Remote regulation signal-based power distribution terminal warehouse debugging method and device

By using a debugging method based on remote signal adjustment in the power distribution terminal warehouse, the debugging of the power distribution terminal is automatically completed, and the problem of low debugging efficiency caused by different fixed values ​​and control words in different regions is solved, achieving efficient and accurate Multiple terminals are debugged simultaneously.

CN119401646AActive Publication Date: 2025-02-07国网陕西省电力有限公司西安供电公司

Patent Information

Application Number
CN202411500150.9
Authority / Receiving Office
CN · China
Patent Type
Applications(China)
Current Assignee / Owner
Filing Date
2024-10-25
Publication Date
2025-02-07
Estimated Expiration
2044-10-25

AI Technical Summary

Technical Problem

The network connection and commissioning of power distribution automation terminals has high requirements for on-site staff proficiency, time consumption, low efficiency, high wireless communication costs and experimental errors caused by information transmission errors.

Method used

Using the power distribution terminal warehouse debugging method based on remote adjustment signals, send remote adjustment information through the main station, complete remote adjustment test, download the debugging task sheet, obtain the pre-stored test template, output the experimental signal to the power distribution terminal, and receive the response data , check the debugging results and realize automated debugging.

Benefits of technology

Solve the problem of inability to batch closed-loop testing caused by different protection fixed values ​​and control words in different areas of power distribution terminals, improve the simultaneous debugging efficiency of multiple power distribution terminals, reduce the demand for manual configuration test templates, improve the correctness of debugging and Efficiency and wireless communication reduces the need for personnel communication and confirmation.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN119401646A_ABST
    Figure CN119401646A_ABST
Patent Text Reader

Abstract

The invention discloses a power distribution terminal warehouse debugging method and device based on a remote regulation signal, and belongs to the field of power systems, and the method comprises the steps: downloading a remote signaling debugging task list from a main station after the main station issues remote regulation information to a power distribution terminal and completes a remote regulation test with the power distribution terminal; obtaining a pre-stored remote signaling test template according to the remote signaling debugging task list, and outputting an experiment signal corresponding to remote signaling debugging to the power distribution terminal according to the remote signaling test template; receiving remote signaling response data forwarded by the power distribution terminal through the master station, wherein the remote signaling response data is generated after the power distribution terminal applies the experimental signal; and checking the remote signaling response data according to the test data in the remote signaling test template, and judging a remote signaling debugging result. The method solves the problem that batch closed-loop testing cannot be carried out due to the fact that the power distribution terminals are derived from different protection setting values and control words in different regions, simultaneous debugging of the multiple power distribution terminals is facilitated, the debugging correctness and efficiency are guaranteed, and safe and reliable operation of a power distribution network is guaranteed.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the field of electric power systems, and in particular to a method and device for debugging a distribution terminal warehouse based on a remote control signal. Background Art

[0002] As an important equipment for distribution network automation, the stability and reliability of the functions and performance of distribution automation terminals directly affect the safety of electricity use and property safety of industry and residents. In order to achieve safe and reliable distribution networks, relevant enterprises and units must invest a lot of manpower and material resources to carry out the inspection and testing of distribution terminals, whether from the factory inspection of distribution terminal manufacturers or the acceptance inspection of power companies and annual inspection tests.

[0003] At present, in the network access and joint debugging of distribution automation terminals, the fault setting value is mainly sent to the tested terminal through the relay protection tester, and the staff on the tested terminal side and the master station side communicate to confirm whether the data uploaded by the tested terminal is accurate. Specifically, this test method requires the use of relay protection test instruments on site to add power to the distribution terminal and correctly activate the device protection. It also requires personnel on both the test terminal side and the master station side to be responsible for operation and communication. It can be seen that the above-mentioned test method currently has the following problems: it has high requirements for the proficiency of on-site staff, it is time-consuming and inefficient in large-scale debugging during batch debugging or maintenance, and there are additional wireless communication costs for operations in different locations and experimental errors caused by information transmission errors. Summary of the invention

[0004] The main purpose of the present invention is to solve the problem that closed-loop debugging cannot be performed during centralized warehouse debugging due to the different protection settings and control words of distribution terminals from different regions, as well as the problem of low debugging efficiency caused by the current reliance on manual one-to-one debugging of distribution terminals.

[0005] The present invention provides a distribution terminal warehouse debugging method based on remote regulation signals, comprising: after the master station sends remote regulation information to the distribution terminal and completes the remote regulation test with the distribution terminal, downloading the remote signal debugging task list from the master station; according to the remote signal debugging task list, obtaining the pre-stored remote signal test template, and outputting the experimental signal corresponding to the remote signal debugging to the distribution terminal according to the remote signal test template; receiving the remote signal response data forwarded by the distribution terminal via the master station, the remote signal response data is generated by the distribution terminal after the experimental signal is applied; according to the test data in the remote signal test template, checking the remote signal response data to determine the remote signal debugging result; wherein the master station stores a template setting list, and when the remote regulation test is performed between the master station and the distribution terminal, the setting value of each distribution terminal is modified according to the template setting list, and the setting value in the test template is pre-set according to the template setting list.

[0006] In the distribution terminal warehouse debugging method based on remote control signals of the present invention, after judging the remote signal debugging result, it also includes: downloading the telemetry debugging task list from the main station, obtaining the pre-stored telemetry test template according to the telemetry debugging task list, and outputting the experimental signal corresponding to the telemetry debugging to the distribution terminal according to the telemetry test template; receiving the telemetry response data forwarded by the distribution terminal via the main station, the telemetry response data is generated by the distribution terminal after applying the experimental signal corresponding to the telemetry debugging; checking the telemetry response data according to the test data in the telemetry test template to judge the telemetry debugging result.

[0007] In the distribution terminal warehouse debugging method based on remote control signals of the present invention, after the remote signal debugging is completed and the result is qualified, the method also includes: downloading the remote control debugging task list from the master station; waiting for the master station to issue the remote control command to the distribution terminal, and after the distribution terminal sends the internal remote control node data generated after executing the remote control command to the master station, receiving the remote control node data forwarded by the master station; checking the remote control node data according to the expected value of the remote control data, and judging the remote control debugging result, the expected value of the remote control data is determined according to the remote control debugging task list.

[0008] In the distribution terminal warehouse debugging method based on remote adjustment signals of the present invention, the remote signal debugging task list, the telemetry debugging task list or the remote control debugging task list is a debugging task list common to each distribution terminal.

[0009] In the distribution terminal warehouse debugging method based on remote adjustment signals of the present invention, the remote adjustment test includes the distribution terminal modifying the internal protection setting value and control word according to the remote adjustment setting value list issued by the master station.

[0010] In the power distribution terminal warehouse debugging method based on remote adjustment signals of the present invention, the joint adjustment device and the main station are connected by wireless communication via NB-LOT.

[0011] In the distribution terminal warehouse debugging method based on remote adjustment signals of the present invention, when there are multiple joint debugging devices, after downloading the remote signal or telemetry debugging task list from the main station, it also includes: each joint debugging device sends the remote signal or telemetry debugging task list to the host computer; accordingly, according to the remote signal or telemetry debugging task list, obtain the pre-stored remote signal or telemetry test template, specifically receive the remote signal or telemetry test template sent by the host computer; after receiving the debugging start signal sent by the host computer, output the experimental signal to the distribution terminal according to the remote signal or telemetry test template.

[0012] The present invention also provides a distribution terminal warehouse debugging device based on remote regulation signals, comprising: an extraction module, which is used to send remote regulation information to the distribution terminal at the master station, and download the remote signal debugging task list from the master station after completing the remote regulation test between the master station and the distribution terminal; an output module, which is used to obtain a pre-stored remote signal test template according to the remote signal debugging task list, and output the experimental signal corresponding to the remote signal debugging to the distribution terminal according to the remote signal test template; a receiving module, which is used to receive the remote signal response data forwarded by the distribution terminal via the master station, and the remote signal response data is generated by the distribution terminal after applying the experimental signal; a judgment module, which is used to check the remote signal response data according to the test data in the remote signal test template, and judge the remote signal debugging result; wherein the master station stores a template setting list, and when the remote regulation test is performed between the master station and the distribution terminal, the setting value of each distribution terminal is modified according to the template setting list, and the setting value in the test template is pre-set according to the template setting list.

[0013] In the distribution terminal warehouse debugging device based on remote control signals of the present invention, the extraction module is also used to download the telemetry debugging task list from the master station; the output module is also used to obtain the pre-stored telemetry test template according to the telemetry debugging task list, and output the experimental signal corresponding to the telemetry debugging to the distribution terminal according to the telemetry test template; the receiving module is also used to receive the telemetry response data forwarded by the distribution terminal via the master station, and the telemetry response data is generated by the distribution terminal after applying the experimental signal corresponding to the telemetry debugging; the judgment module is also used to check the telemetry response data according to the test data in the telemetry test template to judge the telemetry debugging result.

[0014] In the distribution terminal warehouse debugging device based on remote control signals of the present invention, the output module is also used to download the remote control debugging task list from the master station; the receiving module is also used to wait for the master station to issue the remote control command to the distribution terminal, and after the distribution terminal sends the internal remote control node data generated after executing the remote control command to the master station, it receives the remote control node data forwarded by the master station; the judgment module is also used to check the remote control node data according to the expected value of the remote control data, and judge the remote control debugging result, and the expected value of the remote control data is determined according to the remote control debugging task list.

[0015] The beneficial effects of the present invention are: solving the problem of being unable to perform closed-loop testing in batches due to the fact that the protection settings and control words of distribution terminals in different regions are different, facilitating the simultaneous debugging of multiple distribution terminals, and the test template does not need to be manually configured, further ensuring the correctness and efficiency of the debugging. In addition, the method can be implemented through unlimited communication without the need for personnel communication and confirmation, further improving the debugging efficiency and reliability, and ensuring the safe and reliable operation of the distribution network. BRIEF DESCRIPTION OF THE DRAWINGS

[0016] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for use in the embodiments or the description of the prior art. Obviously, the drawings described below are some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0017] Figure 1 It is a flow chart of a power distribution terminal warehouse debugging method based on remote adjustment signals according to an embodiment of the present invention;

[0018] Figure 2 It is a flow logic diagram of a power distribution terminal warehouse debugging method based on remote adjustment signals according to an embodiment of the present invention;

[0019] Figure 3 It is a schematic diagram of the debugging process of the remote signaling signal according to an embodiment of the present invention;

[0020] Figure 4 is a schematic diagram of a debugging process of a telemetry signal according to an embodiment of the present invention;

[0021] Figure 5 It is a schematic diagram of the debugging process of the remote control signal according to an embodiment of the present invention. DETAILED DESCRIPTION

[0022] In order to make the purpose, technical solution and advantages of the present invention more clearly understood, the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.

[0023] In the distribution network system, the distribution terminal devices often come from different regions and have different brands, and the protection settings and control words are not the same. At present, the protection function debugging can only be done by connecting the actual distribution terminal to the upper computer software of the distribution terminal manufacturer to fill in the settings and data one by one. It is very dependent on the on-site personnel's understanding of the distribution terminals of various brands, as well as the on-site personnel's certification of filling in the protection settings and control words. Batch debugging of distribution terminal devices requires continuous additions and settings of distribution terminal devices, which is less efficient when large-scale testing of distribution terminals is required. At present, the means of communication between the experimental site and the main station can only rely on manual labor, and most of the wireless communication means on the market are slightly more expensive. In addition, the current debugging method of the distribution terminal has high requirements on the work proficiency of on-site staff. Based on this, the present invention provides a distribution terminal warehouse debugging method and device based on remote adjustment signals.

[0024] Combine the following Figures 1 to 5 The power distribution terminal warehouse debugging method and device based on remote adjustment signal of the present invention are described. Figure 1is a flow chart of a power distribution terminal warehouse debugging method based on remote adjustment signals according to an embodiment of the present invention, the method is applied to a joint adjustment device, such as Figure 1 As shown, the present invention provides a distribution terminal warehouse debugging method based on remote adjustment signals, comprising:

[0025] S1. After the master station sends remote adjustment information to the distribution terminal and completes the remote adjustment test with the distribution terminal, the remote signal debugging task list is downloaded from the master station. The master station stores a template setting list. When the master station performs the remote adjustment test with the distribution terminal, the setting value of each distribution terminal is modified according to the template setting list.

[0026] Among them, the distribution terminal and the joint adjustment device can be wired in advance before S1. After the test starts, the master station can send a remote adjustment command to the distribution terminal. In the present invention, the protection settings and control words of all distribution terminals that need to be tested are modified according to the same setting list, that is, the template setting list of the master station, so that the problem of different settings of distribution terminals in different regions can be avoided. Then the master station side generates a universal remote signal debugging task list for the distribution terminal according to the work standards and requirements of this time. Figure 2 : is a flow chart of a power distribution terminal warehouse debugging method based on remote adjustment signals according to an embodiment of the present invention, such as Figure 2 As shown, multiple joint debugging devices and distribution terminals can be used for debugging at the same time.

[0027] S2. According to the telesignal debugging task list, obtain the pre-stored telesignal test template, and output the experimental signal corresponding to the telesignal debugging to the distribution terminal according to the telesignal test template. Among them, the fixed values ​​in the test template (including the telesignal test template and the test template used for telemetry mentioned later) are pre-set according to the template fixed value list.

[0028] The test template is configured on the joint debugging device. The setting value of the test template is modified in advance according to the template setting list of the master station. The test template can reduce the test data configuration work before the experiment for the on-site debugging personnel. The test template can be continuously improved or modified according to the requirements of the current region to achieve customization for different ratios and different test purposes. The test template can also contain multiple sub-templates, respectively for remote adjustment and remote signaling tests, or for each sub-item of remote adjustment and remote signaling. The specific template can be found according to the debugging task list to be processed.

[0029] Figure 3 It is a schematic diagram of the debugging process of the telesignaling signal of an embodiment of the present invention. In S2, the joint debugging device searches for the required telesignaling test template from the test template according to the telesignaling debugging task list, reads the signal data therein, applies the experimental signal to carry out the debugging operation, and the experimental signal may include status information such as simulated alarm conditions, switch positions or valve positions.

[0030] S3. Receive the remote signaling response data forwarded by the power distribution terminal via the master station, wherein the remote signaling response data is generated by the power distribution terminal after applying the experimental signal.

[0031] like Figure 3 As described above, the distribution terminal responds after receiving the experimental signal, and sends the response data (i.e., remote signal response data) to the master station through the distribution network. The master station then transmits the remote signal response data to the debugging device through wireless communication. The following can be used: Figure 2 NB-LOT network in.

[0032] S4. According to the test data in the remote signal test template, the remote signal response data is checked to determine the remote signal debugging result.

[0033] The debugging device compares and judges the experimental data (i.e., telesignal response data) sent by the distribution terminal from the master station and the test data of the joint debugging device itself (experimental signals applied according to the test template), and finally realizes the adaptive joint debugging of telesignaling of the distribution terminal. After completion, an experimental report can be generated.

[0034] The distribution terminal warehouse debugging method based on remote control signals of the present invention, when the remote control test is performed between the master station and the distribution terminal, the setting value of each distribution terminal is modified according to the template setting list of the master station, which solves the problem that the distribution terminals are from different regions and have different protection settings and control words, which makes it impossible to perform batch closed-loop testing. The remote signaling test template is determined through the remote signaling debugging task list and the corresponding signal is applied, which is conducive to the simultaneous debugging of multiple distribution terminals, and the test template does not need to be manually configured, which further ensures the correctness and efficiency of the debugging. In addition, the method can be implemented through unlimited communication without the need for personnel communication and confirmation, which further improves the debugging efficiency and reliability, and ensures the safe and reliable operation of the distribution network.

[0035] In one embodiment, after determining the telemetering debugging result, it also includes: downloading the telemetering debugging task list from the main station, obtaining a pre-stored telemetering test template according to the telemetering debugging task list, and outputting the experimental signal corresponding to the telemetering debugging to the distribution terminal according to the telemetering test template; receiving the telemetering response data forwarded by the distribution terminal via the main station, the telemetering response data is generated by the distribution terminal after applying the experimental signal corresponding to the telemetering debugging; according to the test data in the telemetering test template, the telemetering response data is checked to determine the telemetering debugging result.

[0036] Figure 4For the debugging process of telemetry signals during the experiment, the joint debugging device downloads the task list of telemetry debugging from the main station. Then the joint debugging device determines the telemetry test template according to the experimental task list, and outputs the experimental signal including the analog quantity to the distribution terminal. After receiving the experimental signal including the analog quantity, the distribution terminal uploads the internal telemetry actual value to the main station. The main station forwards the actual telemetry value of the distribution terminal to the joint debugging device. After receiving the actual telemetry value sent by the main station, the joint debugging device compares it with the telemetry expected value in the internal telemetry test template to judge the experimental result and generate a report.

[0037] In one embodiment, after the remote signal debugging is completed and the result is qualified, the method also includes: downloading the remote control debugging task list from the master station; waiting for the master station to issue the remote control command generated according to the debugging task to the distribution terminal, and the distribution terminal to send the internal remote control node data generated after executing the remote control command to the master station, and then receiving the remote control node data forwarded by the master station; checking the remote control node data according to the expected value of the remote control data to determine the remote control debugging result, and the expected value of the remote control data is determined according to the remote control debugging task list.

[0038] Figure 5 FIG. 1 is a schematic diagram of a debugging flow of a remote control signal according to an embodiment of the present invention. Figure 5 As shown, the master station downloads the remote control information to the distribution terminal, modifies the internal setting and control word, completes the remote control test and passes the remote control test, and the joint debugging device downloads the remote control debugging task list from the master station. After the experiment starts, the master station issues a remote control command to the distribution terminal to command the switch to operate. After the experiment is over, the distribution terminal sends the internal remote control actual value to the master station, that is, the remote control node data. The master station sends the remote control node data sent by the distribution terminal to the joint debugging device. Finally, the joint debugging device compares the remote control actual value in the remote control node data sent by the master station with the remote control expected value in the remote control debugging task list, and determines the experimental results to generate an experimental report.

[0039] In one embodiment, the telesignaling debugging task list, telemetry debugging task list or remote control debugging task list is a debugging task list common to each power distribution terminal. That is, each debugging task list is a task list common to all power distribution terminals, and the joint debugging device can apply corresponding experimental signals to multiple power distribution terminals at the same time according to the telesignaling and telemetry debugging task list, thereby achieving one-time addition to complete the debugging of multiple power distribution terminals.

[0040] In one embodiment, the remote adjustment test includes the power distribution terminal modifying the internal protection setting value and control word according to the remote adjustment setting value list issued by the master station, as shown in the steps of the above embodiment.

[0041] In one embodiment, the joint debugging device and the master station are connected by wireless communication via NB-LOT. The power distribution terminal device and the master station are connected by wireless communication via NB-LOT, which has the advantages of low power consumption, low cost, and is suitable for large-scale Internet of Things deployment, solving the problems of high power consumption and high deployment cost of ordinary wireless connections.

[0042] In one embodiment, when there are multiple joint debugging devices, after downloading the telesignaling or telemetering debugging task list from the master station, it also includes: each joint debugging device sends the telesignaling or telemetering debugging task list to the host computer; accordingly, according to the telesignaling or telemetering debugging task list, obtain the pre-stored telesignaling or telemetering test template, specifically receiving the telesignaling or telemetering test template sent by the host computer; after receiving the debugging start signal sent by the host computer, output the experimental signal to the distribution terminal according to the telesignaling or telemetering test template.

[0043] When there are multiple joint debugging devices, each joint debugging device in the above-mentioned embodiment can output the experimental signal corresponding to the telesignaling or telemetering debugging to the distribution terminal according to the telesignaling or telemetering test template. It can also be the embodiment of the present invention that a master computer controls multiple joint debugging devices at the same time to realize batch running of debugging templates to achieve the purpose of batch debugging of distribution terminals. When multiple joint debugging devices are connected to the host computer and a communication connection is established, each joint debugging device sends the telesignaling or telemetering debugging task sheet to the host computer, the host computer selects the telesignaling or telemetering test template, and issues it in the joint debugging device, and then the host computer sends a debugging start signal, and the joint debugging device outputs the experimental signal to the distribution terminal according to the telesignaling or telemetering test template. Based on this, the debugging of multiple joint debugging devices and multiple distribution terminals can be realized by a single person, further improving the debugging efficiency.

[0044] In summary of the above embodiments, after the remote adjustment command of the master station is issued, the joint adjustment device and the master station can be connected by wireless communication through NB-LOT. Then the master station issues a debugging task list to the joint adjustment device according to the test requirements. The joint adjustment device conducts experiments one by one according to the debugging task list and the test template. During the experiment, the master station will inform the joint adjustment device of the expected results of the experiment through NB-LOT transmission. At the same time, the master station will receive the 101 message data of the distribution terminal device, where the message data includes the actual result information. The joint adjustment device will compare the expected results with the actual results. The experimental points that meet the criteria will be given a "correct" command, and the experimental points that do not meet the criteria will be given an "incorrect" command. Finally, after all the experimental points are completed, the joint adjustment device will generate a test report.

[0045] The present invention also provides a distribution terminal warehouse debugging device based on remote regulation signals, which is applied to a joint debugging device and includes: an extraction module, which is used to send remote regulation information to the distribution terminal at the master station, and download the remote signal debugging task list from the master station after completing the remote regulation test between the master station and the distribution terminal; an output module, which is used to obtain a pre-stored remote signal test template according to the remote signal debugging task list, and output the experimental signal corresponding to the remote signal debugging to the distribution terminal according to the remote signal test template; a receiving module, which is used to receive the remote signal response data forwarded by the distribution terminal via the master station, and the remote signal response data is generated by the distribution terminal after applying the experimental signal; a judgment module, which is used to check the remote signal response data according to the test data in the remote signal test template, and judge the remote signal debugging result; wherein the master station stores a template setting list, and when the remote regulation test is performed between the master station and the distribution terminal, the setting value of each distribution terminal is modified according to the template setting list, and the setting value in the test template is pre-set according to the template setting list.

[0046] In one embodiment, the extraction module is also used to download the telemetry debugging task list from the master station; the output module is also used to obtain the pre-stored telemetry test template according to the telemetry debugging task list, and output the experimental signal corresponding to the telemetry debugging to the distribution terminal according to the telemetry test template; the receiving module is also used to receive the telemetry response data forwarded by the distribution terminal via the master station, and the telemetry response data is generated by the distribution terminal after applying the experimental signal corresponding to the telemetry debugging; the judgment module is also used to check the telemetry response data according to the test data in the telemetry test template to judge the telemetry debugging result.

[0047] In one embodiment, the output module is also used to download a remote control debugging task list from the main station; the receiving module is also used to wait for the main station to issue a remote control command to the distribution terminal, and after the distribution terminal sends the internal remote control node data generated after executing the remote control command to the main station, it receives the remote control node data forwarded by the main station; the judgment module is also used to check the remote control node data according to the expected value of the remote control data, and judge the remote control debugging result, and the expected value of the remote control data is determined according to the remote control debugging task list.

[0048] The power distribution terminal warehouse debugging device based on remote control signals provided in the embodiment of the present invention has the same implementation principle and technical effects as those of the aforementioned power distribution terminal warehouse debugging method based on remote control signals. For the sake of brief description, for parts not mentioned in the embodiment of the power distribution terminal warehouse debugging device based on remote control signals, reference may be made to the corresponding contents in the aforementioned power distribution terminal warehouse debugging method based on remote control signals.

[0049] When implementing the specific plan, the joint debugging device can adopt a modular design. The overall structure includes analog voltage and multiple groups of analog current outputs, hard node input quantities, hard node output quantities, emergency stop button, wireless NB-LOT communication interface, USB interface, RJ45 interface, industrial computer human-computer interaction interface, AC 220V power supply interface, etc.

[0050] The overall structure of the device adopts modular design, which can effectively reduce the size and weight of the equipment and is easy to carry. The remote adjustment function based on wireless communication solves the problem of batch closed-loop testing during the FTU device centralized warehouse debugging process due to the different protection settings and control words of the distribution terminals from different regions. Multiple distribution terminal warehouse debugging devices and test templates are combined to achieve the debugging efficiency and correctness of the distribution automation terminal, ensuring the safe and reliable operation of the distribution network.

[0051] The present invention also provides a computer-readable storage medium, such as a flash memory, a hard disk, a multimedia card, a card-type memory (for example, an SD or DX memory, etc.), a random access memory (RAM), a static random access memory (SRAM), a read-only memory (ROM), an electrically erasable programmable read-only memory (EEPROM), a programmable read-only memory (PROM), a magnetic memory, a disk, an optical disk, a server, an App application store, etc., on which a computer program is stored, and the program realizes corresponding functions when executed by a processor. The computer-readable storage medium of this embodiment realizes the method embodiment of the power distribution terminal warehouse debugging method based on the remote adjustment signal when executed by the processor.

[0052] It should be pointed out that, according to the needs of implementation, the various steps / components described in this application can be split into more steps / components, and two or more steps / components or partial operations of steps / components can be combined into new steps / components to achieve the purpose of the present invention.

[0053] The order of execution of each step in the above embodiment does not mean the order of execution. The execution order of each process should be determined by its function and internal logic, and should not constitute any limitation on the implementation process of the embodiment of the present application.

[0054] It should be understood that those skilled in the art can make improvements or changes based on the above description, and all these improvements and changes should fall within the scope of protection of the appended claims of the present invention.

Claims

1. A distribution terminal warehouse debugging method based on remote adjustment signals, applied to a joint adjustment device, characterized in that: include: After the master station sends the remote adjustment information to the distribution terminal and completes the remote adjustment test with the distribution terminal, the remote signal debugging task list is downloaded from the master station; According to the telesignal debugging task list, a pre-stored telesignal test template is obtained, and according to the telesignal test template, an experimental signal corresponding to the telesignal debugging is output to the power distribution terminal; Receiving remote signaling response data forwarded by the power distribution terminal via the master station, wherein the remote signaling response data is generated by the power distribution terminal after the experimental signal is applied; According to the test data in the remote signal test template, the remote signal response data is checked to determine the remote signal debugging result; The master station stores a template setting list. When the master station and the distribution terminal perform remote adjustment testing, the setting values ​​of each distribution terminal are modified according to the template setting list. The setting values ​​in the test template are pre-set according to the template setting list.

2. The power distribution terminal warehouse debugging method based on remote control signal according to claim 1 is characterized in that: After determining the remote signal debugging result, the method further includes: Downloading a telemetry debugging task list from the master station, obtaining a pre-stored telemetry test template according to the telemetry debugging task list, and outputting an experimental signal corresponding to the telemetry debugging to the power distribution terminal according to the telemetry test template; Receiving telemetry response data forwarded by the power distribution terminal via the master station, wherein the telemetry response data is generated by the power distribution terminal after applying an experimental signal corresponding to telemetry debugging; According to the test data in the telemetry test template, the telemetry response data is checked to determine the telemetry debugging result.

3. The power distribution terminal warehouse debugging method based on remote control signal according to claim 1 is characterized in that: After the remote signal debugging is completed and the result is qualified, the method further includes: Download the remote control debugging task sheet from the master station; Waiting for the master station to send a remote control command to the power distribution terminal, and after the power distribution terminal sends the internal remote control node data generated after executing the remote control command to the master station, receiving the remote control node data forwarded by the master station; According to the expected value of the remote control data, the remote control node data is checked to determine the remote control debugging result, and the expected value of the remote control data is determined according to the remote control debugging task list.

4. The power distribution terminal warehouse debugging method based on remote control signals according to any one of claims 1 to 3, characterized in that: The remote signaling debugging task list, the telemetry debugging task list or the remote control debugging task list is a debugging task list common to each power distribution terminal.

5. The power distribution terminal warehouse debugging method based on remote control signal according to claim 1 is characterized in that: The remote adjustment test includes the distribution terminal modifying the internal protection setting value and control word according to the remote adjustment setting value list issued by the master station.

6. The power distribution terminal warehouse debugging method based on remote adjustment signal according to claim 1 is characterized in that: The joint debugging device and the main station are connected by wireless communication via NB-LOT.

7. The power distribution terminal warehouse debugging method based on remote adjustment signal according to claim 1 or 2, characterized in that: When there are multiple joint debugging devices, after downloading the telesignaling or telemetry debugging task list from the master station, the following steps are also included: Each joint debugging device sends the telesignaling or telemetry debugging task list to the host computer; Accordingly, according to the telesignaling or telemetering debugging task list, a pre-stored telesignaling or telemetering test template is obtained, specifically, the telesignaling or telemetering test template sent by the host computer is received; After receiving the debugging start signal sent by the host computer, the experimental signal is output to the distribution terminal according to the telesignaling or telemetry test template.

8. A distribution terminal warehouse debugging device based on remote control signals, characterized in that: include: The extraction module is used to send remote adjustment information from the master station to the distribution terminal, and download the remote signal debugging task list from the master station after completing the remote adjustment test with the distribution terminal; An output module, used for obtaining a pre-stored telesignaling test template according to the telesignaling debugging task list, and outputting an experimental signal corresponding to the telesignaling debugging to the power distribution terminal according to the telesignaling test template; A receiving module, used for receiving remote signaling response data forwarded by the power distribution terminal via the master station, wherein the remote signaling response data is generated by the power distribution terminal after the experimental signal is applied; A judgment module, used to check the remote signal response data according to the test data in the remote signal test template and judge the remote signal debugging result; The master station stores a template setting list. When the master station and the distribution terminal perform remote adjustment testing, the setting values ​​of each distribution terminal are modified according to the template setting list. The setting values ​​in the test template are pre-set according to the template setting list.

9. The power distribution terminal warehouse debugging device based on remote adjustment signal according to claim 8, characterized in that: The extraction module is also used to download the telemetry debugging task list from the main station; The output module is further used to obtain a pre-stored telemetry test template according to the telemetry debugging task list, and output an experimental signal corresponding to the telemetry debugging to the power distribution terminal according to the telemetry test template; The receiving module is further used to receive telemetry response data forwarded by the power distribution terminal via the master station, wherein the telemetry response data is generated by the power distribution terminal after applying an experimental signal corresponding to telemetry debugging; The judgment module is also used to check the telemetry response data according to the test data in the telemetry test template to judge the telemetry debugging result.

10. The power distribution terminal warehouse debugging device based on remote adjustment signal according to claim 8, characterized in that: The output module is also used to download the remote control debugging task list from the main station; The receiving module is further used to wait for the master station to send the remote control command to the power distribution terminal, and after the power distribution terminal sends the internal remote control node data generated after executing the remote control command to the master station, receive the remote control node data forwarded by the master station; The judgment module is further used to check the remote control node data according to the expected value of the remote control data to judge the remote control debugging result. The expected value of the remote control data is determined according to the remote control debugging task list.

Citation Information

Patent Citations

  • Simultaneous automatic joint debugging method and system for multiple unmanned power distribution terminals of master station

    CN111564905A

  • Debugging method for universally and efficiently processing automatic terminal of city network distribution network

    CN111799889A

  • Full-type distribution automation equipment complete function self-adaptive debugging system and method

    CN116593800A

  • Distribution network point-to-point joint debugging information interaction method and device

    CN117335569A

  • Power distribution network automation terminal joint debugging method and device based on simulation master station

    CN118040903A

Cited By

  • Power distribution switch primary and secondary set digital-intelligent joint debugging device and joint debugging method

    CN119891566A