A cofferdam combining permanent structure pile foundation and temporary steel sheet pile and its construction method
By combining permanent structural pile foundations and temporary steel sheet piles in docks and flood control wall projects, the supporting structure and cofferdam are formed, and the problems of high cost and difficult displacement control in the existing technology are solved, and resource conservation and efficient construction are achieved. Effect.
Patent Information
- Application Number
- CN201910965941.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2019-10-12
- Publication Date
- 2024-11-08
- Estimated Expiration
- 2039-10-12
AI Technical Summary
The cofferdams in existing docks and flood control wall projects are costly in environments with large water depths and poor construction conditions, and ordinary steel sheet pile structures are difficult to meet the requirements of high displacement control, resulting in waste of resources and environmental impact, especially when constructing at the same time. construction platform and temporary flood prevention measures.
A cofferdam design is adopted that combines permanent structural pile foundations and temporary steel sheet piles. A water stop curtain is formed through double rows of steel sheet piles, connecting beams and fills, and a support structure is formed by combining steel cross beams, steel longitudinal beams and horizontal shear braces to form a temporary structure. The steel platform and cofferdam are welded by steel purlins to form a reliable connection, suitable for areas with deep water depth and high environmental protection requirements.
Effectively control the displacement of temporary cofferdams, reduce the impact on surrounding buildings, and reduce the cost of engineering. It is suitable for small sites and water platforms construction, and has both construction platforms and temporary flood prevention functions to meet high-demand conditions.
Smart Images

Figure CN110685290B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of cofferdam engineering, dock engineering and flood control wall, in particular to a cofferdam combining permanent structure pile foundation and temporary steel sheet pile and a construction method thereof, which is suitable for simultaneously constructing flood control wall and dock engineering. Background Art
[0002] At present, the cofferdams in dock and flood control wall projects are mainly earth cofferdams and steel sheet pile cofferdams. For environments with deep water and poor construction conditions, earth cofferdams are expensive and have a great impact on the surrounding environment and buildings. At the same time, in recent years, the standards of flood control wall projects have been further improved, and the retaining height has been continuously increased. Ordinary steel sheet pile structures can no longer meet the requirements of displacement control. Especially when the dock project and the flood control wall project are built at the same time, due to professional and coordination reasons, the two are always built separately, wasting a lot of manpower and material resources, and there is neither a good construction platform nor good temporary flood control measures.
[0003] With the improvement of people's environmental awareness and the requirement to reduce cost, there is a need for temporary cofferdams that can be used in deep water areas, which can serve as both a construction platform and a temporary flood control structure. Summary of the invention
[0004] The purpose of the present invention is to design a cofferdam combining a permanent structure pile foundation and a temporary steel sheet pile in view of the shortcomings of the prior art. The permanent structure pile foundation and the temporary steel sheet pile are integrally connected, so as to better control the displacement of the temporary cofferdam, have little impact on the existing buildings in the surrounding area, reasonably utilize the permanent structure pile foundation, and reduce the project cost. The present invention is suitable for an environment where the rear site is small and only a water platform can be used for construction; it is also suitable for conditions with deep water and high requirements for the cofferdam; it is especially suitable for the construction of a front open-type structure and a rear water-stop structure (such as a dock and a flood control wall, etc.) in areas with high environmental protection requirements and limited construction sites.
[0005] The object of the present invention is achieved in this way: a cofferdam combining a permanent structure pile foundation and a temporary steel sheet pile comprises a double row of steel sheet piles consisting of temporary steel sheet piles and permanent steel sheet piles, and a permanent structure pile foundation, characterized in that a connecting beam is arranged between the double rows of steel sheet piles, and the double rows of steel sheet piles, the connecting beam therebetween and the backfill constitute a water-stop curtain; steel cross beams, steel longitudinal beams and horizontal shear braces are installed on the upper part of the permanent structure pile foundation, and the permanent structure pile foundation and its upper steel cross beams, steel longitudinal beams and horizontal shear braces constitute a supporting structure, which also serves as a temporary construction steel platform; steel purlins are welded between the steel platform and the double rows of steel sheet piles to form a temporary cofferdam.
[0006] Furthermore, the steel perimeter purlin is welded between the steel cross beam and the front row of steel sheet piles.
[0007] Furthermore, the pile tips of the double-row steel sheet piles are driven into a dense sand layer with low permeability and a standard penetration of more than 50 blows.
[0008] Furthermore, the temporary steel sheet piles are the front row steel sheet piles, the permanent steel sheet piles are the rear row steel sheet piles, and the temporary steel sheet piles are not lower than the elevation of the permanent steel sheet piles.
[0009] The distance between permanent steel sheet piles and temporary steel sheet piles is determined by the required stiffness. Taking into account factors such as pile pulling, the distance between permanent steel sheet piles and temporary steel sheet piles should not be less than 1.5 meters. The design elevation of permanent steel sheet piles is determined by the requirements of shore structures; if there is no special purpose, the design elevation of temporary steel sheet piles can be consistent with the design elevation of permanent steel sheet piles; if there are other uses, such as temporary flood control walls, they must meet temporary flood control requirements.
[0010] Furthermore, a cofferdam construction method combining a permanent structure pile foundation with a temporary steel sheet pile is provided, characterized in that the method comprises the following steps:
[0011] (1) Double-row steel sheet pile construction: permanent steel sheet piles and temporary steel sheet piles are driven in staggered rows. The double-row steel sheet piles are connected by connecting beams, and backfill soil between the double-row steel sheet piles to form a temporary water-stop curtain;
[0012] (2) Permanent pile foundation construction: piles shall be driven to the designed elevation according to the requirements of permanent structure pile foundation;
[0013] (3) Steel platform construction: steel cross beams, steel longitudinal beams and horizontal shear braces are installed on the top of the permanent pile foundation to form a temporary steel platform, forming a supporting structure that also serves as a temporary construction steel platform;
[0014] (4) Steel purlin construction: weld the steel purlin between the steel platform and the double rows of steel sheet piles, so that the steel platform and the steel sheet piles form a reliable connection to form a temporary cofferdam;
[0015] (5) Dismantle the temporary cofferdam. After the cofferdam is formed, cast the structure behind the cofferdam and backfill the site; then dismantle the temporary steel sheet piles, connecting beams, steel cross beams, steel longitudinal beams, horizontal shear braces and steel purlins in the double row of steel sheet piles; finally, construct the permanent structure.
[0016] Compared with the prior art, the present invention can better control the displacement of temporary cofferdams, has little impact on existing buildings in the surrounding area, reasonably utilizes permanent structure pile foundations, and reduces project costs; it is suitable for environments where the rear site is small and only water platforms can be used for construction; it is also suitable for conditions with deep water and high requirements for cofferdams; it is especially suitable for areas with high environmental protection requirements and limited construction sites to build front open structures and rear water-stopping structures (such as docks and flood control walls, etc.). BRIEF DESCRIPTION OF THE DRAWINGS
[0017] Figure 1It is a schematic diagram of the structure of the present invention. DETAILED DESCRIPTION
[0018] The present invention is described in detail below based on the accompanying drawings and specific embodiments of the present invention.
[0019] See attached Figure 1 The present invention includes permanent steel sheet piles 1 and temporary steel sheet piles 2, as well as a connecting beam 3 connecting two rows of steel sheet piles and a fill 4 between the two rows of steel sheet piles to form a water-stop curtain; the permanent open structure pile foundation 5 and its upper steel cross beam 6, steel longitudinal beam 7 and horizontal shear brace 8 constitute a temporary steel platform and supporting structure, and can also serve as a temporary construction steel platform; the steel purlin 9 connects the steel platform with the double-layer steel sheet piles to form a temporary cofferdam as a whole.
[0020] A cofferdam construction method combining permanent structural pile foundation and temporary steel sheet piles, characterized in that the double-row steel sheet pile structure also serves as a temporary flood control wall during the construction period, and the steel platform structure also serves as a construction platform. The method comprises the following steps:
[0021] (1) Double-row steel sheet pile construction
[0022] Permanent steel sheet piles 1 and temporary steel sheet piles 2 are driven in staggered rows, with the pile tips driven into a dense sand layer with low permeability and a standard penetration rating of more than 50 blows or a depth where the seepage diameter meets the requirements; the double rows of steel sheet piles are connected by a connecting beam 3 to form a temporary water-stop curtain, and backfill soil 4 in the middle.
[0023] (2) Permanent pile foundation construction
[0024] Inject the piles to the designed elevation according to the requirements of permanent structure pile foundation 5.
[0025] (3) Steel platform construction
[0026] A steel cross beam 6, a steel longitudinal beam 7 and a horizontal shear brace 8 are installed on the upper part of the permanent pile foundation to form a temporary steel platform, forming a supporting structure and serving as a temporary construction steel platform.
[0027] (4) Steel purlin construction
[0028] Steel purlins 9 are welded between the steel platform and the double-row steel sheet piles, so that the steel platform and the steel sheet piles are reliably connected to form a temporary cofferdam.
[0029] (5) Removal of temporary cofferdam
[0030] After the cofferdam is formed, the structure behind the cofferdam is poured and the site is backfilled; then the temporary steel sheet piles 2, the connecting beams 3, the steel cross beams 6, the steel longitudinal beams 7 and the horizontal shear braces 8 and the steel perimeter purlins 9 in the double-row steel sheet piles are removed; finally, the permanent structure is constructed.
[0031] Although the content of the present invention has been described in detail through the above preferred embodiments, it should be appreciated that the above description should not be considered as a limitation of the present invention. After reading the above content, it will be apparent to those skilled in the art that various modifications and substitutions of the present invention will occur. Therefore, the protection scope of the present invention should be limited by the appended claims.
Claims
1. A cofferdam combining a permanent structure pile foundation and a temporary steel sheet pile, comprising a double row of steel sheet piles consisting of temporary steel sheet piles and permanent steel sheet piles, and a permanent structure pile foundation, characterized in that A connecting beam is arranged between the double rows of steel sheet piles, and the double rows of steel sheet piles, the connecting beam therebetween and the backfill constitute a water-stop curtain, wherein the temporary steel sheet piles are the front row of steel sheet piles, and the permanent steel sheet piles are the rear row of steel sheet piles, and the temporary steel sheet piles are not lower than the elevation of the permanent steel sheet piles; steel cross beams, steel longitudinal beams and horizontal shear braces are installed on the upper part of the pile foundation of the permanent structure, and the pile foundation of the permanent structure and the steel cross beams, steel longitudinal beams and horizontal shear braces on the upper part constitute a supporting structure, which also serves as a temporary construction steel platform; steel perimeter purlins are welded between the steel platform and the double rows of steel sheet piles to form a temporary cofferdam, and the steel perimeter purlins are welded between the steel cross beams and the front row of steel sheet piles.
2. A cofferdam combining a permanent structure pile foundation and a temporary steel sheet pile as claimed in claim 1, characterized in that The pile tips of the double-row steel sheet piles are driven into a dense sand layer with low permeability and a standard penetration of more than 50 blows.
3. A cofferdam construction method combining permanent structural pile foundation and temporary steel sheet pile, characterized in that The method comprises the following steps: (1) constructing double-row steel sheet piles, driving permanent steel sheet piles and temporary steel sheet piles in staggered rows, connecting the double-row steel sheet piles with connecting beams, and backfilling soil between the double-row steel sheet piles so that the double-row steel sheet piles form a temporary water-stop curtain; (2) Permanent pile foundation construction: piles shall be driven to the designed elevation according to the requirements of permanent structure pile foundation; (3) Steel platform construction: steel cross beams, steel longitudinal beams and horizontal shear braces are installed on the top of the permanent pile foundation to form a temporary steel platform, forming a supporting structure that also serves as a temporary construction steel platform; (4) Steel purlin construction: weld the steel purlin between the steel platform and the double rows of steel sheet piles, so that the steel platform and the steel sheet piles form a reliable connection to form a temporary cofferdam; (5) Dismantle the temporary cofferdam. After the cofferdam is formed, cast the structure behind the cofferdam and backfill the site; then dismantle the temporary steel sheet piles, connecting beams, steel cross beams, steel longitudinal beams, horizontal shear braces and steel purlins in the double row of steel sheet piles; finally, construct the permanent structure.
Citation Information
Patent Citations
Construction method of large tube well fixed point precipitation, sealing bottom free concrete and steel sheet pile cofferdam deepwater bearing platform
CN102877420A
Deep mucky riverbed pipe gallery river crossing dual-steel-plate pile cofferdam structure and construction method
CN107299630A
Double-rowed cofferdam and method for manufacturing the same
CN1837511A
Composite batardeau of steel light structure
CN201132960Y
Novel cofferdam in super thick soft foundation
CN204551500U