Assembly type installation adjusting device
Through the prefabricated installation and adjustment device, the support structure of hanging beams and support beams is used to solve the accuracy and safety problems of traditional steel tie rod connecting nodes during high altitude installation, and the stability, precise height adjustment and aesthetics of multi-level suspension structures are achieved. promote.
Patent Information
- Application Number
- CN202420995282.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Utility models(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-09
- Publication Date
- 2025-01-14
- Estimated Expiration
- 2034-05-09
AI Technical Summary
During the installation process of traditional steel tie rods, the connecting nodes of high altitudes need to be adjustable up and down to ensure the accuracy of the installation elevation, and the tension and stress must be ensured to avoid damage to the steel tie rods. At the same time, the exposed ear plates are susceptible to impact or corrosion, which affects the structure. safety and aesthetics.
A prefabricated installation and adjustment device is designed. Through the hanging beams and support beams mounted on the steel beams on the floor, the connecting nodes are supported by adjustable connecting rods and support limits to avoid direct pressure on the steel pull rods. And adjust the relative position through threaded connections to ensure high accuracy and no easy damage.
The height adjustment accuracy of multi-level suspension structure is improved, which avoids damage to the steel pull rod during installation, and hides the connection nodes, improving the safety and aesthetics of the structure.
Smart Images

Figure CN222350281U_ABST
Abstract
Description
Technical Field
[0001] The utility model relates to the field of multi-story suspended structure buildings, in particular to an assembled installation adjustment device. Background Art
[0002] Steel tie rods have the advantages of strong bearing capacity, high safety, and convenient and quick use, which makes them widely used in some large-span cantilever and complex structure construction projects. Traditional steel tie rods are installed by connecting ear plates. If the diameter of the steel tie rod is large, the thickness of the connecting ear plate is also large, which brings great difficulties to node design, material procurement, processing and installation. In addition, when the steel tie rod is connected to the steel beam, the ear plate is exposed, and the exposed ear plate will be hit or corroded, affecting the safety and aesthetics of the structure.
[0003] In the prior art, there is a connection node 300 in which each steel tie rod is connected by a sleeve-type connector and supports the floor steel beam, which can avoid the appearance of thick plates, hide the connection node at the floor, and improve the safety and aesthetics of the structure. For example, a steel tie rod connection node disclosed in Chinese patent application number 202222778363.0 supports the steel beam and connects each tie rod through a steel sleeve, a locking device and a steel pad. However, during the high-altitude installation process of this connection node, it needs to be adjustable up and down to ensure the accuracy of the installation elevation of the finished steel tie rod connection assembly, and during the process, it is necessary to ensure that the steel tie rod is pulled and stressed evenly during construction to avoid damage to the steel tie rod body.
[0004] Therefore, in order to meet the installation requirements of the above-mentioned connection structure, a device and method that can assist in adjusting the height thereof is now needed. Utility Model Content
[0005] In view of the existing phenomenon, the utility model provides an assembled installation adjustment device and a multi-layer suspension structure height adjustment method, which are used to solve the above technical problems.
[0006] The technical solution of the present application is: an assembled installation and adjustment device for temporarily supporting and adjusting a multi-story suspended structure, the multi-story suspended structure comprising: an upper steel tie rod and a lower steel tie rod connected by a connecting node, and a floor steel beam supported by the connecting node, the assembled installation and adjustment device comprising: a hanging beam hung on the floor steel beam, a supporting beam, a connecting rod connecting the hanging beam and the supporting beam at an adjustable relative distance, and a supporting and limiting member arranged on the supporting beam, supporting the connecting node and radially limiting the lower steel tie rod.
[0007] Furthermore, it also includes a secondary supporting beam vertically arranged with respect to the supporting beam, and the supporting beam and the secondary supporting beam jointly support the supporting limiter.
[0008] Furthermore, the supporting and limiting member includes two detachable limiting blocks which are arranged in a ring shape, and the inner side wall of the ring shape limits the lower section of the steel pull rod.
[0009] Furthermore, the limit block includes an upper side plate, a lower side plate, a limit sleeve plate, and a stiffening rib arranged between the upper side plate and the lower side plate.
[0010] Furthermore, the connecting rod is a screw rod threadably connected to the hanging beam and the supporting beam.
[0011] Furthermore, the connection node is threadedly connected to the upper steel tie rod, and the relative position can be adjusted through the threaded connection.
[0012] Furthermore, a first pad is provided on the hanging beam, and the connecting rod is connected to the first pad.
[0013] Furthermore, a second pad is provided on the supporting beam, and the connecting rod is connected to the second pad.
[0014] Furthermore, the hanging beam and the supporting beam are made of channel steel.
[0015] Another technical solution of the present application is: using the assembled installation adjustment device to temporarily support the connection node to adjust the multi-story suspended structure to its designed elevation.
[0016] The beneficial effects of this application are:
[0017] The installation process of existing multi-story suspended structures often requires the assistance of lifting equipment, and the accuracy of adjusting the installation height is low. The assembled installation adjustment device of the present application is hung on the floor steel beam through a hanging beam, which can bear the weight with the help of the floor steel beam and form a support for the connection node through a supporting beam and a supporting limiter, and adjust the height of the connection node with the support force of the floor steel beam. The present application uses the connecting rod to bear tension, and uses the connecting node to bear part of the pressure without compressing the steel tie rod, which conforms to the design and use occasions of the steel tie rod and is not easy to cause damage to the steel tie rod. The supporting limiter also forms a radial limit on the lower section of the steel tie rod to prevent the lower section of the steel tie rod from shaking during height adjustment, resulting in unstable connection. BRIEF DESCRIPTION OF THE DRAWINGS
[0018] The accompanying drawings, which are incorporated into the specification and constitute a part of the specification, illustrate embodiments of the utility model and are used together with the description to explain the principles of the utility model. The accompanying drawings described below are some embodiments of the utility model, but not all embodiments. For those of ordinary skill in the art, other accompanying drawings can be obtained based on these accompanying drawings without creative work.
[0019] Figure 1 A schematic diagram of a specific embodiment of the present application;
[0020] Figure 2 It is a schematic diagram of an assembly of a specific embodiment of the present application;
[0021] Figure 3 A schematic diagram of a stopper according to a specific embodiment of the present application;
[0022] Figure 4 It is a schematic cross-sectional view of an assembly of a specific embodiment of the present application.
[0023] Reference numerals: upper steel tie rod 101; lower steel tie rod 102; floor steel beam 200; steel beam sleeve 201; connection node 300; connection sleeve 301; support sleeve 302; ring plate 303; support rib 305; gasket 304; seal 306;
[0024] Hanging beam 1; supporting beam 2; connecting rod 3; secondary supporting beam 4; supporting limiter 5; upper side plate 51; lower side plate 52; limit sleeve plate 53; stiffening rib 54; first pad 31; second pad 32. DETAILED DESCRIPTION
[0025] In order to make the purpose, technical solution and advantages of the utility model clearer, the technical solution of the utility model will be clearly and completely described below in combination with the embodiments of the utility model. Obviously, the described embodiments are part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments of the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.
[0026] Some embodiments of the present application provide an assembled installation adjustment device for temporarily supporting a multi-story suspended structure, the multi-story suspended structure comprising: an upper steel tie rod 101 and a lower steel tie rod 102 connected by a connecting node 300, and a floor steel beam 200 supported by the connecting node 300, the assembled adjustment device comprising: a hanging beam 1 hung on the steel beam, a supporting beam 2, a connecting rod 3 connecting the hanging beam 1 and the supporting beam 2 at an adjustable relative distance, and a supporting and limiting member 5 arranged on the supporting beam 2, supporting the connecting node 300 and radially limiting the lower steel tie rod 102.
[0027] The installation process of existing multi-story suspended structures often requires the assistance of lifting equipment, and the accuracy of adjusting the installation height is low. The assembled installation adjustment device of the present application is hung on the floor steel beam 200 through the hanging beam 1, and can bear the weight with the help of the floor steel beam 200 and form a support for the connection node 300 through the supporting beam 2 and the supporting limiter 5, and adjust the height of the connection node 300 with the support force of the floor steel beam 200. The present application uses the connecting rod 3 to bear tension, and uses the connection node 300 to bear part of the pressure without compressing the steel tie rod, which meets the design and use occasions of the steel tie rod and is not easy to cause damage to the steel tie rod. The supporting limiter 5 also forms a radial limit on the lower section steel tie rod 102 to prevent the lower section steel tie rod 102 from shaking during height adjustment, causing the connection to become unstable.
[0028] Considering that the connection node 300 is usually arranged in a ring shape, in order to fully support the connection node 300, the support limiter 5 should be in full contact with the connection node 300, so it has a certain contact area. In some embodiments, the assembled installation adjustment device also includes a secondary support beam 4 arranged perpendicularly to the support beam 2, and the support beam 2 and the secondary support beam 4 jointly support the support limiter 5 to support the support limiter 5 in multiple directions. For example, the secondary support beam 4 is arranged perpendicularly to the support beam 2 and is connected to the support beam 2 by high-strength bolts.
[0029] The supporting limiter 5 needs to limit the lower steel tie rod 102 in the circumferential direction, so it needs to have a limiter that matches the shape of the steel tie rod. Considering the convenience of installing the supporting limiter 5, in some embodiments, the supporting limiter 5 includes two detachable limit blocks that are surrounded by a ring, and the inner side wall of the ring limits the steel tie rod. Setting the supporting limiter 5 in this way can avoid inserting the supporting limiter 5 from the lower steel tie rod 102, and can be assembled and installed from the side of the lower steel tie rod 102.
[0030] The support and limit member 5 needs to be under pressure. In some embodiments, the limit block includes an upper side plate 51 , a lower side plate 52 , and a stiffening rib 54 disposed between the upper side plate 51 and the lower side plate 52 to enhance the pressure-bearing capacity of the support and limit member 5 .
[0031] In some embodiments, the connecting rod 3 is a screw threadedly connected to the hanging beam 1 and the supporting beam 2. Using the screw as the connecting rod 3 to connect the hanging beam 1 and the floor steel beam 200 can achieve a relatively stable adjustable connection and is easy to implement.
[0032] The present application can also be used to assist in adjusting the relative position of the connection node 300 and the upper steel tie rod 101 .
[0033] In some embodiments, as an existing multi-story suspension structure, the connection node 300 is threadedly connected to the upper steel tie rod 101 and the lower steel tie rod 102, and the relative position can be adjusted by the threaded connection. The adjustment device of the present application acts on this kind of multi-story suspension structure. After supporting the connection node 300 upward, it is also relatively easy to adjust the relative position between the upper steel tie rod 101 and the connection node 300 through the threaded connection. In the process of adjusting the relative position of the connection node 300 and the upper steel tie rod 101, the relative position of the connection node 300 and the supporting limiter 5 will inevitably change, affecting the supporting effect. The connection rod 3 can adjustably connect the hanging beam 1 and the supporting beam 2 to make the supporting effect of the connection node 300 of the present application adjustable. When adjusting the relative position of the connection node 300 and the upper steel tie rod 101, the relative position of the hanging beam 1 and the supporting beam 2 can be adjusted accordingly to control the supporting force of the connection node 300 to be within a range suitable for construction.
[0034] In order to increase the contact area between the connecting rod 3 and the hanging beam 1 , in some embodiments, a first pad 31 is provided on the hanging beam 1 , and the connecting rod 3 is connected to the first pad 31 to avoid stress concentration on the hanging beam 1 and damage to the hanging beam 1 .
[0035] In order to increase the contact area between the connecting rod 3 and the supporting beam 2, in some embodiments, a second pad 32 is provided on the supporting beam 2, and the connecting rod 3 is connected to the second pad 32 to avoid stress concentration on the supporting beam 2 and damage to the supporting beam 2.
[0036] In some embodiments, the hanging beam 1 and the supporting beam 2 are made of channel steel. Channel steel is light in weight and suitable for shearing, and is more suitable for serving as the hanging beam 1 and the supporting beam 2 of the present application.
[0037] Some embodiments of the present application also provide a method for adjusting the height of a multi-story suspended structure, using the above-mentioned steel tie rod assembly adjustment device to temporarily support the connection node 300 to adjust the multi-story suspended structure to its designed elevation, so as to construct the multi-story suspended structure more stably and accurately.
[0038] Some embodiments of the present application include a steel tie rod connection node 300, which is used to connect two steel tie rods in a multi-story suspension structure and support a floor steel beam 200, including: a connecting sleeve 301 provided with a first internal thread and an external thread, a supporting sleeve 302 provided with a second internal thread 21 threadedly connected to the external thread, and a ring plate 303 fixedly arranged on the outside of the supporting sleeve 302 for supporting the floor steel beam 200; two steel tie rods are threadedly connected to both ends of the first internal thread.
[0039] The internal thread of the connecting sleeve 301 connects the two steel tie rods. The connecting sleeve 301 only bears tension, and the force transmission between it and the steel tie rod is uniform and not easy to be damaged. The present application is also provided with a supporting sleeve 302 threadedly connected to the outside of the connecting sleeve 301. Compared with the traditional connection node, the threaded connection can make the construction operation of the supporting sleeve 302 easier when adjusting the elevation, and the force on the upper and lower tie rods is more uniform during adjustment, which will not cause stress concentration and damage to the steel tie rod and the supporting sleeve 302. The ring plate 303 is used to increase the contact area between the connection node and the floor steel beam 200, so that the support is more reliable.
[0040] In some embodiments, a gasket 304 is provided between the ring plate 303 and the floor steel beam 200 to make the force transmitted from the floor steel chain to the steel tie rod more uniform. Typically, the gasket 304 is a rubber pad.
[0041] In some embodiments, a supporting rib 305 for supporting the ring plate 303 is provided between the ring plate 303 and the supporting sleeve 302, so that the force of the ring plate 303 supporting the floor steel beam 200 can be more evenly transmitted to the supporting sleeve 302. Preferably, the supporting rib 305, the supporting sleeve 302 and the ring plate 303 are welded. Preferably, 4-8 supporting ribs 305 are evenly arranged along the circumference of the ring plate 303. The thickness of the supporting rib 305 is calculated and designed based on factors such as the diameter of the steel tie rod and the load of the floor steel beam 200. Empirically, its thickness is 40-80 mm.
[0042] In some embodiments, the supporting sleeve 302 and the ring plate 303 are connected by welding. The connection between the supporting sleeve 302 and the ring plate 303 needs to withstand greater stress. Welding has higher connection strength and is more convenient to construct, which can meet the implementation requirements of this application.
[0043] The design parameters of the ring plate 303 are calculated and designed based on factors such as the diameter of the steel tie rod and the load of the floor steel beam 200. Empirically, the outer diameter of the ring plate 303 is at least 200 mm larger than the outer diameter of the connecting sleeve 301, and the thickness of the ring plate 303 is 20-60 mm.
[0044] In some embodiments, locking members 11 for locking and fixing the steel rods are provided at both ends of the connecting sleeve 301. The locking members 11 are used to further lock and fix the relative positions of the two steel rods in combination with the threaded connection. The locking members 11 can be set as locking nuts.
[0045] In some embodiments, the floor steel beam 200 is an I-shaped structure, including an upper plate, a web plate, and a lower plate 201, and the upper end of the connecting sleeve 301 is higher than the lower plate 201. The connecting sleeve 301 used for threaded connection of two steel tie rods usually has a relatively long length because it must have a threaded section of a certain length. Setting the upper end of the connecting sleeve 301 higher than the lower plate 201 allows the connecting sleeve 301 to be partially accommodated in the floor steel beam 200, thereby increasing the aesthetics and sealing performance.
[0046] In some embodiments, a floor slab 300 is cast above the floor steel beam 200, and a seal 306 is provided between the floor slab 300 and the steel tie rod to prevent the steel tie rod from being corroded or damaged. The seal 306 is usually a rubber cover.
[0047] Specific embodiments of the present application are listed below to further illustrate the solutions of the present application.
[0048] A specific embodiment of an assembled installation and adjustment device is used for temporarily supporting and adjusting a multi-story suspended structure.
[0049] The multi-story suspension structure adjusted by this embodiment includes: an upper steel tie rod 101 and a lower steel tie rod 102 connected by a connection node 300, and a floor steel beam 200 supported by the connection node 300, and the relative position of the connection node 300 and the upper steel tie rod 101 is adjustable. A steel beam sleeve 201 is provided in the floor steel beam 200 for the steel tie rod to pass through.
[0050] The connection node 300 specifically includes: a connection sleeve 301 , a supporting sleeve 302 , a ring plate 303 , a supporting rib 305 , a gasket 304 , a locking member 3011 , and a sealing member 306 .
[0051] The connecting sleeve 301 is provided with a first internal thread and an external thread. The internal thread of the connecting sleeve 301 connects the upper steel tie rod 101 and the lower steel tie rod 102.
[0052] The supporting sleeve 302 is provided with a second internal thread 21. The supporting sleeve 302, the ring plate 303, and the supporting rib 305 are welded and connected. After welding, the supporting sleeve 302 is threadedly connected to the outside of the connecting sleeve 301. The outer diameter of the ring plate 303 is 300 mm greater than the outer diameter of the connecting sleeve 301. There are 8 supporting ribs 305 evenly arranged along the circumference of the ring plate 303, and the thickness of the supporting rib 305 is 60 mm.
[0053] The gasket 304 is a rubber gasket and the sealing member 306 is a rubber cover.
[0054] This embodiment includes: a hanging beam 1 , a supporting beam 2 , a connecting rod 3 , a supporting limiter 5 , and also includes a secondary supporting beam 4 , a first pad 31 and a second pad 32 .
[0055] The hanging beam 1 and the supporting beam 2 are both made of channel steel with through holes at the ends, and the two are connected by a connecting rod 3 with threads at both ends. The threaded connecting rod 3 passes through the through holes on the hanging beam 1 and the supporting beam 2, and is threadedly connected to the nut with the first pad 31 and the second pad 32 respectively.
[0056] The secondary supporting beam 4 is vertically arranged with the supporting beam 2 and connected with the supporting beam 2 by high-strength bolts.
[0057] The supporting limiter 5 includes two detachable limit blocks in an annular shape, and the limit blocks include an upper side plate 51, a lower side plate 52, a limit sleeve 53, and a stiffening rib 54 disposed between the upper side plate 51 and the lower side plate 52. The two limit sleeves 53 form an inner side wall of an annular shape to limit the steel tie rod, and the two limit blocks are assembled and locked by high-strength bolts.
[0058] The connecting rod 3 is a screw rod threadably connected to the hanging beam 1 and the supporting beam 2 .
[0059] Using this embodiment to adjust the height of the multi-story suspended structure includes the following steps:
[0060] S1, insert the upper steel tie rod 101 and the lower steel tie rod 102 connected by the connecting sleeve 301 into the steel beam sleeve 201, insert the lower steel tie rod 102 into the supporting sleeve 302 and threadedly connect with the connecting sleeve 301;
[0061] S2. Install the present embodiment according to the following steps in sequence: place the hanging beam 1 and the first pad 31 on the floor steel beam 200, insert the connecting rod 3 and lock it with the hanging beam 1, insert the supporting beam 2 and the second pad 32 and lock it with the connecting rod 3; connect the secondary supporting beam 4 and the supporting beam 2 with high-strength bolts; assemble the two limit blocks from both sides of the lower steel tie rod 102 into a whole and place them on the supporting beam 2 and the secondary supporting beam 4;
[0062] S3. According to the design elevation of the multi-story suspension structure, the nuts connecting the connecting rod 3 with the hanging beam 1 and the supporting beam 2 are adjusted, and the supporting limiter 5 places the supporting sleeve 302 at the required position.
[0063] The contents described above can be implemented individually or in combination in various ways, and these variations are all within the protection scope of the present utility model.
[0064] It should be noted that, in this article, relational terms such as first and second, etc. are only used to distinguish one entity or operation from another entity or operation, and do not necessarily require or imply any such actual relationship or order between these entities or operations. Moreover, the terms "include", "comprise" or any other variants thereof are intended to cover non-exclusive inclusion, so that a process, method, article or device comprising a series of elements includes not only those elements, but also other elements not explicitly listed, or also includes elements inherent to such process, method, article or device. In the absence of further restrictions, the elements defined by the statement "comprise a ..." do not exclude the presence of other identical elements in the process, method, article or device comprising the elements.
[0065] The above contents are further detailed descriptions of the present invention in combination with specific preferred implementation methods, and the specific embodiments of the present invention cannot be considered to be limited to these descriptions. For ordinary technicians in the technical field to which the present invention belongs, several simple deductions or substitutions can be made without departing from the concept of the present invention, which should be regarded as falling within the protection scope of the present invention.
Claims
1. An assembled installation adjustment device for temporarily supporting and adjusting a multi-story suspension structure, the multi-story suspension structure comprising: An upper steel tie rod (101) and a lower steel tie rod (102) connected by a connection node (300), and a floor steel beam (200) supported by the connection node (300), characterized in that the assembled installation adjustment device comprises: a hanging beam (1) hung on the floor steel beam (200), a supporting beam (2), a connecting rod (3) connecting the hanging beam (1) and the supporting beam (2) at an adjustable relative distance, and a supporting limiter (5) provided on the supporting beam (2), supporting the connection node (300) and radially limiting the lower steel tie rod (102).
2. The assembled installation and adjustment device according to claim 1, characterized in that: It also comprises a secondary supporting beam (4) arranged perpendicularly to the supporting beam (2), wherein the supporting beam (2) and the secondary supporting beam (4) together support the supporting limiter (5).
3. The assembled installation and adjustment device according to claim 1, characterized in that: The supporting limiting member (5) comprises two detachable limiting blocks which are arranged in a ring shape, and the inner side wall of the ring shape limits the lower steel pull rod (102).
4. The assembled installation and adjustment device according to claim 3, characterized in that: The limit block comprises an upper side plate (51), a lower side plate (52), a limit sleeve plate (53), and a stiffening rib (54) arranged between the upper side plate (51) and the lower side plate (52).
5. The assembled installation and adjustment device according to claim 1, characterized in that: The connecting rod (3) is a screw rod threadably connected to the hanging beam (1) and the supporting beam (2).
6. The assembled installation and adjustment device according to claim 1, characterized in that: The connection node (300) is threadedly connected to the upper steel tie rod (101), and the relative position can be adjusted through the threaded connection.
7. The assembled installation and adjustment device according to claim 1, characterized in that: A first pad (31) is provided on the hanging beam (1), and the connecting rod (3) is connected to the first pad (31).
8. The assembled installation and adjustment device according to claim 1, characterized in that: A second pad (32) is provided on the supporting beam (2), and the connecting rod (3) is connected to the second pad (32).
9. The assembled installation and adjustment device according to claim 1, characterized in that: The hanging beam (1) and the supporting beam (2) are made of channel steel.
Citation Information
Patent Citations
Steel tie rod connecting node
CN218521969U
Cited By
Assembly type installation adjusting device and height adjusting method for multi-story and high-rise suspension structure
CN118273541A