primer (such as asphalt paint, ship bottom paint, epoxy asphalt paint, epoxy zinc-rich paint, etc.) twice to ensure that the paint film thickness is uniform and there is no gap. The outer layer is wrapped with asphalt-impregnated linen or asphalt fiberglass cloth (three oils and two cloths). The linen or fiberglass cloth should be wrinkle-free when wrapped, and the edge should be evenly pressed. The width is 10~15mm, the overlap is 50~80mm, and it should be firmly adhered.
[0051] S2. According to the design requirements, the retaining wall foundation pit is excavated along the bottom of the original slope of 800. The foundation pit excavation should adopt the vertical pit wall excavation method. After excavation, the steel bars should be tied and the formwork should be installed on the retaining wall foundation pit in time, and concrete should be poured. The concrete should be C30 concrete. The concrete should fill the entire foundation pit without leaving any gaps. The construction of the base 100 is completed after the concrete solidifies.
[0052] S3, tie the steel bars and install the template on the upper surface of the base 100 according to the design requirements of the column 101, install the hollow tube 700 according to the position of the reserved hole 102, and then pour C30 concrete to complete the construction of the column 101; S4, tying steel bars and installing formwork on the upper surface of the base 100 according to the design requirements of the wall panel 600, installing a drain pipe according to the position of the drain hole 602, and then pouring C30 concrete to complete the construction of the wall panel 600; S5, laying the filter layer 200 and the fill layer 300 layer by layer, and compacting the fill layer 300. When the height of the filter layer 200 and the fill layer 300 is close to the height of the hollow tube 700, reversely excavate the intersection of the fill layer 300 and the original slope 800 to install the inner end anchor assembly 500; S6, passing the anchor rod 103 through the hollow tube 700, and connecting the end of the anchor rod 103 close to the column 101 to the outer anchor assembly 400, and connecting the end of the anchor rod 103 away from the column 101 to the inner anchor assembly 500; S7, repeat steps S4 to S6, and then pour concrete anchor piers outside the first pad 401 at the outer end of the anchor rod 103 to form anchor heads 406, thus completing the construction of the retaining wall.
[0053] The present application constructs the columns 101 and the base 100 by means of on-site casting. Compared with the prefabricated columns 101 in the traditional technology, it can not only better adapt to the terrain and geological conditions of the site, but also ensure the construction quality and enhance the integrity of the structure. Due to the complexity and uncertainty of the construction site, the method of on-site casting of columns and bases can be adjusted and optimized according to the actual situation to ensure that the columns 101 and the base 100 are more closely attached to the foundation, thereby improving the stability and bearing capacity of the structure. At the same time, the filling layer 300 is compacted layer by layer, which can effectively ensure the compaction effect of the filling layer 300.
[0054] Please refer to Figure 6 In one embodiment of the present application, S5 includes excavating a first installation pit 701 for installing the inner end anchor assembly 500 at the intersection of the fill layer 300 and the original slope 800 at one end of the anchor rod 103 away from the column 101, and placing the inner end anchor assembly 500 inside the first installation pit 701. The construction method of reversely excavating the first installation pit 701 after compaction and then installing the inner end anchor assembly 500 can improve the firmness of the inner end anchor assembly 500.
[0055] Please refer to Figure 6 In one embodiment of the present application, S6 includes excavating a second installation pit 702 in the opposite direction on the compacted fill layer 300 corresponding to the middle of the anchor rod 103, and supporting a temporary retaining template inside the first installation pit 701 and the second installation pit 702. The second installation pit 702 can temporarily suspend the middle of the anchor rod 103 during the construction process, and by supporting a temporary retaining template inside the first installation pit 701 and the second installation pit 702, it is possible to prevent soil blocks from falling into the first installation pit 701 or the second installation pit 792 during the compaction of the soil layer. The first installation pit 701 and the second installation pit 702 can be used to set an installation fixing structure on the outside of the middle of the anchor rod 103 and the outside of the inner end anchor assembly 500 for enhanced fixation, thereby further improving the firmness of the anchor rod 103 and the inner end anchor assembly 500 during use.
[0056] Please refer to Figure 6In one embodiment of the present application, when the height of the filter layer 200 and the fill layer 300 is close to the top of the temporary retaining formwork, the temporary retaining formwork is removed, and C15 concrete is poured inside the first installation pit 701 and the second installation pit 702, and the anchor rod 103 is repeatedly rotated forward and reversely multiple times using a rotating tool such as an electric wrench, and finally the anchor rod 103 is rotated to the designed installation position. By pouring C15 concrete inside the first installation pit 701 and the second installation pit 702, the anchor rod 103 and the inner end anchor assembly 500 can be fixed by concrete, which effectively solves the problem that the soil backfill around the anchor rod 103 and the inner end anchor assembly 500 is difficult to compact, which is conducive to improving the overall engineering quality.
[0057] Please refer to Figure 1 and Figure 6 In one embodiment of the present application, when constructing the anchor head 406 in S7, an ash bucket is used to hold the outer end of the anchor rod 103 to cast self-compacting concrete and ensure the quality of concrete casting. The ash bucket can effectively prevent leakage of slurry and avoid leakage of self-compacting concrete from the end of the anchor rod during casting, thereby ensuring sufficient concrete casting volume and reliable quality.
[0058] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A two-way anchor plate retaining wall, characterized in that: The invention comprises a base (100) arranged along the bottom of an original slope (800), the top of the base (100) being fixedly connected to upright posts (101) distributed at equal intervals, a filter layer (200) and a fill layer (300) being arranged in sequence on the side of the upright posts (101) facing the original slope (800), a reserved hole (102) being opened on the upright posts (101) in a direction facing the original slope (800), an anchor rod (103) being movably inserted in the reserved hole (102), and the An outer end anchoring assembly (400) is provided at one end of the anchor rod (103) close to the column (101), and the outer end anchoring assembly (400) is fixedly arranged on the column (101). An inner end anchoring assembly (500) is provided at one end of the anchor rod (103) away from the column (101), and the inner end anchoring assembly (500) is fixedly arranged inside the intersection of the fill layer (300) and the original slope (800). A wall panel (600) is arranged between the columns (101).
2. A two-way anchor plate retaining wall according to claim 1, characterized in that: The filter layer (200) is constructed by packing gravel in geotextile woven bags in a stacking and backfilling manner, and the thickness of the filter layer (200) is (40) cm to (60) cm.
3. A two-way anchor plate retaining wall according to claim 1, characterized in that: A bending portion (1031) is provided in the middle of the anchor rod (103), and both ends of the anchor rod (103) are coaxially arranged straight portions (1032). A rotating portion (1033) is provided at one end of the anchor rod (103) close to the column (101), and a concrete fixing platform (301) is cast inside the fill layer (300) corresponding to the bending portion (1031).
4. The two-way anchor plate retaining wall according to claim 1, characterized in that: The outer end anchoring assembly (400) comprises a first pad (401), a first mounting hole (402) is provided at the center of the first pad (401), the anchor rod (103) is inserted into the first mounting hole (402), a first anchor sleeve (403) is fixedly connected to the side of the first pad (401) away from the column (101), a first internal thread (404) is provided on the inner side of the first anchor sleeve (403), a first external thread (405) is provided on the outer side of the anchor rod (103) corresponding to the first internal thread (404), and an anchor head (406) is provided at the outer end of the anchor rod (103) corresponding to the shape of the first pad (401).
5. The two-way anchor plate retaining wall according to claim 1, characterized in that: The inner end anchoring assembly (500) comprises an anchoring plate (501), a second mounting hole (502) is provided at the center of the anchoring plate (501), the anchor rod (103) is inserted into the second mounting hole (502), a second anchoring sleeve (503) is fixedly connected to a side of the anchoring plate (501) away from the column (101), a second internal thread (504) is provided on an inner side surface of the second anchoring sleeve (503), and a second external thread (505) is provided on an outer side surface of the anchor rod (103) corresponding to the second internal thread (504).
6. The two-way anchor plate retaining wall according to claim 1, characterized in that: A mounting groove (601) is provided on the side of the upright column (101) corresponding to the wall panel (600), and a plurality of drainage holes (602) are provided on the wall panel (600).
7. A construction method for a bidirectional anchor plate retaining wall as claimed in any one of claims 1 to 6, characterized in that The steps include: S1. Construction preparation, including familiarizing yourself with construction drawings, conducting on-site surveys, and preparing materials and equipment required for construction; S2, excavating a retaining wall foundation pit along the bottom of the original slope (800) according to design requirements, tying steel bars and installing formwork on the retaining wall foundation pit, and pouring concrete to complete the construction of the base (100); S3, tying steel bars and installing a formwork on the upper surface of the base (100) according to the design requirements of the column (101), installing a hollow tube (700) according to the position of the reserved hole (102), and then pouring concrete to complete the construction of the column (101); S4, tying steel bars and installing a formwork on the upper surface of the base (100) according to the design requirements of the wall panel (600), installing a drain pipe according to the position of the drain hole (602), and then pouring concrete to complete the construction of the wall panel (600); S5, laying the filter layer (200) and the fill layer (300) layer by layer, and compacting the fill layer (300); when the height of the filter layer (200) and the fill layer (300) is close to the height of the hollow tube (700), reversely excavating the intersection of the fill layer (300) and the original slope (800) to install the inner end anchor assembly (500); S6, passing the anchor rod (103) through the hollow tube (700), and connecting the end of the anchor rod (103) close to the column (101) to the outer anchor assembly (400), and connecting the end of the anchor rod (103) away from the column (101) to the inner anchor assembly (500); S7, repeating steps S4 to S6, and then pouring a concrete anchor pier outside the first pad (401) at the outer end of the anchor rod (103) to form an anchor head (406), thereby completing the construction of the retaining wall.
8. The construction method of the bidirectional anchor plate retaining wall according to claim 7, characterized in that: The S5 comprises excavating a first installation pit (701) for installing the inner end anchor assembly (500) at an end of the anchor rod (103) away from the column (101) corresponding to the intersection of the fill layer (300) and the original slope (800), and placing the inner end anchor assembly (500) inside the installation pit (701).
9. The construction method of the bidirectional anchor plate retaining wall according to claim 8, characterized in that: The step S6 includes excavating a second installation pit (702) in the opposite direction on the compacted fill layer (300) corresponding to the middle of the anchor rod (103), and supporting temporary retaining templates inside the first installation pit (701) and the second installation pit (702).
10. The construction method of the bidirectional anchor plate retaining wall according to claim 9, characterized in that: When the heights of the filter layer (200) and the fill layer (300) are close to the top of the temporary retaining formwork, the temporary retaining formwork is removed, and concrete is poured inside the first installation pit (701) and the second installation pit (702). At the same time, a rotating tool is used to repeatedly rotate the anchor rod (103) in forward and reverse directions for multiple times, and finally the anchor rod (103) is rotated to the designed installation position.
Citation Information
Cited By
Anchoring type soil retaining moulding bed and construction method thereof
CN120776717A