Construction method and structure of water-stop steel plate for post-casting belt construction joint
The use of on-site steel waste to form L-shaped steel bars at a 45° angle and a closing mesh with ribs addresses welding inconsistencies in waterstop steel plates, enhancing installation and reducing leakage and material waste, thus improving construction quality and cost-effectiveness.
Patent Information
- Application Number
- CN202010118465.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-02-26
- Publication Date
- 2024-12-03
- Estimated Expiration
- 2040-02-26
AI Technical Summary
Existing waterstop steel plates in construction joints face issues with inconsistent welding quality, leading to leakage and material waste, compromising project quality and increasing costs.
A construction method and structure that utilizes on-site steel waste to create L-shaped steel bars welded at a 45° angle and incorporates a closing mesh fixed with ribs, enhancing the installation process and reducing leakage risks.
Improves construction quality and efficiency while saving materials and reducing costs by ensuring secure installation and minimizing secondary reworks.
Smart Images

Figure CN111173044B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a construction method and structure of a water-stop steel plate for a post-cast belt construction joint, belonging to the technical field of building foundation construction. Background Art
[0002] During the construction of the basement structure, waterstop steel plates are usually used as a waterproofing method for the construction joints and post-cast strips of the foundation slab, basement roof, fire water tank and other parts. The waterproofing technology of waterstop steel plates is mature and has a good water-stopping effect. The existing technology for installing waterstop steel plates is to use a short vertical steel bar to directly spot weld it vertically on the waterstop steel plate, but the welding quality is often difficult to control, and it is easy to weld through the waterstop steel plate, resulting in leakage problems in the later stage, and the quality of the project cannot be guaranteed. The existing waterstop steel plates have quality risks during installation, so the existing technology still has shortcomings and needs to be further improved. Summary of the invention
[0003] The purpose of the present invention is to provide a construction method and structure for a water-stop steel plate for a post-cast strip construction joint, so as to utilize steel waste at the construction site as a fixing material, and the method is simple to manufacture and firmly installed. The method can be applicable to the construction of a water-stop steel plate for a post-cast strip construction joint in parts such as foundation slabs, basement top slabs, and fire water tanks, thereby improving the construction quality and efficiency of the water-stop steel plate, and effectively saving construction materials, reducing construction costs, and overcoming the shortcomings of the prior art.
[0004] To achieve the above object, the present invention adopts the following technical solution:
[0005] A construction method of a post-casting belt construction joint water-stop steel plate of the present invention is constructed according to the following steps:
[0006] a. Lay and tie two layers of bottom steel mesh on the foundation cushion or formwork;
[0007] b. Make water-stop steel plate;
[0008] c. Weld the top of the supporting steel bar to both sides of the water-stop steel plate, support the bottom of the supporting steel bar on the foundation cushion or the top surface of the formwork, and weld the supporting steel bar to the bottom steel mesh;
[0009] d. Weld the horizontal section of the L-shaped steel bar at an angle of 45° to the top surface of the waterstop steel plate;
[0010] e. Fix the closing mesh on the L-shaped steel bar through the closing mesh fixing ribs;
[0011] f. Tie up the reinforcement bars and pour the concrete, and then complete the construction of the water-stop steel plate at the construction joint of the post-cast strip.
[0012] In the construction method of the waterstop steel plate for the construction joint of the above-mentioned post-cast strip, obtuse-angled folded edges are provided on both sides of the waterstop steel plate, and the top of the supporting steel bar is welded to the obtuse-angled folded edges on both sides of the waterstop steel plate.
[0013] In the above-mentioned construction method of water-stop steel plate for construction joint of post-cast strip, the L-shaped steel bar is divided into horizontal section and vertical section at the 90° bend; the angle between the horizontal section and the center line of the water-stop steel plate is 45°, and it is welded to the top surface of the water-stop steel plate.
[0014] In the construction method of the water-stop steel plate for the construction joint of the aforementioned post-cast zone, the closing mesh is located between the closing mesh fixing ribs and the vertical section of the L-shaped steel bar; and is fixed by welding the closing mesh fixing ribs and the vertical section of the L-shaped steel bar.
[0015] The structure of a waterstop steel plate for a construction joint of a post-cast strip constructed according to the above-mentioned construction method of the waterstop steel plate for the construction joint of the post-cast strip of the present invention is that the structure includes a foundation cushion layer or a formwork; two layers of bottom steel mesh are provided on the foundation cushion layer or the formwork, and a pair of parallel waterstop steel plates are provided on the top of the two layers of bottom steel mesh; a group of supporting steel bars are welded on both sides of each waterstop steel plate; the bottom end of the supporting steel bar is supported on the top surface of the foundation cushion layer or the formwork, and the middle part of the supporting steel bar is welded to the bottom steel mesh; the top surface of the waterstop steel plate is welded to the horizontal section of the L-shaped steel bar, and the vertical section of the L-shaped steel bar is perpendicular to the top surface of the waterstop steel plate; a closing net is provided on one side of the vertical section of the L-shaped steel bar, and the closing net is fixedly connected to the vertical section of the L-shaped steel bar through the closing net fixing ribs.
[0016] In the structure of the aforementioned water-stop steel plate for the construction joint of the post-cast zone, the angle between the horizontal section of the L-shaped steel bar and the center line of the water-stop steel plate is 45°.
[0017] In the structure of the aforementioned post-casting strip construction joint waterstop steel plate, the shape of the waterstop steel plate is a long rectangle, and obtuse-angled folded edges are provided on both sides of the waterstop steel plate, and the top of the supporting steel bar is welded to the obtuse-angled folded edges on both sides of the waterstop steel plate.
[0018] Due to the adoption of the above-mentioned technical scheme, compared with the prior art, the present invention is that the on-site steel bar waste is bent into L-shaped steel bars, and the horizontal section of the L-shaped steel bar is spot welded on the waterstop steel plate at a 45° angle, which solves the problems of the prior art that it is easy to weld through the waterstop steel plate, causing leakage, affecting the project quality, and wasting materials. The construction quality of the construction joint of the post-casting belt is effectively improved, the secondary rework is reduced, and the construction cost is saved. BRIEF DESCRIPTION OF THE DRAWINGS
[0019] Figure 1 It is a front view of the present invention;
[0020] Figure 2 is a side view of the present invention;
[0021] Figure 3 is a top view of the present invention;
[0022] Figure 4 It is a three-dimensional axonometric drawing of the present invention.
[0023] The markings in the figure are as follows: 1-foundation cushion or formwork, 2-bottom steel mesh, 3-waterstop steel plate, 4-support steel bars, 5-L-shaped steel bars, 6-horizontal section, 7-vertical section, 8-closing mesh, 9-closing mesh fixing bars, 10-obtuse folded edge, 11-center line of waterstop steel plate. DETAILED DESCRIPTION
[0024] The present invention is further described in detail below in conjunction with the accompanying drawings and embodiments.
[0025] A construction method of a post-casting belt construction joint water-stop steel plate of the present invention, as Figures 1 to 4 As shown, the method is constructed according to the following steps:
[0026] a. Lay and tie two layers of bottom steel mesh 2 on the foundation cushion or formwork 1;
[0027] b. Make water-stop steel plate 3;
[0028] c. Weld the top of the support steel bar 4 to both sides of the water stop steel plate 3, support the bottom of the support steel bar 4 on the foundation cushion or the top surface of the formwork 1, and weld the support steel bar 4 to the bottom steel mesh 2;
[0029] d. The horizontal section 6 of the L-shaped steel bar 5 is tilted 45° and welded to the top surface of the water stop steel plate 3;
[0030] e. The closing net 8 is fixed to the L-shaped steel bar 5 by the closing net fixing rib 9;
[0031] f. Tie up the reinforcement bars and pour the concrete, and then complete the construction of the water-stop steel plate at the construction joint of the post-cast strip.
[0032] The water-stop steel plate 3 is provided with blunt-angled edges 10 on both sides, and the top of the supporting steel bar 4 is welded to the blunt-angled edges 10 on both sides of the water-stop steel plate 3. The L-shaped steel bar 5 is divided into a horizontal section 6 and a vertical section 7 at the 90° bend; the angle between the horizontal section 6 and the center line 11 of the water-stop steel plate is 45°, and is welded to the top surface of the water-stop steel plate 3. The closing net 8 is located between the closing net fixing rib 9 and the vertical section 7 of the L-shaped steel bar 5; and is fixed by welding the closing net fixing rib 9 to the vertical section 7 of the L-shaped steel bar 5.
[0033] The structure of the post-casting belt construction joint water-stopping steel plate of the present invention is formed according to the construction method of the post-casting belt construction joint water-stopping steel plate, as shown in FIG. Figures 1 to 4As shown, the structure includes a foundation cushion or formwork 1; two layers of bottom steel mesh 2 are provided on the foundation cushion or formwork 1, and a pair of parallel water-stop steel plates 3 are provided on the top of the two layers of bottom steel mesh 2; a group of supporting steel bars 4 are welded on both sides of each water-stop steel plate 3; the bottom end of the supporting steel bar 4 is supported on the top surface of the foundation cushion or formwork 1, and the middle part of the supporting steel bar 4 is welded to the bottom steel mesh 2; the top surface of the water-stop steel plate 3 is welded to the horizontal section 6 of the L-shaped steel bar 5, and the vertical section 7 of the L-shaped steel bar 5 is perpendicular to the top surface of the water-stop steel plate 3; a closing net 8 is provided on one side of the vertical section 7 of the L-shaped steel bar 5, and the closing net 8 is fixedly connected to the vertical section 7 of the L-shaped steel bar 5 through the closing net fixing rib 9. The angle between the horizontal section 6 of the L-shaped steel bar 5 and the center line 11 of the water-stop steel plate is 45°. The shape of the water-stop steel plate 3 is a long rectangle, and the two sides of the water-stop steel plate 3 are provided with blunt-angled folds 10, and the top of the supporting steel bar 4 is welded to the blunt-angled folds 10 on both sides of the water-stop steel plate 3.
[0034] The present invention is specifically constructed, such as Figures 1 to 4 As shown, the bottom steel mesh 2 is tied on the foundation cushion or the formwork 1, and then C10 ribbed steel bars are used as support steel bars 4 welded to both sides of the waterstop steel plate 3. The bottom of the support steel bars 4 is supported on the foundation cushion or the top surface of the formwork 1. The middle part of the support steel bar 4 is welded to the bottom steel mesh 2. The waterstop steel plate 3 is a rectangular strip structure, and the two sides of the waterstop steel plate 3 in the length direction are bent with obtuse folded edges 10, forming an "eight-shaped" shape on both sides of the waterstop steel plate 3, and the support steel bars 4 are welded to the edges of the obtuse folded edges 10. Then, the C8 ribbed steel scrap on the construction site is used to fold a 90° right angle to form an L-shaped steel bar 5 as a support body for the closing mesh 8. The horizontal section 6 of the L-shaped steel bar 5 is as shown Figure 3 As shown, it is spot welded at a 45° angle on the top surface of the waterstop steel plate 3, and the spot welding position is located slightly in front of the bend of the waterstop steel plate 3. Then, the C12 ribbed steel bar waste on the construction site is used as the closing net fixing rib 9 to fix the closing net 8 on one side of the vertical section of the L-shaped steel bar 5, and the closing net 8 is tied to the closing net fixing rib 9 with iron wire. After the closing net 8 is fixed, the tying of the surface ribs is started, and the concrete pouring of the construction joint of the post-cast strip is carried out. The construction process of the present invention is simple and fast, the installation is firm, the material is simple to make, and the quality is guaranteed. Compared with traditional vertical spot welding, the phenomenon of welding through the waterstop steel plate is easily solved by the method of the present invention.
Claims
1. A construction method for a post-casting belt construction joint water-stop steel plate, characterized in that: The method is constructed according to the following steps: a. Lay and tie two layers of bottom steel mesh (2) on the foundation cushion or formwork (1); b. Making a water-stop steel plate (3); c. The top of the support steel bar (4) is welded to both sides of the water stop steel plate (3), the bottom of the support steel bar (4) is supported on the top surface of the foundation cushion or the template (1), and the support steel bar (4) is welded to the bottom steel mesh (2); d. The horizontal section (6) of the L-shaped steel bar (5) is tilted 45° and welded to the top surface of the water stop steel plate (3); e. The closing net (8) is fixed to the L-shaped steel bar (5) by the closing net fixing rib (9); f. Tie the reinforcement and pour the concrete, and then complete the construction of the water-stop steel plate at the construction joint of the post-cast belt; Obtuse-angled folded edges (10) are provided on both sides of the water-stopping steel plate (3), and the top of the supporting steel bar (4) is welded to the obtuse-angled folded edges (10) on both sides of the water-stopping steel plate (3); The L-shaped steel bar (5) is divided into a horizontal section (6) and a vertical section (7) at a 90° bend; the angle between the horizontal section (6) and the center line (11) of the water-stop steel plate is 45°, and the horizontal section (6) is welded to the top surface of the water-stop steel plate (3); The closing net (8) is located between the closing net fixing ribs (9) and the vertical section (7) of the L-shaped steel bar (5); and is fixed by welding the closing net fixing ribs (9) and the vertical section (7) of the L-shaped steel bar (5).
2. A structure of a post-casting strip construction joint water-stopping steel plate constructed by the construction method of the post-casting strip construction joint water-stopping steel plate according to claim 1, comprising a basic cushion layer or a template (1); characterized in that: Two layers of bottom steel mesh (2) are provided on the foundation cushion layer or formwork (1), and a pair of parallel water-stop steel plates (3) are provided on the top of the two layers of bottom steel mesh (2); a group of supporting steel bars (4) are welded to both sides of each water-stop steel plate (3); the bottom ends of the supporting steel bars (4) are supported on the top surface of the foundation cushion layer or formwork (1), and the middle parts of the supporting steel bars (4) are welded to the bottom steel mesh (2); the top surface of the water-stop steel plate (3) is welded to the horizontal section (6) of the L-shaped steel bar (5), and the vertical section (7) of the L-shaped steel bar (5) is perpendicular to the top surface of the water-stop steel plate (3); a closing mesh (8) is provided on one side of the vertical section (7) of the L-shaped steel bar (5), and the closing mesh (8) is fixedly connected to the vertical section (7) of the L-shaped steel bar (5) through closing mesh fixing bars (9).
3. The structure of the water-stop steel plate for the post-casting construction joint according to claim 2 is characterized in that: The angle between the horizontal section (6) of the L-shaped steel bar (5) and the center line (11) of the water-stop steel plate is 45°.
4. The structure of the water-stop steel plate for the post-casting construction joint according to claim 2 is characterized in that: The waterstop steel plate (3) is in the shape of a long rectangle, and obtuse folded edges (10) are provided on both sides of the waterstop steel plate (3). The top of the supporting steel bar (4) is welded to the edges of the obtuse folded edges (10) on both sides of the waterstop steel plate (3).