An integrated excavation construction method for converting a shaft construction channel into a large-section tunnel
By adopting the shaft construction channel conversion method and the double-side wall guide pit method in the construction of the subway station tunnel, staged conversion and frame beam support were carried out, which solved the problems of uneven surrounding rock support and long construction period in the construction channel conversion section, and improved Improve construction safety and efficiency.
Patent Information
- Application Number
- CN201810678928.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-06-27
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2038-06-27
AI Technical Summary
In urban rail transit projects, during the construction of subway station tunnels, there are problems such as uneven stress and severe bias pressure on the surrounding rock support in the construction channel transition section, resulting in a long construction period and difficulty in construction safety control.
An integrated excavation construction method is used to convert the shaft construction channel into a large-section tunnel, by performing phased conversion construction between the cross channel and the large-section subway station tunnel, and opening up an internal cross channel in the double-side wall guide pit method, using frame beams Provide support to reduce mutual interference and construction period of the construction process.
It effectively solves the problem of uneven surrounding rock support in the section connection section between the construction channel and the subway station tunnel, shortens the construction period, and improves construction safety and efficiency.
Smart Images

Figure CN108843338B_ABST
Abstract
Description
Technical Field
[0001] The present invention belongs to the technical field of large-section tunnel construction, and relates to an integrated excavation construction method for converting a shaft construction channel into a large-section tunnel. Specifically, it relates to a double-hole rock pillar method - an improved integrated excavation construction method for converting a shaft-construction channel into a large-section tunnel based on a double-side wall pilot pit excavation method. Background Art
[0002] With the rapid development of society and the acceleration of urbanization, the scale of cities is constantly expanding. The population in large and megacities is dense, and the traffic for people to travel has become congested. In order to meet people's travel requirements and achieve the goal of convenient and fast transportation, people gradually turn their attention to the construction of urban rail transit. Among them, the construction of subway stations in rail transit projects often adopts open-cut method or dark-cut method for construction. However, the traditional open-cut method is no longer applicable in the prosperous areas of the city, so the dark-cut method with less impact on the surrounding environment is adopted for the construction of subway stations. The dark-cut method construction requires the construction of a vertical shaft-cross passage structure to enter the station tunnel to open up the working face, and then complete the excavation and support of the overall structure of the station tunnel.
[0003] Compared with interval tunnels, subway station tunnels have larger cross-section requirements. According to the international tunnel classification, they are large-section tunnels or even extra-large-section tunnels. The multi-step step method, the middle partition wall method, the CRD method, and the double-side wall pilot method are often used for the construction of large-section tunnels. Among them, the double-side wall pilot method has the best effect on surface settlement control and force balance of the support structure, but it is also the most expensive and longest construction method. Therefore, subway stations are built in urban central areas that are sensitive to surface settlement and deformation. The large-section double-side wall pilot method is used for the construction of underground subway station tunnels. The double-side wall pilot method has good control over surface settlement when excavating large-section subway station tunnels, but the long construction period will affect the entire construction period.
[0004] The vertical shaft-cross passage is used to transfer to the station tunnel to open up the working face for dark excavation construction. The cross passage is usually excavated by the step method. Because the subway station excavation section is large, it faces the problem of converting the small-section construction passage step method construction to the large-section station tunnel excavation construction. During the conversion construction, the surrounding rock stress of the conversion section will be disturbed multiple times. The cross-section construction of the small-section tunnel is changed to the large-section tunnel, causing the cross-section connection section to be biased. The greater the difference in cross-sectional area, the more serious the bias. This places high requirements on the support of the horse head gate in the conversion section, which is not conducive to construction safety control. Figure 1 The figure shows the schematic diagram of the construction channel conversion subway station tunnel construction.
[0005] In summary, the long construction period of double-side wall pilot pit excavation for large-section subway station tunnels and the construction problems of variable-section conversion of construction channels are issues that need to be resolved in current urban rail transit projects. Summary of the invention
[0006] The purpose of the present invention is to overcome the problem of uneven stress and severe bias pressure on the surrounding rock-support of the conversion section in the construction channel conversion subway station tunnel, and to overcome the shortcomings of the existing construction scheme that uses the construction channel to transfer to the subway station tunnel to complete the long excavation period of the station. The overall study of the construction of the vertical shaft, the horizontal channel, and the double-side wall pilot pit method of the railway station tunnel, as well as the conversion of construction procedures and construction safety issues between them, proposes an integrated excavation construction method for the conversion of the vertical shaft construction channel to a large-section tunnel, to achieve the following purposes:
[0007] 1) During the conversion construction between the cross passage and the large-section subway station tunnel, the phased conversion construction is completed at the same elevation. The upper step of the cross passage corresponds to the upper step of the left (right) pilot pit in the double-side wall pilot pit, the middle step of the cross passage corresponds to the middle step of the left (right) pilot pit in the double-side wall pilot pit, and the lower step of the cross passage corresponds to the left (right) pilot pit invert arch in the double-side wall pilot pit. After each phased conversion construction is completed, the large-section subway tunnel continues to excavate at the same step to the larger and smaller mileages, and does not continue to construct towards the bottom of the large-section tunnel. This can solve the safety problems and construction period problems of the conversion construction between the cross passage and the large-section subway station tunnel.
[0008] 2) The double-side wall pilot tunnel method is used to open up internal transverse passages during large-section tunnel construction, improve the traditional middle partition wall support, and replace it with the erection of frame beams to ensure the safe construction of the internal transverse passages, facilitate the construction of slag discharge, support, and Feng Shui circuits between the left and right guide tunnels, and further solve the safety problems of the double-side wall pilot tunnel method in opening up internal transverse passages and the slow construction period of subway station excavation.
[0009] 3) Reasonably arrange the construction procedures of the vertical shaft, transverse passage and large-section subway station tunnel, as well as the conversion of construction procedures between them, so as to minimize the mutual interference between the vertical shaft-transverse passage and the transverse passage inside the large-section tunnel.
[0010] The technical solution is as follows:
[0011] An integrated excavation construction method for converting a shaft construction channel into a large-section tunnel comprises the following steps:
[0012] (1) The first step of the construction channel is constructed to the temporary support contour line of the main tunnel, forming an A-type construction channel, and the surrounding rock above the construction channel is expanded and reinforced with I-beams;
[0013] (2) Before excavating the first pilot pit section of the nine-step double-side wall pilot pit of the subway station tunnel, two right pilot pit initial support steel frames were set up in the large and small mileage directions of the main tunnel as replacement beams to replace the A-type construction channel steel frame. After the steel frame replacement was completed, the first pilot pit stone of the main tunnel was excavated uphill with a slope of 10% in the large and small mileage directions of the main tunnel to provide initial support for this section.
[0014] (3) After the first pilot pit section completely overlaps with the upper pilot pit on the right, the seventh pilot pit section and the second pilot pit section of the nine-step double-side wall pilot pit method and the arch expansion section are excavated within the width of the B-type construction channel toward the left side of the main tunnel to provide temporary support for the B-type construction channel and initial support for the arch of the main tunnel.
[0015] (4) The seventh pilot pit and the second pilot pit of the double-side wall pilot pit method of the main tunnel are excavated in the direction of the large and small mileage of the main tunnel respectively, and the initial support of this part of the pilot pit is implemented.
[0016] (5) While step (4) is under construction, step (5) is carried out to excavate the lower step position of construction channel A. After the excavation of the lower step position is completed, the main tunnel is entered and the excavation is continued forward to excavate the stone of the lower step position, extend the steel frame support beam of type A construction channel, and provide initial support for this part.
[0017] (6) Excavate the third pilot pit on the right side of the main tunnel in the direction of the large and small mileage of the main tunnel, carry out initial support and temporary support for this part, and set up temporary cross bracing.
[0018] (7) After the third pilot pit is excavated to the B-type construction channel, the eighth and fourth pilot pits within the B-type construction channel are excavated toward the left side of the main tunnel, initial support is provided on the left side of the main tunnel, the steel frame of the B-type construction channel is extended, and temporary cross bracing is erected.
[0019] (8) Excavate the third and fourth pilot pits in the main tunnel towards the large and small mileage directions of the main tunnel, and provide initial support for these pilot pits;
[0020] (9) While the construction step (8) is being carried out, the portion of the construction channel A with the same elevation as the main tunnel inverted arch portion is excavated. After the excavation is completed, the overall reinforcing ring frame of the horse head gate of the construction channel A is constructed. After the concrete strength of the reinforcing ring frame reaches the design strength standard value, the primary support steel frame of the main tunnel is extended and firmly connected to the reinforcing ring frame. Then, the excavation continues forward, the stonework of the fifth pilot pit of the main tunnel is excavated, and the initial support of this portion is constructed;
[0021] (10) Excavate the lower fifth pilot pit on the right side of the main tunnel in the direction of the large and small mileages of the main tunnel, and provide initial support for this part of the pilot pit.
[0022] (11) After the fifth pilot pit is excavated to the B-type construction channel, the ninth and sixth pilot pits within the B-type construction channel are excavated toward the left side of the main tunnel, initial support is provided on the left side of the main tunnel, the temporary steel frame of the construction channel is extended, and temporary cross bracing is installed;
[0023] (12) Excavate the fifth and sixth pilot pits under the main tunnel in the direction of the main tunnel’s major and minor mileages, provide initial support for these pilot pits, and erect temporary cross braces;
[0024] (13) Remove the temporary construction conversion support, and excavate the seventh, eighth and ninth pilot pits of the core soil pilot pit in the middle of the section respectively. The initial support of the main tunnel is closed into a ring. After the longitudinal length reaches the length of the formwork trolley, the trolley is installed and the main tunnel lining is constructed.
[0025] Furthermore, in step (9), the width of the type B construction channel ranges from a clearance of 4 to 6 m.
[0026] Furthermore, in the B-type construction channel described in step (7), each steel frame includes a top crossbeam (1), an I-type joint (2), an I&V-type joint (3), an I&I-type joint (4), an I&I&I-type joint (5) and a locking foot anchor rod (6);
[0027] The top of the steel frame is composed of a top crossbeam (1), and a 300mm bend is provided in the middle of the top crossbeam (1); I-type joints (2) are used at both ends of the top crossbeam to connect two vertical I20b I-beams, and I&I-type joints are used at the connection points of the vertical steel sections, and locking anchor rods (6) are provided; a cross brace is provided every 3.5m of the vertical steel sections, and the connection method of the cross brace and the vertical I20b I-beam is an I&V-type joint (3); at the bottom of the vertical steel sections, channel steel is added to connect with an I&I&I-type joint (4); each steel frame is arranged at an interval of 0.5m, and longitudinal I22 longitudinal connecting steel bars are provided between each steel frame at a circumferential spacing of 1.0m.
[0028] The beneficial effects of the present invention are:
[0029] 1) The cross-sectional area of the connecting section between the construction channel and the subway station tunnel during construction is not much different. The core soil in the middle of the station tunnel is removed from the B-type construction channel to the construction channel. Therefore, the rock column in the middle of the subway station tunnel and the overall initial support at the connecting section will improve the surrounding rock-support stress state of the connecting section before excavation.
[0030] 2) The Type B construction channel inside the subway station tunnel and the Type A construction channel working surface in the connecting section are operated simultaneously. Compared with the traditional construction plan, two station-sized mileage working surfaces are added, shortening the construction period.
[0031] 3) The overall combination of the construction channel step method and the nine-step double-side wall pilot pit method for subway station tunnels simplifies the conversion process of the two construction methods and makes them easier to construct. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 Schematic diagram of construction of subway station tunnel for construction channel conversion;
[0033] Figure 2 Schematic diagram of the construction process of the double-hole rock pillar method;
[0034] Figure 3 Schematic diagram of type A channel layout;
[0035] Figure 4 Cross-section of type A construction channel;
[0036] Figure 5 Schematic diagram of the excavation process of part B;
[0037] Figure 6 Schematic diagram of the cross section of type B channel;
[0038] Figure 7 Process 4;
[0039] Figure 8 Construction step 5;
[0040] Fig. 9 Construction step 6;
[0041] Fig.10 Construction step 7;
[0042] Fig.11 Construction step 8;
[0043] Fig.12 Construction step 9;
[0044] Fig.13 Construction step 10;
[0045] Fig.14 Construction step 11;
[0046] Fig.15 Construction step 12;
[0047] Fig.16 Construction step 13;
[0048] Figure 17B-type construction channel, where Figure 17(a) is the cross-sectional design of the B-type construction channel, Figure 17(b) is the design drawing of the steel frame of the B-type construction channel, and Figure 17(c) is the elevation layout of the steel frame of the B-type construction channel. a-main tunnel initial support anchor rod; b-main tunnel excavation outline; c-secondary lining; d-station main tunnel; e-the shaded part is the unexcavated part; f-center line of the construction channel, 1-top beam; 2-I-type joint; 3-I&V-type joint; 4-I&I-type joint; 5-I&I&I-type joint; 6-locking foot anchor rod;
[0049] Fig.18 Schematic diagram of Guanshuilu Station;
[0050] Figure 19 is a flow chart of the rock pillar method in double tunnels at the Guanshui Road subway station site, wherein Figure 19(a) shows the construction steps (1) to (4) of the present invention, Figure 19(b) shows steps (5) to (11) of the present invention, and Figure 19(c) shows steps (12) to (13) of the present invention. DETAILED DESCRIPTION
[0051] The technical solution of the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0052] An integrated excavation construction method for converting a shaft construction channel into a large-section tunnel comprises the following steps:
[0053] (1) The first step of the construction channel is constructed to the temporary support contour line of the main tunnel wall to form an A-type construction channel. Figure 3 As shown in the figure, the upper surrounding rock of the construction channel is expanded, and I-beams are added to strengthen the support. The cross section of the A-type construction channel is as follows Figure 4 shown.
[0054] (2) Excavation of the 9-step double-side wall pilot pit of the subway station tunnel, namely Figure 5 Middle B part. Before excavating the B part, two right pilot pit initial support steel frames are set up in the direction of the main tunnel's large and small mileages as underpinning beams to underpin the A-type construction channel steel frame. After the steel frame underpinning is completed, the main tunnel B part (the right upper pilot pit and part of the middle pilot pit) is excavated with a slope of 10% uphill in the direction of the main tunnel's large and small mileages, and the initial support of this part is implemented.
[0055] (3) After the B part completely overlaps with the upper pilot pit on the right side (i.e., the longitudinal excavation length along the main tunnel reaches 3 times the width of the construction channel), the pilot pits 7 and 2 parts of the nine-step double-side wall pilot pit method and the arch expansion part are excavated to the left side of the main tunnel within the width range of the B-type construction channel (clearance 4 to 6m), and temporary support for the B-type construction channel and initial support for the main tunnel arch are implemented. The cross-sectional form of the B-type channel is as follows: Figure 6 shown.
[0056] (4) Excavate the pilot pits 1 and 2 of the double-side wall pilot pit method of the main tunnel in the direction of the large and small mileage of the main tunnel respectively, and provide initial support for these pilot pits.
[0057] (5) While carrying out step 4, carry out step 5 and excavate the lower step position of construction channel A, such as Figure 6 As shown in the C part of the figure. After the excavation of the C part is completed, enter the main tunnel and continue to dig forward, excavate the stone of the C part of the main tunnel, extend the steel frame support beam of the A-type construction channel, and implement the initial support of this part.
[0058] (6) Excavate the middle guide pit 3 on the right side of the main tunnel in the direction of the large and small mileage of the main tunnel, carry out initial support and temporary support for this part, and set up temporary cross bracing.
[0059] (7) After the pilot pit 3 is excavated to the B-type construction channel, the pilot pits 8 and 4 are excavated to the left of the main tunnel within the range of the B-type construction channel, and the initial support on the left side of the main tunnel is implemented. The steel frame of the B-type construction channel is extended and a temporary cross brace is erected.
[0060] (8) Excavate pilot pits 3 and 4 in the main tunnel towards the large and small mileage directions of the main tunnel respectively, and provide initial support for these pilot pits.
[0061] (9) While construction step 8 is in progress, the D section of the construction channel A is excavated. After the excavation is completed, a reinforcing ring frame is constructed. After the concrete strength of the reinforcing ring frame reaches the design strength standard value, the primary support steel frame of the main tunnel is extended and firmly connected to the reinforcing ring frame. Then, the excavation continues forward, 5 sections of stone are excavated for the main tunnel pilot pit, and the initial support of this section is constructed.
[0062] (10) Excavate the lower pilot pit 5 on the right side of the main tunnel in the direction of the large and small mileage of the main tunnel, and provide initial support for this part of the pilot pit.
[0063] (11) After the pilot pit 5 is excavated to the B-type construction channel, the pilot pits 9 and 6 within the B-type construction channel are excavated toward the left side of the main tunnel, initial support is provided on the left side of the main tunnel, the temporary steel frame of the construction channel is extended, and temporary cross bracing is erected.
[0064] (12) Excavate the main tunnel under the main tunnel in the direction of the large and small mileages, respectively, carry out initial support for this part of the pilot tunnel, and set up temporary cross braces.
[0065] (13) Remove the temporary construction transfer support, excavate the core soil guide pits 7, 8, and 9 in the middle of the section respectively, and close the main tunnel into a ring with initial support. After the longitudinal length reaches the length of the formwork trolley, install the trolley and construct the main tunnel lining.
[0066] According to the overall construction process plan for the vertical shaft, the horizontal passage and the subway station tunnel of the present invention, the mileage of the vertical shaft and the horizontal passage and the mileage of the internal B-type horizontal passage of the double-side wall horizontal passage must be set greater than 3 times the width of the horizontal passage hole to avoid mutual disturbance between the vertical shaft-horizontal passage construction and the internal horizontal passage construction.
[0067] The cross passage and subway station tunnel are constructed at the same elevation to avoid the connection section bias caused by the construction of variable cross-section tunnels of large and small sections.
[0068] When excavating a large-section tunnel using the double-sidewall pilot method to open an internal cross passage, it is necessary to erect frame beams for conversion construction, as shown in Figure 17. Each steel frame includes an I-type joint, an I&V-type joint, an I&I-type joint, an I&I&I-type joint, a locking foot anchor rod, and a top cross beam. Fig.17bThe top of the steel frame is composed of a top crossbeam, the length of which is determined by the width of the communication channel. The material is I20b I-beam, and the middle of the top crossbeam has a 300mm bend to fit the changes in the tunnel vault; I-type joints are used at both ends of the top crossbeam to connect two vertical I20b I-beams. The length of the I-beam depends on the height of the on-site communication channel. At the connection of the vertical steel, I&I type joints are used, and locking anchor rods (the length and type depend on the on-site surrounding rock conditions, such as I22 locking anchor rods L = 3.5m) are set to fix the changes at the connection of the steel to stabilize the deformation of the overall steel frame; a cross brace is set every 3.5m for the vertical steel, and the cross brace is also made of I20b I-beam. The connection method between the cross brace and the vertical I20b I-beam is I&V type joint; at the bottom of the vertical steel, channel steel is added to connect with I&I&I type joints.
[0069] Each steel frame is arranged at intervals of 0.5m, and longitudinal I22 longitudinal connecting steel bars are set between each steel frame with a circumferential spacing of 1.0m.
[0070] Implementation Cases
[0071] The present invention was used in the Zhongguanshui Road subway station of the first phase of Guiyang Urban Rail Transit Line 2, and good results were achieved according to on-site construction results.
[0072] Guiyang Urban Rail Transit Line 2 is an important subway line under construction in Guiyang, Guizhou Province. The line starts from Qijilukou Station, passes through Longdongbao International Airport, Nanming District Administrative Center and other key construction areas of Guiyang City, and ends at the Passenger Transport East Station. The first phase of Line 2 (Qijilukou Station ~ Youzha Street Station) has a total length of 27.4km, all underground. There are 24 stations in total. The average station spacing is 1162m, the maximum station spacing is 2070m, the minimum station spacing is 645m, and there are 5 transfer stations in total.
[0073] Guanshui Road Station is the 23rd station of the Phase I project of Line 2. The proposed station is an intermediate station located below the crossroad of Baoshan South Road and Guanshui Road. The station is arranged in a north-south direction along the Baoshan South Road intersection. The main structure is located below Baoshan South Road. The starting mileage is ZDK35+945.357~ZDK36+125.357, with a total length of 180m. The long-distance end of the station is close to the Nanming River. Affected by the section tunnel passing under the Nanming River, the track surface of this station is buried at a depth of 33.3~42m. It is planned to adopt an underground two-story island-type dark-cut station, with a five-center circle horseshoe section of curved wall + inverted arch, and a single-arch double-layer structure. The station tunnel vault is covered with soil of about 17.5 to 20.5 m, of which the overburden thickness is 3.5 to 12.5 m. The tunnel surrounding rock level is V-level. The mining method is used for construction. The maximum excavation section width of the station body is 22.16 m and the height is 19.21 m. It is a large-section dark-cut tunnel and is constructed using the double side wall pilot method. Figure 19 is a 3D flow chart of the double-hole rock pillar method used in the Guanshui Road subway station. The following is a brief description of each step of the flow chart:
[0074] (a) The No. 1 wind pavilion and construction shaft of Guanshui Road was excavated to the elevation of the first step arch bottom of the horizontal channel according to the inverted shaft wall method, and then the horizontal channel construction was started. Then, according to the "double-hole rock pillar method" of the present invention, the subway station tunnel construction was started. Step 4 in Figure (a) is to excavate the B-type construction channel. Figure 19 (a) shows the construction steps (1) to (4) of the present invention.
[0075] (b) While the internal B-type construction channel is excavated toward the subway tunnel pilot pits 1 and 2, the remaining parts of the vertical shaft and the transverse channel are excavated, and the subway station tunnel excavation pilot pits 3 and 5 are transferred to the internal B-type transverse channel, according to steps (5) to (11) of the present invention.
[0076] (c) Excavate from the inside of the B-type cross passage to the subway station tunnel, gradually remove the temporary intermediate partition wall support, and apply the secondary lining according to steps (12) to (13) of the present invention.
[0077] The above is only a preferred specific implementation manner of the present invention, and the protection scope of the present invention is not limited thereto. Any simple change or equivalent replacement of the technical solution that can be obviously obtained by any technician familiar with the technical field within the technical scope disclosed in the present invention falls within the protection scope of the present invention.
Claims
1. An integrated excavation construction method for converting a shaft construction channel into a large-section tunnel, characterized in that: The following steps are involved: (1) The first step of the construction channel is constructed to the temporary support contour line of the main tunnel, forming an A-type construction channel, and the surrounding rock above the construction channel is expanded and reinforced with I-beams; (2) Excavation of the first pilot pit section of the nine-step double-side wall pilot pit of the subway station tunnel. Before excavation, two right pilot pit initial support steel frames were set up in the large and small mileage directions of the main tunnel as replacement beams to replace the A-type construction channel steel frame; after the steel frame replacement was completed, the first pilot pit stone of the main tunnel was excavated uphill with a slope of 10% in the large and small mileage directions of the main tunnel, and the initial support of this section was implemented; (3) Part B completely overlaps with the upper pilot pit on the right side, where Part B refers to the first pilot pit part, that is, the excavation length along the longitudinal direction of the main tunnel reaches 3 times the width of the construction channel, and the seventh pilot pit part and the second pilot pit part of the nine-step double-side wall pilot pit method within the width of the B-type construction channel are excavated to the left side of the main tunnel, and the arch expansion part is used to implement temporary support for the B-type construction channel and initial support for the arch of the main tunnel; (4) Excavate the seventh and second pilot pits of the double-side wall pilot pit method of the main tunnel in the direction of the main tunnel's major and minor mileages, and provide initial support for these pilot pits; (5) While step (4) is being carried out, step (5) is being carried out to excavate the lower step position of construction channel A. After the excavation of the lower step position is completed, the main tunnel is entered and the excavation is continued forward to excavate the stone at the lower step position, extend the steel frame support beam of the A-type construction channel, and provide initial support for this part; (6) Excavate the third pilot pit on the right side of the main tunnel in the direction of the main tunnel’s major and minor mileages, provide initial support and temporary support for this part, and erect temporary cross braces; (7) After the third pilot pit is excavated to the B-type construction channel, the eighth and fourth pilot pits within the B-type construction channel are excavated toward the left side of the main tunnel, initial support is provided on the left side of the main tunnel, the steel frame of the B-type construction channel is extended, and temporary cross bracing is erected; (8) Excavate the third and fourth pilot pits in the main tunnel towards the large and small mileage directions of the main tunnel, and provide initial support for these pilot pits; (9) While construction step (8) is being carried out, a portion of the construction channel A having the same elevation as the invert portion of the main tunnel is excavated; After the excavation is completed, the reinforced ring frame is constructed. When the concrete strength of the reinforced ring frame reaches the design strength standard value, the primary support steel frame of the main tunnel is extended and firmly connected to the reinforced ring frame. Then, the excavation continues, the stone of the fifth pilot pit of the main tunnel is excavated, and the initial support of this part is constructed. (10) Excavate the lower fifth pilot pit on the right side of the main tunnel in the direction of the main tunnel’s major and minor mileages, and provide initial support for this pilot pit; (11) After the fifth pilot pit is excavated to the B-type construction channel, the ninth and sixth pilot pits within the B-type construction channel are excavated toward the left side of the main tunnel, initial support is provided on the left side of the main tunnel, the temporary steel frame of the construction channel is extended, and temporary cross bracing is erected; (12) Excavate the fifth and sixth pilot pits under the main tunnel in the direction of the main tunnel’s major and minor mileages, provide initial support for these pilot pits, and erect temporary cross braces; (13) Remove the temporary construction conversion support, and excavate the seventh, eighth and ninth pilot pits of the core soil pilot pit in the middle of the section respectively. The initial support of the main tunnel is closed into a ring. After the longitudinal length reaches the length of the formwork trolley, the trolley is installed and the main tunnel lining is constructed.
2. The integrated excavation construction method for converting a shaft construction channel into a large-section tunnel according to claim 1 is characterized in that: In step (9), the width of the type B construction channel ranges from 4 to 6 m.
Citation Information
Patent Citations
Tunnel double upper sidewall heading construction method
CN101858220A
Tunnel excavation construction method
CN102155233A
Convoluted excavation method for undermined tunnel with extra-large cross section
CN102400689A
Bidirectional punching method for underground excavation of subway station
CN102953739A
Vertical in-tunnel construction method of multilayer transverse channel of underground excavation station of metro, and construction method on east side and west side
CN103452561A