A superstructure and construction method for a wide box girder low tower cable-stayed bridge

By using the combined structure of the main girder body and deck components and the diagonal brace assembly in the short tower cable-stayed bridge, the problems of the shear lag effect and the insufficiency of conventional hanging baskets in the construction of wide box girders in the short tower cable-stayed bridge are solved. The mechanical performance and construction efficiency of the main beam body are improved, and the cost and difficulty are reduced.

CN110644349BActive Publication Date: 2024-10-29SHANDONG TRAFFIC PLANNING DESIGN INST
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN201911055414.3
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2019-10-31
Publication Date
2024-10-29
Estimated Expiration
2039-10-31

AI Technical Summary

Technical Problem

In the wide box girder structure of the short tower cable-stayed bridge, due to the complex lateral stress and obvious shear lag effect, conventional hanging baskets are difficult to meet the construction requirements, affecting the stress performance of the main girder body, and the construction safety and cost are high.

Method used

The combined structure of the main beam body and bridge deck components is adopted. The bridge deck beam structure is formed through components such as diagonal brace assemblies and U-shaped channel steel. Prefabricated panels and wet joint technology are used to achieve the horizontal extension and longitudinal extension of the main beam body. Bearing force, reducing construction difficulty and cost.

Benefits of technology

It effectively reduces the shear lag effect of the short-tower cable-stayed bridge, improves the lateral stress performance of the main girder body, adapts to the construction needs of wide box girder, reduces the construction cost and difficulty, and improves the construction speed and quality.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN110644349B_ABST
    Figure CN110644349B_ABST
Patent Text Reader

Abstract

The present invention relates to an upper structure and construction method for a wide box girder low-tower cable-stayed bridge, comprising a main girder body, the main girder body being a box girder structure, and the two sides of the upper surface of the main girder body being symmetrically overlapped with bridge deck components; a diagonal brace assembly is provided between the main girder body and the bridge deck component, the diagonal brace assembly is arranged obliquely, the lower end of the diagonal brace assembly is fixed to the lower part of the main girder body, the upper end of the diagonal brace assembly is in contact with the lower end surface of the inclined surface component and supports the bridge deck component; the bridge deck component can extend the main girder body in the width direction, and the main girder body and the bridge deck component form a bridge deck beam structure. The present invention can reduce the shear lag effect of the main girder body of a wide box girder low-tower cable-stayed bridge, improve the lateral force performance of the main girder body, and solve the problem that conventional hanging baskets cannot meet the cantilever casting of wide box girders of low-tower cable-stayed bridges.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridges, and in particular relates to a superstructure and a construction method for a wide box girder and low-tower cable-stayed bridge. Background Art

[0002] The low-tower cable-stayed bridge, also known as the partial cable-stayed bridge, is a beam-cable combined system bridge between the continuous beam and the cable-stayed bridge. The low-tower cable-stayed bridge has good economic performance because of its low tower and high beam, which reduces cable fatigue and improves cable utilization. It has flexible span layout, a reasonable single span of 100 to 300 meters, and a wide range of applications. The main beam height is about 1 / 2 of the continuous beam with the same span, and the appearance is light. Therefore, it has a wide range of application prospects.

[0003] Due to the cross-sectional stress characteristics of the main beam, the cable towers of low-tower cable-stayed bridges are mostly arranged in the central dividing strip and use the central cable plane. In recent years, with the continuous increase in domestic traffic volume, my country's high-grade highways, especially long-span bridges across large rivers, have begun to build six-lane and eight-lane width projects. Due to the increase in lateral width, the lateral stress of the main beam of the low-tower cable-stayed bridge has become more complex, and the shear lag effect has become more obvious, which has reduced the stress performance of the main beam and affected the application and promotion of low-tower cable-stayed bridges in wide box girders.

[0004] The inventors learned that in the construction of low-tower cable-stayed bridges, the hanging basket cantilever casting method is generally used for construction. Compared with the full-bridge support construction, this method is more capable of overcoming unfavorable terrain and enables the bridge superstructure to be constructed in sections. It has the advantages of simple construction, low cost, good structural integrity, relatively simple maintenance, and less maintenance workload.

[0005] However, the inventors believe that for two-way six-lane and two-way eight-lane central cable-surface low-tower cable-stayed bridges, since their box girders are wider and the lateral width of the basket is increased, conventional baskets cannot meet the force requirements and must be redesigned, which not only increases costs but also brings new challenges to the design and manufacture of the wide basket and its safety during cantilever construction. Summary of the invention

[0006] The purpose of the present invention is to provide an upper structure and a construction method for a wide box girder low tower cable-stayed bridge, which can reduce the shear lag effect of the main beam of the wide box girder low tower cable-stayed bridge, improve the lateral force performance of the main beam, and solve the problem that conventional hanging baskets cannot meet the cantilever casting requirements of wide box girders of low tower cable-stayed bridges.

[0007] To achieve the above object, the present invention adopts the following technical solution: an upper structure for a wide box girder and low tower cable-stayed bridge, comprising a main girder body, the main girder body is a box girder structure, and bridge deck components are symmetrically overlapped on both sides of the upper surface of the main girder body;

[0008] A diagonal brace assembly is provided between the main beam body and the bridge deck assembly, the diagonal brace assembly is arranged obliquely, the lower end of the diagonal brace assembly is fixed to the lower part of the main beam body, and the upper end of the diagonal brace assembly contacts the lower end surface of the inclined plane assembly to support the bridge deck assembly;

[0009] The bridge deck assembly is a longitudinal force-bearing member on the support and diagonal brace assembly, which can realize the extension of the main beam body in the width direction. The main beam body and the bridge deck assembly form a bridge deck beam body structure.

[0010] Furthermore, the diagonal brace assembly includes a steel pipe, a base is fixedly installed at the lower end of the steel pipe, and embedded steel plates are respectively provided at the lower parts of the two side surfaces of the main beam body, and the base and the embedded steel plates are fixedly connected by embedded bolts.

[0011] Furthermore, the diagonal brace assembly includes a U-shaped channel steel, which is arranged horizontally and located directly below the bridge deck assembly. The U-shaped channel steel is fixedly connected to a steel pipe, and concrete is poured in the U-shaped channel steel. The upper surface of the U-shaped channel steel contacts the lower surface of the bridge deck assembly to achieve support.

[0012] Furthermore, legs are provided on both sides of the main beam body, and the legs are used to overlap the bridge deck assembly. The bridge deck assembly is connected to the upper surface of the main beam body through a wet joint, and the wet joint is a cast-in-place concrete structure.

[0013] Furthermore, the bridge deck assembly includes a prefabricated plate, and the prefabricated plate is a square plate.

[0014] Furthermore, an end plate is fixedly provided on one end of the U-shaped channel steel close to the main beam body, and embedded bolts are provided on one side of the main beam body close to the U-shaped channel steel, and the embedded bolts are fixedly connected to the end plate.

[0015] Furthermore, the bridge deck assembly on each side of the main beam body is formed by splicing a plurality of prefabricated panels in sequence, and the plurality of prefabricated panels on the same side are connected by wet joints.

[0016] The present invention also provides a construction method applicable to a wide box girder and low tower cable-stayed bridge. The constructed method applicable to a wide box girder and low tower cable-stayed bridge utilizes the upper structure for the wide box girder and low tower cable-stayed bridge, and comprises the following steps:

[0017] Step 1: Construction of bottom structure: including pile foundation, cap and pier construction;

[0018] Step 2: Use the bracket method to construct the middle beam, connecting segments and tower columns, and install the hanging basket;

[0019] Step 3: The cable-free area of ​​the main beam body is cantilevered to tension the longitudinal prestress; one or more beam sections are delayed to firmly connect the steel diagonal brace assembly with the embedded parts of the main beam body, hoist the precast panels, and cast the transverse wet joints;

[0020] Step 4: The cable-attached beam section of the main beam body is cantilevered, and the hanging basket moves from the bridge tower to both sides. The main beam body is constructed symmetrically, and the longitudinal prestressing force is tensioned; and the inclined cables are installed in sequence and tensioned in place;

[0021] The transverse diagonal brace joint section is constructed synchronously with one or more beam sections after the other; the side span cast-in-place bracket is installed, and the side span cast-in-place section is cast;

[0022] Step 5, complete the construction of the closure section of the main beam mid-span and side span, and tension the longitudinal prestressed steel strands of the closure section, synchronously construct the steel diagonal brace assembly, and cast the longitudinal wet joints of the bridge deck;

[0023] Furthermore, in step 3, concrete is poured into the steel pipe; when the concrete in the steel pipe reaches the designed strength, the prefabricated panel is hoisted above the steel diagonal brace assembly.

[0024] Beneficial effects of the present invention:

[0025] 1) The wide box girder of the low-tower cable-stayed bridge is broken down into parts. The wide box girder is formed by splicing the narrower main girder and the bridge deck components, which is convenient for the construction of the girder using the hanging basket, and the forces on each component are clearer;

[0026] 2) The conventional width hanging basket can be used for cantilever casting construction, which avoids the redesign of the wide hanging basket, reduces the construction difficulty, saves construction costs, and reduces the influence of the shear lag effect of the full width box girder of the traditional low-tower cable-stayed bridge.

[0027] 3) The width of the main beam can be adapted to the range below 42 meters, which can meet the width requirements of most existing highways, municipal roads, and ordinary highway bridges; the steel structure can be manufactured in the factory and hoisted and installed on site, with fast construction speed and reliable quality. BRIEF DESCRIPTION OF THE DRAWINGS

[0028] The drawings in the specification, which constitute a part of the present application, are used to provide a further understanding of the present application. The illustrative embodiments of the present application and their descriptions are used to explain the present application and do not constitute a limitation on the present application.

[0029] Figure 1 It is a schematic diagram of the cross section of the main beam body in an embodiment of the present invention;

[0030] Figure 2 for Figure 1 Detailed structural diagram of Part A;

[0031] Figure 3 This is a schematic diagram of the structure of the end sealing plate in an embodiment of the present invention;

[0032] Figure 4 for Figure 1 Detailed structural diagram of Part B;

[0033] Figure 5 This is a schematic diagram of the plan layout of the prefabricated panels in an embodiment of the present invention;

[0034] Figure 6 This is a schematic diagram of the transverse joint of the prefabricated plate in an embodiment of the present invention;

[0035] Figure 7 This is a diagram showing the division of the cross-section area of ​​a wide box girder in an embodiment of the present invention;

[0036] Figure 8 This is a schematic diagram of the main viewing direction of the lower structure construction in an embodiment of the present invention;

[0037] Fig. 9 It is a schematic diagram of the top view of the construction of the lower structure in an embodiment of the present invention;

[0038] Fig.10 A schematic diagram of the main viewing direction tower column construction in an embodiment of the present invention;

[0039] Fig.11 A schematic diagram of the construction of a tower column from a top-down direction in an embodiment of the present invention;

[0040] Fig.12 It is a schematic diagram of cantilever casting of a beam section in a cable-free area of ​​a main beam body in the main viewing direction in an embodiment of the present invention;

[0041] Fig.13 It is a schematic diagram of cantilever casting of a beam section in a cable-free area of ​​a main beam body in a top view in an embodiment of the present invention;

[0042] Fig.14 It is a schematic diagram of cantilever casting of a beam section with a cable area of ​​a main beam body in the main viewing direction and installation of a stay cable in an embodiment of the present invention;

[0043] Fig.15 It is a schematic diagram of cantilever casting of a beam section with cable area of ​​a main beam body and installation of a stay cable in a top view in an embodiment of the present invention;

[0044] Fig.16 This is the construction of the main beam body joint section in the main viewing direction in the embodiment of the present invention;

[0045] Fig.17 This is the construction of the main beam joint section in the top view in the embodiment of the present invention;

[0046] Fig.18 It is the construction of auxiliary structure in the main viewing direction in the embodiment of the present invention;

[0047] Fig.19This is the construction of the auxiliary structure in the top view in the embodiment of the present invention;

[0048] In the figure: 1. Main beam; 2. Diagonal brace assembly; 3. Bridge deck member; 4. End plate; 5. Wet joint; 6. Precast plate; 7. U-shaped channel steel; 8. Embedded bolts; 9. Embedded flange steel plate; 10. Flange steel plate base; 11. Square steel pipe; 12. Rivets; 13. Pier; 13A. Cap; 13B. Pile foundation; 14. Cast-in-place support; 15. Hanging basket; 16. Tower column; 17. Connection segment; 18. Cable-free segment; 19. Guardrail; 20. Side span cast-in-place segment; 20A. Side span cast-in-place support; 21. Cable. DETAILED DESCRIPTION

[0049] It should be noted that the following detailed descriptions are illustrative and are intended to provide further explanation of the present application. Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those commonly understood by those skilled in the art to which the present application belongs.

[0050] It should be noted that the terms used herein are only for describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprise" and / or "include" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.

[0051] In a typical embodiment of the present invention, as shown in 1-3, a superstructure for a wide box girder and low tower cable-stayed bridge comprises a main girder body 1, wherein the main girder body 1 is a box girder structure, and bridge deck components 3 are symmetrically overlapped on both sides of the upper surface of the main girder body 1;

[0052] A diagonal brace assembly 2 is provided between the main beam body 1 and the bridge deck assembly 3. The diagonal brace assembly 2 is arranged obliquely, the lower end of the diagonal brace assembly 2 is fixed to the lower part of the main beam body 1, and the upper end of the diagonal brace assembly 2 contacts the lower end surface of the inclined plane assembly to support the bridge deck assembly;

[0053] The bridge deck assembly 3 can realize the extension of the main beam body 1 in the width direction, and the main beam body 1 and the bridge deck assembly 3 form a bridge deck beam structure.

[0054] Specifically, the main beam 1 is a concrete main beam 1, the concrete main beam 1 and the bridge deck assembly 3 (precast slab 6) can be made of C50 or higher concrete, and the material of the steel brace assembly 2 can be Q355, Q370, Q420 grade steel in the national standard. The steel main beam 1 and the concrete bridge deck are connected by cylindrical head welded nails, and the shear nail model is generally M19, M22, and the length is 2 / 3 of the height of the U-channel steel 7, and is not less than 15 cm.

[0055] During the construction of the wide box girder structure, the hanging basket 15 is first used to cantilever cast the middle main box girder, and then the steel diagonal brace assembly 2 is installed and firmly connected with the embedded steel bars or embedded bolts 8 of the middle main box girder, and then the precast panels 6 are hoisted, and finally the wet joints 5 are cast to form a whole and bear the force together.

[0056] The diagonal brace assembly 2 includes a steel pipe, a base is fixedly installed at the lower end of the steel pipe, and embedded steel plates are respectively provided at the lower part of the two side surfaces of the main beam body 1, and the base and the embedded steel plates are fixedly connected by embedded bolts 8.

[0057] Specifically, the steel pipe can be a square steel pipe 11. The base is a flange steel plate base 10, and the embedded steel plate is an embedded flange steel plate 9.

[0058] In some embodiments, the top width B1 of the main beam body 1 can be 34 to 42 meters; the bottom width B2 = 0.5 to 0.6B1; the cantilever length of the intermediate box beam B3 = 0.8 to 1.0 meters; the transverse diagonal brace connection section B4 = 0.13 to 0.15B1, B5 = 0.08 to 0.1B1, the standard spacing of steel diagonal braces d = 4.0 or 4.5m; the height H1 of the main beam body 1 is determined according to the actual span of the bridge; the thickness of the bridge deck H2 = 0.25 to 0.3 meters.

[0059] The diagonal brace assembly 2 includes a U-shaped channel steel 7, which is arranged horizontally and located directly below the bridge deck assembly 3. The U-shaped channel steel 7 is fixedly connected to a steel pipe, and concrete is poured in the U-shaped channel steel 7. The upper surface of the U-shaped channel steel 7 contacts the lower surface of the bridge deck assembly 3 to achieve support.

[0060] Specifically, rivets should be provided in the U-channel steel to facilitate the fixation of concrete.

[0061] The main beam body 1 is provided with legs on both sides, and the legs are used to overlap the bridge deck assembly 3. The bridge deck assembly 3 is connected to the upper surface of the main beam body 1 through a wet joint 5, and the wet joint 5 is a cast-in-place concrete structure.

[0062] The bridge deck assembly 3 includes a prefabricated plate 6, which is a square plate.

[0063] An end plate 4 is fixedly provided at one end of the U-shaped channel steel 7 close to the main beam body 1 , and an embedded bolt 8 is provided at one side of the main beam body 1 close to the U-shaped channel steel 7 , and the embedded bolt 8 is fixedly connected to the end plate 4 .

[0064] The bridge deck assembly 3 on each side of the main beam body 1 is formed by splicing a plurality of prefabricated panels 6 in sequence, and the plurality of prefabricated panels 6 on the same side are connected via wet joints 5 .

[0065] Specifically, a low-tower cable-stayed bridge has the characteristics of rigid beams, low towers and concentrated cables. Its overall rigidity is mainly provided by the main beam, and the cable 21 mainly plays the role of stiffening the beam body and adjusting the force. The wide box beam section suitable for a low-tower cable-stayed bridge proposed in this embodiment divides the entire cross-section into a relatively narrow box beam in the middle and a combination of transverse steel braces. The middle main box beam provides the overall rigidity of the bridge, meets the space required for the longitudinal prestressing arrangement, and bears the longitudinal force of the main beam; the transverse brace combination section provides sufficient section width and bears the transverse local force; the ratio of the transverse length to the longitudinal length of the precast plate 6 is close to 2, which is a one-way plate with the short side bearing the load, and only distributed steel bars need to be configured in the long side direction.

[0066] This embodiment also provides a construction method applicable to a wide box girder and low tower cable-stayed bridge. The constructed method applicable to a wide box girder and low tower cable-stayed bridge utilizes the upper structure for the wide box girder and low tower cable-stayed bridge, and includes the following steps:

[0067] Step 1, bottom structure construction: including the construction of pile foundation 13B, cap 13A and pier body of pier 13;

[0068] Step 2, using the bracket method to construct the main beam 1, the connecting segment 17, the segment and the tower column 16, and install the hanging basket 15;

[0069] Step 3, the cable-free segment 18 of the main beam body 1 is cantilevered to tension the longitudinal prestress; one or more beam segments are delayed, the steel diagonal brace assembly 2 is firmly connected to the embedded parts of the main beam body 1, the precast plate 6 is hoisted, and the transverse wet joint 5 is cast;

[0070] Step 4: The cable-stayed section of the main beam 1 is constructed by cantilever, the hanging basket 15 moves from the bridge tower to both sides, the main beam 1 is constructed symmetrically, and the longitudinal prestress is tensioned; and the inclined cables 21 are installed in sequence and tensioned in place;

[0071] The transverse diagonal brace combination section is constructed synchronously with one or more beam sections after lagging; the side span cast-in-place bracket 20A is installed, and the side span cast-in-place section 20 is cast;

[0072] Step 5, completing the construction of the mid-span and side span closure sections of the main beam 1, and tensioning the longitudinal prestressed steel strands of the closure section, synchronously constructing the steel diagonal brace assembly 2, and casting the longitudinal wet joint 5 of the bridge deck;

[0073] After the curing of the bridge deck is completed, the construction of auxiliary structures such as bridge deck pavement, guardrails 19, expansion joints, and lamp posts is carried out.

[0074] In step 3, concrete is poured into the steel pipe; when the concrete in the steel pipe reaches the designed strength, the prefabricated panel 6 is hoisted above the steel diagonal brace assembly 2.

[0075] Although the above describes the specific implementation mode of the present invention in conjunction with the accompanying drawings, it is not intended to limit the scope of protection of the present invention. Those skilled in the art should understand that various modifications or variations that can be made by those skilled in the art on the basis of the technical solution of the present invention without creative work are still within the scope of protection of the present invention.

Claims

1. A superstructure for a wide box girder and low tower cable-stayed bridge, characterized in that: It comprises a main beam body, the main beam body is a box beam structure, and the two sides of the upper surface of the main beam body are symmetrically overlapped with bridge deck components; A diagonal brace assembly is provided between the main beam body and the bridge deck assembly, the diagonal brace assembly is arranged obliquely, the lower end of the diagonal brace assembly is fixed to the lower part of the main beam body, and the upper end of the diagonal brace assembly contacts the lower end surface of the inclined surface assembly to support the bridge deck assembly; the diagonal brace assembly includes a U-shaped channel steel, the U-shaped channel steel is arranged horizontally, the U-shaped channel steel is located directly below the bridge deck assembly, the U-shaped channel steel is fixedly connected to the steel pipe, concrete is poured in the U-shaped channel steel, and the upper surface of the U-shaped channel steel contacts the lower surface of the bridge deck assembly to achieve support; an end plate is fixedly provided at one end of the U-shaped channel steel close to the main beam body, and a side of the main beam body close to the U-shaped channel steel is provided with embedded bolts, and the embedded bolts are fixedly connected to the end plate; The bridge deck assembly can realize the extension of the main beam in the width direction, and the main beam and the bridge deck assembly form a bridge deck beam structure; The two sides of the main beam body are provided with legs, and the legs are used to overlap the bridge deck assembly. The bridge deck assembly is connected to the upper surface of the main beam body through a wet joint, and the wet joint is a concrete cast-in-place structure; The bridge deck components on each side of the main beam are formed by splicing multiple precast panels in sequence, and multiple precast panels on the same side are connected by wet joints.

2. The upper structure for a wide box girder and low tower cable-stayed bridge according to claim 1, characterized in that: The diagonal brace assembly comprises a steel pipe, a base is fixedly mounted on the lower end of the steel pipe, and embedded steel plates are respectively provided at the lower parts of the two side surfaces of the main beam body, and the base is fixedly connected to the embedded steel plates by embedded bolts.

3. A construction method suitable for a wide box girder and low tower cable-stayed bridge, characterized in that: The constructed cable-stayed bridge suitable for a wide box girder and a low tower utilizes the upper structure for a cable-stayed bridge with a wide box girder and a low tower as claimed in any one of claims 1 to 2, and comprises the following steps: Step 1: Construction of bottom structure: including pile foundation, cap and pier construction; Step 2: Use the bracket method to construct the middle beam, connecting segments and tower columns, and install the hanging basket; Step 3: The cable-free area of ​​the main beam body is cantilevered to tension the longitudinal prestress; one or more beam sections are delayed to firmly connect the steel diagonal brace assembly with the embedded parts of the main beam body, hoist the precast panels, and cast the transverse wet joints; Step 4: The cable-attached beam section of the main beam body is cantilevered, and the hanging basket moves from the bridge tower to both sides. The main beam body is constructed symmetrically, and the longitudinal prestressing force is tensioned; and the inclined cables are installed in sequence and tensioned in place; The transverse diagonal brace joint section is constructed synchronously with one or more beam sections after the other; the side span cast-in-place bracket is installed, and the side span cast-in-place section is cast; Step 5, complete the construction of the main beam mid-span and side span joint sections, tension the longitudinal prestressed steel strands of the joint sections, construct the steel diagonal brace assemblies simultaneously, and cast the longitudinal wet joints of the bridge deck.

4. The construction method applicable to a wide box girder and low tower cable-stayed bridge according to claim 3 is characterized in that: In step 3, concrete is poured into the steel pipe; when the concrete in the steel pipe reaches the designed strength, the prefabricated panel is hoisted above the steel diagonal brace assembly.

Citation Information

Patent Citations

  • Upper structure for wide box girder extradosed cable-stayed bridge

    CN211395312U

  • Section division type precast segment construction method

    JP2001164512A