Prefabricated bionic components for slope drainage adapting to freeze-thaw deformation and construction method
By designing the U-shaped groove connecting structure and assembly construction method that imitates animal joints, the problem of drainage structure damage caused by freezing and melting is solved, and the stable drainage effect under freezing and melting deformation conditions and convenience in high cold environments are achieved. construction.
Patent Information
- Application Number
- CN202010216843.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-03-25
- Publication Date
- 2024-11-26
- Estimated Expiration
- 2040-03-25
AI Technical Summary
The existing rigid drainage structure is prone to breaking and breaking under the action of freezing force, and loses its drainage effect. Especially in permafrost areas, it cannot adapt to the deformation of freezing and melting cycles, resulting in poor drainage effect and hypoxia and high cold environments in plateaus The construction problem is quite difficult.
Design a prefabricated bionic component for slope drainage adapted to freeze-thaw deformation, using a multi-section U-shaped groove body connected, similar to an animal joint structure, the bottom plate and the side plate are connected by reinforced rods, which can rotate and deform when frozen or melted, and maintain The structure is stable, and the assembly construction method is adopted to avoid on-site pouring of concrete.
It realizes the stability of drainage function under freeze-thaw cycle deformation conditions, adapts to high-altitude and oxygen-deficient environments, and is convenient to construct, avoids construction problems in frozen soil areas, ensures component quality and life, and is suitable for 10-60% ground slopes. .
Smart Images

Figure CN111305353B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a drainage ditch, in particular to a prefabricated bionic component for slope drainage adapting to freeze-thaw deformation and a construction method thereof. Background Art
[0002] Frozen soil (including permafrost and seasonal frozen soil) is widely distributed around the world. When the slopes in frozen areas freeze, frost heave will occur, and the slope surface will slightly bulge and deform. After the ice melts in the warm season, thaw settlement will occur. The frost heave force is generally dozens of times greater than the weight of the drainage structure. This causes the current rigid drainage structure to be easily dislocated and broken under the action of frost heave force, and lose its drainage effect. This problem is particularly serious in permafrost areas. Conventional rigid drainage ditches cannot resist frost heave deformation and are basically completely destroyed under the action of a freeze-thaw cycle. In order to solve this problem, dry-laid rubble drainage ditches are currently used in the area. Dry-laid rubble drainage ditches are better at adapting to frost heave deformation, but there are many gaps, which are prone to water leakage and poor drainage effect. Since it uses dry masonry construction, it can only be used in flat areas on the surface and cannot be used as a slope drainage measure.
[0003] At present, the Sichuan-Tibet Expressway, Qinghai-Tibet Expressway and Sichuan-Tibet Railway are all in the survey and design stage. Especially for the Qinghai-Tibet Expressway, most sections are in the permafrost zone, and there is an urgent need for suitable slope drainage engineering measures. Based on this, it is necessary to develop a drainage structure that can adapt to the hypoxic and cold working environment of the plateau and can adapt to the deformation of frost heave and thaw settlement cycles. Summary of the invention
[0004] The purpose of the present invention is to provide a prefabricated bionic component for slope drainage that can adapt to freeze-thaw deformation and a construction method thereof. The component can rotate like an animal joint. When frost heave or thaw settlement occurs and the bottom plate rises or falls, the interface rotates accordingly but does not separate, so as to achieve the purpose of adapting to frost heave and thaw settlement cycle deformation.
[0005] The technical solution adopted by the present invention is:
[0006] The prefabricated bionic component for slope drainage adapting to freeze-thaw deformation is characterized by:
[0007] The component comprises a plurality of U-shaped troughs which are small in front and large in the back and are sequentially connected and inserted;
[0008] The U-shaped trough body includes a bottom plate and side plates perpendicular to the bottom plate on both sides thereof; the bottom plate is an isosceles trapezoidal plate which is narrow in the front and wide in the back, and longitudinal protrusions of the bottom plate are arranged on the end faces on both sides thereof; the side plates are rectangular plates, and longitudinal grooves of the side plates are arranged on the inner side of the bottom at positions corresponding to the longitudinal protrusions of the bottom plate; the longitudinal protrusions of the bottom plate are inserted into the longitudinal grooves of the side plates, so that the bottom plate and the side plates form a U-shaped trough body which is small in the front and large in the back.
[0009] The surface of the front end of the bottom plate is an arc surface whose height decreases forward, forming a convex arc surface;
[0010] The bottom surface of the rear end of the bottom plate is a concave arc surface, the shape of which corresponds to the convex arc surface of the front end;
[0011] When two adjacent U-shaped trough bodies are plugged in front and back, the convex arc surface of the rear U-shaped trough body is located below the concave arc surface of the front U-shaped trough body.
[0012] A horizontally penetrating bottom plate circular hole is provided on the convex arc surface at the front end of the bottom plate.
[0013] A side plate circular hole is arranged at the rear end of the side plate corresponding to the circular hole of the bottom plate.
[0014] When two adjacent U-shaped trough bodies are plugged in front and back, the circular holes in the bottom plate of the rear U-shaped trough body correspond to the circular holes in the side plates of the front U-shaped trough body and the steel bars are inserted.
[0015] The diameter of the steel bar is 1 cm smaller than the circular holes in the bottom plate and the side plate.
[0016] The bottom plate and side plates are precast concrete blocks produced in a modular manner in the factory.
[0017] The bottom surface of the bottom plate is provided with anti-skid teeth.
[0018] Multiple sections of U-shaped trough bodies are sequentially connected and plugged into each other to form a drainage ditch, and a cushion layer is arranged at the bottom.
[0019] The cushion layer is a 15~20cm thick sand and gravel cushion layer.
[0020] The construction method of the prefabricated bionic component for slope drainage adapting to freeze-thaw deformation is characterized by:
[0021] The following steps are involved:
[0022] Step 1: Locate and dig the foundation trench, and lay a 15-20cm thick sand and gravel cushion layer;
[0023] Step 2: Install the bottom plate, install the side plates on both sides of the bottom plate to form a U-shaped trough, insert the second bottom plate under the first bottom plate, and insert the two side plates on the second bottom plate; insert a steel bar into the reserved holes of the two side plates respectively, make the connection parts close together, and connect the two U-shaped troughs together, repeat in sequence to complete the assembly of the drainage ditch;
[0024] Step 3: Use sand and gravel to backfill the foundation pit fertilizer trough on both sides of the drainage ditch to complete the drainage ditch construction.
[0025] The present invention has the following advantages:
[0026] (1) The prefabricated components are designed to imitate the animal joint structure, connecting adjacent components like "animal joints" to form a drainage system.
[0027] (2) The system is a flexible system. When frost heave or thaw settlement occurs, the connection is like an "animal joint". During the freeze-thaw deformation process, the connection can rotate and deform without being squeezed and damaged. It can adapt to the repeated deformation of the freeze-thaw cycle and maintain the stability of the structure and its drainage function.
[0028] (3) The serrated bottom can firmly connect the component to the slope cushion layer, maintaining the stability of the component on the slope.
[0029] (4) The use of prefabricated construction eliminates the need for on-site concrete pouring, which can solve the construction difficulties in permafrost areas. In permafrost areas, when digging the drainage ditch foundation trench at temperatures above zero degrees Celsius, the frozen soil will melt and the side walls of the foundation trench will collapse. When construction is carried out at temperatures below zero degrees Celsius, concrete cannot be poured. The use of prefabricated construction can solve this problem.
[0030] (5) The components are prefabricated and can be prefabricated in a centralized manner to ensure the quality and life of the components in cold environments.
[0031] (6) After the trough body is divided into the bottom plate and the side plate, the weight of a single component is reduced to less than 50 kg, and it can be installed and constructed manually. The construction is convenient and can adapt to the high-altitude and oxygen-deficient working environment.
[0032] (7) The present invention can adapt to ground slopes of 10-60% and can be used as rapids troughs, intercepting ditches, drainage ditches, etc. BRIEF DESCRIPTION OF THE DRAWINGS
[0033] Figure 1 It is the front view of the rear end of the present invention.
[0034] Figure 2 It is the front view of the present invention.
[0035] Figure 3 This is a schematic diagram of the side panel of the drainage ditch.
[0036] Figure 4 This is a schematic diagram of the drainage ditch bottom plate.
[0037] Figure 5 This is a cross-sectional diagram of the gutter installation.
[0038] Figure 6 Schematic diagram of the installation plan for the gutter.
[0039] Figure 7 Schematic diagram of inserting steel bars into the circular holes of the side plates and the bottom plates.
[0040] In the figure: 1-side plate, 2-bottom plate, 3-side plate circular hole, 4-bottom plate circular hole, 5-side plate longitudinal groove, 6-bottom plate longitudinal protrusion, 7-concave arc surface, 8-convex arc surface, 9-reinforcement rod, 10-anti-slip teeth, 11-cushion. DETAILED DESCRIPTION
[0041] The present invention is described in detail below in conjunction with specific implementation modes.
[0042] The present invention relates to a prefabricated bionic component for slope drainage adapting to freeze-thaw deformation, the component comprising a plurality of U-shaped troughs with a small front and a large rear section, which are sequentially connected and inserted. The U-shaped trough comprises a bottom plate 2 and side plates 1 perpendicular to the bottom plate 2 on both sides of the bottom plate 2; the bottom plate 2 is an isosceles trapezoidal plate narrow in front and wide in rear, and the end surfaces on both sides of the bottom plate are provided with bottom plate longitudinal protrusions 6; the side plate 1 is a rectangular plate, and the inner side of the bottom is provided with a side plate longitudinal groove 5 at a position corresponding to the bottom plate longitudinal protrusion 6; the bottom plate longitudinal protrusion 6 is inserted into the side plate longitudinal groove 5, so that the bottom plate 2 and the side plate 1 form a U-shaped trough with a small front and a large rear section.
[0043] The surface of the front end of the bottom plate 2 is an arc surface with a height decreasing forward, forming a convex arc surface 8, which is a convex 1 / 4 arc-shaped cylinder; the bottom surface of the rear end of the bottom plate 2 is a concave arc surface 7, the shape of which corresponds to the convex arc surface 8 at the front end, and is a depression of the 1 / 4 arc-shaped column; when two adjacent U-shaped trough bodies are plugged front and back, the convex arc surface 8 of the rear U-shaped trough body is located below the concave arc surface 7 of the front U-shaped trough body.
[0044] The convex arc surface 8 at the front end of the bottom plate 2 is provided with a horizontally penetrating bottom plate circular hole 4, and the rear end of the side plate 1 is provided with a horizontally penetrating side plate circular hole 3 at the position corresponding to the bottom plate circular hole 4; when two adjacent U-shaped trough bodies are plugged in front and back, the bottom plate circular hole 4 of the rear U-shaped trough body corresponds to the side plate circular hole 3 of the front U-shaped trough body and a steel bar 9 is inserted to prevent the two adjacent U-shaped trough bodies from being completely disconnected. The diameter of the steel bar 9 is about 1 cm smaller than the diameter of the bottom plate circular hole 4 and the side plate circular hole 3. Since the connection between the two U-shaped trough bodies is a circular contact, it can rotate like the joints of animals. When frost heave or thaw settlement occurs, the bottom plate rises or falls, and the interface rotates accordingly, but does not disengage, so as to achieve the purpose of adapting to the frost heave and thaw settlement cycle deformation.
[0045] The bottom plate 2 and the side plate 1 are both prefabricated concrete blocks produced in a factory in a modular manner. The bottom surface of the bottom plate 2 is provided with anti-slip teeth 10 .
[0046] Multiple sections of U-shaped trough bodies are sequentially connected and inserted to form a drainage ditch, and a cushion layer 11 is arranged at the bottom. The cushion layer 11 is a 15-20 cm thick sand and gravel cushion layer.
[0047] The present invention adopts a connection method that imitates animal joints. Two adjacent bottom plates 2 can rotate and deform, can adapt to frost heave and thaw deformation, and have good durability. The specific description of each part is as follows:
[0048] (1) The side plate 1 is a rectangular body with standard length, width and height. A rectangular groove is reserved at the bottom of the side for assembly with the bottom plate 2. A circular hole is reserved to ensure that the circular connection between two adjacent U-shaped trough bodies is tightly connected and to insert the steel bar 9.
[0049] (2) The bottom plate 2 is a trapezoidal body with standard length, width and height. There is a rectangular prism protrusion on both sides of the bottom plate, which is used to insert the side plates 1 on both sides to form a U-shaped trough. The bottom plate 2 is narrow at the front and wide at the rear. The narrow end is thin and has a 1 / 4 cylinder with a circular hole at the top along the axis of the cylinder. The wide end is thick and has a 1 / 4 cylinder groove at the bottom. A serrated protrusion is set at the bottom of the bottom plate 2 to prevent slipping.
[0050] (3) Circular holes are reserved on the bottom plate 2 and the side plate 1. After the adjacent bottom plate 2 and side plate 1 are installed, a circular steel bar 9 is inserted on both sides to connect the two adjacent U-shaped troughs. The diameter of the steel bar 9 is about 1 cm smaller than the inner diameter of the hole.
[0051] The construction method of the above-mentioned prefabricated bionic component for slope drainage adapting to freeze-thaw deformation comprises the following steps:
[0052] Step 1: Locate and dig the foundation trench, and lay a 15-20cm thick sand and gravel cushion layer;
[0053] Step 2: Install the bottom plate 2, install the side plates 1 on both sides of the bottom plate 2 to form a U-shaped trough, insert the second bottom plate 2 under the first bottom plate 2, and insert two side plates 1 on the second bottom plate 2; insert a steel bar 9 into the reserved holes of the two side plates respectively, make the connection parts close together, and connect the two U-shaped troughs together, and repeat in sequence to complete the assembly of the drainage ditch;
[0054] Step 3: Use sand and gravel to backfill the foundation pit fertilizer trough on both sides of the drainage ditch to complete the drainage ditch construction.
[0055] The content of the present invention is not limited to the embodiments listed, and any equivalent changes made to the technical solution of the present invention by ordinary technicians in this field after reading the description of the present invention are covered by the claims of the present invention.
Claims
1. Construction method of prefabricated bionic components for slope drainage that adapt to freeze-thaw deformation, Features: The component comprises a plurality of U-shaped troughs which are small in front and large in the back and are sequentially connected and inserted; The U-shaped trough body comprises a bottom plate (2) and side plates (1) perpendicular to the bottom plate (2) on both sides thereof; the bottom plate (2) is an isosceles trapezoidal plate which is narrow at the front and wide at the rear, and is provided with bottom plate longitudinal projections (6) on both side end surfaces; the side plates (1) are rectangular plates, and are provided with side plate longitudinal grooves (5) at positions on the inner sides of the bottom corresponding to the bottom plate longitudinal projections (6); the bottom plate longitudinal projections (6) are inserted into the side plate longitudinal grooves (5), so that the bottom plate (2) and the side plates (1) form a U-shaped trough body which is smaller at the front and larger at the rear; The surface of the front end of the bottom plate (2) is an arc surface whose height decreases toward the front, forming a convex arc surface (8); The bottom surface of the rear end of the bottom plate (2) is a concave arc surface (7), the shape of which corresponds to the convex arc surface (8) at the front end; When two adjacent U-shaped trough bodies are plugged in front and back, the convex arc surface (8) of the rear U-shaped trough body is located below the concave arc surface (7) of the front U-shaped trough body; A convex arc surface (8) at the front end of the bottom plate (2) is provided with a bottom plate circular hole (4) extending transversely therethrough. A side plate circular hole (3) is provided at a position of the rear end of the side plate (1) corresponding to the bottom plate circular hole (4); When two adjacent U-shaped trough bodies are plugged in front and back, the circular hole (4) on the bottom plate of the rear U-shaped trough body corresponds to the circular hole (3) on the side plate of the front U-shaped trough body and the steel bar (9) is inserted; The following steps are involved: Step 1: Locate and dig the foundation trench, and lay a 15-20cm thick sand and gravel cushion layer; Step 2: Install the bottom plate (2), install the side plates (1) on both sides of the bottom plate (2) to form a U-shaped trough body, insert the second bottom plate (2) under the first bottom plate (2), and insert the two side plates (1) on the second bottom plate (2); insert a steel bar (9) into the reserved holes of the two side plates respectively, so that the connection parts are tightly attached, and connect the two U-shaped trough bodies together, and repeat in sequence to complete the assembly of the drainage ditch; Step 3: Use sand and gravel to backfill the foundation pit fertilizer trough on both sides of the drainage ditch to complete the drainage ditch construction.
2. The construction method of the prefabricated bionic component for slope drainage adapting to freeze-thaw deformation according to claim 1, Features: The diameter of the steel bar (9) is 1 cm smaller than the bottom plate circular hole (4) and the side plate circular hole (3).
3. The construction method of the prefabricated bionic component for slope drainage adapting to freeze-thaw deformation according to claim 1 or 2, Features: The bottom plate (2) and the side plate (1) are both prefabricated concrete blocks produced in a factory in a modular manner.
4. The construction method of the prefabricated bionic component for slope drainage adapting to freeze-thaw deformation according to claim 3, Features: Anti-slip teeth (10) are provided on the bottom surface of the bottom plate (2).
5. The construction method of the prefabricated bionic component for slope drainage adapting to freeze-thaw deformation according to claim 4, Features: Multiple sections of U-shaped trough bodies are sequentially connected and inserted to form a drainage ditch, and a cushion layer (11) is arranged at the bottom.
6. The construction method of the prefabricated bionic component for slope drainage adapting to freeze-thaw deformation according to claim 5, Features: The cushion layer (11) is a 15-20 cm thick sand and gravel cushion layer.