Power grid technical improvement and overhaul project risk monitoring method, system, equipment and medium
By realizing centralized management and sharing of information in the power grid technical transformation and overhaul project, and configuring risk monitoring programs and data collection systems for each key project, the problem of insignificance of information islands and poor processing methods is solved, and efficient and accurate risk monitoring is achieved to ensure the smooth progress of the project.
Patent Information
- Application Number
- CN202411717369.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Applications(China)
- Current Assignee / Owner
- Filing Date
- 2024-11-27
- Publication Date
- 2025-03-14
AI Technical Summary
The existing risk monitoring plan for the overhaul of the power grid has information islands in the communication mechanism, which is difficult to detect and correct potential violations and risks in a timely manner, and the unified handling method is prone to poorly targeted problems.
Through the upload nodes and information upload nodes of technical transformation and overhaul project, centralized management and sharing of information can be realized, information silos are broken, and connection relationships are established with the data collection systems corresponding to each key technical transformation and overhaul project, and data is obtained uniformly. Configure the corresponding risk monitoring procedures and data acquisition systems for each key project to achieve accurate monitoring and effective management of project risks.
It improves the transparency and traceability of information, realizes the automation and intelligence of risk monitoring, improves the efficiency and accuracy of risk monitoring, reduces interference and misjudgment from human factors, and ensures the smooth progress and timely completion of the power grid technical transformation and overhaul project.
Smart Images

Figure CN119624118A_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of project risk monitoring, and in particular to a method, system, equipment and medium for risk monitoring of power grid technical transformation and overhaul projects. Background Art
[0002] At present, State Grid has successfully built the PMS3.0 system, which is based on equipment management and asset management and aims to improve the safe operation level and power supply reliability of power transmission and transformation facilities. It comprehensively covers the whole process of production management business of power companies from dispatching, transmission to transformation and other units at all levels, and is a comprehensive system integrating power equipment asset management. In particular, its modules such as technical transformation and overhaul front-end application and technical transformation and overhaul business service provide strong support for the smooth operation of technical transformation and overhaul business.
[0003] However, although the current technical transformation and overhaul professional management system has taken shape, there are still obvious business breakpoints and management weaknesses in key links such as risk warning and control. In response to these problems, although some risk monitoring plans have been gradually implemented, these measures still seem to be inadequate in the face of complex and changeable power grid operation risks.
[0004] Specifically, the risk warning of technical transformation and overhaul projects requires close collaboration among multiple systems, but the existing solutions have information islands in the communication mechanism, which leads to the obstruction of information transmission and difficulty in timely detection and correction of potential violations and risks. At the same time, due to the large number of technical transformation and overhaul projects, if a unified treatment method is adopted, it is easy to have the problem of lack of pertinence. Summary of the invention
[0005] In view of the above-mentioned deficiencies in the prior art, the present application provides a method, system, equipment and medium for risk monitoring of power grid technical transformation and overhaul projects to solve the problems that the existing solutions have information islands in the communication mechanism, making it difficult to timely discover and correct potential violations and risks, and that the technical transformation and overhaul projects adopt a unified processing method, which is prone to the problem of lack of targeting.
[0006] In a first aspect, the present application provides a method for risk monitoring of a power grid technical transformation and overhaul project, the method comprising: Through the technical transformation and overhaul project upload node, all technical transformation and overhaul projects are obtained, and key technical transformation and overhaul projects are determined from all technical transformation and overhaul projects; through the information upload node, the risk monitoring program corresponding to each key technical transformation and overhaul project and the data collection system corresponding to each key technical transformation and overhaul project are obtained; a connection relationship is established with the data collection system corresponding to each key technical transformation and overhaul project, and then the collected data uploaded by the data collection system is obtained; among which, the collected data at least includes: the reserve data of the project's reserve stage, the total control amount data of the annual plan, the progress data of each project in the implementation stage, the accounting data, and the material in and out data; the collected data is input into the corresponding risk monitoring program to obtain the risk monitoring results.
[0007] The project risk monitoring method provided in the embodiment of the present application realizes the centralized management and sharing of information through the technical transformation and overhaul project upload node and the information upload node, effectively breaks the information island, and improves the transparency and traceability of information. By establishing a connection relationship with the corresponding data acquisition system of each key technical transformation and overhaul project, all data involved in the key technical transformation and overhaul project are further uniformly obtained, which solves the problem that there are information islands in the communication mechanism of the existing scheme, which makes it difficult to timely discover and correct potential violations and risks. Technical transformation and overhaul projects usually involve multiple aspects, and the use of a unified processing method is often not targeted. This application determines the key technical transformation and overhaul projects from all technical transformation and overhaul projects, and configures the corresponding risk monitoring program and data acquisition system for each key project, so as to realize the accurate monitoring and effective management of project risks. In addition, by inputting the collected data into the corresponding risk monitoring program, this application realizes the automation and intelligence of risk monitoring. The efficiency and accuracy of risk monitoring are improved, the interference and misjudgment of human factors are reduced, and it helps to ensure the smooth progress and timely completion of the power grid technical transformation and overhaul project.
[0008] In one implementation of the present application, an intelligent summary generation algorithm is provided in the technical transformation and overhaul project upload node. Through the technical renovation and overhaul project upload node, all technical renovation and overhaul projects are obtained, and key technical renovation and overhaul projects are determined from all technical renovation and overhaul projects, including: All technical transformation and overhaul projects are input into the intelligent summary generation algorithm in turn to obtain summary data of each technical transformation and overhaul project; the summary data is compared with the preset risk key information conditions to determine the technical transformation and overhaul projects that meet the preset risk key information conditions as key technical transformation and overhaul projects.
[0009] In one implementation of the present application, before inputting the collected data into the corresponding risk monitoring program to obtain the risk monitoring result, the method further includes: Obtain the collected data generated in the historical time period and the actual risk information of the collected data; Input the collected data generated in the historical time period into the risk monitoring program to obtain predicted risk information; Based on the actual risk information, the accuracy of the predicted risk information is calculated. When the accuracy is greater than the preset threshold, it is determined that the current risk monitoring program is normal; otherwise, an abnormal alarm message is generated to the information upload node that uploads the risk monitoring program.
[0010] In one implementation of the present application, the collected data is input into a corresponding risk monitoring program to obtain risk monitoring results, which specifically includes: Determine the data collection system corresponding to the collected data, and then determine the key technical transformation and overhaul projects corresponding to the data collection system, and then determine the risk monitoring procedures corresponding to the key technical transformation and overhaul projects; input the collected data into the corresponding risk monitoring program to obtain the risk monitoring results.
[0011] In a second aspect, the present application provides a risk monitoring system for power grid technical transformation and overhaul projects, the system comprising: The technical transformation and overhaul project upload node is used to obtain all technical transformation and overhaul projects, and to determine the key technical transformation and overhaul projects from all technical transformation and overhaul projects; the information upload node is used to obtain the risk monitoring program corresponding to each key technical transformation and overhaul project and the data collection system corresponding to each key technical transformation and overhaul project; the central processing node is used to establish a connection relationship with the data collection system corresponding to each key technical transformation and overhaul project, and then obtain the collected data uploaded by the data collection system; among which, the collected data at least includes: the reserve data of the project's reserve stage, the total control amount data of the annual plan, the progress data of each project in the implementation stage, the accounting data, and the material in and out data; the collected data is input into the corresponding risk monitoring program to obtain the risk monitoring results.
[0012] In one implementation of the present application, the technical transformation and overhaul project upload node includes a key determination unit, which is used to input all technical transformation and overhaul projects into the intelligent summary generation algorithm in sequence to obtain summary data of each technical transformation and overhaul project; compare the summary data with preset risk key information conditions, and determine that the technical transformation and overhaul projects that meet the preset risk key information conditions are key technical transformation and overhaul projects.
[0013] In one implementation of the present application, the central processing node includes a program monitoring unit, Obtain the collected data generated in the historical time period and the actual risk information of the collected data; Input the collected data generated in the historical time period into the risk monitoring program to obtain predicted risk information; Based on the actual risk information, the accuracy of the predicted risk information is calculated. When the accuracy is greater than the preset threshold, it is determined that the current risk monitoring program is normal; otherwise, an abnormal alarm message is generated to the information upload node that uploads the risk monitoring program.
[0014] In one implementation of the present application, the central processing node includes a result obtaining unit, It is used to determine the data collection system corresponding to the collected data, and then determine the key technical renovation and overhaul projects corresponding to the data collection system, and then determine the risk monitoring procedures corresponding to the key technical renovation and overhaul projects; Input the collected data into the corresponding risk monitoring program to obtain the risk monitoring results.
[0015] In a third aspect, the present application provides a risk monitoring device for power grid technical transformation and overhaul projects, the device comprising: processor; and a memory having executable codes stored thereon, which, when executed, causes a processor to execute a risk monitoring method for a power grid technical renovation and overhaul project as described in any one of the above items.
[0016] In a fourth aspect, the present application provides a non-volatile computer storage medium having computer instructions stored thereon, which when executed implement a method for monitoring the risks of a power grid technical renovation and overhaul project as described above.
[0017] Those skilled in the art can understand that the present application has at least the following beneficial effects: The present application provides a method, system, equipment and medium for monitoring the risks of power grid technical transformation and overhaul projects. Through the technical transformation and overhaul project upload node and information upload node, the centralized management and sharing of information are realized, the information island is effectively broken, and the transparency and traceability of information are improved. By establishing a connection relationship with the corresponding data acquisition system of each key technical transformation and overhaul project, all data involved in the key technical transformation and overhaul project are further uniformly acquired, and the existing scheme solves the problem that there are information islands in the communication mechanism, which makes it difficult to timely discover and correct potential violations and risks. Technical transformation and overhaul projects usually involve multiple aspects, and the use of a unified processing method is often not targeted. The present application determines the key technical transformation and overhaul projects from all technical transformation and overhaul projects, and configures the corresponding risk monitoring program and data acquisition system for each key project, so as to realize the accurate monitoring and effective management of project risks. In addition, by inputting the collected data into the corresponding risk monitoring program, the present application realizes the automation and intelligence of risk monitoring. The efficiency and accuracy of risk monitoring are improved, the interference and misjudgment of human factors are reduced, and it helps to ensure the smooth progress and timely completion of the power grid technical transformation and overhaul project. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] Some embodiments of the present disclosure are described below with reference to the accompanying drawings, in which: Figure 1 It is a flow chart of a risk monitoring method for power grid technical transformation and overhaul projects provided in an embodiment of the present application.
[0019] Figure 2It is a schematic diagram of the internal structure of a risk monitoring system for power grid technical transformation and overhaul projects provided in an embodiment of the present application.
[0020] Figure 3 It is a schematic diagram of the internal structure of a risk monitoring device for a power grid technical transformation and overhaul project provided in an embodiment of the present application. DETAILED DESCRIPTION
[0021] It should be understood by those skilled in the art that the embodiments described below are only preferred embodiments of the present disclosure, and do not mean that the present disclosure can only be implemented through the preferred embodiments. The preferred embodiments are only used to explain the technical principles of the present disclosure, and are not used to limit the protection scope of the present disclosure. Based on the preferred embodiments provided by the present disclosure, all other embodiments obtained by ordinary technicians in this field without creative work should still fall within the protection scope of the present disclosure.
[0022] It should also be noted that the terms "include", "comprises" or any other variations thereof are intended to cover non-exclusive inclusion, so that a process, method, commodity or device including a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, commodity or device. In the absence of more restrictions, the elements defined by the sentence "comprises a ..." do not exclude the existence of other identical elements in the process, method, commodity or device including the elements.
[0023] The technical solution proposed in the embodiments of the present application is described in detail below with reference to the accompanying drawings.
[0024] The embodiment provides a method for monitoring the risk of a power grid technical renovation and overhaul project. Figure 1 As shown, the method provided in the embodiment of the present application mainly includes the following steps: Step 110: Obtain all technical renovation and overhaul projects through the technical renovation and overhaul project upload node, and determine key technical renovation and overhaul projects from all technical renovation and overhaul projects.
[0025] It should be noted that the technical renovation and overhaul project upload node can be any intelligent device such as a server that can upload data. The scheme for determining the key technical renovation and overhaul project can be automatically identified and obtained through an intelligent algorithm or the key technical renovation and overhaul project selected by external triggering can be obtained through a preset interface.
[0026] In some embodiments, an intelligent summary generation algorithm (e.g., AISummarizer) is provided in the technical transformation and overhaul project upload node. This step may be specifically as follows: All technical transformation and overhaul projects are input into the intelligent summary generation algorithm in turn to obtain summary data of each technical transformation and overhaul project; the summary data is compared with the preset risk key information conditions to determine the technical transformation and overhaul projects that meet the preset risk key information conditions as key technical transformation and overhaul projects.
[0027] It should be noted that the preset risk key information condition may be that the asset exceeds a preset threshold, or any feasible condition.
[0028] Step 120: Obtain the risk monitoring program corresponding to each key technical renovation and overhaul project and the data collection system corresponding to each key technical renovation and overhaul project through the information upload node.
[0029] It should be noted that the information uploading node can be any intelligent device such as a server that can upload data.
[0030] Step 130: Establish a connection relationship with the data acquisition system corresponding to each key technical transformation and overhaul project, and then obtain the collected data uploaded by the data acquisition system.
[0031] It should be noted that the collected data includes at least: reserve data in the reserve stage of the project, total control amount data of the annual plan, progress data of each project in the implementation stage, accounting data, and material in and out data.
[0032] Establishing a connection with the corresponding data collection system of each key technical transformation and overhaul project, the specific process can be: Configure the data acquisition systems of each key technical renovation and overhaul project so that they can send data to the data exchange platform according to the predetermined standards and frequencies, and develop corresponding connection interfaces in this system to receive and process the data transmitted from the data exchange platform; Test the connection in the actual environment to ensure the correct transmission and reception of data. Set up a monitoring module in this system to monitor the connection status and data transmission of each data acquisition system in real time. Once a connection abnormality or data transmission problem is found, an alarm will be issued and processed immediately. Regularly maintain and update the connection interface and data exchange platform to ensure their normal operation and compatibility. Continuously optimize and upgrade the connection architecture and data processing logic according to business needs and technological development.
[0033] Step 140: Input the collected data into the corresponding risk monitoring program to obtain the risk monitoring results.
[0034] In addition, before inputting the collected data into the risk monitoring program, the accuracy can be verified first. When the accuracy does not meet the requirements, an abnormal alarm message can be generated. Specifically, the scheme for accuracy verification can be as follows: Acquire the collected data generated in the historical time period and the actual risk information of the collected data; input the collected data generated in the historical time period into the risk monitoring program to obtain predicted risk information; calculate the accuracy of the predicted risk information based on the actual risk information, and when the accuracy is greater than the preset threshold, determine that the current risk monitoring program is normal; otherwise, generate abnormal alarm information to the information upload node that uploads the risk monitoring program.
[0035] In some embodiments, this step may specifically include: Determine the data collection system corresponding to the collected data, and then determine the key technical transformation and overhaul projects corresponding to the data collection system, and then determine the risk monitoring procedures corresponding to the key technical transformation and overhaul projects; input the collected data into the corresponding risk monitoring program to obtain the risk monitoring results.
[0036] In addition, this application Figure 2 A risk monitoring system for power grid technical renovation and overhaul projects is provided in the embodiment of the present application. Figure 2 As shown, the system provided in the embodiment of the present application mainly includes: The technical renovation and overhaul project upload node 210 is used to obtain all technical renovation and overhaul projects and determine key technical renovation and overhaul projects from all technical renovation and overhaul projects.
[0037] The technical renovation and overhaul project upload node 210 includes a key determination unit, which is used to input all technical renovation and overhaul projects into the intelligent summary generation algorithm in sequence to obtain summary data of each technical renovation and overhaul project; compare the summary data with the preset risk key information conditions, and determine that the technical renovation and overhaul projects that meet the preset risk key information conditions are key technical renovation and overhaul projects.
[0038] The information upload node 220 is used to obtain the risk monitoring program corresponding to each key technical transformation and overhaul project and the data collection system corresponding to each key technical transformation and overhaul project.
[0039] The central processing node 230 is used to establish a connection relationship with the corresponding data collection system of each key technical transformation and overhaul project, and then obtain the collected data uploaded by the data collection system; wherein the collected data at least includes: the reserve data of the project's reserve stage, the total control amount data of the annual plan, the progress data of each project in the implementation stage, the accounting data, and the material in and out data; the collected data is input into the corresponding risk monitoring program to obtain the risk monitoring results.
[0040] The central processing node 230 includes a program monitoring unit, which obtains the collected data generated in the historical time period and the actual risk information of the collected data; inputs the collected data generated in the historical time period into the risk monitoring program to obtain predicted risk information; calculates the accuracy of the predicted risk information based on the actual risk information, and when the accuracy is greater than a preset threshold, determines that the current risk monitoring program is normal; otherwise, generates abnormal alarm information to the information uploading node that uploads the risk monitoring program.
[0041] The central processing node 230 includes a result acquisition unit, which is used to determine the data acquisition system corresponding to the collected data, and then determine the key technical transformation and overhaul project corresponding to the data acquisition system, and then determine the risk monitoring program corresponding to the key technical transformation and overhaul project; input the collected data into the corresponding risk monitoring program to obtain the risk monitoring result.
[0042] The above is a method embodiment of the present application. Based on the same inventive concept, the present application embodiment also provides a risk monitoring device for power grid technical transformation and overhaul projects. Figure 3 As shown, the device includes: a processor; and a memory, on which executable code is stored. When the executable code is executed, the processor executes a risk monitoring method for power grid technical transformation and overhaul projects as described in the above embodiment.
[0043] Specifically, the server side obtains all technical transformation and overhaul projects through the technical transformation and overhaul project upload node, and determines the key technical transformation and overhaul projects from all the technical transformation and overhaul projects; obtains the risk monitoring program corresponding to each key technical transformation and overhaul project and the data collection system corresponding to each key technical transformation and overhaul project through the information upload node; establishes a connection relationship with the data collection system corresponding to each key technical transformation and overhaul project, and then obtains the collected data uploaded by the data collection system; wherein the collected data at least includes: the reserve data of the reserve stage of the project, the total control amount data of the annual plan, the progress data of each project in the implementation stage, the accounting data, and the material in and out data; the collected data is input into the corresponding risk monitoring program to obtain the risk monitoring result.
[0044] In addition, an embodiment of the present application further provides a non-volatile computer storage medium on which executable instructions are stored. When the executable instructions are executed, a risk monitoring method for a power grid technical transformation and overhaul project as described above is implemented.
[0045] So far, the technical solutions of the present disclosure have been described in combination with the above multiple embodiments, but it is easy for those skilled in the art to understand that the protection scope of the present disclosure is not limited to these specific embodiments. Without departing from the technical principles of the present disclosure, those skilled in the art can split and combine the technical solutions in the above-mentioned various embodiments, and can also make equivalent changes or replacements to the relevant technical features. Any changes, equivalent replacements, improvements, etc. made within the technical concept and / or technical principle of the present disclosure will fall within the protection scope of the present disclosure.
Claims
1. A method for monitoring the risks of power grid technical renovation and overhaul projects, characterized in that: The method comprises: Obtain all technical renovation and overhaul projects through the technical renovation and overhaul project upload node, and determine key technical renovation and overhaul projects from all technical renovation and overhaul projects; Through the information upload node, the risk monitoring procedures and data collection systems corresponding to each key technical renovation and overhaul project are obtained; Establish a connection with the corresponding data collection system of each key technical transformation and overhaul project, and then obtain the collected data uploaded by the data collection system; the collected data at least includes: the reserve data of the project's reserve stage, the total control amount data of the annual plan, the progress data of each project in the implementation stage, the account data, and the material in and out data; Input the collected data into the corresponding risk monitoring program to obtain the risk monitoring results.
2. The method for monitoring the risk of power grid technical renovation and overhaul projects according to claim 1 is characterized in that: The upload node for technical renovation and overhaul projects is equipped with an intelligent summary generation algorithm. Through the technical renovation and overhaul project upload node, all technical renovation and overhaul projects are obtained, and key technical renovation and overhaul projects are determined from all technical renovation and overhaul projects, including: All technical transformation and overhaul projects are input into the intelligent summary generation algorithm in turn to obtain summary data of each technical transformation and overhaul project; the summary data is compared with the preset risk key information conditions to determine the technical transformation and overhaul projects that meet the preset risk key information conditions as key technical transformation and overhaul projects.
3. The method for monitoring the risk of power grid technical renovation and overhaul projects according to claim 1 is characterized in that: Before inputting the collected data into the corresponding risk monitoring program to obtain the risk monitoring results, the method further includes: Obtain the collected data generated in the historical time period and the actual risk information of the collected data; Input the collected data generated in the historical time period into the risk monitoring program to obtain predicted risk information; Based on the actual risk information, the accuracy of the predicted risk information is calculated. When the accuracy is greater than the preset threshold, it is determined that the current risk monitoring program is normal; otherwise, an abnormal alarm message is generated to the information upload node that uploads the risk monitoring program.
4. The method for monitoring the risk of power grid technical renovation and overhaul projects according to claim 1 is characterized in that: Input the collected data into the corresponding risk monitoring program to obtain risk monitoring results, including: Determine the data collection system corresponding to the collected data, and then determine the key technical renovation and overhaul projects corresponding to the data collection system, and then determine the risk monitoring procedures corresponding to the key technical renovation and overhaul projects; Input the collected data into the corresponding risk monitoring program to obtain the risk monitoring results.
5. A risk monitoring system for power grid technical transformation and overhaul projects, characterized in that: The system comprises: The technical renovation and overhaul project upload node is used to obtain all technical renovation and overhaul projects and determine key technical renovation and overhaul projects from all technical renovation and overhaul projects; Information upload node, used to obtain the risk monitoring procedures and data collection systems corresponding to each key technical renovation and overhaul project; The central processing node is used to establish a connection with the corresponding data collection system of each key technical transformation and overhaul project, and then obtain the collected data uploaded by the data collection system; wherein the collected data at least includes: the reserve data of the project's reserve stage, the total control amount data of the annual plan, the progress data of each project in the implementation stage, the accounting data, and the material in and out data; the collected data is input into the corresponding risk monitoring program to obtain the risk monitoring results.
6. The risk monitoring system for power grid technical renovation and overhaul projects according to claim 5 is characterized in that: The technical transformation and overhaul project upload node includes a key determination unit, which is used to input all technical transformation and overhaul projects into the intelligent summary generation algorithm in sequence to obtain summary data of each technical transformation and overhaul project; compare the summary data with the preset risk key information conditions, and determine that the technical transformation and overhaul projects that meet the preset risk key information conditions are key technical transformation and overhaul projects.
7. The risk monitoring system for power grid technical renovation and overhaul projects according to claim 5 is characterized in that: The central processing node includes a program monitoring unit, Obtain the collected data generated in the historical time period and the actual risk information of the collected data; Input the collected data generated in the historical time period into the risk monitoring program to obtain predicted risk information; Based on the actual risk information, the accuracy of the predicted risk information is calculated. When the accuracy is greater than the preset threshold, it is determined that the current risk monitoring program is normal; Otherwise, an abnormal alarm message is generated and sent to the information upload node of the risk monitoring program.
8. The risk monitoring system for power grid technical renovation and overhaul projects according to claim 5 is characterized in that: The central processing node includes a result acquisition unit, It is used to determine the data collection system corresponding to the collected data, and then determine the key technical renovation and overhaul projects corresponding to the data collection system, and then determine the risk monitoring procedures corresponding to the key technical renovation and overhaul projects; Input the collected data into the corresponding risk monitoring program to obtain the risk monitoring results.
9. A risk monitoring device for power grid technical transformation and overhaul projects, characterized in that: The device comprises: processor; and a memory having executable code stored thereon, which, when the executable code is executed, enables the processor to execute a risk monitoring method for a power grid technical renovation and overhaul project as described in any one of claims 1-4.
10. A non-volatile computer storage medium, characterized in that: Computer instructions are stored thereon, and when the computer instructions are executed, a method for monitoring the risks of a power grid technical renovation and overhaul project is implemented as described in any one of claims 1 to 4.