Prestressed high-strength concrete pipe pile with protective coating structure

By setting up assembly structures, strengthening structures and protective structures on concrete pipe piles, the problems of insufficient strength and inconvenient assembly of concrete pipe piles are solved, and the effect of easy assembly and strength improvement is achieved.

CN222632223UActive Publication Date: 2025-03-18FUJIAN DALI NEW BUILDING MATERIALS TECH CO LTD
View PDF 1 Cites 0 Cited by

Patent Information

Application Number
CN202420608648.6
Authority / Receiving Office
CN · China
Patent Type
Utility models(China)
Current Assignee / Owner
Filing Date
2024-03-27
Publication Date
2025-03-18
Estimated Expiration
2034-03-27

AI Technical Summary

Technical Problem

The existing concrete pipe piles are insufficient in strength and are inconvenient for assembly, which limits their effectiveness in practical applications.

Method used

A prestressed high-strength concrete pipe pile with a protective coating structure was designed. By setting up assembly structures, strengthening structures and protective structures on the main body of the pipe pile, it is easy to assemble and improve strength.

Benefits of technology

Through the mounting structure design and the mounting structure of the assembly structure, the assembly convenience and overall strength of the pipe piles are improved, ensuring the stability and service life of the assembly.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN222632223U_ABST
    Figure CN222632223U_ABST
Patent Text Reader

Abstract

The utility model relates to the technical field of building materials, and provides a prestressed high-strength concrete pipe pile with a protective coating structure, which comprises a pipe pile main body and a support tray, supporting trays are arranged on the outer walls of the two ends of the pipe pile body, and a protection structure is arranged on one side of each supporting tray on the outer wall of the pipe pile body. Built-in grooves are evenly formed in the inner wall of the pipe pile body, and reinforcing structures are arranged in the built-in grooves. According to the utility model, the assembly structure is arranged, the tubular pile is convenient to assemble due to the clamping structure formed by the convex block and the groove, and the positioning of the tubular pile is reinforced through the threaded connection formed by the threaded hole and the through hole through the assembly bolt after the assembly and the positioning, so that the device is not easy to fall off after the assembly; therefore, the purposes of convenient assembly and stable and reliable assembly are achieved.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The utility model relates to the technical field of building materials, in particular to a prestressed high-strength concrete pipe pile with a protective coating structure. Background Art

[0002] In order to enhance the bearing capacity and stability of the soil and solve the problems of foundation settlement, settlement difference and foundation lateral displacement during the construction process, concrete pipe piles are usually used for reinforcement;

[0003] To this end, the patent with publication number CN204282352U discloses a prestressed concrete pipe pile with pull-out resistance, firmness and long service life, which includes a cylindrical pipe pile body filled with concrete; a steel bar skeleton wrapped in the pipe pile body, the steel bar skeleton includes an outer steel bar skeleton and an inner steel bar skeleton arranged in the outer steel bar skeleton; the outer steel bar skeleton includes outer ring bars arranged at equal intervals from the outside to the inside, and six outer vertical bars correspondingly arranged on the inner side of the outer ring bars and connected to the outer ring bars via iron wires; the inner steel bar skeleton includes inner ring bars arranged at equal intervals from the outside to the inside, and six inner vertical bars correspondingly arranged on the inner side of the inner ring bars and connected to the inner ring bars via iron wires; the connection points of the inner vertical bars and the inner ring bars in adjacent planes are connected to the connection points of the outer vertical bars and the outer ring bars via tensioning iron wires;

[0004] The concrete pipe piles mentioned above increase the strength of the device through annular reinforcement and vertical reinforcement to meet the actual use requirements, but such reinforcement strength is limited and it is difficult to assemble the pipe piles to meet the actual required height application, which has certain limitations during use. Utility Model Content

[0005] The utility model aims to provide a prestressed high-strength concrete pipe pile with a protective coating structure, so as to solve the defects of the existing concrete pipe piles that are insufficient in strength and inconvenient to assemble.

[0006] In order to solve the above technical problems, the utility model provides the following technical solutions: a prestressed high-strength concrete pipe pile with a protective coating structure, comprising a pipe pile body and a support tray;

[0007] Support trays are provided on the outer walls at both ends of the pipe pile body, and a protective structure is provided on one side of the support tray on the outer wall of the pipe pile body;

[0008] Built-in grooves are evenly formed on the inner wall of the pipe pile body, and the interior of the built-in grooves is provided with a reinforcement structure;

[0009] The top of the pipe pile body is evenly provided with an assembling structure, and the assembling structure includes a protrusion, a groove, a through hole, a threaded hole and an assembling bolt. The protrusion is evenly provided at the top of the pipe pile body, and the groove is evenly opened at the bottom of the pipe pile body. Through holes are opened on the outer wall of the protrusion, and a threaded hole is opened on one side of the groove on the outer wall of the pipe pile body, and assembling bolts are arranged inside the threaded hole.

[0010] Preferably, the protective structure includes a closed primer layer, an adhesive layer and an anti-corrosion layer, the closed primer layer is arranged on one side of the supporting tray on the outer wall of the pipe pile body, the outer side of the closed primer layer is provided with an adhesive layer, and the outer side of the adhesive layer is provided with an anti-corrosion layer.

[0011] Preferably, the reinforcement structure includes a reinforcement support, a clamping block, a built-in reinforcement tube and a clamping groove, the reinforcement supports are arranged inside the built-in groove, the reinforcement supports are provided with a clamping block on the side away from the built-in groove, the inner side of the pipe pile body is provided with a built-in reinforcement tube, and the outer wall of the built-in reinforcement tube is evenly provided with clamping grooves.

[0012] Preferably, the built-in grooves are distributed at equal intervals on the inner wall of the pipe pile body, and the built-in grooves and the reinforcing support form a snap-fit ​​structure.

[0013] Preferably, the clamping blocks are all arranged inside the clamping grooves, and the clamping blocks and the built-in reinforcement tube form a clamping structure through the clamping grooves.

[0014] Preferably, the protrusions are distributed at equal intervals on the top end of the pipe pile body, and the grooves are distributed at equal intervals on the bottom end of the pipe pile body.

[0015] Preferably, the protrusions are all arranged inside the grooves, and the protrusions and the grooves form a snap-fit ​​structure.

[0016] Preferably, the assembling bolts all extend to the interior of the through hole, and the threaded hole and the through hole are threadedly connected via the assembling bolts.

[0017] The utility model provides a prestressed high-strength concrete pipe pile with a protective coating structure, which has the advantages of:

[0018] By providing an assembling structure, the clamping structure composed of the protrusion and the groove makes it easy to assemble the pipe pile, and after the assembly and positioning, the threaded connection formed by the threaded hole and the through hole through the assembly bolt is used to strengthen its positioning, so that the device is not easy to fall off after assembly, thereby achieving the purpose of easy assembly and stable and reliable assembly;

[0019] By providing a reinforcement structure, the clamping block and the built-in reinforcement tube are installed through the clamping structure formed by the clamping groove, so that the pipe pile is strengthened as a whole, and the cross-section of the clamping block is triangular in design to further play a reinforcing role. When the reinforcement support or the built-in reinforcement tube is damaged, it is easy to replace, thereby achieving the purpose of improving the overall strength of the pipe pile and facilitating maintenance. BRIEF DESCRIPTION OF THE DRAWINGS

[0020] Figure 1 It is a three-dimensional structural schematic diagram of the utility model;

[0021] Figure 2 It is a three-dimensional structural schematic diagram of the utility model;

[0022] Figure 3 It is a three-dimensional structural schematic diagram of the utility model;

[0023] Figure 4 It is a partial cross-sectional structural schematic diagram of the utility model;

[0024] Figure 5 It is a three-dimensional structural schematic diagram of the utility model.

[0025] Explanation of the reference numerals in the figure: 1. Pipe pile body; 2. Support tray; 3. Protection structure; 301. Sealing primer layer; 302. Adhesive layer; 303. Anti-corrosion layer; 4. Built-in groove; 5. Reinforcement structure; 501. Reinforced support; 502. Snap-in block; 503. Built-in reinforcement pipe; 504. Snap-in groove; 6. Assembly structure; 601. Protrusion; 602. Groove; 603. Through hole; 604. Threaded hole; 605. Assembly bolt. DETAILED DESCRIPTION

[0026] The following will be combined with the drawings in the embodiments of the utility model to clearly and completely describe the technical solutions in the embodiments of the utility model. Obviously, the described embodiments are only part of the embodiments of the utility model, not all of the embodiments. Based on the embodiments in the utility model, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the utility model.

[0027] See also Figure 1-Figure 5 The utility model provides a prestressed high-strength concrete pipe pile with a protective coating structure, which includes a pipe pile body 1 and a support tray 2.

[0028] Reference Figure 1 and Figure 3As shown, support trays 2 are provided on the outer walls at both ends of the pipe pile body 1, and a protective structure 3 is provided on one side of the support tray 2 on the outer wall of the pipe pile body 1. The protective structure 3 includes a closed primer layer 301, an adhesive layer 302 and an anti-corrosion layer 303. The closed primer layer 301 is provided on one side of the support tray 2 on the outer wall of the pipe pile body 1, and the outer side of the closed primer layer 301 is provided with an adhesive layer 302, and the outer side of the adhesive layer 302 is provided with an anti-corrosion layer 303.

[0029] In order to enhance the bearing capacity and stability of the soil and solve the problems of foundation settlement, settlement difference and foundation lateral displacement during the construction process, concrete pipe piles are usually used to strengthen it. However, traditional concrete pipe piles may cause corrosion and other phenomena during long-term use, thereby damaging the pipe piles and affecting the overall service life. By setting up a protective structure 3, the pipe piles are protected and their service life is increased.

[0030] Reference Figure 1 and Figure 2 As shown, built-in grooves 4 are evenly opened on the inner wall of the pipe pile body 1, and the interior of the built-in grooves 4 is provided with a reinforcement structure 5, which includes a reinforcement support 501, a clamping block 502, a built-in reinforcement tube 503 and a clamping groove 504. The reinforcement supports 501 are all arranged inside the built-in grooves 4, and the side of the reinforcement supports 501 away from the built-in grooves 4 is provided with a clamping block 502. The inner side of the pipe pile body 1 is provided with a built-in reinforcement tube 503, and the outer wall of the built-in reinforcement tube 503 is evenly opened with clamping grooves 504. The built-in grooves 4 are evenly distributed on the inner wall of the pipe pile body 1. The built-in grooves 4 and the reinforcement supports 501 form a clamping structure, and the clamping blocks 502 are all arranged inside the clamping grooves 504. The clamping blocks 502 and the built-in reinforcement tube 503 form a clamping structure through the clamping grooves 504.

[0031] In the process of using pipe piles to strengthen the foundation strength, the traditional pipe piles are insufficient in strength and may be damaged during use, which is not conducive to subsequent use and causes unnecessary losses. By providing a reinforcement structure 5, it is convenient to strengthen the overall strength of the pipe piles, so that they are not easily damaged during use, thereby reducing the losses incurred during use and increasing their service life.

[0032] Reference Figure 1 , Figure 4 and Figure 5As shown, an assembling structure 6 is evenly arranged at the top of the pipe pile body 1, and the assembling structure 6 includes a protrusion 601, a groove 602, a through hole 603, a threaded hole 604 and an assembling bolt 605. The protrusion 601 is evenly arranged at the top of the pipe pile body 1, and the groove 602 is evenly opened at the bottom of the pipe pile body 1. Through holes 603 are opened on the outer wall of the protrusion 601, and a threaded hole 604 is opened on one side of the groove 602 on the outer wall of the pipe pile body 1. Assembling bolts 605 are arranged inside the threaded hole 604. The protrusions 601 are evenly distributed at the top of the pipe pile body 1, and the grooves 602 are evenly distributed at the bottom of the pipe pile body 1.

[0033] The traditional pipe pile is an integrated design, and in the actual use process, it may be necessary to change its height according to specific needs. However, it is difficult to assemble the traditional pipe pile conveniently to change the overall height, so it has certain limitations in the use process. By setting the assembly structure 6, it can be conveniently assembled to facilitate the change of the overall height, thereby greatly increasing the practicality of the device.

[0034] Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art may still modify the technical solutions described in the aforementioned embodiments, or make equivalent substitutions for some of the technical features therein. Any modifications, equivalent substitutions, improvements, etc. made within the spirit and principles of the present invention shall be included in the protection scope of the present invention.

Claims

1. A prestressed high-strength concrete pipe pile with a protective coating structure, comprising a pipe pile body (1) and a support tray (2); Features: Support trays (2) are provided on the outer walls of both ends of the pipe pile body (1), and a protective structure (3) is provided on one side of the support tray (2) on the outer wall of the pipe pile body (1); Built-in grooves (4) are evenly arranged on the inner wall of the pipe pile body (1), and the interior of the built-in grooves (4) is provided with a reinforcement structure (5); The top of the pipe pile body (1) is evenly provided with an assembling structure (6), the assembling structure (6) comprising a convex block (601), a concave groove (602), a through hole (603), a threaded hole (604) and an assembling bolt (605), the convex block (601) is evenly provided at the top of the pipe pile body (1), the concave groove (602) is evenly provided at the bottom of the pipe pile body (1), the outer wall of the convex block (601) is provided with a through hole (603), one side of the concave groove (602) on the outer wall of the pipe pile body (1) is provided with a threaded hole (604), and the inside of the threaded hole (604) is provided with an assembling bolt (605).

2. The prestressed high-strength concrete pipe pile with a protective coating structure according to claim 1, characterized in that: The protective structure (3) comprises a closed primer layer (301), an adhesive layer (302) and an anti-corrosion layer (303); the closed primer layer (301) is arranged on the outer wall of the pipe pile body (1) on one side of the supporting tray (2); the adhesive layer (302) is arranged on the outer side of the closed primer layer (301); and the anti-corrosion layer (303) is arranged on the outer side of the adhesive layer (302).

3. The prestressed high-strength concrete pipe pile with a protective coating structure according to claim 1, characterized in that: The reinforcement structure (5) comprises a reinforcement support (501), a clamping block (502), a built-in reinforcement tube (503) and a clamping groove (504); the reinforcement support (501) is arranged inside the built-in groove (4); the clamping block (502) is arranged on the side of the reinforcement support (501) away from the built-in groove (4); the built-in reinforcement tube (503) is arranged on the inner side of the pipe pile body (1); and the clamping grooves (504) are evenly arranged on the outer wall of the built-in reinforcement tube (503).

4. The prestressed high-strength concrete pipe pile with a protective coating structure according to claim 3, characterized in that: The built-in grooves (4) are distributed at equal intervals on the inner wall of the pipe pile body (1), and the built-in grooves (4) and the reinforcing support (501) form a snap-fit ​​structure.

5. The prestressed high-strength concrete pipe pile with a protective coating structure according to claim 3, characterized in that: The clamping blocks (502) are all arranged inside the clamping grooves (504), and the clamping blocks (502) and the built-in reinforcement tube (503) form a clamping structure through the clamping grooves (504).

6. The prestressed high-strength concrete pipe pile with a protective coating structure according to claim 1, characterized in that: The protrusions (601) are distributed at equal intervals on the top end of the pipe pile body (1), and the grooves (602) are distributed at equal intervals on the bottom end of the pipe pile body (1).

7. The prestressed high-strength concrete pipe pile with a protective coating structure according to claim 1, characterized in that: The protrusions (601) are all arranged inside the grooves (602), and the protrusions (601) and the grooves (602) form a snap-fit ​​structure.

8. The prestressed high-strength concrete pipe pile with a protective coating structure according to claim 1, characterized in that: The assembly bolts (605) all extend into the interior of the through hole (603), and the threaded hole (604) and the through hole (603) are threadedly connected via the assembly bolts (605).

Citation Information

Patent Citations

  • Pre-tensioned prestressed concrete tubular pile

    CN204282352U