A concrete component construction method capable of avoiding slag inclusion and slurry leakage
By setting a purge hole in the lower part of the formwork and using the method of sealing angle steel and anti-leakage angle steel combined with rubber and plastic sponge strips, the problem of garbage cleaning and bottom sealing in the formwork during the construction of vertical components such as concrete columns and walls has been solved, and quality problems have been avoided. defects, improving project quality and construction efficiency.
Patent Information
- Application Number
- CN201811155110.X
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2018-09-30
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2038-09-30
AI Technical Summary
During the construction of vertical components such as concrete columns and walls, it is difficult to clean the garbage inside the formwork and the bottom of the formwork cannot be sealed, resulting in quality defects such as slag inclusions, root rot, honeycombs, and pitted surfaces.
Set a purge hole in the lower part of the formwork, and use blocking angle steel and anti-leakage angle steel combined with rubber and plastic sponge strips to clean the garbage in the formwork and seal the bottom to prevent slurry leakage.
It effectively avoids quality defects such as slag inclusions, rotten roots, honeycombs and pitted surfaces, ensures the quality of the project, and reduces the construction difficulty and secondary repair costs.
Smart Images

Figure CN109138410B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the field of construction of vertical components such as reinforced concrete columns and concrete walls in building engineering, and in particular to a concrete component construction method capable of avoiding slag inclusion and slurry leakage. Background Art
[0002] During the construction of vertical components such as concrete columns and walls, wooden formwork (bamboo plywood, multi-layer board, etc.) is often used. After the formwork is installed in place, the sawdust and other construction waste generated in the formwork cannot be blown and washed, leaving garbage inside the formwork. When pouring concrete into the formwork, the garbage remaining in the formwork can easily cause quality defects such as concrete slag inclusions and root rot, affecting the quality of the project.
[0003] In addition, the construction formwork of vertical components such as concrete columns and walls in the prior art cannot be sealed at the bottom, and there is a gap between the formwork and the ground. When pouring concrete into the formwork, due to the good fluidity of concrete, root leakage is prone to occur, causing quality defects such as honeycombs and rough surfaces in the concrete components, affecting the quality of the project. Summary of the invention
[0004] In order to solve the above technical problems, the present invention provides a concrete component construction method which is convenient for blowing and flushing garbage at the bottom of the template and preventing leakage of slurry at the base of columns and walls, thereby avoiding quality defects such as slag inclusion, root rot, honeycomb and rough surface in column and wall concrete.
[0005] To achieve the above object, the present invention adopts the following technical solution:
[0006] A concrete component construction method capable of avoiding slag inclusion specifically comprises the following steps:
[0007] (1) Processing and installation of pouring templates: Cut the pouring templates according to the structural design dimensions, open a purge hole at the bottom of the pouring templates, and install the pouring templates in place;
[0008] (2) Processing leakproof angle steel and plugging angle steel: Process leakproof angle steel and plugging angle steel respectively according to the design dimensions of the casting template, drill fixing holes on the vertical surfaces of the leakproof angle steel and plugging angle steel, and the hole diameter is slightly larger than the diameter of the steel nails used for fixing; cut a notch on the bottom surface of the plugging angle steel at the position corresponding to the fixing square wood, and the length and width of the notch are the same as those of the fixing square wood;
[0009] (3) Fix the blocking angle steel: temporarily fix the blocking angle steel to the casting template with fixing nails through the fixing holes. The lower side of the vertical surface of the blocking angle steel is flush with the upper end of the purge hole. At this time, the purge hole is in an open state.
[0010] (4) Fix the leakproof angle steel: add a rubber-plastic sponge strip of leakproof slurry under the leakproof angle steel, and fix the leakproof angle steel to the casting template with fixing nails through the fixing holes;
[0011] (5) Cleaning up the garbage inside the formwork: After installing and fixing the square timber to reinforce the formwork, and completing the reinforcement of the formwork system, use high-pressure air or high-pressure water to blow out the sawdust inside the formwork from the purge hole on one side of the casting formwork and clean it up before the formwork is accepted;
[0012] (6) Block the purge hole: Pull out the fixing nails on the blocking angle steel, install a rubber-plastic sponge strip at the bottom of the blocking angle steel, and drop the blocking angle steel to the bottom of the template. At this time, the vertical surface of the blocking angle steel will block the purge hole;
[0013] (7) Pouring concrete: Pour concrete into the casting formwork. After it is formed and dried, remove the casting formwork, fixed square timber, blocking angle steel, leakproof angle steel and rubber-plastic sponge strips;
[0014] The construction structure of the concrete member that can avoid slag inclusion and slurry leakage includes a casting template and a fixed square wood arranged outside the casting template, the fixed square wood is fixed to the casting template, a purge hole is arranged at the lower part of the casting template, a plugging member is arranged at the purge hole, and the plugging member is movable;
[0015] The purge holes are symmetrically arranged on two opposite sides of the casting template;
[0016] The blocking member is a blocking angle steel arranged between the casting template and the fixed square timber, and the blocking angle steel can move up and down;
[0017] The blocking angle steel comprises a vertical surface and a bottom surface perpendicular to each other, the vertical surface is located between the casting template and the fixed square timber, and a fixing hole is arranged on the vertical surface; a notch is arranged on the bottom surface at a position corresponding to the fixed square timber, and the length and width of the notch are the same as those of the fixed square timber;
[0018] The bottom of the side of the casting template where the purge hole is not provided is provided with a leak-proof angle steel, the leak-proof angle steel is provided between the casting template and the fixed square wood, and the vertical surface of the leak-proof angle steel is provided with a fixing hole;
[0019] Fix the leakproof angle steel on the casting formwork by passing fixing nails through the fixing holes.
[0020] Preferably, a rubber-plastic sponge strip is provided at the lower end of the blocking angle steel, and the length of the rubber-plastic sponge strip is the same as that of the casting template.
[0021] Preferably, a rubber-plastic sponge strip is provided at the lower end of the leak-proof angle steel, and the length of the rubber-plastic sponge strip is the same as that of the casting template.
[0022] Beneficial Effects
[0023] The concrete component construction structure that can avoid slag inclusion and slurry leakage described in the present invention is convenient for purging and flushing garbage at the bottom of the template by setting a purge hole on the template, ensuring that the garbage in the template is cleaned up and in place, and avoiding the retention of garbage inside the template. The bottom of the template and the purge port are blocked by blocking angle steel, leak-proof angle steel and rubber-plastic sponge strips to prevent the roots of vertical components such as columns and walls from leaking during the concrete construction process, and to avoid the occurrence of slag inclusion, root rot, honeycomb and rough surface quality defects in concrete components. The application of this technology successfully solves the quality defects of concrete columns and walls such as slag inclusion and root rot without increasing costs, ensuring the quality of the project.
[0024] This patent can be promoted and applied in all vertical structural formwork systems (bamboo plywood, multi-layer board and other on-site processed formwork) at construction sites. Angle steel plugging is convenient for workers to operate, and materials can be used in a cyclical manner, which reduces the difficulty of construction. It avoids the cost of secondary repair of concrete leakage and quality defects, and has broad prospects for promotion. BRIEF DESCRIPTION OF THE DRAWINGS
[0025] Figure 1 This is a structural schematic diagram of the concrete component construction structure described in Example 1 of the present invention when the purge hole is in an open state.
[0026] Figure 2 This is a structural schematic diagram of the concrete component construction structure described in Example 1 of the present invention when the purge hole is in a closed state.
[0027] Figure 3 This is a schematic diagram of the top view of the concrete component construction structure described in Example 1 of the present invention.
[0028] Figure 4 This is a schematic structural diagram of the blocking angle steel described in Example 1 of the present invention.
[0029] Figure 5 This is a schematic structural diagram of the leak-proof angle steel described in Example 1 of the present invention.
[0030] Figure 6 This is a photo of the leak-proof angle steel at the concrete column construction site.
[0031] In the figure: 1: reinforced concrete column; 2: pouring formwork; 3: fixing square timber; 4: blocking angle steel; 5: leak-proof angle steel; 6: fixing hole; 7: rubber-plastic sponge strip; 8: purge hole; 9: notch; 10: vertical surface; 11: bottom surface. DETAILED DESCRIPTION
[0032] The technical solution of the present invention is further described in detail below with reference to the embodiments and the accompanying drawings.
[0033] Example 1
[0034] like Figure 1As shown, a concrete component construction structure that can avoid slag inclusion and slurry leakage includes a casting template 2 and a fixed square timber 3 arranged outside the casting template, the fixed square timber 3 is fixed to the casting template 2 by steel nails, and a purge hole 8 is arranged at the lower part of the casting template 2, and a sealing member is arranged at the purge hole 8, and the sealing member is movable.
[0035] The purge holes are symmetrically arranged on two opposite sides of the casting template, and two purge holes are arranged on each side.
[0036] The blocking member is a blocking angle steel 4 disposed between the casting template and the fixed square timber, and the blocking angle steel 4 can move up and down. The blocking angle steel includes a vertical surface 10 and a bottom surface 11 perpendicular to each other, the vertical surface is located between the casting template and the fixed square timber, and a fixing hole 6 is disposed on the vertical surface; a notch 9 is disposed on the bottom surface at a position corresponding to the fixed square timber, and the length and width of the notch are the same as those of the fixed square timber. A rubber sponge strip 7 is disposed at the lower end of the blocking angle steel, and the length of the rubber sponge strip 7 is the same as that of the casting template.
[0037] The bottom of the side of the casting template where the purge hole is not provided is provided with a leak-proof angle steel 5, and the leak-proof angle steel 5 includes a vertical surface and a bottom surface perpendicular to each other, and the vertical surface is located between the casting template and the fixed square wood, and the vertical surface is provided with a fixing hole 6. The leak-proof angle steel is fixed to the casting template by passing a fixing nail through the fixing hole. The lower end of the leak-proof angle steel is provided with a rubber sponge strip 7, and the length of the rubber sponge strip 7 is the same as that of the casting template.
[0038] Example 2
[0039] A method for constructing a concrete component that can avoid slag inclusion and slurry leakage, wherein the construction structure of the concrete component is as described in Example 1, and specifically comprises the following steps:
[0040] (1) Processing and installation of pouring formwork: Cut the pouring formwork according to the structural design dimensions, open a purge hole about 20 mm high at the bottom of the pouring formwork, and install the pouring formwork in place. The pouring formwork is made of bamboo plywood (multi-layer board);
[0041] (2) Processing leakproof angle steel and plugging angle steel: Process leakproof angle steel and plugging angle steel respectively according to the design dimensions of the casting template, drill fixing holes on the vertical surfaces of the leakproof angle steel and plugging angle steel, and the hole diameter is slightly larger than the diameter of the steel nails used for fixing; cut a notch on the bottom surface of the plugging angle steel at the position corresponding to the fixing square wood, and the length and width of the notch are the same as those of the fixing square wood;
[0042] (3) Fix the blocking angle steel: temporarily fix the blocking angle steel to the casting template with fixing nails through the fixing holes. The lower side of the vertical surface of the blocking angle steel is flush with the upper end of the purge hole. At this time, the purge hole is in an open state.
[0043] (4) Fix the leakproof angle steel: add a rubber-plastic sponge strip of leakproof slurry under the leakproof angle steel, and fix the leakproof angle steel to the casting template with fixing nails through the fixing holes;
[0044] (5) Cleaning up the garbage inside the formwork: After installing and fixing the square timber to reinforce the formwork, and completing the reinforcement of the formwork system, use high-pressure air or high-pressure water to blow out the sawdust and other garbage inside the formwork from the purge hole on one side of the casting formwork before the formwork is accepted;
[0045] (6) Block the purge hole: Pull out the fixing nails on the blocking angle steel, install a rubber-plastic sponge strip at the bottom of the blocking angle steel, and drop the blocking angle steel to the bottom of the template. At this time, the vertical surface of the blocking angle steel will block the purge hole;
[0046] (7) Pouring concrete: Pour concrete into the casting formwork. After it is formed and dried, remove the casting formwork, fixing square timber, sealing angle steel, anti-leakage angle steel and rubber-plastic sponge strips.
[0047] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the scope of protection of the present invention.
Claims
1. A method for constructing a concrete component that can avoid slag inclusion and slurry leakage, characterized in that: The following steps are involved: (1) Processing and installation of pouring templates: Cut the pouring templates according to the structural design dimensions, open a purge hole at the bottom of the pouring templates, and install the pouring templates in place; (2) Processing leakproof angle steel and plugging angle steel: Process leakproof angle steel and plugging angle steel respectively according to the design dimensions of the casting template, drill fixing holes on the vertical surfaces of the leakproof angle steel and plugging angle steel; cut a notch on the bottom surface of the plugging angle steel at the position corresponding to the fixed square wood, and the length and width of the notch are the same as those of the fixed square wood; (3) Fix the blocking angle steel: temporarily fix the blocking angle steel to the casting template with fixing nails through the fixing holes. The lower side of the vertical surface of the blocking angle steel is flush with the upper end of the purge hole. At this time, the purge hole is in an open state. (4) Fix the leak-proof angle steel: add a rubber-plastic sponge strip of leak-proof slurry under the leak-proof angle steel, and fix the leak-proof angle steel to the casting template with fixing nails through the fixing holes; (5) Cleaning up the garbage inside the formwork: After installing and fixing the square timber to reinforce the formwork, and completing the reinforcement of the formwork system, before the formwork is accepted, use high-pressure air or high-pressure water to blow out the sawdust inside the formwork from the purge hole on one side of the pouring formwork and clean it up; (6) Block the purge hole: Pull out the fixing nails on the blocking angle steel, install a rubber-plastic sponge strip on the lower part of the blocking angle steel, and drop the blocking angle steel to the bottom of the template. At this time, the vertical surface of the blocking angle steel will block the purge hole; (7) Pouring concrete: Pour concrete into the casting formwork. After it is formed and dried, remove the casting formwork, fixed square timber, blocking angle steel, leakproof angle steel and rubber-plastic sponge strips; The construction structure of the concrete member that can avoid slag inclusion and slurry leakage includes a casting template and a fixed square wood arranged outside the casting template, the fixed square wood is fixed to the casting template, a purge hole is arranged at the lower part of the casting template, a plugging member is arranged at the purge hole, and the plugging member is movable and tightly sealed; The purge holes are symmetrically arranged on two opposite sides of the casting template; The blocking member is a blocking angle steel arranged between the casting template and the fixed square timber, and the blocking angle steel can move up and down; The blocking angle steel comprises a vertical surface and a bottom surface perpendicular to each other, the vertical surface is located between the casting template and the fixed square timber, and a fixing hole is arranged on the vertical surface; a notch is arranged on the bottom surface at a position corresponding to the fixed square timber, and the length and width of the notch are the same as those of the fixed square timber; The bottom of the side of the casting template where the purge hole is not provided is provided with a leak-proof angle steel, the leak-proof angle steel is provided between the casting template and the fixed square wood, and the vertical surface of the leak-proof angle steel is provided with a fixing hole; Fix the leakproof angle steel on the casting formwork by passing fixing nails through the fixing holes.
2. A method for constructing a concrete component that can avoid slag inclusion and grout leakage according to claim 1, characterized in that: A rubber-plastic sponge strip is arranged at the lower end of the blocking angle steel, and the length of the rubber-plastic sponge strip is the same as that of the casting template.
3. A concrete component construction method capable of avoiding slag inclusion and grout leakage according to claim 1, characterized in that: A rubber-plastic sponge strip is arranged at the lower end of the leak-proof angle steel, and the length of the rubber-plastic sponge strip is the same as that of the casting template.