Ventilation groove structure of ship ballast tank
By designing a breathable groove structure composed of vertical and transverse steel plates, the problem that the ballast tank air permeability pipe cannot be placed at the highest point in the prior art is solved, and the complete discharge of air in the ballast tank is achieved, and the ship stability and cargo are improved. Load space and prevent corrosion and thermal expansion and contraction problems.
Patent Information
- Application Number
- CN202411248545.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-09-06
- Publication Date
- 2024-11-29
AI Technical Summary
The existing design of the ballast tank air pipe of the existing ship must avoid the cargo tank bottom plate structure and cannot be placed at the highest point of the ballast tank, which makes it difficult to discharge air, affecting the stability and floating adjustment of the ship, and the top is prone to corrosion and thermal expansion and contraction. Deformation.
Design a breathable groove structure. The breathable groove consists of vertical and transverse steel plates, which are fixedly connected to the cargo valley bottom plate and the side wall of the ballast tank to form a hollow tubular structure. The air pipe passes vertically out of the deck and communicates with the breathable groove. The breathable groove penetrates the cargo valley bottom plate. The through holes of the lower structural parts ensure that the air can be completely discharged.
The complete air leakage at the top of the ballast tank is achieved, the free liquid level is avoided, the stability of the ship is improved, the number of ballast tanks is reduced, the cargo loading space is increased, and bulkhead corrosion and thermal expansion and contraction are prevented. pressure.
Smart Images

Figure CN119037623A_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of ships, in particular to a venting groove structure of a ship ballast tank. Background Art
[0002] To ensure the stability of the ship, the ship needs to be equipped with multiple ballast water tanks to load ballast water to adjust the buoyancy of the ship. To ensure that the air in the tank can be discharged smoothly when the ballast tank is filled with water. Each ballast tank needs to be equipped with a vent pipe to the open area. The air pipe should be set at the highest point of the tank to ensure that the air in the tank is completely discharged. Due to the need for ship stability, some ballast tanks are located below the cargo hold, and their tops are completely covered by the cargo hold. If an air pipe is set on the top of this ballast tank, the air pipe must be arranged in the cargo hold, which affects the loading of cargo. At the same time, if the air pipe is arranged in the cargo hold, the ballast water will leak into the cargo hold through the air pipe when the pipe is damaged. The hull structure on the bottom plate of the cargo hold needs to be set below the bottom plate to ensure that the inner wall of the cargo hold is smooth and convenient for cargo loading and unloading. The existing air pipe design scheme is: a transverse air pipe is set on the side wall of the ballast tank, first leading to the side area, and then upward to the open area. The diameter of the air pipe is too large, and passing through the hull structure will make it difficult to meet the hull strength. Therefore, the transverse air pipe needs to be arranged below the cargo ship hull structure. At this time, the air pipe is not at the highest point of the ballast tank. A large amount of air has accumulated on the top of the ballast tank and cannot be discharged.
[0003] The disadvantage of the prior art is that the height of the transverse air duct is limited by the structural components under the cargo hold floor and cannot be arranged at the highest point of the ballast tank. A large amount of air accumulates on the top of the ballast tank and cannot be discharged.
[0004] The resulting disadvantages are as follows:
[0005] When a ship is sailing, the ballast water in the ballast tank sloshes to form a free liquid surface, generating a large amount of free moment, which affects the stability of the ship.
[0006] The ballast tanks cannot be filled with water, resulting in the actual ballast volume of the ship being less than the design requirement, and the buoyancy of the ship cannot be adjusted to the design condition;
[0007] The top of the ballast tank is exposed to alternating air and water for a long time, and the tank wall is prone to corrosion;
[0008] The air trapped on top expands and contracts as the temperature changes, creating pressure on the ballast tanks and causing the hull panels to deform. Summary of the invention
[0009] The object of the present invention is to provide a venting groove structure for a ship ballast tank to overcome the defects in the prior art.
[0010] The object of the present invention is achieved as follows: A venting groove structure for a ship ballast tank, comprising:
[0011] A vent structure, which is fixedly connected to the cargo hold bottom plate and the ballast tank side wall, is in a strip shape as a whole, and extends outward from the bottom ballast tank to the side ballast tank area, and is a hollow tubular structure, the inner end of which is connected to the bottom ballast tank;
[0012] The air pipe is vertically fixed in the side ballast tank, the upper section of which passes upward through the deck and communicates with the outside atmosphere, and the lower section of which is fixedly connected to and communicates with the outer end of the air permeable groove structure.
[0013] Furthermore, it also includes a sub-bottom plate structure fixedly connected to the cargo hold floor, the sub-bottom plate structure is provided with a through hole, the air vent structure penetrates the through hole of the sub-bottom plate structure of the cargo hold floor, and a gap is left between the through hole of the sub-bottom plate structure.
[0014] Furthermore, the air permeable groove structure is composed of a vertical steel plate and a transverse steel plate fixedly combined with each other, the vertical steel plate is vertically arranged and the upper edge thereof is fixedly connected to the cargo hold bottom plate, the transverse steel plate is horizontally arranged and one side thereof is fixedly connected to the ballast tank side wall, the other side of the transverse steel plate is vertically fixedly connected to the lower edge of the vertical steel plate, the transverse steel plate, the vertical steel plate, the cargo hold bottom plate and the ballast tank side wall are combined to form an inner cavity of the air permeable groove structure, and gaps are left between the vertical steel plate and the transverse steel plate and the through holes of the structural member under the bottom plate.
[0015] Furthermore, a vertical bridging plate is welded and fixed to one side of the vertical steel plate, and the vertical bridging plate is fixedly connected to the cargo hold bottom plate by welding.
[0016] Furthermore, a transverse bridging plate is welded and fixed to one side of the transverse steel plate, and the transverse bridging plate is fixedly connected to the side wall of the ballast tank by welding.
[0017] Furthermore, a plurality of reinforcing shaft plates for structural reinforcement are fixedly connected to the bottom of the bottom plate lower structure, the reinforcing shaft plates are fixedly connected to the side walls of the ballast tank, and the reinforcing shaft plates are located directly below the through holes of the bottom plate lower structure.
[0018] Furthermore, the ventilation groove structures are provided in plurality and distributed along the length direction of the hull; the ventilation groove structures are distributed on the left side and / or the right side of the hull.
[0019] The beneficial effects of the present invention are:
[0020] 1. The air on the top of the ballast tank can be completely permeable, and no free liquid surface will be formed in the ballast tank, which is beneficial to the stability of the ship;
[0021] 2. The ballast tanks can be fully filled, allowing the ship to reduce the number of ballast tanks and leave more cargo space;
[0022] 3. The top area of the ballast tank is always filled with water, so the bulkhead will not be exposed to humid air and is not prone to corrosion;
[0023] 4. There is no residual air in the ballast tank, and when the ambient temperature changes, the thermal expansion and contraction of the gas will not generate additional pressure on the bulkhead. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 It is a structural arrangement diagram of the present invention.
[0025] Figure 2 yes Figure 1 AA view in.
[0026] Figure 3 yes Figure 1 BB section view in.
[0027] Figure 4 It is a schematic diagram of the structural details of the ventilation groove. DETAILED DESCRIPTION
[0028] The following will be combined with the attached embodiment of the present invention Figure 1-4 , the technical solutions in the embodiments of the present invention are clearly and completely described. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0029] like Figure 1 , 2 As shown, a venting slot structure for a ship ballast tank is proposed, comprising:
[0030] The air trough structure 1 is fixedly connected to the cargo hold bottom plate 2 and the ballast tank side wall 5. The air trough structure 1 is in a strip shape as a whole and extends outward from the bottom ballast tank to the side ballast tank area. The air trough structure 1 is a hollow tubular structure, and its inner end is connected to the inside of the bottom ballast tank. There are multiple air trough structures 1, which are distributed along the length direction of the hull. The air trough structures 1 are distributed on the left side and / or the right side of the hull, that is, the air trough structures 1 can be distributed on the left side or the right side of the hull, and can also be distributed on both the left and right sides of the hull;
[0031] The air pipe 6 is vertically fixed in the side ballast tank, and its upper section passes through the deck 7 upward. The upper end of the air pipe 6 is fixedly connected with an air pipe head, thereby connecting the air cavity of the ballast tank with the outside atmosphere, that is, achieving a ventilation effect. The lower section of the air pipe 6 is fixedly connected and connected to the outer end of the ventilation groove structure 1.
[0032] The opening at the outer end of the air-permeable groove structure 1 is connected to the air pipe 6 , and the inner end of the air-permeable groove structure 1 is connected to the air hole 12 of the mid-bottom ballast tank 9 .
[0033] by Figure 1-2 Taking the example shown, the inner end of the air groove structure 1 is connected to the air hole 12 of the middle bottom ballast tank 9, the air groove structure 1 passes through the left bottom ballast tank 10, the outer end of the air groove structure 1 is in the left ballast tank 11, the lower end of the air pipe 6 is fixedly connected to the outer end of the air groove structure 1, and the outer end opening of the air groove structure 1 is connected to the air pipe 6.
[0034] As a preferred embodiment, Figure 3 , 4 As shown, it also includes a bottom plate substructure 3 fixedly connected to the cargo hold bottom plate 2, the bottom plate substructure 3 is provided with a through hole, the air vent structure 1 penetrates the through hole of the bottom plate substructure 3 of the cargo hold bottom plate 2, and a gap is left between the through hole of the bottom plate substructure 3 to prevent the hull structure from deforming and squeezing the air vent structure 1.
[0035] As a preferred embodiment, Figure 4 As shown, the air trough structure 1 is composed of a vertical steel plate 1a and a transverse steel plate 1b fixedly combined with each other. The air trough structure 1 is an airtight structure. The vertical steel plate 1a is arranged vertically and its upper edge is fixedly connected to the cargo hold bottom plate 2, the transverse steel plate 1b is arranged horizontally and one side thereof is fixedly connected to the ballast tank side wall 5, and the other side of the transverse steel plate 1b is vertically fixedly connected to the lower edge of the vertical steel plate 1a. The transverse steel plate 1b, the vertical steel plate 1a, the cargo hold bottom plate 2 and the ballast tank side wall 5 are combined to form the inner cavity of the air trough structure 1, and a gap of 10 mm is left between the vertical steel plate 1a and the transverse steel plate 1b and the through holes of the lower structure 3 of the bottom plate to avoid direct contact between the air trough structure 1 and the lower structure 3 of the bottom plate.
[0036] In order to facilitate the fixing of the venting trough structure 1, a vertical bridge plate 1c is welded and fixed to one side of the vertical steel plate 1a, and the vertical bridge plate 1c is welded and fixed to the cargo hold bottom plate 2; a transverse bridge plate 1d is welded and fixed to one side of the transverse steel plate 1b, and the transverse bridge plate 1d is welded and fixed to the ballast tank side wall 5. In the process of constructing the venting trough structure 1, the vertical steel plate 1a and the transverse steel plate 1b are welded and fixed based on the vertical bridge plate 1c and the transverse bridge plate 1d, so as to avoid the venting trough structure 1 from damaging the paint of the hull structure during installation.
[0037] like Figure 3As shown, as a preferred embodiment, a plurality of reinforcing shaft plates 4 for structural reinforcement are fixedly connected to the bottom of the above-mentioned bottom plate structure 3, and the reinforcing shaft plates 4 are fixedly connected to the ballast tank side walls 5. The reinforcing shaft plates 4 are located directly below the through holes of the bottom plate structure 3, thereby structurally reinforcing the parts of the bottom plate structure 3 corresponding to the through holes.
[0038] As a preferred process structure setting scheme, the total cross-sectional area of the air trough (the inner cavity of the air trough structure 1) should be 1.25 times the cross-sectional area of the ballast tank injection pipe, and the required area of a single trough is the required total area divided by the number.
[0039] As a preferred process structure setting scheme, in order to ensure that the ballast tank can ventilate smoothly under any floating state, each ballast tank is provided with at least two ventilation grooves, respectively at the bow and the stern of the ballast tank.
[0040] As an optimal process structure setting scheme, the height of the air vent is as small as possible, and generally should be less than 1 / 4 of the height of the structural member penetrated; if the height of the air vent exceeds 1 / 4 of the height of the structural member 3 under the bottom plate, a reinforcing shaft plate 4 needs to be set under the air vent for reinforcement; the width of the air vent is obtained by dividing the required area of a single air vent by the groove height.
[0041] In the description of the present invention, it should be noted that the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "front", "back" and the like indicate directions or positional relationships based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific direction, be constructed and operated in a specific direction, and therefore cannot be understood as a limitation on the present invention; in the present invention, it should also be noted that the terms "installation" and "connection" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, an integrally formed connection, a mechanical connection, or an indirect connection through an intermediate connecting component, and the specific meaning of the terms in this utility model can be understood according to the specific circumstances.
[0042] It is obvious to those skilled in the art that the present invention is not limited to the details of the exemplary embodiments described above, and that the present invention can be implemented in other specific forms without departing from the spirit or essential features of the present invention. Therefore, the embodiments should be regarded as exemplary and non-limiting from any point of view, and the scope of the present invention is defined by the appended claims rather than the above description, and it is intended that all changes falling within the meaning and scope of the equivalent elements of the claims are included in the present invention, and any reference numerals in the claims should not be regarded as limiting the claims involved.
[0043] In addition, it should be understood that although the present specification is described according to implementation modes, not every implementation mode contains only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.
Claims
1. A venting groove structure for a ship ballast tank, characterized in that: include: A venting groove structure (1), the venting groove structure (1) is fixedly connected to the cargo hold bottom plate (2) and the ballast tank side wall (5), and is in a strip shape as a whole, and extends outward from the bottom ballast tank to the side ballast tank area, and the venting groove structure (1) is a hollow tubular structure, and its inner end is connected to the bottom ballast tank; An air pipe (6) is vertically fixed in the side ballast tank, an upper section of which passes upward through the deck (7) and is connected to the outside atmosphere, and a lower section of which is fixedly connected to and connected to the outer end of the air permeable groove structure (1).
2. The venting groove structure of a ship ballast tank according to claim 1, characterized in that: It also includes a bottom plate structure (3) fixedly connected to the cargo hold bottom plate (2), wherein the bottom plate structure (3) is provided with a through hole, and the air permeable groove structure (1) passes through the through hole of the bottom plate structure (3) of the cargo hold bottom plate (2), and a gap is left between the through hole of the bottom plate structure (3).
3. The venting groove structure of a ship ballast tank according to claim 2, characterized in that: The air permeable groove structure (1) is composed of a vertical steel plate (1a) and a transverse steel plate (1b) fixedly combined with each other. The vertical steel plate (1a) is arranged vertically and its upper edge is fixedly connected to the cargo hold bottom plate (2). The transverse steel plate (1b) is arranged horizontally and one side of it is fixedly connected to the ballast tank side wall (5). The other side of the transverse steel plate (1b) is vertically fixedly connected to the lower edge of the vertical steel plate (1a). The transverse steel plate (1b), the vertical steel plate (1a), the cargo hold bottom plate (2) and the ballast tank side wall (5) are combined to form an inner cavity of the air permeable groove structure (1). A gap is left between the vertical steel plate (1a) and the transverse steel plate (1b) and the through hole of the bottom plate lower structure (3).
4. The venting groove structure of a ship ballast tank according to claim 3, characterized in that: A vertical bridging plate (1c) is welded and fixed to one side of the vertical steel plate (1a), and the vertical bridging plate (1c) is fixedly connected to the cargo hold bottom plate (2) by welding.
5. The venting groove structure of a ship ballast tank according to claim 3, characterized in that: A transverse bridging plate (1d) is welded and fixed to one side of the transverse steel plate (1b), and the transverse bridging plate (1d) is fixedly connected to the ballast tank side wall (5) by welding.
6. The venting groove structure of a ship ballast tank according to claim 2, characterized in that: A plurality of reinforcing shaft plates (4) for structural reinforcement are fixedly connected to the bottom of the bottom plate lower structure (3); the reinforcing shaft plates (4) are fixedly connected to the ballast tank side walls (5); and the reinforcing shaft plates (4) are located directly below the through holes of the bottom plate lower structure (3).
7. A venting slot structure for a ship ballast tank according to any one of claims 1 to 6, characterized in that: The ventilation slot structures (1) are provided in plurality and are distributed along the length direction of the hull.
8. The venting groove structure of a ship ballast tank according to claim 7, characterized in that: The ventilation groove structure (1) is distributed on the left side and / or the right side of the hull.