Concrete preparation device and proportion adjusting method

By introducing moisture content sensors and controllers into the concrete configuration device, the moisture content of sand samples is detected and adjusted in real time, the problem of difficult to control concrete strength and durability in traditional methods is solved, and the stability and accuracy of concrete quality are achieved.

CN119017547APending Publication Date: 2024-11-26JIANHUA CONSTRUCTION MATERIALS (CHINA) CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202411144362.8
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-08-20
Publication Date
2024-11-26

AI Technical Summary

Technical Problem

During the concrete configuration process, traditional methods find it difficult to detect the moisture content of the sand sample in real time, which makes it difficult to strictly control the strength and durability of the concrete, and there is lag and uncertainty in the detection results.

Method used

A concrete configuration device is designed, including a moisture content sensor and a controller, which can detect the moisture content of sand samples in real time and adjust the ratio of concrete raw materials in real time according to the detection results. By dividing sand samples into two steps, the concrete is ensured. The moisture content is within a suitable range.

Benefits of technology

Real-time monitoring and adjustment of concrete moisture content is achieved, the strength and durability of concrete are improved, the uncertainty of man-made operation is reduced, and the stability of concrete quality is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119017547A_ABST
    Figure CN119017547A_ABST
Patent Text Reader

Abstract

The invention discloses a concrete configuration device and a proportion adjusting method, the concrete configuration device comprises a first configuration unit and a controller, and the first configuration unit comprises a first discharging bin, a first weighing assembly and a detection assembly. The first weighing assembly comprises a first weighing bin, a feeding port of the first weighing bin is communicated with a discharging port of the first discharging bin, and the first weighing bin is used for weighing the sand sample in the first discharging bin; the detection assembly comprises a water content sensor, the water content sensor is electrically connected with the controller, the water content sensor is arranged between the discharge port of the first blanking bin and the feed port of the first weighing bin, and the water content sensor is used for detecting the water content of the sand sample in the first blanking bin. The concrete preparation device can detect the moisture content of the sand sample in real time and adjust the raw material ratio of the concrete according to the moisture content of the sand sample.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of concrete configuration, and in particular to a concrete configuration device and a mix ratio adjustment method. Background Art

[0002] Compressive strength, durability, etc. are the main indicators for measuring concrete quality. In the process of concrete preparation, the moisture content of concrete directly affects the strength and durability of concrete. Among the raw materials for concrete preparation, the content of sand often affects the change of moisture content. In traditional concrete preparation devices, concrete is usually sampled for moisture content regularly or in batches. Only the moisture content of the sample at a certain sampling point is obtained. In addition, due to the influence of objective factors such as transportation and manual test operations, the test results have a certain lag and uncertainty. Operators are still required to increase or decrease the amount of water based on experience and observation of the mixing conditions. In this way, it is impossible to strictly control the quality of concrete. Summary of the invention

[0003] In view of this, the purpose of the present application is to overcome the deficiencies in the prior art and to provide a concrete configuration device that can detect the moisture content of a sand sample in real time and adjust the raw material ratio of the concrete according to the moisture content of the sand sample.

[0004] The present application also provides a method for adjusting the mix ratio of concrete.

[0005] To achieve the above objectives, the technical solutions adopted in this application are as follows:

[0006] The concrete configuration device according to the first aspect of the embodiment of the present application includes a first configuration unit and a controller, wherein the first configuration unit includes: a first feed bin; a first weighing component, wherein the first weighing component includes a first weighing bin, wherein the feed port of the first weighing bin is connected to the discharge port of the first feed bin, and the first weighing bin is used to weigh the weight of the sand sample in the first feed bin; a detection component, wherein the detection component includes a moisture content sensor, wherein the moisture content sensor is electrically connected to the controller, and the moisture content sensor is arranged between the discharge port of the first feed bin and the feed port of the first weighing bin, and the moisture content sensor is used to detect the moisture content of the sand sample in the first feed bin; wherein the preset weight of sand for each sand mixing is akg, and each time the sand is mixed, the sand sample is divided into two steps for sand mixing, the first feed bin is used to carry the sand sample of the first step of each sand mixing, and the weight of the sand sample in the first feed bin is b n kg, meets: b n =[(a+aw)×m]kg, w is the moisture content detected by the moisture content sensor during the n-1th sand mixing, m is a preset percentage, and n is a positive integer greater than 1.

[0007] The concrete configuration device of the present application has the following advantages:

[0008] In the above concrete configuration device, each time the concrete is configured, the proportion of sand and other concrete raw materials must be configured according to the set moisture content of the concrete. In each configuration process, the sand sample is configured in two steps, so that the configuration proportion of the remaining sand sample and other concrete raw materials can be adjusted in time according to the new moisture content measured after the first step of sand configuration. In each case, when the sand sample is configured in the first step, b n =[(a+aw)×m]kg of sand sample is poured into the first feeding bin, and the sand sample of this weight flows out from the discharge port of the first feeding bin, and enters the first weighing bin through the feed port of the first weighing bin. Before the sand sample enters the first weighing bin, the moisture content of the sand sample flowing out from the discharge port of the first feeding bin can be detected by the moisture content sensor, and the configuration ratio of the remaining sand sample and other concrete raw materials can be adjusted in time according to the moisture content. In this way, the above-mentioned concrete configuration device can detect the moisture content of the sand sample in real time and adjust the raw material ratio of the concrete according to the moisture content of the sand sample. Further, each time the sand sample is configured, the preset sand weight akg plus the preset sand weight and the moisture content of the sand sample detected by the moisture content sensor during the last sand configuration are used as the adjusted sand weight, that is, (a+aw)kg. In this way, the reduction in sand concentration caused by the moisture content can be compensated, thereby reducing the impact on the strength and durability of the concrete.

[0009] According to the concrete configuration device of the first aspect of the present application, the following condition is satisfied: 80%≤m≤90%.

[0010] According to the concrete configuration device of the first aspect of the present application, the detection component also includes a fixing part and a fixing sleeve, one end of the fixing part is fixedly connected to the outer wall of the first lower silo, the other end of the fixing part is fixedly connected to the fixing sleeve, and the end of the fixing sleeve away from the fixing part is sleeved on the moisture content sensor.

[0011] According to the concrete configuration device of the first aspect of the present application, the first configuration unit further includes a purge component, the purge component is fixedly connected to the detection component, and the purge component is used to purge the moisture content sensor.

[0012] According to the concrete configuration device of the first aspect of the present application, the first weighing assembly further includes a first weighing sensor, the first weighing sensor is connected to the first weighing bin, and the first weighing sensor is electrically connected to the first weighing bin and the controller.

[0013] According to the concrete configuration device of the first aspect of the present application, the concrete configuration device also includes a second configuration unit, the second configuration unit includes a second lower material bin and a second weighing bin, and the discharge port of the second lower material bin is connected to the feed port of the second weighing bin.

[0014] According to the concrete configuration device of the first aspect of the present application, the second configuration unit also includes a second weighing sensor, the second weighing sensor is connected to the second weighing bin, and the second weighing sensor is electrically connected to the second weighing bin and the controller.

[0015] According to the concrete configuration device of the first aspect of the present application, the concrete configuration device includes a plurality of second configuration units, and the second weighing sensor of each second configuration unit is electrically connected to the controller.

[0016] According to the concrete configuration device of the first aspect of the present application, after the first configuration unit completes the first step of sand configuration each time, the second material discharging bin is used to configure the cement, gravel, water, water reducer and the sand sample of the second step of sand configuration each time in the concrete, and the weight of the cement, gravel, water, water reducer and the sand sample of the second step of sand configuration each time in the second material discharging bin is weighed by the second weighing bin;

[0017] Among them, after completing the first step of sand mixing each time, the weight of cement, crushed stone, water, water reducing agent and the sand sample of the second step of sand mixing each time is determined according to the new water content of the sand sample.

[0018] The concrete mix ratio adjustment method according to the second aspect of the present application is applied to the concrete configuration device as described above, comprising:

[0019] The first step of mixing sand is carried out in the first lower material bin, and the weight of the sand sample in the first lower material bin is b n kg, meets: b n =[(a+aw)×m]kg, a is the preset weight of sand for each sand mixing, w is the moisture content detected by the moisture content sensor during the n-1th sand mixing, m is the preset percentage, and n is a positive integer greater than 1;

[0020] Complete the second step of preparing sand and other concrete raw materials.

[0021] The concrete mix ratio adjustment method of the present application has the following advantages:

[0022] In the above-mentioned concrete mix ratio adjustment method, the moisture content of the sand sample can be detected at any time, and the configuration ratio of the sand sample, cement, crushed stone, water and water reducing agent can be adjusted in time according to the detected moisture content. In this way, the above-mentioned concrete mix ratio adjustment method can make the moisture content of the concrete meet the strength and durability requirements of the concrete. BRIEF DESCRIPTION OF THE DRAWINGS

[0023] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0024] Figure 1 A schematic diagram showing the structure of the first configuration unit in the present application is shown;

[0025] Figure 2 A schematic diagram showing the structure of the detection component in the present application is shown;

[0026] Figure 3 A schematic diagram of the structure of the first weighing assembly in the present application is shown;

[0027] Figure 4 A schematic diagram showing the structure of the second configuration unit in the present application is shown;

[0028] Figure 5 A schematic diagram of the process of adjusting the proportion of concrete in the present application is shown;

[0029] Figure 6 A schematic flow chart of a method for adjusting the mix ratio of concrete according to an embodiment of the present application is shown.

[0030] Description of main component symbols:

[0031] 10- a first configuration unit;

[0032] 100-first lower silo;

[0033] 200-first weighing assembly; 210-first weighing bin; 220-first weighing sensor;

[0034] 300-detection component; 310-water content sensor; 320-fixing part; 330-fixing sleeve;

[0035] 400-Purge assembly;

[0036] 20 - second configuration unit; 21 - second unloading bin; 22 - second weighing bin; 23 - second weighing sensor. DETAILED DESCRIPTION

[0037] The embodiments of the present application are described in detail below, and examples of the embodiments are shown in the accompanying drawings, wherein the same or similar reference numerals throughout represent the same or similar elements or elements having the same or similar functions. The embodiments described below with reference to the accompanying drawings are exemplary and are only used to explain the present application, and cannot be understood as limiting the present application.

[0038] In the description of the present application, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "up", "down", "front", "back", "left", "right", "vertical", "horizontal", "top", "bottom", "inside", "outside", "clockwise", "counterclockwise", "axial", "radial", "circumferential" and the like indicate orientations or positional relationships based on the orientations or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present application and simplifying the description, and do not indicate or imply that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, and therefore should not be understood as a limitation on the present application.

[0039] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of the features. In the description of this application, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.

[0040] In this application, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in this application can be understood according to specific circumstances.

[0041] In the present application, unless otherwise clearly specified and limited, a first feature being “above” or “below” a second feature may mean that the first and second features are in direct contact, or the first and second features are in indirect contact through an intermediate medium. Moreover, a first feature being “above”, “above”, and “above” a second feature may mean that the first feature is directly above or obliquely above the second feature, or simply means that the first feature is higher in level than the second feature. A first feature being “below”, “below”, and “below” a second feature may mean that the first feature is directly below or obliquely below the second feature, or simply means that the first feature is lower in level than the second feature.

[0042] Reference Figures 1 to 3 As shown, the concrete configuration device involved in the embodiment of the present application includes a first configuration unit 10 and a controller. The first configuration unit 10 includes: a first lower silo 100, a first weighing component 200 and a detection component 300.

[0043] Specifically, the first weighing component 200 includes a first weighing bin 210, the feed port of the first weighing bin 210 is connected to the discharge port of the first lower bin 100, and the first weighing bin 210 is used to weigh the weight of the sand sample in the first lower bin 100; the detection component 300 includes a moisture content sensor 310, the moisture content sensor 310 is electrically connected to the controller, and the moisture content sensor 310 is arranged between the discharge port of the first lower bin 100 and the feed port of the first weighing bin 210, and the moisture content sensor 310 is used to detect the moisture content of the sand sample in the first lower bin 100; wherein, the preset sand weight for each sand mixing is akg, and each time the sand is mixed, the sand sample is divided into two steps for sand mixing, the first lower bin 100 is used to carry the sand sample of the first step of each sand mixing, and the weight of the sand sample in the first lower bin 100 is b n kg, meets: b n =[(a+aw)×m]kg, w is the moisture content detected by the moisture content sensor 310 during the n-1th sand mixing, m is a preset percentage, and n is a positive integer greater than 1.

[0044] In the above concrete configuration device, each time the concrete is configured, the proportion of sand and other concrete raw materials must be configured according to the set moisture content of the concrete. In each configuration process, the sand sample is configured in two steps, so that the configuration proportion of the remaining sand sample and other concrete raw materials can be adjusted in time according to the new moisture content measured after the first step of sand configuration. In each case, when the sand sample is configured in the first step, b n =[(a+aw)×m]kg of sand sample is poured into the first lower material bin 100, and the sand sample of this weight flows out from the discharge port of the first lower material bin 100, and enters the first weighing bin 210 through the feed port of the first weighing bin 210. Before the sand sample enters the first weighing bin 210, the moisture content of the sand sample flowing out from the discharge port of the first lower material bin 100 can be detected by the moisture content sensor 310, and the configuration ratio of the remaining sand sample and other concrete raw materials can be adjusted in time according to the moisture content. In this way, the above-mentioned concrete configuration device can detect the moisture content of the sand sample in real time and adjust the raw material ratio of the concrete according to the moisture content of the sand sample. Furthermore, each time the sand sample is prepared, the preset sand weight akg plus the preset sand weight and the moisture content of the sand sample detected by the moisture content sensor 310 during the last sand preparation is used as the adjusted sand weight, that is, (a+aw)kg. In this way, the reduction in sand concentration caused by the moisture content can be compensated, thereby reducing the impact on the strength and durability of the concrete.

[0045] Specifically, it satisfies: 80%≤m≤90%.

[0046] More specifically, m may be 80%, 84%, 88%, 90%, and so on.

[0047] It should be noted that in the process of preparing concrete, keeping the moisture content of concrete between 0 and 12% can meet the strength and durability requirements of concrete. If the moisture content of concrete is less than 0, the ductility and adhesion of the concrete will be too low. If the moisture content of concrete is greater than 12%, the strength and durability of the concrete will be reduced.

[0048] In this embodiment, when m is less than 80%, the sand sample added to the first lower hopper 100 will be less than 80% of (a+aw) kg. In this way, when the remaining sand sample is configured in the second step, the weight of the remaining sand sample will be greater than 20% of (a+aw) kg, and the moisture content of the sand sample after the two-step sand mixing will be too low, so that the durability of the configured concrete cannot meet the requirements. When m is greater than 90%, the sand sample added to the first lower hopper 100 will be greater than 90% of (a+aw) kg. In this way, when the remaining sand sample is configured in the second step, the weight of the remaining sand sample will be less than 10% of (a+aw) kg, and the moisture content of the sand sample after the two-step sand mixing will be too high, so that the strength of the configured concrete cannot meet the requirements. When 80%≤m≤90%, the moisture content of the sand sample after the two-step sand mixing can meet the strength and durability requirements of the concrete.

[0049] Reference Figure 2 As shown, the detection component 300 also includes a fixing member 320 and a fixing sleeve 330. One end of the fixing member 320 is fixedly connected to the outer wall of the first lower silo 100, and the other end of the fixing member 320 is fixedly connected to the fixing sleeve 330. The end of the fixing sleeve 330 away from the fixing member 320 is sleeved on the moisture content sensor 310.

[0050] In this embodiment, since one end of the fixing member 320 is fixedly connected to the outer wall of the first lower material bin 100, and the other end of the fixing member 320 is fixedly connected to the fixing sleeve 330, the fixing sleeve 330 can be fixed by the fixing member 320. At the same time, since the end of the fixing sleeve 330 away from the fixing member 320 is sleeved on the moisture content sensor 310, the moisture content sensor 310 can be fixed by the fixing sleeve 330. When the sand sample flows through the moisture content sensor 310, the impact of the sand sample can be avoided to cause the moisture content sensor 310 to be displaced, so that the moisture content sensor 310 can detect the moisture content of the sand sample flowing out through the discharge port of the first lower material bin 100 each time.

[0051] Continue to refer to Figure 2As shown, the first configuration unit 10 further includes a purge component 400 , which is fixedly connected to the detection component 300 , and the purge component 400 is used to purge the water content sensor 310 .

[0052] In this embodiment, when the sand sample flows through the moisture content sensor 310, some sand samples will remain on the moisture content sensor 310. As the number of sand mixing increases, the sand samples will gradually accumulate on the moisture content sensor 310, so that the detection accuracy of the moisture content sensor 310 is reduced. In this way, after each sand mixing, the moisture content sensor 310 can be purged by the purge component 400 to prevent the sand samples from accumulating on the moisture content sensor 310.

[0053] Reference Figure 3 As shown, the first weighing assembly 200 further includes a first weighing sensor 220 , which is connected to the first weighing bin 210 , and the first weighing sensor 220 is electrically connected to the first weighing bin 210 and the controller.

[0054] In this embodiment, since the first weighing sensor 220 is electrically connected to the first weighing bin 210 and the controller, when the sand sample enters the first weighing bin 210 through the feed port of the first weighing bin 210, the weight signal of the sand sample in the first weighing bin 210 can be transmitted to the controller in real time through the first weighing sensor 220.

[0055] Reference Figure 4 As shown, the concrete configuration device further includes a second configuration unit 20 , which includes a second lower material bin 21 and a second weighing bin 22 , and a discharge port of the second lower material bin 21 is connected to a feed port of the second weighing bin 22 .

[0056] In this embodiment, cement, gravel, water, water reducing agent and sand samples of the second step of sand mixing in concrete can be configured through the second material bin 21, and cement, gravel, water, water reducing agent and sand samples of the second step of sand mixing in concrete can be weighed through the second weighing bin 22 to complete the final configuration of the concrete.

[0057] Continue to refer to Figure 4 As shown, the second configuration unit 20 further includes a second weighing sensor 23, which is connected to the second weighing bin 22, and the second weighing sensor 23 is electrically connected to the second weighing bin 22 and the controller.

[0058] In this embodiment, since the second weighing sensor 23 is electrically connected to the second weighing bin 22 and the controller, when the cement, gravel, water, water reducer in the concrete and the sand sample of the second step of each sand mixing enter the second weighing bin 22 through the feed port of the second weighing bin 22, the weight signal of the cement, gravel, water, water reducer in the concrete in the second weighing bin 22 and the sand sample of the second step of each sand mixing can be transmitted to the controller in real time through the second weighing sensor 23.

[0059] Specifically, the concrete configuration device includes a plurality of second configuration units 20, and the second weighing sensor 23 of each second configuration unit 20 is electrically connected to the controller.

[0060] It is understandable that cement, crushed stone, water, water reducing agent and sand sample of the second step of each sand mixing process in concrete can be simultaneously mixed by multiple second mixing units 20, so as to improve the mixing efficiency of concrete.

[0061] Specifically, after the first configuration unit 10 completes the first step of sand mixing each time, the second lower material bin 21 is used to configure cement, crushed stone, water, water reducing agent and sand sample of the second step of sand mixing each time in the concrete, and the weight of cement, crushed stone, water, water reducing agent and sand sample of the second step of sand mixing each time in the second lower material bin 21 is weighed by the second weighing bin 22;

[0062] Among them, after completing the first step of sand mixing each time, the weight of cement, crushed stone, water, water reducing agent and the sand sample of the second step of sand mixing each time is determined according to the new water content of the sand sample.

[0063] In this embodiment, during each batching process, after the first step of sand batching is completed, the weight of cement, gravel, water, water reducing agent and the sand sample of the second step of sand batching is adjusted according to the new moisture content of the sand sample in the first lower hopper 100 detected by the moisture content sensor 310, so that the moisture content of the concrete can be within the qualified range, thereby ensuring the strength and durability of the concrete.

[0064] Reference Figure 5 As shown, the concrete mix ratio adjustment method involved in the embodiment of the present application is applied to the above-mentioned concrete configuration device, including:

[0065] S100: The first step of mixing sand into the first material bin 100 is performed, and the weight of the sand sample in the first material bin 100 is b n kg, meets: b n =[(a+aw)×m]kg, a is the preset sand weight for each sand mixing, w is the moisture content detected by the moisture content sensor 310 during the n-1th sand mixing, m is the preset percentage, and n is a positive integer greater than 1.

[0066] Specifically, each time the ingredients are mixed, the sand in the raw materials of the concrete is mixed first, and after the mixing of the sand is completed, cement, crushed stone, water and water reducing agent are mixed. Each time the sand sample is mixed, the sand sample is divided into two parts for two-step mixing. In the first step of mixing, b is added to the first lower bin 100. n =[(a+aw)×m]kg sand sample, and detect b through the moisture content sensor 310 n kg of moisture content, and use this moisture content as w for the next sand mixing.

[0067] S200: Complete the second step of mixing sand and other concrete raw materials.

[0068] Specifically, each time the ingredients are mixed, after the first configuration of the sand sample is completed, the weight of the sand sample for the second step and the weight of other concrete raw materials are adjusted according to the new moisture content detected by the moisture content sensor 310, so that the moisture content of the final concrete meets the strength and durability requirements of the concrete, wherein the weight of the sand sample for the second step may be equal to [(a+aw)×(1-m)]kg, or may not be equal to [(a+aw)×(1-m)]kg, and the specific weight depends on the final moisture content required for the concrete.

[0069] In the above-mentioned concrete mix ratio adjustment method, the moisture content of the sand sample can be detected at any time, and the configuration ratio of the sand sample, cement, crushed stone, water and water reducing agent can be adjusted in time according to the detected moisture content. In this way, the above-mentioned concrete mix ratio adjustment method can make the moisture content of the concrete meet the strength and durability requirements of the concrete.

[0070] Reference Figure 6 As shown, the following takes the preset sand weight akg, the preset cement weight ckg, the preset crushed stone weight dkg, the preset water addition amount ekg, and the preset water reducing agent weight fkg as an example to configure the concrete:

[0071] S1000, adding [(a+aw)×m]kg of sand sample into the first lower silo 100, and calculating the moisture content of [(a+aw)×m]kg of sand sample;

[0072] S2000, calculate the formula according to the moisture content of [(a+aw)×m]kg of the sand sample, confirm whether the sand sample, cement, crushed stone, water and water reducing agent of the second step of sand preparation are configured with the preset weight, and assume that the sand sample, cement, crushed stone, water and water reducing agent of the second step of sand preparation in the calculated formula are configured with the preset weight, then add [(a+aw)×(1-m)]kg of sand sample and ckg of cement into the second feeding bin 21 to feed [(a+aw)×(1-m)]kg of sand sample and ckg of cement, and stir;

[0073] S3000, add (e-aw) kg of water into the second unloading bin 21 to complete the unloading of water, and mix the (e-aw) kg of water with the sand sample and cement after mixing;

[0074] S4000, add dkg of crushed stone into the second material bin 21 to complete the discharge of crushed stone, then add fkg of water reducer into the second material bin 21 to complete the discharge of water reducer, and mix dkg of crushed stone and fkg of water reducer with the mixed water, sand sample and cement to obtain the final concrete.

[0075] Specifically, if the weight of the sand sample in the second step of sand mixing, the weight of cement, the weight of crushed stone, the weight of water and the weight of the water reducing agent in the calculated formula do not match the preset weight, the weight of the corresponding ingredients will be adjusted according to the calculation results to ensure that the moisture content of the concrete meets the requirements of strength and durability.

[0076] In the description of this specification, the description with reference to the terms "one embodiment", "some embodiments", "example", "specific example", or "some examples" etc. means that the specific features, structures, materials or characteristics described in conjunction with the embodiment or example are included in at least one embodiment or example of the present application. In this specification, the schematic representations of the above terms do not necessarily refer to the same embodiment or example. Moreover, the specific features, structures, materials or characteristics described may be combined in any one or more embodiments or examples in a suitable manner. In addition, those skilled in the art may combine and combine the different embodiments or examples described in this specification and the features of the different embodiments or examples, without contradiction.

[0077] Although the embodiments of the present application have been shown and described above, it can be understood that the above embodiments are exemplary and cannot be understood as limitations on the present application. Ordinary technicians in this field can change, modify, replace and modify the above embodiments within the scope of the present application.

Claims

1. A concrete configuration device, characterized in that: The invention comprises a first configuration unit and a controller, wherein the first configuration unit comprises: First lower silo; A first weighing component, the first weighing component comprises a first weighing bin, a feed port of the first weighing bin is connected to a discharge port of the first lower bin, and the first weighing bin is used to weigh the weight of the sand sample in the first lower bin; A detection component, the detection component includes a moisture content sensor, the moisture content sensor is electrically connected to the controller, and the moisture content sensor is arranged between the discharge port of the first lower material bin and the feed port of the first weighing bin, and the moisture content sensor is used to detect the moisture content of the sand sample in the first lower material bin; The preset weight of each sand mixing is akg, and the sand sample is divided into two steps for each sand mixing. The first lower material bin is used to carry the sand sample of the first step of each sand mixing. The weight of the sand sample in the first lower material bin is b. n kg, meets: b n =[(a+aw)×m]kg, w is the moisture content detected by the moisture content sensor during the n-1th sand mixing, m is a preset percentage, and n is a positive integer greater than 1.

2. The concrete dispensing device according to claim 1, characterized in that: Satisfies: 80%≤m≤90%.

3. The concrete dispensing device according to claim 1, characterized in that: The detection component also includes a fixing part and a fixing sleeve, one end of the fixing part is fixedly connected to the outer wall of the first lower silo, the other end of the fixing part is fixedly connected to the fixing sleeve, and the end of the fixing sleeve away from the fixing part is sleeved on the moisture content sensor.

4. The concrete dispensing device according to claim 1, characterized in that: The first configuration unit also includes a purge component, which is fixedly connected to the detection component and is used to purge the moisture content sensor.

5. The concrete dispensing device according to claim 1, characterized in that: The first weighing assembly also includes a first weighing sensor, which is connected to the first weighing bin, and is electrically connected to the first weighing bin and the controller.

6. The concrete dispensing device according to any one of claims 1 to 5, characterized in that: The concrete configuration device further includes a second configuration unit, which includes a second lower material bin and a second weighing bin, and a discharge port of the second lower material bin is connected to a feed port of the second weighing bin.

7. The concrete dispensing device according to claim 6, characterized in that: The second configuration unit further includes a second weighing sensor, which is connected to the second weighing bin, and is electrically connected to the second weighing bin and the controller.

8. The concrete dispensing device according to claim 7, characterized in that: The concrete configuration device includes a plurality of the second configuration units, and the second weighing sensor of each of the second configuration units is electrically connected to the controller.

9. The concrete dispensing device according to claim 6, characterized in that: After the first configuration unit completes the first step of sand mixing each time, the second material discharging bin is used to configure cement, gravel, water, water reducing agent and sand sample of the second step of sand mixing each time in the concrete, and the weight of cement, gravel, water, water reducing agent and sand sample of the second step of sand mixing each time in the second material discharging bin is weighed by the second weighing bin; Among them, after completing the first step of sand mixing each time, the weight of cement, crushed stone, water, water reducing agent and the sand sample of the second step of sand mixing each time is determined according to the new water content of the sand sample.

10. A method for adjusting the mix ratio of concrete, characterized in that: A device for disposing concrete as claimed in any one of claims 1 to 9, comprising: The first step of mixing sand is carried out in the first lower material bin, and the weight of the sand sample in the first lower material bin is b n kg, meets: b n =[(a+aw)×m]kg, a is the preset weight of sand for each sand mixing, w is the moisture content detected by the moisture content sensor during the n-1th sand mixing, m is the preset percentage, and n is a positive integer greater than 1; Complete the second step of preparing sand and other concrete raw materials.