Electric hanging basket rear support heightening construction device

By designing an electric hanging basket rear bracket lift construction device and using adjustable structural components, the problem that the hanging basket cannot be adapted to the ultra-high wall in the prior art is solved, and the hanging basket installation suitable for multiple heights is achieved Construction improves the safety and flexibility of construction.

CN222435834UActive Publication Date: 2025-02-07SHANXI CONSTR ENG GROUP CORP
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202421206077.X
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-05-30
Publication Date
2025-02-07
Estimated Expiration
2034-05-30

AI Technical Summary

Technical Problem

The existing electric hanging basket cannot be adapted to the ultra-high daughter's wall, resulting in the inability to carry out construction work such as building facade insulation and curtain walls.

Method used

Design a construction device for lifting the rear bracket of the electric hanging basket, including pad plate, counterweight block, base post, heightened rod, top rod, rear beam, middle beam, cantilever front beam, reinforced wire rope, upper pillar and multi-shaped fixing The components, through the combination and adjustment of these components, enable adjustable height of the hanging basket and length of the beam.

Benefits of technology

The device is simple in structure, reasonable in design, easy to install, reliable and stable in steel structure, and high in safety. It is suitable for the installation and construction of hanging baskets under ultra-high wall conditions of various heights.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222435834U_ABST
    Figure CN222435834U_ABST
Patent Text Reader

Abstract

The utility model belongs to the technical field of building construction, and particularly relates to an electric hanging basket rear support heightening construction device which comprises a base plate, a balancing weight is connected to the top surface of the base plate, a base rod is connected to the top surface of the base plate, a heightening rod is connected to the top surface of the base rod, and an ejector rod is connected to the top surface of the heightening rod. The surface of the top end of the top rod is connected with one end of a rear beam, the surface of the other end of the rear beam is connected with a middle beam, the surface of the other end of the middle beam is connected with an overhanging front beam, the surface of the bottom of the other end of the overhanging front beam is connected with the surface of the top of a parapet wall, and the surface of the top of the overhanging front beam is connected with an upper supporting column. The hanging basket is simple in structure, reasonable in design, convenient to install, made of a steel structure, reliable and stable in structure and high in safety, meanwhile, the length of the girder can be adjusted, the height of the rear support can be adjusted, and the hanging basket is suitable for hanging basket installation construction under the working condition of ultrahigh parapet walls with various heights.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model belongs to the technical field of building construction, and in particular relates to a rear bracket heightening construction device for an electric hanging basket. Background Art

[0002] The electric hanging basket is a kind of aerial work equipment which adopts the electric lifting system. It has the advantages of high efficiency, safety, convenience and stability, and is widely used in construction, decoration, maintenance and other fields.

[0003] In housing construction and public construction projects, insulation layers are designed on the exterior walls for energy conservation. The construction of the insulation layers requires the use of electric hanging baskets. With the development of society, people have certain requirements for the aesthetics of buildings, and will raise the roof parapets to design various shapes. This results in the conventional hanging baskets being insufficient in height and unable to be installed, making it impossible to carry out construction operations such as building facade insulation and curtain walls. In this case, there is an urgent need for a hanging basket heightening construction device that can be installed for super-high parapets.

[0004] Therefore, the utility model provides a construction device for raising the rear support of an electric hanging basket to solve the above-mentioned problem. Utility Model Content

[0005] The utility model aims to provide a construction device for raising the rear support of an electric hanging basket, aiming to solve the problem in the prior art that the hanging basket cannot be adapted to an ultra-high parapet.

[0006] To achieve the above-mentioned purpose, the utility model provides the following technical scheme: a construction device for raising the rear support of an electric hanging basket, comprising a pad, a counterweight block is connected to the top surface of the pad, and a base rod is connected to the top surface of the base rod, a raising rod is connected to the top surface of the raising rod, a top rod is connected to the top surface of the top rod, and one end of the rear beam is connected to the other end surface of the rear beam is connected to the middle beam, and the other end surface of the middle beam is connected to the cantilevered front beam, the bottom surface of the other end of the cantilevered front beam is connected to the top surface of the parapet, and the top surface of the cantilevered front beam is connected to an upper support, a pulley arranged on the top surface of the upper support is connected to a reinforcing steel wire rope, one end of the reinforcing steel wire rope is connected to the rear beam, and the other end of the reinforcing steel wire rope is connected to the cantilevered front beam, one end of the reinforcing steel wire rope is connected to the hanging basket, and a "J"-shaped fixing piece is connected to the top surface of one end of the cantilevered front beam.

[0007] In order to achieve the position of the fixed pad, as a preferred embodiment of the utility model of an electric hanging basket rear bracket heightening construction device, the pad is fixed to the top surface of the roof by two M16 expansion bolts.

[0008] In order to connect the base rod, the heightening rod and the top rod, as a preferred embodiment of the utility model, an electric hanging basket rear support heightening construction device is connected by M16 bolts.

[0009] In order to realize the connection between the rear beam, the middle beam and the cantilevered front beam and the connection between the upper support and the cantilevered front beam, as a preferred construction device for raising the rear support of an electric hanging basket in the utility model, the rear beam, the middle beam and the cantilevered front beam are also connected by M16 bolts, and the upper support and the cantilevered front beam are connected by bolts.

[0010] In order to realize the installation of the reinforcing steel wire rope, as a preferred construction device for raising the rear support of an electric hanging basket of the utility model, the front and rear ends of the reinforcing steel wire rope are respectively fixed to the ends of the rear beam and the cantilevered front beam by steel wire rope clamps.

[0011] In order to fix the cantilevered front beam to prevent side sliding, as a preferred construction device for raising the rear support of an electric hanging basket of the utility model, the "X"-shaped fixing piece is threadedly connected to the parapet by using M16 expansion bolts.

[0012] Compared with the prior art, the beneficial effects of the utility model are:

[0013] The utility model has a simple structure, reasonable design, and easy installation. It is made of steel structure, has a reliable and stable structure, and has high safety. At the same time, the length of the beam can be adjusted, and the height of the rear bracket can be adjusted. It is suitable for the installation and construction of hanging baskets under super-high parapet wall working conditions of various heights. BRIEF DESCRIPTION OF THE DRAWINGS

[0014] The accompanying drawings are used to provide a further understanding of the present invention and constitute a part of the specification. Together with the embodiments of the present invention, they are used to explain the present invention and do not constitute a limitation of the present invention. In the accompanying drawings:

[0015] Figure 1 This is a schematic diagram of the main structure of the utility model;

[0016] Figure 2 This is a schematic diagram of the rear bracket structure of the utility model;

[0017] Figure 3 This is a schematic diagram of the front end fixing structure of the utility model on the parapet;

[0018] Figure 4 It is a schematic diagram of the structure of the X-shaped fixing piece of the utility model.

[0019] In the figure: 1. pad; 2. counterweight; 3. base rod; 4. heightening rod; 5. top rod; 6. rear beam; 7. middle beam; 8. cantilevered front beam; 9. reinforced steel wire rope; 10. upper support; 11. I-shaped fixing; 12. hanging basket; 13. parapet. DETAILED DESCRIPTION

[0020] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0021] See also Figure 1-Figure 4 The utility model provides the following technical solutions: a construction device for raising the rear support of an electric hanging basket, comprising a pad 1, a counterweight 2 is connected to the top surface of the pad 1, and a base rod 3 is connected to the top surface of the pad 1, a raising rod 4 is connected to the top surface of the base rod 3, a top rod 5 is connected to the top surface of the raising rod 4, and a top rod 5 is connected to the top surface of the top rod 5. The top surface of the top rod 5 is connected to one end of a rear beam 6, the other end surface of the rear beam 6 is connected to a middle beam 7, the other end surface of the middle beam 7 is connected to a cantilevered front beam 8, the other end bottom surface of the cantilevered front beam 8 is connected to the top surface of a parapet 13, and the top surface of the cantilevered front beam 8 is connected to an upper support 10, a pulley arranged on the top surface of the upper support 10 is connected to a reinforcing steel wire rope 9, one end of the reinforcing steel wire rope 9 is connected to the rear beam 6, and the other end of the reinforcing steel wire rope 9 is connected to the cantilevered front beam 8, one end of the reinforcing steel wire rope 9 is connected to a hanging basket 12, and a top surface of one end of the cantilevered front beam 8 is connected to a "J"-shaped fixing piece 11.

[0022] Preferably, the backing plate 1 is fixed to the top surface of the roof by two M16 expansion bolts.

[0023] When in use, the pad 1 is fixed on the roof by two M16 expansion bolts to fix the pad 1, and then the counterweight 2 is placed on the pad 1 to increase the counterweight of the pad 1 and improve the stability of the pad 1 when in use.

[0024] Preferably, the base rod 3, the heightening rod 4 and the top rod 5 are connected by M16 bolts.

[0025] During specific use, the rear support of the heightening construction device is composed of a top rod 5, a heightening rod 4, and a base rod 3. At the same time, the top rod 5 and the base rod 3 are made of 70×70×4mm square tubes, and the heightening rod 4 is made of 80×80×4mm square tubes. The base rod 3, the heightening rod 4 and the top rod 5 are connected by M16 bolts, so that the installation position between the base rod 3, the heightening rod 4 and the top rod 5 can be freely adjusted, thereby achieving the purpose of freely adjusting the height of the rear support.

[0026] Preferably, the rear beam 6, the middle beam 7 and the cantilevered front beam 8 are also connected by M16 bolts, and the upper support 10 and the cantilevered front beam 8 are connected by bolts.

[0027] During specific use, the beam installed for heightening construction is composed of a rear beam 6, a middle beam 7, and a cantilevered front beam 8. The rear beam 6 and the cantilevered front beam 8 are inserted into the middle beam 7, so that the rear beam 6, the middle beam 7, and the cantilevered front beam 8 are connected by M16 bolts and can be freely retracted, thereby achieving the purpose of adjusting the length of the beam and ensuring that the front is higher and the back is lower.

[0028] Preferably, the front and rear ends of the reinforcing steel wire rope 9 are respectively fixed to the ends of the rear beam 6 and the cantilevered front beam 8 by steel wire rope clamps.

[0029] During specific use, the reinforcing steel wire rope 9 is made of a steel wire rope with a diameter of 8.3 mm. The front and rear ends of the reinforcing steel wire rope 9 are respectively fixed to the ends of the rear beam 6 and the cantilevered front beam 8 by steel wire rope clamps. The reinforcing steel wire rope 9 is fixed using four steel wire rope clamps, and the spacing between the steel wire rope clamps is 6 to 7d.

[0030] Preferably, the X-shaped fixing member 11 is threadedly connected to the parapet 13 by using M16 expansion bolts.

[0031] During specific use, the cantilevered front beam 8 is placed on the top surface of the parapet 13, and then the I-shaped fixing piece 11 is placed on the upper end of the cantilevered front beam 8. Use M16 expansion bolts to penetrate the I-shaped fixing piece 11 and screw it into the parapet 13. This can fix the position of the I-shaped fixing piece 11 on the parapet 13 and fix the position of the cantilevered front beam 8 at the same time to prevent the cantilevered front beam 8 from sliding sideways when in use.

[0032] Working principle: When using the electric hanging basket rear bracket heightening construction device, fix the pad 1 at the specified position of the roof with two M16 expansion bolts, and then place the counterweight 2 on the pad 1 to increase the counterweight of the pad 1 and improve the stability of the pad 1 when in use. At this time, the rear bracket can be installed through the M16 bolts, so that the top rod 5 and the base rod 3 can slide on the heightening rod 4, so that the top rod 5 and the base rod 3 can be adjusted to the appropriate position, and then fixed and connected with M16 bolts, so as to achieve the purpose of freely adjusting the height of the rear bracket. At this time, the beam can be installed. According to the spacing between the rear bracket and the parapet 13, the top rod 5 is connected to the rear beam 6 by bolts, and the positions of the rear beam 6, the middle beam 7 and the cantilevered front beam 8 are adjusted, so that the rear beam 6 and the cantilevered front beam 8 can be telescopically slid in the middle beam 7. After the rear beam 6 and the cantilevered front beam 8 are adjusted to the appropriate position, they can be connected by M16 bolts, so as to achieve the purpose of adjusting the length of the beam. The upper support 10 can be connected with the cantilever front beam 8 by bolts, and the position of the cantilever front beam 8 can be fixed with the "X" shaped fixing piece 11. At this time, the reinforcing wire rope 9 can be installed, and the front and rear ends of the reinforcing wire rope 9 are respectively fixed to the ends of the rear beam 6 and the cantilever front beam 8 with a wire rope clamp. At the same time, one end of the reinforcing wire rope 9 will be connected to the pulley installed at the top of the upper support 10 to prevent the reinforcing wire rope 9 from being greatly worn during use. In this way, the cantilevered front beam 8 and the upper support 10, and the upper support 10 and the rear bracket will be connected by reinforcing wire rope 9. At this time, one end of the reinforcing wire rope 9 is connected to the hanging basket 12, and the assembly of the electric hanging basket rear bracket heightening construction device can be completed, so that the operator can operate normally. In this way, the operator can adjust the height of the rear bracket and the length of the beam according to the height of the parapet 13, so that the electric hanging basket rear bracket heightening construction device can be suitable for the hanging basket 12 installation and construction under the working conditions of the super-high parapet 13 of various heights.

[0033] Finally, it should be noted that the above description is only a preferred embodiment of the utility model and is not intended to limit the utility model. Although the utility model is described in detail with reference to the above embodiments, those skilled in the art can still modify the technical solutions recorded in the above embodiments or replace some of the technical features therein by equivalents. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the utility model shall be included in the protection scope of the utility model.

Claims

1. A construction device for raising the rear support of an electric hanging basket, comprising a pad (1), characterized in that: The top surface of the pad (1) is connected to a counterweight (2), and the top surface of the pad (1) is connected to a base rod (3), the top surface of the base rod (3) is connected to a heightening rod (4), the top surface of the heightening rod (4) is connected to a top rod (5), the top surface of the top rod (5) is connected to one end of a rear beam (6), the other end surface of the rear beam (6) is connected to a middle beam (7), the other end surface of the middle beam (7) is connected to a cantilevered front beam (8), and the bottom surface of the other end of the cantilevered front beam (8) is connected to a middle beam (7). The upper surface is connected to the top surface of a parapet (13), and the top surface of the cantilevered front beam (8) is connected to an upper support (10), a pulley arranged on the top surface of the upper support (10) is connected to a reinforcing steel wire rope (9), one end of the reinforcing steel wire rope (9) is connected to a rear beam (6), and the other end of the reinforcing steel wire rope (9) is connected to the cantilevered front beam (8), one end of the reinforcing steel wire rope (9) is connected to a hanging basket (12), and the top surface of one end of the cantilevered front beam (8) is connected to a "J"-shaped fixing piece (11).

2. The electric hanging basket rear support heightening construction device according to claim 1 is characterized in that: The backing plate (1) is fixed to the top surface of the roof by two M16 expansion bolts.

3. The electric hanging basket rear support heightening construction device according to claim 1 is characterized in that: The base rod (3), the heightening rod (4) and the top rod (5) are connected by M16 bolts.

4. The electric hanging basket rear support heightening construction device according to claim 1 is characterized in that: The rear beam (6), the middle beam (7), and the cantilevered front beam (8) are also connected via M16 bolts, and the upper support (10) and the cantilevered front beam (8) are connected via bolts.

5. The electric hanging basket rear support heightening construction device according to claim 1 is characterized in that: The front and rear ends of the reinforcing steel wire rope (9) are respectively fixed to the ends of the rear beam (6) and the cantilevered front beam (8) by means of steel wire rope clamps.

6. The electric hanging basket rear support heightening construction device according to claim 1 is characterized in that: The X-shaped fixing piece (11) is threadedly connected to the parapet wall (13) by using M16 expansion bolts.

Citation Information

Cited By

  • Split type double-pulley double-steel-wire-rope tensioning hanging basket construction method for old renovation project

    CN120331453A