New and old lock chamber connecting structure
By laying new and old gate rooms in the middle of water conservancy buildings and setting side piers and gravel cushions, the integrity and construction convenience of the connecting structure of new and old gate rooms is solved, the risk of uneven settlement is reduced, and the water flow is ensured. Smooth and safe construction.
Patent Information
- Application Number
- CN202420871823.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-04-24
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2034-04-24
AI Technical Summary
When the existing water conservancy buildings are expanded, the connecting structures of new and old gate rooms are prone to damage the integrity, inconvenient construction, and uneven settlement problems.
The old gate chamber and the new gate chamber are arranged at intervals along the width of the river channel, and the side piers of equal length are set, and a semicircular partition piers are set on the side piers to form a gravel cushion layer, and the side piers and partition piers are connected as one, adding Planting tendons and geomembrane are equipped with anti-seepage and water stops to form an integral structure.
It realizes convenient construction of new and old gate rooms, reduces land occupation, reduces the probability of uneven settlement, ensures smooth water flow, and enhances integrity and construction safety.
Smart Images

Figure CN222349603U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of sluice chamber arrangement structures, in particular to a new and old sluice chamber connection structure. Background Art
[0002] After years of use, the operation of some water conservancy structures no longer meets the current flow capacity requirements. In order to meet the new flow capacity requirements, the expansion of existing water conservancy structures is imperative.
[0003] In the field of sluices, common forms of expansion include arranging a new lock chamber adjacent to the old one, and expanding the lock chamber by demolishing part of the old one. However, this arrangement destroys the integrity of the lock chamber, is inconvenient to construct, and there are problems such as uneven settlement between the new and old lock chambers. Utility Model Content
[0004] In view of the above problems existing in the prior art, the purpose of the utility model is to provide a new and old lock chamber connection structure, which ensures convenient construction and good integrity of the new and old lock chambers and avoids uneven settlement of the lock chambers.
[0005] The utility model discloses a new and old lock chamber connection structure, comprising an old lock chamber and a newly built lock chamber arranged at intervals along the width direction of a river channel, and side piers of equal length are arranged on adjacent sides of the new and old lock chambers along the water flow direction;
[0006] It also includes two semicircular partition piers arranged upstream and downstream of the side piers and connecting two adjacent side piers into one. The area surrounded by all the partition piers and the side piers is backfilled with a crushed stone cushion layer; the two adjacent side piers are connected into one under the crushed stone cushion layer.
[0007] As a preferred technical solution, the top elevations of the partition piers, the side piers and the crushed stone cushion layer are the same.
[0008] As a preferred technical solution, a plurality of embedded reinforcement bars are provided at the connection point between the two side piers below the gravel cushion layer for reinforcement.
[0009] As a preferred technical solution, the bottom layer of the crushed stone cushion layer is wrapped by a geomembrane, and the geomembrane is adhered to the upper surface of the side pier.
[0010] As an optimal technical solution, a concrete anti-seepage blanket is provided upstream or downstream of the old lock chamber, and a new anti-seepage blanket connected with the existing anti-seepage blanket is provided upstream or downstream of the newly built lock chamber. The two anti-seepage blankets are flush with and connected to the bottom of their respective lock chambers.
[0011] As a preferred technical solution, a bottom protection is provided at the bottom of the partition pier, which extends outward from the bottom of the partition pier and is connected with two anti-seepage blankets.
[0012] As a preferred technical solution, the bottom protection and the top of the anti-seepage blanket are at the same elevation.
[0013] As a preferred technical solution, an existing energy stilling pool structure is provided downstream of the old lock chamber, and a new energy stilling pool with the same structure as the existing energy stilling pool is provided downstream of the new lock chamber; the downstream bottom protection is provided with a slope section with the same slope as the two energy stilling pools, and the slope section is located on the left and right sides of the downstream partition pier.
[0014] As a preferred technical solution, a first waterstop is provided at the bottom of the gravel cushion layer; and a second waterstop is provided at the junction of the partition pier and the side pier.
[0015] As an optimal technical solution, a third waterstop is provided at the junction of the bottom of the new lock chamber and the old lock chamber with the anti-seepage blanket; a fourth waterstop is provided at the junction of the anti-seepage blanket and the bottom protection.
[0016] Compared with the prior art, the utility model has the following beneficial effects:
[0017] The utility model is to arrange the expansion lock chambers adjacent to and at intervals on both sides of the old lock chamber, combining the principle of convenient construction and reducing land occupation, the new lock chamber is arranged at intervals from the old lock chamber, and the area between the two is filled with side piers and gravel cushions, so that the new and old lock chambers form a whole. In order to make the water flow smooth, semicircular partition piers are respectively arranged on the upstream and downstream sides of the side piers of the new and old lock chambers, so that the water flows through the new and old lock chambers through the river channel.
[0018] The construction of the new lock chamber is convenient, the construction has little impact on the safety of the old lock chamber, and because the new lock chamber has good integrity with the old lock chamber, the probability of uneven settlement is greatly reduced. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] In order to more clearly illustrate the technical solution of the implementation of the utility model, the utility model will be described in detail below in combination with the drawings and detailed implementation. Obviously, the drawings described below are only some implementations of the utility model. For ordinary technicians in this field, other drawings can be obtained based on these drawings without creative labor. Among them:
[0020] Figure 1 It is a schematic diagram of the overall structure of the connection structure between the new and old lock chambers of the utility model;
[0021] Figure 2 for Figure 1 AA section view;
[0022] Figure 3 for Figure 1 BB cross-sectional view;
[0023] Figure 4 This is a distribution diagram of the water stop belt of the utility model.
[0024] In the figure: 1. Old lock chamber; 2. New lock chamber; 3. Side piers; 3-1. New lock chamber side piers; 3-2. Old lock chamber side piers; 4. Gravel cushion; 5. Geomembrane; 6. Partition piers; 7. Reinforced concrete bottom protection; 8-1. Existing anti-seepage blanket; 9-1. First waterstop; 9-2. Second waterstop; 9-3. Third waterstop; 9-4. Fourth waterstop; 10. Existing energy stilling pool; 11. New energy stilling pool; 12. Slope section; 13. Embedded reinforcement. DETAILED DESCRIPTION
[0025] In order to make the above-mentioned objects, features and advantages of the present invention more obvious and easy to understand, the specific implementation methods of the present invention are described in detail below with reference to the accompanying drawings.
[0026] In order to make the purpose, technical solution and advantages of the present invention more clear, the implementation mode of the present invention will be further described in detail below with reference to the accompanying drawings.
[0027] Example 1
[0028] like Figure 1-3 As shown, the utility model provides a new and old lock chamber connection structure, including an old lock chamber 1 and a newly built lock chamber 2 arranged at intervals along the width direction of the river channel. Due to the limitation of the width of the river channel, this embodiment is described by taking a newly built lock chamber and an old lock chamber as an example.
[0029] Side piers 3 of equal length are provided on the adjacent sides of the new and old lock chambers along the water flow direction, and the area between the side piers 3 is backfilled with a crushed stone cushion layer 4 of a certain thickness and compacted manually.
[0030] Adjacent side piers 3 are connected as one under the gravel cushion layer 4, and the connection is reinforced by roughening and placing a plurality of embedded steel bars 13. Preferably, the width of the side piers and the gravel cushion layer is 1m.
[0031] Preferably, the bottom layer of the crushed stone cushion layer 4 is wrapped with a 5 mm thick geomembrane 5 to prevent water seepage, and KS glue is applied to the side of the geomembrane 5 that contacts the upper surface of the side pier 3 for bonding. A first water stop strip 9-1 is provided at the bottom of the crushed stone cushion layer 4.
[0032] In this embodiment, the newly built lock chamber side piers 3 - 1 and the old lock chamber side piers 3 - 2 on the left and right sides of the gravel cushion layer 4 have the same elevation as the top of the gravel cushion layer 4 .
[0033] The utility model is also provided with a partition pier 6 which connects the adjacent newly built lock chamber side pier 3-1 and the old lock chamber side pier 3-2 into one body. The partition pier 6 has the same elevation as the top of the side pier 3, and a second water stop 9-2 is arranged at the connection; the partition pier 6 is respectively arranged upstream and downstream of the side pier 3; preferably, the partition pier 6 is arranged in a semicircular shape, so as to facilitate the diversion of water to the lock chambers on the left and right sides of the partition pier 6.
[0034] In practice, a concrete anti-seepage blanket is usually provided upstream or downstream of the old lock chamber 1. In order to enhance the integrity of the connection between the new and old lock chambers, a new anti-seepage blanket 8-2 connected with the existing anti-seepage blanket 8-1 is provided upstream or downstream of the newly built lock chamber 2. The two anti-seepage blankets are flush with and connected to the bottom of their respective lock chambers, and a third waterstop 9-3 is provided at the connection; a square reinforced concrete bottom guard 7 is integrally formed at the bottom of the partition pier 6, and the bottom guard 7 extends outward from the bottom of the partition pier 6 and is connected to the two anti-seepage blankets, and a fourth waterstop 9-4 is provided at the connection; preferably, the bottom guard 7 and the top of the two anti-seepage blankets have the same elevation, and the two are connected in a plane, which is more convenient for construction.
[0035] Example 2
[0036] This embodiment is applicable to the case where an existing stilling pool 10 is provided downstream of the old lock chamber 1:
[0037] On the basis of Example 1, a new energy dissipation pool 11 with the same structure as the existing energy dissipation pool 10 is provided downstream of the newly built gate chamber 2; in order to enhance the integrity of the building, the reinforced concrete bottom protection 7 downstream is provided with a slope section 12 with the same slope as the two energy dissipation pools, and the slope section 12 is located on the left and right sides of the downstream partition 6.
[0038] The utility model lock chamber interval arrangement reduces the safety impact of construction on the old lock chamber 1 and the uneven settlement of the new and old lock chambers, and the partition pier 6 is added to make the water flow smooth.
[0039] Although the present invention has been described above with reference to the embodiments, various modifications may be made thereto and parts thereof may be replaced with equivalents without departing from the scope of the present invention. In particular, as long as there is no structural conflict, the various features in the embodiments disclosed in the present invention may be used in combination with each other in any manner, and the fact that these combinations are not exhaustively described in this specification is only for the sake of omitting space and saving resources. Therefore, the present invention is not limited to the specific embodiments disclosed herein, but includes all technical solutions falling within the scope of the claims.
Claims
1. A new and old lock chamber connection structure, characterized in that: It includes old lock chambers and newly built lock chambers arranged at intervals along the width of the river channel, and side piers of equal length are provided on the adjacent sides of the old and new lock chambers along the water flow direction; It also includes two semicircular partition piers arranged upstream and downstream of the side piers and connecting adjacent side piers into one, and the areas surrounded by all the partition piers and the side piers are backfilled with a gravel cushion layer; two adjacent side piers are connected into one under the gravel cushion layer.
2. The new and old lock chamber connection structure according to claim 1, characterized in that: The top elevations of the partition piers, side piers and crushed stone cushion layer are the same.
3. The new and old lock chamber connection structure according to claim 1, characterized in that: A plurality of reinforcing steel bars are arranged at the connection between the two side piers below the crushed stone cushion layer.
4. The new and old lock chamber connection structure according to claim 1, characterized in that: The bottom layer of the crushed stone cushion layer is wrapped by a geomembrane, and the geomembrane is adhered to the upper surface of the side pier.
5. The new and old lock chamber connection structure according to claim 1, characterized in that: A concrete anti-seepage blanket is provided upstream or downstream of the old lock chamber, and a new anti-seepage blanket connected with the existing anti-seepage blanket is provided upstream or downstream of the newly built lock chamber. The two anti-seepage blankets are flush with and connected with the bottom of their respective lock chambers.
6. The new and old lock chamber connection structure according to claim 5, characterized in that: A bottom protection is provided at the bottom of the partition pier, which extends outward from the bottom of the partition pier and is connected with two anti-seepage blankets.
7. The new and old lock chamber connection structure according to claim 6, characterized in that: The bottom protection and the tops of the two anti-seepage blankets are at the same elevation.
8. The new and old lock chamber connection structure according to claim 6, characterized in that: An existing stilling pool structure is provided downstream of the old lock chamber, and a new stilling pool with the same structure as the existing stilling pool is provided downstream of the new lock chamber; the bottom protection at the downstream is provided with a slope section with the same slope as the two stilling pools, and the slope section is located on the left and right sides of the downstream partition pier.
9. The new and old lock chamber connection structure according to claim 1, characterized in that: A first water stop is provided at the bottom of the crushed stone cushion layer; and a second water stop is provided at the junction of the partition pier and the side pier.
10. The new and old lock chamber connection structure according to claim 6, characterized in that: A third waterstop is provided at the junction of the bottom of the new lock chamber and the old lock chamber and the anti-seepage blanket; a fourth waterstop is provided at the junction of the anti-seepage blanket and the bottom protection.
Citation Information
Cited By
Long-period reconstruction construction method for flood discharge gate
CN119877485A