A tube blowing device
By designing the conical sleeve and nozzle structure, the problem of poor airtightness between the purge device and the copper pipe is solved, and adaptability and efficient cleaning of copper pipes of different diameters is achieved, reducing noise and operation complexity.
Patent Information
- Application Number
- CN202010037725.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-01-14
- Publication Date
- 2024-11-22
- Estimated Expiration
- 2040-01-14
AI Technical Summary
During the rolling process of existing copper pipes, the air tightness between the purge device and the copper pipe is poor, resulting in high-pressure air leakage, high noise and low cleaning efficiency. It is insufficient adaptability to copper pipes of different diameters, so the purge head needs to be replaced frequently. .
A pipe rolling purging device including a conical sleeve and a nozzle is designed. The outer side of the conical sleeve is conical, the inner diameter of the sleeve is larger than the inner diameter of the vent hole, and there are multiple vent holes and grooves at the front end of the nozzle, and the conical sleeve is placed in high-pressure gas. The lower part is locked at the break of the copper pipe to improve air tightness and improve the airflow state through the pipeline fixing device and elastic flow diversion ring.
It improves the adaptability to copper tubes of different inner diameters, reduces the step of replacing the purge head, enhances airtightness and working efficiency, reduces noise, and ensures the effective use of high-pressure gas.
Smart Images

Figure CN111069310B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of copper tube processing, in particular to a tube rolling and blowing device. Background Art
[0002] When copper tubes are rolled using the three-roll rolling technology, water needs to be added for cooling, and water stains often remain on the inner wall of the copper tube. If the water stains are not cleaned, it is easy to cause the copper tube to break or be scratched in the subsequent production process.
[0003] At present, high-pressure gas flushing is generally used to clean water stains on the inner wall of copper tubes. The existing purge head and copper tube have poor air tightness, and high-pressure air is easy to leak from the gap between the copper tube and the purge head, resulting in waste of air compressor efficiency and poor uniformity of air flow in the copper tube. To meet the cleaning standard, the air pressure of the air compressor must be increased. When high-pressure air leaks, high-decibel noise will be generated, which will interfere with the operator. For copper tubes of different diameters, it is necessary to replace purge heads of different sizes, which increases the process. Summary of the invention
[0004] Aiming at the problems of poor air tightness between the purge device and the copper tube and poor adaptability to copper tubes with different radii in the prior art solutions, the present invention provides a tube rolling purge device.
[0005] The present invention provides the following technical solutions: a pipe rolling purging device, comprising a spray gun and a conical sleeve, wherein a vent hole is arranged inside the conical sleeve, a sleeve is arranged at the rear end of the conical sleeve, and the inner diameter of the sleeve is greater than the inner diameter of the vent hole; the spray gun comprises a nozzle, the outer wall of the front end of the nozzle is interference fit with the inner wall of the sleeve, a groove is arranged inside the rear end of the nozzle, a plurality of jet holes are evenly arranged at the front end of the nozzle and are connected to the groove, a hollow air inlet head is connected to the inner wall of the groove, and an air inlet pipe is connected to the rear end of the air inlet head; a limiting convex ring is arranged on the outer side of the rear end of the nozzle.
[0006] By adopting the above technical solution, a conical sleeve is added to the front end of the nozzle, and the outer side of the conical sleeve is a cone with a small front and a large back, and its maximum diameter can be larger than the maximum inner diameter of the copper tube, so that the fracture of copper tubes with different inner diameters has a contact surface with the surface of the conical sleeve; a vent is provided inside the conical sleeve, and high-pressure gas is sprayed into the copper tube from the vent for purging. The inner diameter of the sleeve of the conical sleeve is larger than the inner diameter of the vent, so that the inner diameters of the conical sleeve and the sleeve form a step-like change, and the bottom surface of the conical sleeve is perpendicular to the flow direction of the airflow. The high-pressure gas is sprayed from the jet hole of the nozzle to the bottom surface of the conical sleeve, giving the conical sleeve a forward extrusion force, pushing the conical sleeve against the fracture of the copper tube, and the conical sleeve deforms on the contact surface with the fracture of the copper tube, filling and closing the gap, and improving the air tightness; when cleaning, the conical sleeve can be self-locked at the fracture of the copper tube under the pressure of the high-pressure gas. The front end of the nozzle is evenly provided with a plurality of air injection holes, so that the bottom surface of the conical sleeve is subjected to even extrusion force.
[0007] Preferably, the sum of the width of the sleeve and the width of the limiting protrusion is greater than the width S of the nozzle.
[0008] By adopting the above technical solution, the bottom surface of the conical sleeve is prevented from directly contacting the nozzle, and a cavity for high-pressure gas to pass through is formed between the conical sleeve and the nozzle.
[0009] Preferably, the distance between the air injection hole and the center line of the nozzle is greater than the radius of the vent hole.
[0010] By adopting the above technical solution, the pressure generated when the high-pressure gas is ejected from the jet hole can all directly act on the bottom surface of the conical sleeve, preventing the pressure from being lost and thus reducing the air tightness.
[0011] Preferably, the multiple air injection holes have the same radius, and the sum of their cross-sectional areas is greater than the cross-sectional area of the vent hole of the tapered sleeve.
[0012] By adopting the above technical solution, the radii of the multiple jet holes are the same, and the gas flow and pressure through each jet hole are similar; the cross-sectional area of the multiple jet holes is larger than that of the vent hole, which can generate a continuous pressure difference in the cavity surrounded by the conical sleeve, the sleeve and the nozzle, further improving the air tightness.
[0013] Preferably, a plurality of concave rings are provided on the outer wall of the front end of the nozzle, and a sealing ring is provided inside the concave rings.
[0014] By adopting the above technical solution, the air tightness between the sleeve and the nozzle is improved, and the gas pressure is prevented from being lost from the gap between the sleeve and the nozzle.
[0015] Preferably, a pipe fixing device is also provided on the outer wall of the limiting convex ring, and the pipe fixing device includes a hollow connecting sleeve and a fixing sleeve; the connecting sleeve is fixedly connected to the limiting convex ring; the fixing sleeve includes a ring, and a plurality of connecting rods are connected between the ring and the connecting sleeve, a mounting hole is provided at the top of the ring, a limiting tube is provided on the mounting hole, a screw is threadedly connected to the inner wall of the limiting tube, a handle is provided on the top of the screw, and a buffer pad is provided at the bottom of the screw.
[0016] By adopting the above technical solution, the pipeline fixing device can preliminarily connect and fix the purge device and the copper pipe.
[0017] Preferably, the inner wall of the collar is provided with an anti-slip layer.
[0018] By adopting the above technical solution, the anti-slip layer can increase the friction between the pipeline fixture and the copper pipe, increase the stability of the structure and prevent the pipeline fixture from scratching the surface of the copper pipe when it is pressed tightly.
[0019] Preferably, the front end opening of the vent hole is in an inverted cone shape.
[0020] By adopting the above technical solution, the front end opening of the vent hole is an open inverted cone, which increases the injection angle of the high-pressure gas.
[0021] Preferably, an elastic guide ring is further provided on the inner wall of one end of the sleeve close to the conical sleeve; and a guide cone is provided at the front end of the nozzle.
[0022] By adopting the above technical solution, after the gas pressure increases to a certain level, the elastic guide ring is squeezed and deformed by the dynamic pressure of the gas, and its center gradually deviates toward the vent to form an arc-shaped guide surface. Through the joint action with the guide cone, turbulence is reduced, the internal gas flow state is improved, and a part of the dynamic pressure is retained in the high-pressure gas, thereby reducing pressure loss.
[0023] The beneficial effects of the present invention are: 1. The outer side surface of the conical sleeve is conical, which can adapt to copper tubes with different inner diameters within a certain range, thereby improving the application scope of the present invention, reducing the steps of replacing the purge head, and simplifying the process; 2. The high-pressure gas can not only clean the copper tube, but also generate an extrusion force on the conical sleeve, so that the conical sleeve is self-locked at the fracture of the copper tube, solving the problems of poor air tightness between the conical sleeve and the fracture of the copper tube and high noise during cleaning; 3. The extrusion force is generated by the pipeline fixing device and the high-pressure gas, so that the present invention and the copper tube can be stably connected during the cleaning process, freeing the operator's hands and improving work efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 The figure is a schematic diagram of three-dimensional decomposition of an embodiment of the present invention.
[0025] Figure 2 A three-dimensional schematic diagram of an embodiment of the present invention.
[0026] Figure 3 A cross-sectional view of an embodiment of the present invention.
[0027] Figure 4 It is a front view of an embodiment of the spray head of the present invention.
[0028] Figure 5 It is a three-dimensional schematic diagram of an embodiment of the pipeline fixing device of the present invention.
[0029] Figure 6 It is a side view of an embodiment of the pipeline fixing device of the present invention.
[0030] Figure 7 for Figure 6 AA cross-section diagram.
[0031] Figure 8 It is a cross-sectional view of another embodiment of the present invention.
[0032] Fig. 9 It is a schematic diagram of an embodiment of the elastic guide ring of the present invention.
[0033] Figure markings: 1-spray gun, 11-spray head, 111-groove, 112-jet hole, 113-limiting convex ring, 114-sealing ring, 12-inlet head, 13-inlet pipe, 2-conical sleeve, 21-vent, 22-sleeve, 3-pipe fixing device, 31-connecting sleeve, 32-fixing sleeve, 321-ring, 322-limiting tube, 323-screw, 324-handle, 325-buffer pad, 33-connecting rod, 4-elastic guide ring, 5-guide cone. DETAILED DESCRIPTION
[0034] The following is a more detailed description of the embodiments of the present invention in conjunction with the accompanying drawings and the accompanying drawings so that a person skilled in the art can implement the embodiments after reading the description. It should be understood that the specific embodiments described herein are only used to explain the present invention and are not used to limit the present invention.
[0035] The present invention provides a Figure 1 and Figure 2A pipe rolling purging device shown in the figure comprises a spray gun 1 and a conical sleeve 2, wherein an air vent 21 is arranged inside the conical sleeve 2, and a sleeve 22 is arranged at the rear end of the conical sleeve 2, and the inner diameter of the sleeve 22 is larger than the inner diameter of the air vent 21; the spray gun 1 comprises a nozzle 11, and the outer wall of the front end of the nozzle 11 is interference fit with the inner wall of the sleeve 22, and a groove 111 is arranged inside the rear end of the nozzle 11, and a plurality of jet holes 112 are evenly arranged at the front end of the nozzle 11 and are connected to the groove 111, and a hollow air inlet head 12 is connected to the inner wall of the groove 111, and an air inlet pipe 13 is connected to the rear end of the air inlet head 12; a limiting convex ring 113 is arranged on the outer side of the rear end of the nozzle 11.
[0036] The spray gun can be made of stainless steel; the spray head and the air inlet head can be connected by thread or by welding; the air inlet head and the air inlet pipe can be connected by welding; the air inlet pipe can be connected to the air outlet pipe of the air compressor. Figure 3 As shown, the high-pressure gas enters the nozzle from the air inlet pipe and is then ejected through a plurality of jet holes at the front end of the nozzle.
[0037] The conical sleeve can be made of copolymerized polyhexamethylene adipamide, which has high mechanical strength, certain elasticity and deformation. Its outer side is a cone with a small front and a large back, and the minimum diameter is smaller than the minimum inner diameter of the copper tube to be cleaned, so that the conical sleeve can be inserted into the copper tube for cleaning; the maximum diameter is larger than the maximum inner diameter of the copper tube to be cleaned, so that the fracture of copper tubes with different inner diameters has a contact surface with the surface of the conical sleeve.
[0038] The inner diameter of the sleeve is larger than the inner diameter of the vent hole, so that the inner wall of the conical sleeve and the sleeve changes in a step-like manner, such as Figure 3 As shown in the figure, the step-shaped change is the bottom surface of the conical sleeve. The bottom surface of the conical sleeve is perpendicular to the airflow direction from the air jet hole. The high-pressure airflow directly impacts the bottom surface of the conical sleeve, giving the conical sleeve a forward dynamic pressure P, pushing the conical sleeve against the fracture of the copper tube. The conical sleeve deforms on the contact surface with the copper tube fracture, filling and closing the gap between the two, improving the air tightness. At this time, the contact pressure Pm acting on the contact surface can be expressed as:
[0039] Pm=Po+Pp
[0040] Where Po is the initial contact pressure between the conical sleeve and the copper tube, which can be 0; Pp is the contact pressure transmitted from the conical sleeve to the copper tube after the high-pressure gas is introduced, which can be expressed as:
[0041] Pp=K·P
[0042] In the formula, K is the side pressure coefficient, which is a constant for fixed materials; P is the dynamic pressure transmitted to the tapered sleeve by the high-pressure gas.
[0043] As long as the high-pressure gas maintains the dynamic pressure P on the tapered sleeve, the tapered sleeve can self-lock at the fracture of the copper tube and maintain sufficient airtightness.
[0044] The high-pressure gas finally sprays out from the vent holes of the tapered tube and cleans the water stains on the inner wall of the copper tube.
[0045] The sleeve and the front end of the nozzle are interference fit, and the interference should not be too high, preferably 1-2 mm, which can not only ensure the tightness of the structure, but also provide a certain airtightness to prevent the gas from losing pressure. The limiting convex ring can resist the sleeve to play a limiting role. In a preferred embodiment, the inner diameter of the sleeve can be selected to be 56 mm, and the diameter of the front end of the nozzle can be 57 mm.
[0046] Preferably, the sum of the width of the sleeve 22 and the width of the limiting convex ring 113 is greater than the width of the nozzle 11 .
[0047] like Figure 3 As shown, the width of the sleeve is L1, and the width of the limiting convex ring is L2, and the sum of the two is greater than the width S of the nozzle 11. A cavity should be reserved between the conical sleeve, the sleeve and the nozzle so that the high-pressure gas flow can pass quickly. The width of this cavity should not be too large, otherwise the gas pressure will drop quickly and the conical sleeve will not be able to provide sufficient dynamic pressure P. In a preferred embodiment, the width can be selected to be 15~20mm.
[0048] Preferably, the distance between the air injection hole 112 and the center line of the nozzle 11 is greater than the radius of the vent hole 21 .
[0049] like Figure 3 As shown, the distance between the jet hole 112 and the center line of the nozzle 11 is R1, and the radius of the vent hole 21 is R. The high-pressure gas ejected from the jet hole should be fully transferred to the bottom surface of the conical sleeve. If the distance R1 between the jet hole and the center line of the nozzle is less than the radius R of the vent hole, a part of the high-pressure gas will be ejected directly from the vent hole, causing the dynamic pressure P to be lost.
[0050] In this preferred embodiment, the inner diameter of the sleeve can be selected to be 56 mm, the radius of the vent hole can be selected to be 11 mm, and after calculation, the radius of the jet hole can be 5 mm, and the distance from the jet hole to the center line of the nozzle can be 14 mm.
[0051] Preferably, the multiple air injection holes 112 have the same radius, and the sum of their cross-sectional areas is greater than the area of the vent hole 21 of the conical sleeve 2 .
[0052] The radii of the multiple jet holes are the same, and the gas flow and dynamic pressure through each jet hole are similar, so that the conical sleeve is evenly stressed, vibration is avoided, and the structural stability is ensured. The cross-sectional area of the multiple jet holes is larger than that of the vent hole. When the flow rate provided by the air compressor is constant, the gas flow rate in the vent hole will inevitably increase, and the static pressure will decrease accordingly. Compared with the static pressure of the gas in the cavity surrounded by the conical sleeve, the sleeve and the nozzle, a static pressure difference is formed, which further stabilizes the overall structure.
[0053] In this preferred embodiment, the radius of the vent hole can be selected to be 11 mm, the radius of the air jet hole can be selected to be 5 mm, and the ratio of the cross-sectional areas of the two is 4.84, so the number of the air jet holes is selected to be at least 5.
[0054] Preferably, a plurality of concave rings are further provided on the outer wall of the front end of the nozzle 11, and a sealing ring 114 is provided in the concave rings.
[0055] The sealing ring can be an O-type sealing ring made of hydrogenated nitrile rubber, fixed in the concave ring, to further increase the air tightness between the sleeve and the nozzle. In this preferred embodiment, the front end radius of the nozzle can be 57mm, the depth of the concave ring is 2mm, the diameter of the sealing ring is 56mm, and the cross-sectional diameter of the sealing ring can be 2.5mm.
[0056] like Figure 5 and Figure 6 As shown, a pipe fixing device 3 is also provided on the outer wall of the limiting convex ring 113, and the pipe fixing device 3 includes a hollow connecting sleeve 31 and a fixing sleeve 32; the connecting sleeve 31 is fixedly connected to the limiting convex ring 113; the fixing sleeve 32 includes a collar 321, and a plurality of connecting rods 33 are connected between the collar 321 and the connecting sleeve 31, and a mounting hole is provided at the top of the collar 321, and a limiting tube 322 is provided on the mounting hole, and a screw 323 is threadedly connected to the inner wall of the limiting tube 322, a handle 324 is provided on the top of the screw 323, and a buffer pad 325 is provided at the bottom of the screw 323.
[0057] The pipe fixing device can be made of stainless steel or cast iron. The connecting sleeve can be welded on the limiting convex ring of the nozzle, and its inner diameter is not less than the outer diameter of the limiting convex ring. The connecting rod and the connecting sleeve and the fixing sleeve can also be connected by welding. The cross-sectional structure of the fixing sleeve is as follows: Figure 7 As shown, the inner diameter of the collar is not less than the maximum outer diameter of the copper pipe to be cleaned. When fixing, the copper pipe is inserted into the collar and pressed against the conical sleeve, and then the screw and the buffer pad are pressed against the copper pipe by rotating the handle. The buffer pad can be made of EVA ethylene-vinyl acetate copolymer, which has good buffering and shock resistance.
[0058] like Figure 7 As shown, the inner wall of the collar 321 is provided with an anti-slip layer.
[0059] The anti-slip layer can be made of EVA ethylene-vinyl acetate copolymer, which has good buffering and shock resistance and can protect the surface of the copper tube from damage when pressed.
[0060] like Figure 8 As shown, the front end opening of the vent hole 21 is in an inverted cone shape.
[0061] In another preferred embodiment, the front end of the vent hole is an open inverted cone, which utilizes the wall attachment principle to increase the injection angle of the high-pressure gas, reduce the negative pressure generated when the high-pressure gas is ejected from the vent hole opening, reduce the generation of turbulence, and thus reduce the pressure loss of the high-pressure gas when passing through the vent hole. The side of the inverted cone can be a linear cone or a smooth arc.
[0062] like Fig. 9 As shown, an elastic guide ring 4 is further provided on the inner wall of one end of the sleeve 22 close to the conical sleeve 2; and a guide cone 5 is provided at the front end of the nozzle 11.
[0063] The air pressure required for cleaning is different according to the length and inner diameter of the copper tube to be cleaned. Generally, the longer the length of the copper tube to be cleaned and the larger the inner diameter, the greater the required cleaning air pressure. However, for the conical sleeve, it is sufficient to maintain a certain dynamic pressure. If the dynamic pressure is too large, it will exceed the deformation limit of the conical sleeve, which is easy to damage the conical sleeve. In view of this situation, in another preferred embodiment, an elastic guide ring is provided on the inner wall of the sleeve, and its cross section is a pair of L-shaped symmetrical about the center line of the sleeve. The short end of the L-shaped ring is close to the sleeve and the conical sleeve, and the dynamic pressure can be transmitted to the conical sleeve; its long end is deformed after the dynamic pressure reaches a certain limit, gradually deviating to the vent hole, forming an arc-shaped guide surface, and the combined effect of the guide cone set at the front end of the nozzle reduces turbulence, improves the internal gas flow state, and retains part of the dynamic pressure in the high-pressure gas, which also reduces the pressure loss of the high-pressure gas and improves the purging efficiency. Due to its elasticity, it has good adaptability to air pressures of different intensities. The elastic guide ring can be made of rubber or polyamide, and the thickness of its long end affects its elastic limit; the guide cone can be a cone with a concave side made of stainless steel.
[0064] The above is an embodiment of the present invention, and its description is relatively specific and detailed, but it cannot be understood as limiting the scope of the patent of the present invention. It should be pointed out that for ordinary technicians in this field, several modifications and improvements can be made without departing from the concept of the present invention, which all belong to the protection scope of the present invention. Therefore, the protection scope of the patent of the present invention shall be based on the attached claims.
Claims
1. A pipe purging device, comprising a spray gun (1) and a conical sleeve (2), wherein the conical sleeve (2) is provided with a vent hole (21) inside, and a sleeve (22) is provided at the rear end of the conical sleeve (2), wherein the inner diameter of the sleeve (22) is larger than the inner diameter of the vent hole (21), and the spray gun (1) comprises a nozzle (11), characterized in that: The outer wall of the front end of the nozzle (11) is interference-fitted with the inner wall of the sleeve (22); a groove (111) is provided inside the rear end of the nozzle (11); a plurality of jet holes (112) are evenly provided at the front end of the nozzle (11) and are in communication with the groove (111); a hollow air intake head (12) is connected to the inner wall of the groove (111); and an air intake pipe (13) is connected to the rear end of the air intake head (12); a limiting convex ring (113) is provided on the outer side of the rear end of the nozzle (11); An elastic guide ring (4) is also provided on the inner wall of one end of the sleeve (22) close to the conical sleeve (2); the cross section of the elastic guide ring (4) is a pair of L-shaped shapes symmetrical about the center line of the sleeve (22); the short end of the L-shaped ring is tightly attached to the sleeve (22) and the conical sleeve (2), and the dynamic pressure can be transmitted to the conical sleeve (2); the front end of the nozzle (11) is provided with a guide cone (5); the guide cone (5) is a stainless steel cone with a concave side surface; The L-shaped long end of the elastic guide ring (4) deforms when the dynamic pressure reaches a certain limit, gradually deviating toward the vent hole (21) to form an arc-shaped guide surface, and the guide cone (5) provided at the front end of the nozzle (11) acts together to reduce turbulence.
2. A tube blowing device according to claim 1, characterized in that: The sum of the width of the sleeve (22) and the width of the limiting convex ring (113) is greater than the width of the nozzle (11).
3. A pipe rolling and blowing device according to claim 2, characterized in that: The distance between the jet hole (112) and the center line of the nozzle (11) is greater than the radius of the vent hole (21).
4. A tube rolling and blowing device according to claim 3, characterized in that: The multiple air injection holes (112) have the same radius, and the sum of their cross-sectional areas is greater than the area of the vent hole (21) of the conical sleeve (2).
5. A tube-rolling purging device according to claim 4, characterized in that: A plurality of concave rings are also provided on the outer wall of the front end of the nozzle (11), and a sealing ring (114) is provided inside the concave rings.
6. A tube-rolling purging device according to claim 5, characterized in that: A pipeline fixing device (3) is also provided on the outer wall of the limiting convex ring (113), and the pipeline fixing device (3) comprises a hollow connecting sleeve (31) and a fixing sleeve (32); the connecting sleeve (31) is fixedly connected to the limiting convex ring (113); the fixing sleeve (32) comprises a collar (321), a plurality of connecting rods (33) are connected between the collar (321) and the connecting sleeve (31), a mounting hole is provided at the top of the collar (321), a limiting tube (322) is provided on the mounting hole, a screw rod (323) is threadedly connected to the inner wall of the limiting tube (322), a handle (324) is provided at the top of the screw rod (323), and a buffer pad (325) is provided at the bottom of the screw rod (323).
7. A tube-rolling purging device according to claim 6, characterized in that: The inner wall of the collar (321) is provided with an anti-slip layer.