A cold water / ice type steam jet water ring vacuum unit

By adopting a cold water storage/ice-type design in the steam jet ring vacuum unit, stacking condensers and using low-temperature water and step-by-step water, the problems of cooling water pollution and investment in the steam jet ring vacuum unit are solved, and significant Energy efficiency improvement and cost savings.

CN112503987BActive Publication Date: 2024-12-06XIAN XIANGYANG NEW ENVIRONMENTAL PROTECTION TECH CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202011501302.9
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2020-12-17
Publication Date
2024-12-06
Estimated Expiration
2040-12-17

AI Technical Summary

Technical Problem

The existing steam jet water ring vacuum unit has not been effectively solved in the problems of cooling water pollution and investment. At the same time, the Roots mechanical vacuum unit has unstable faults and unstable results, resulting in poor vacuum performance.

Method used

The cold storage water/ice type steam jet water ring vacuum unit is used to place the cooling tank on the ground and stack multiple condensers on it, and the cooling water is supplied by low-temperature water and step water to reduce the consumption of steam and cooling water. It also realizes the storage and recycling of low-temperature water through refrigeration equipment and cold energy storage tanks, cancels the turbid ring water tank and reduces investment costs.

Benefits of technology

It significantly saves the cost of building a load platform, reduces steam consumption by 60%, and cools water consumption by 70%, improves energy efficiency, reduces pollution and investment costs, and at the same time, through the use of cold energy storage tanks, the peak-cutting of electricity is achieved. Filling the valley saves money.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN112503987B_ABST
    Figure CN112503987B_ABST
Patent Text Reader

Abstract

The present invention discloses a cold water / ice type steam jet water ring vacuum unit, comprising a condenser group and a cold storage tank for being placed on the ground, the condenser group is arranged on the cold storage tank, and a plurality of condensers are stacked in sequence in the vertical direction. Each condenser is connected in series in sequence through a pipeline to form a gas flow channel; and the exhaust port of the bottom condenser is connected to the external pipeline for discharging the gas to the atmosphere; the spray device in the top condenser is connected to the cold storage tank pipeline for conveying the cold water or ice water mixture in the cold storage tank to the spray device. Between two adjacent condensers, the drain port of the upper condenser is connected to the water inlet pipeline of the lower condenser for providing spray water for the lower spray device. The use of this vacuum unit no longer requires the construction of a load platform, saving millions of yuan in costs; and the use of low-temperature water of 1 to 20°C and a stepped water use method to supply cooling water to each condenser, with significant energy-saving effects.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of cold storage, energy storage and vacuum acquisition, and in particular relates to a cold storage water / ice type steam jet water ring vacuum unit. Background Art

[0002] The steel liquid vacuum degassing device includes RH vacuum degassing furnace, VD vacuum degassing furnace, VOD vacuum degassing oxygen blowing furnace and VC vacuum degassing pouring furnace. The vacuum units matched with the steel liquid vacuum degassing device are usually the following: full steam jet vacuum unit, steam jet water ring vacuum unit and Roots mechanical vacuum unit.

[0003] The full steam jet vacuum unit is widely used and has stable performance. However, the steam and cooling water consumption is large, the cooling water is seriously polluted, and the investment in the turbid water tank and elevated platform is large. For the steam jet water ring vacuum unit, the energy consumption is reduced due to the use of a water ring vacuum pump as a front pump. The effect of use has been good in the past decade, but the shortcomings of serious cooling water pollution and large investment in the turbid water tank and elevated platform have not been solved. The application of Roots vacuum units has gradually increased in recent years. It is mainly driven by electricity and does not require high-pressure steam. However, there are still some uncertain factors that are prone to failures, resulting in unstable vacuum performance.

[0004] Steam jet water ring vacuum unit has two types: 4-stage jet + water ring pump and 3-stage jet + water ring pump. The difference is whether there is a two-stage booster pump or a three-stage booster pump in front of the C1 condenser. The common point is that the water inlet temperature of the C1 condenser is 35 degrees. In most parts of my country, the lowest temperature of circulating water obtained by cooling towers in summer is about 35 degrees. In some high temperature and high humidity areas, ice cubes are added to the cooling water pool in summer to cool down and obtain 35 degrees of circulating water to ensure the vacuum required for normal production.

[0005] For the C1 condenser with an inlet water temperature of 35 degrees and a vacuum tank vacuum degree of 67Pa, the total compression ratio of the second-stage and third-stage booster pumps is exactly the same, and their steam and cooling water consumption is also similar, with the steam and cooling water consumption being large. At present, the median of the international advanced energy consumption index of the full steam jet vacuum unit at a vacuum degree of 67Pa and 800kg / h is 28t / h of steam consumption (35kg steam / kg dry air per unit), and 1600mm of cooling water. 3 / h(single consumption 2m 3 / h cooling water / kg dry air), steam jet water ring vacuum unit is 20t / h (single consumption 25kg steam), cooling water consumption is 1450m 3 / h / h(single consumption 1.8m 3 / h cooling water). Summary of the invention

[0006] The technical problem to be solved by the present invention is to provide a cold water storage / ice-type steam injection water ring vacuum unit in view of the deficiencies of the above-mentioned prior art, which no longer requires the construction of a load platform, saving millions of yuan in costs; and adopts low-temperature water of 1 to 20°C and a stepped water use method to supply cooling water to each condenser, with significant energy-saving effects.

[0007] In order to solve the above technical problems, the technical solution adopted by the present invention is a cold storage water / ice type steam jet water ring vacuum unit, including a condenser group and a cold storage tank for being placed on the ground, the condenser group is arranged on the cold storage tank, and is composed of a plurality of condensers, and the plurality of condensers are stacked in sequence in the vertical direction.

[0008] Each condenser is a vacuum container with an air inlet, an exhaust port, a water inlet and a drain port; a spray device is provided inside.

[0009] The topmost condenser is connected to the vacuum tank through a pipeline to input the gas in the vacuum tank into it. The condensers are connected in series in sequence through pipelines to form a gas flow channel; and the exhaust port of the bottommost condenser is connected to the external pipeline to discharge the gas into the atmosphere; the spray device in the topmost condenser is connected to the cold storage tank pipeline to transport the cold water or ice water mixture in the cold storage tank to the spray device.

[0010] Between two adjacent condensers, the drain outlet of the upper condenser is connected to the water inlet pipeline of the lower condenser to provide water for spraying of the lower spray device; or the drain outlet of the top condenser is connected to the water inlet pipeline of the other condensers to provide water for spraying of the spray devices of each layer; except for the top condenser, the bottoms of the other condensers are connected to the cold storage tank to transport the sprayed water to the cold storage tank.

[0011] It also includes refrigeration equipment for cooling the sprayed water in the cold storage tank to low-temperature water or an ice-water mixture.

[0012] Furthermore, the temperature of the low-temperature water or ice-water mixture is 1-20°C.

[0013] Furthermore, the refrigeration equipment includes: a heat exchange tube, which is placed in a cold storage tank to cool the water after spraying; a refrigerator, wherein both ends of its refrigerant channel are correspondingly connected to both ends of the heat exchange tube to form a circulation loop for transporting the cooled refrigerant to the heat exchange tube; both ends of its water channel are connected to the cooling tower pipeline to form a circulation loop for cooling the refrigerant passing through the refrigerant channel.

[0014] Furthermore, it also includes a plurality of cold energy storage tanks, each of which is connected to the cold storage tank pipeline and is used to store excess low-temperature water or ice-water mixture in the cold storage tank.

[0015] Furthermore, two stages of booster pumps are connected in series between the vacuum tank and the uppermost condenser, and each booster pump is connected to the steam drum pipeline.

[0016] Furthermore, between two adjacent condensers, a jet pump is connected to the connecting pipelines of the two condensing chambers of the upper condenser, and each jet pump is connected to the steam drum pipeline.

[0017] Furthermore, the bottom of the lowest condenser is connected to the cold storage tank, and the cold storage tank is used as its water storage tank.

[0018] Furthermore, a water ring vacuum pump is arranged on a pipeline connecting the exhaust port of the bottom condenser with the outside, and the pipeline is connected with a water circuit of the water ring vacuum pump.

[0019] Furthermore, in the condenser group, there are three condensers, including: a C1 condenser, a C2 condenser and a C3 condenser which are stacked vertically upward and from top to bottom, and the C3 condenser is arranged on the cold storage tank.

[0020] Furthermore, the exhaust port of the C2 condenser is connected to the air inlet of the C3 condenser via two parallel pipelines, and the two pipelines are correspondingly connected to the S4A jet pump and the S4B jet pump.

[0021] The present invention has the following advantages: (1) Each condenser is stacked in sequence in the vertical direction, and the condenser at the bottom is placed on the cold storage tank, which satisfies the unpowered conveyance of the upper water layer to the lower water layer in the vertical direction, and no longer needs to build a load platform, saving millions of yuan in costs. (2) Low-temperature water of 1 to 20°C and a stepped water use method are used to supply cooling water to each condenser, which reduces the total compression ratio of the booster pump in front of the top condenser and reduces the mixed gas discharged by the jet pump in front of the condenser. The steam consumption is reduced by about 60%, and the cooling water consumption is reduced by about 70%, with significant energy-saving effects. (3) The low-temperature water in the cold storage tank is used to perform a heat exchange in the top condenser. The heat exchange water is divided into parallel multi-channel pipelines and conveyed to the condensers of other layers as cooling water in the condensers of other layers. After the heat exchange, it is discharged into the cold storage tank. The cooling water forms a circulating closed loop, eliminating the huge turbid water pool, saving investment costs and reducing pollution. (4) A cold energy storage tank is installed to store cold energy during the night when the power consumption is low, and to work during the day, thereby reducing the peak and filling the valley, using low-priced electricity and saving costs. BRIEF DESCRIPTION OF THE DRAWINGS

[0022] Figure 1 It is a structural schematic diagram of an energy storage type steam jet water ring vacuum unit of the present invention;

[0023] Among them: 1. Vacuum tank; 2. Coarse dust collector; 3. Fine dust collector; 4. Main stop valve; 5. S1 booster pump; 6. S2 booster pump; 7. S4B jet pump; 8. Valve; 9. C1 condenser; 10. S3 jet pump; 11. First regulating valve; 12. C2 condenser; 13. Second regulating valve; 14. Valve; 15. Exhaust gas flow meter; 17. Water ring vacuum pump; 18. Cooling tower; 20. Refrigeration machine; 21. Refrigerant pump; 22. Refrigerant water tank; 23. Water pump; 24. S4A jet pump; 25. C3 condenser; 26. Water pipe; 27. Cold storage tank; 28. Pipeline; 29. ​​Steam drum, 30. Second pipeline. DETAILED DESCRIPTION

[0024] The present invention provides an energy storage type steam jet water ring vacuum unit, such as Figure 1 As shown, it includes: a condenser group and a cold storage tank 27 for being placed on the ground. The condenser group is arranged on the cold storage tank 27 and is composed of a plurality of condensers, and the plurality of condensers are stacked in sequence in the vertical direction. The condenser group is placed vertically. Since each condenser has a certain height, the water in the condenser is transported to the cold storage tank 27 through a pipeline under the action of gravity, and the cold storage tank 27 also serves as a height support platform. There is no need to build an additional bearing platform to place the condenser group. Conventional flat condensers need to modify an 11-meter-high heavy-load platform, which costs hundreds of thousands of yuan. Therefore, by adopting the condenser group in the present invention, the heavy-load platform alone can save hundreds of thousands of yuan.

[0025] Each of the condensers is a vacuum container, provided with an air inlet, an exhaust port, a water inlet and a drain port; each condenser is provided with a spray device. The spray device is used to spray low-temperature water and is connected to the water inlet pipeline. The water inlet is generally opened at the upper part or the middle part of each condenser. The drain port is located at the lower part. There is no strict position requirement for the air inlet and the exhaust port. Generally, the air inlet is opened in the middle part, and the air outlet is located at the upper part.

[0026] The top condenser is connected to the vacuum tank 1 through a pipeline, and is used to input the gas in the vacuum tank 1 into it. Each of the condensers is connected in series through the pipeline to form a gas flow channel; and the exhaust port of the bottom condenser is connected to the external pipeline to discharge the gas into the atmosphere. When the gas in the vacuum tank 1 is transported by the pipeline, when it reaches the air inlet of the top condenser, it is necessary to ensure that the pressure of the air inlet is met.

[0027] Since the gas in the vacuum tank 1 is carried by the power steam and flows, when it reaches the top condenser, the required compression ratio is reduced because low-temperature water is used as the spray water for the top condenser. And since the pipelines of each condenser are connected in series, the consumption of power steam before the top condenser is reduced.

[0028] The spray device in the uppermost condenser is connected to the cold storage tank 27 pipeline, and is used to transport the low-temperature water in the cold storage tank 27 to the spray device. The temperature of the low-temperature water is 1-20°C.

[0029] Between two adjacent condensers, the drain port of the upper condenser is connected to the water inlet of the lower condenser through a pipeline to provide water for spraying of the lower spray device; or the drain port of the uppermost condenser is connected to the water inlet of the other condensers through a pipeline to provide water for spraying of the spray devices of each layer; except for the uppermost condenser, the bottoms of the other condensers are connected to the cold storage tank 27 to transport the sprayed water to the cold storage tank 27. The arrangement is that the bottom of the lowermost condenser is connected to the cold storage tank 27, and the cold storage tank 27 is used as its water storage tank. Vertical pipelines are set in the other condensers to transport the sprayed water to the cold storage tank 27.

[0030] The temperature of the low-temperature water is 1-20℃. After a heat exchange, the water temperature will generally rise by 5-10℃, that is, the water temperature after a heat exchange is about 6-30℃, which ensures that the water after a heat exchange can continue to be used as the heat exchange water of the next condenser. Then the water after a heat exchange is transported to the spray devices in the other layers of condensers by parallel pipelines, and mixed with the steam in the condensers of each layer for heat exchange. Only the top condenser needs to input low-temperature water through pipelines, and the low-temperature water is used in gradient order, which reduces the use of low-temperature water.

[0031] In the operation of the above-mentioned condensers, the low-temperature water in the cold storage tank 27 is used as cooling water, and a heat exchange is performed in the top condenser. The heat exchange water is divided into parallel multi-channel pipelines and transported to the other layers of condensers as cooling water in the other layers of condensers, and discharged into the cold storage tank 27 after heat exchange. The cooling water forms a circulating closed loop. The water after the secondary heat exchange is cooled and transported to the spray device of the top condenser through pipelines again as cooling water. Because a circulating loop is formed, the processing capacity of the water after the heat exchange is certain and will not increase with the change of time. The processing capacity of the water after the heat exchange is certain and will not increase with the change of time. There is no need to set up an additional cooling water treatment tank. And the sediment in the water after the heat exchange settles to the bottom in the cold storage tank 27 and is treated regularly. It saves investment costs and reduces pollution.

[0032] It also includes refrigeration equipment for cooling the sprayed water in the cold storage tank 27 to cold water or ice water mixture. In the cold storage tank 27, due to the difference in density between cold water and hot water, the cold water or ice water mixture and the water after heat exchange are automatically layered in the cold storage tank 27 or separated by a partition, and the cold water or ice water mixture is located in the lower part of the cold storage tank 27, and the water after heat exchange is located in the upper part of the cold storage tank 27.

[0033] The above refrigeration equipment includes: a heat exchange tube, including a serpentine part and a straight tube part, and the serpentine part is placed in the cold storage tank 27 to cool the sprayed water.

[0034] The two ends of the refrigerant channel of the refrigerator 20 are connected to the two ends of the heat exchange tube correspondingly to form a circulation loop for transporting the cooled refrigerant to the heat exchange tube; both ends of its water channel are connected to the cooling tower 18 pipeline to form a circulation loop for cooling the refrigerant passing through the refrigerant channel.

[0035] It also includes a plurality of cold energy storage tanks, each of which is connected to the cold storage tank 27 by pipeline. Since the electricity rate is low during the evening, the refrigeration equipment can prepare enough low-temperature water or ice-water mixture during this period and store it in a plurality of cold energy storage tanks. During the peak period of electricity consumption, the refrigeration equipment stops working and uses the stored cold water or ice-water mixture. During the peak period of electricity consumption, the refrigeration equipment stops working and uses the stored low-temperature water or ice-water mixture.

[0036] A two-stage booster pump is connected in series between the vacuum tank 1 and the top condenser, and each booster pump is connected to the sub-steam drum 29 pipeline. The sub-steam drum 29 stores a steam source as power steam, which is mixed with the gas derived from the vacuum tank 1 to increase the pressure, so as to carry the gas in the vacuum tank 1 into the top condenser. Between two adjacent condensers, a jet pump is connected to the connecting pipelines of the two condensers, and each jet pump is connected to the sub-steam drum 29 pipeline. Since the temperature of the cold water or ice water mixture used is 1-20°C, the pressure requirement at the outlet can be met after the two-stage booster pump is used for boosting, and at a temperature of 1-20°C, the required steam pressure is lower than the pressure of 35°C water, which reduces the steam consumption. Between two adjacent condensers, a jet pump is connected to the connecting pipeline between the exhaust port and the air inlet.

[0037] An embodiment of the present invention is Figure 1 As shown, in the condenser group, there are three condensers, including: C1 condenser 9, C2 condenser 12 and C3 condenser 25, which are stacked vertically upward and from top to bottom. C3 condenser 25 is placed on the cold storage tank 27 and is connected to the cold storage tank 27. Each condenser is provided with an air inlet, an exhaust port, a water inlet and a drain port. The air inlet and the water inlet are both provided at the upper part of the condenser, and each water inlet is connected to the spray device pipeline in the corresponding cavity. There is no strict position requirement for the exhaust port.

[0038] The drain outlet of the C1 condenser 9 is connected in parallel with the spray devices of the C2 condenser 12 and the C3 condenser 25 ; the spray water device of the C1 condenser 9 is connected to the vacuum tank 1 pipeline, and its exhaust port is connected to the air inlet pipeline of the C2 condenser 12 .

[0039] The exhaust port of the C2 condenser 12 is connected to the air inlet pipeline of the C3 condenser 25, and its drain port is connected to the pipeline of the cold storage tank 27. The specific method is that a connecting pipe is vertically arranged at the bottom of the C2 condenser 12, and the connecting pipe passes through the C3 condenser 25, and the end of the connecting pipe penetrates into the cold storage tank 27, and the bottom of the C3 condenser 25 is connected to the cold storage tank 27.

[0040] In this embodiment, each condenser is stacked in sequence in the vertical direction, and the bottom condenser is placed on the cold storage tank 27. Each condenser and the cold storage tank 27 have a certain height, and the cold water transportation in each layer of condensers is satisfied at their own height. It is no longer necessary to build a load platform for carrying condensers and cold storage tanks 27, saving costs. The cost of building a load platform with an area of ​​300 square meters and a height of about 22 meters is about 2 million.

[0041] The above-mentioned vacuum tank 1 and the air inlet pipeline of the C1 condenser 9 are connected in series, and two-stage booster pumps are connected in series on the pipeline, which are the S1 booster pump 5 and the S2 booster pump 6 connected in series. The S1 booster pump 5 and the S2 booster pump 6 are both connected to the pipeline of the steam drum 29, and the steam source pipeline is transported to each booster pump as power steam. The gas in the vacuum tank 1 passes through the coarse dust collector 2 and the fine dust collector 3 in turn, and the outlet of the fine dust collector 3 is installed with a main stop valve 4. Then it passes through the S1 booster pump 5 and the S2 booster pump 6 in sequence, and in each booster pump, it is mixed with the power steam and pressurized, and is discharged from the outlet of the S2 booster pump 6 to reach the required gas pressure at the inlet of the top condenser.

[0042] The exhaust port of the C3 condenser 25 is connected to the inlet pipeline of each water ring vacuum pump 17, and is discharged into the atmosphere through the water ring vacuum pump 17 through the exhaust pipe 16. An exhaust gas flowmeter 15 is provided on the exhaust pipe 16. The water circuit of the water ring vacuum pump is connected to the upper part of the cold storage tank 27. The exhaust capacity of the water ring vacuum pump 17 is closely related to the inlet water temperature, and the use of low-temperature water enables it to have a better vacuum exhaust capacity.

[0043] During operation, the low-temperature water in the cold storage tank 27 is pumped into the top of the C1 condenser 9 through the water pump 23, sprayed through the spray device, mixed with the gas and power steam entering the C1 condenser 9, and condensed. The temperature of the low-temperature water is slightly increased, and it is discharged from the bottom of the C1 condenser 9 in two ways. One way enters the spray device of the C2 condenser 12 through the first regulating valve 11, and the other way enters the spray device of the C3 condenser 25 through the second regulating valve 13, mixed with the mixed gas entering the C2 condenser 12 and the C3 condenser 25, and condensed. At the same time, the water in the C2 condenser 12 enters the cold storage tank 27 through the water pipe 26, and the water after heat exchange in the C3 condenser 25 directly flows into the cold storage tank 27. After the cold storage tank 27 is cooled, low-temperature water is obtained again, and then pumped into the C1 condenser 9, and the above working process is repeated for recycling.

[0044] The water after heat exchange in the cold storage tank 27 is cooled by refrigeration equipment, which includes: a heat exchange pipe, which is composed of a serpentine part and straight pipe parts at both ends, and the serpentine part is used to be placed in the water after heat exchange in the cold storage tank 27. The refrigerant water tank 22 is arranged outside the cold storage tank 27, and has an outlet and an inlet, and its inlet is connected to one end of the heat exchange pipe. The cooling inlet of the refrigerator 20 is connected to the outlet pipeline of the refrigerant water tank 22, and the cooling outlet is connected to the lower pipeline of the cold storage tank 27, which is used to cool the water after heat exchange to low-temperature water or ice, and transport it to the lower part of the cold storage tank 27 through the pipeline; both ends of the cooling pipeline of the refrigerator 20 are connected to the pipeline of the cooling tower 16 to form a loop.

[0045] The above-mentioned refrigerator 20 is a dual-mode refrigeration, and the refrigerator 20 can store sufficient low-temperature water or ice-water mixture for the cold storage tank 27. The low-temperature water consumption of a steel liquid vacuum degassing device or the low-temperature water consumption during a day can be guaranteed. A plurality of cold energy storage tanks can also be set, each of which is a closed vacuum container, and is also connected to the pipeline in the cold storage tank 27, so that the cold water or ice-water mixture in the cold storage tank 27 can be transported and stored in each cold energy storage tank through the pipeline. At night when electricity consumption is low, enough cold water or ice-water mixture is prepared, and the excess cold water or ice-water mixture is stored in the cold energy storage tank. During the peak electricity consumption during the day, the stored cold water or ice-water mixture is used to reduce the peak and fill the valley, and the use of low-priced electricity is economical and practical.

[0046] A cold storage water / ice steam jet water ring vacuum unit in this embodiment is used to treat molten steel. There are many types of molten steel vacuum degassing devices, such as RH, VD, VOD, VC, etc. Different molten steel vacuum degassing devices require vacuum tanks 1 of different structures and volumes according to the different qualities of molten steel to be treated. The vacuum tank 1 is provided with a lid, which is closed after the lid is covered. Sufficient low-temperature water or ice-water mixture is stored in the cold storage tank 27.

[0047] The working process is as follows: open each water ring vacuum pump 17, open the refrigerator 20, and reduce the water in the cold storage tank 27 to the required low temperature water. The steel liquid ladle is hung on the vacuum tank 1 and closed. First, the water pump 23 supplies low temperature water to each condenser and the water ring vacuum pump 17. Then open the valve 14 to make the water ring vacuum pump 17 reach the required pressure. Open the S4A ejector 24 and the S4B ejector 7 to make the pressure in the vacuum tank 1 reach 8Kpa, and close the S4B ejector 7. Continue to open the S3 ejector pump, the S2 booster pump, and the S1 booster pump 5 to make the vacuum tank 1 reach 67Pa, and maintain the vacuum degree of 67Pa for 10 to 30 minutes. At this time, the work of the steel liquid vacuum degassing device is completed, open the vent valve on the pipeline between the vacuum tank 1 and the coarse dust collector 2, and then turn off the S1 booster pump 5, the S2 booster pump 6, the S3 ejector pump 10, the S4 ejector pump 24, the valve 14, the water ring vacuum pump 17 and the water pump 23.

[0048] During the treatment of the molten steel vacuum degassing device, the waste gas generated in the vacuum tank 1 carries a lot of dust, and the temperature reaches about 1000 degrees. They enter the rough dust collector 2 through the second pipeline 30. First, the waste gas is cooled down, and most of the millimeter-level dust settles at the bottom of the rough dust collector 2. The waste gas enters the fine dust collector 3, and a small amount of millimeter-level dust and most of the micron-level dust are further cooled down and settled at the bottom of the fine dust collector. The remaining small amount of micron-level dust enters the S1 booster pump 5, the S2 booster pump 6 and the C1 condenser 9 are brought into the cold storage tank 27 by low-temperature water, and the dust settled at the bottom is regularly cleaned and discharged through the valve.

[0049] The most classic energy-saving theory of steam jet vacuum units is to install the condenser as early as possible. Since the steam consumption of the C1 condenser increases exponentially with the increase of the total compression ratio, the use of low-temperature water to set the C1 condenser can greatly reduce the total compression ratio of the booster pump, thereby greatly reducing the steam consumption and cooling water consumption.

Claims

1. A cold water / ice type steam jet water ring vacuum unit, characterized in that: It comprises a condenser group and a cold storage tank (27) for being placed on the ground, wherein the condenser group is arranged on the cold storage tank (27) and is composed of a plurality of condensers, and the plurality of condensers are stacked in sequence in a vertical direction; Each of the condensers is a vacuum container, provided with an air inlet, an exhaust port, a water inlet and a drain port; each of the condensers is provided with a spray device; The top condenser is connected to the vacuum tank (1) via a pipeline, and is used to input the gas in the vacuum tank (1) into it, and each of the condensers is connected in series via the pipeline to form a gas flow channel; and the exhaust port of the bottom condenser is connected to the external pipeline, and is used to exhaust the gas to the atmosphere; The spray device in the uppermost condenser is connected to the pipeline of the cold storage tank (27) and is used to transport the cold water or ice water mixture in the cold storage tank (27) to the spray device; Between two adjacent condensers, the drain outlet of the upper condenser is connected to the water inlet of the lower condenser through a pipeline, so as to provide water for spraying of the spraying device of the lower layer; or the drain outlet of the uppermost condenser is connected to the water inlet of the other condensers through a pipeline, so as to provide water for spraying of the spraying devices of the other layers; except for the uppermost condenser, the bottoms of the other condensers are connected to the cold storage tank (27), so as to transport the sprayed water to the cold storage tank (27); Also included is refrigeration equipment for cooling the sprayed water in the cold storage tank (27) to low-temperature water or an ice-water mixture; In the condenser group, there are three condensers, including: a C1 condenser (9), a C2 condenser (12), and a C3 condenser (25) which are stacked in sequence vertically upward from top to bottom, and the C3 condenser (25) is arranged on the cold storage tank (27); During operation, the low-temperature water in the cold storage tank (27) is pumped into the top of the C1 condenser (9) through the water pump (23), sprayed through the spray device, and mixed with the gas and power steam entering the C1 condenser (9). After condensation, the temperature of the low-temperature water increases and it is discharged from the bottom of the C1 condenser (9) in two ways. One way passes through the first regulating valve (11) and enters the spray device of the C2 condenser (12). The other way passes through the second regulating valve (13) and enters the spray device of the C3 condenser (25). It is mixed with the mixed gas entering the C2 condenser (12) and the C3 condenser (25) and condensed. At the same time, the water in the C2 condenser (12) enters the cold storage tank (27) through the water pipe (26). The water after heat exchange in the C3 condenser (25) flows directly into the cold storage tank (27). After being cooled in the cold storage tank (27), low-temperature water is obtained again and then pumped into the C1 condenser (9). The above working process is repeated for recycling.

2. The cold storage water / ice type steam jet water ring vacuum unit according to claim 1, characterized in that: The temperature of the low-temperature water or ice-water mixture is 1-20°C.

3. The cold storage water / ice type steam jet water ring vacuum unit according to claim 2, characterized in that: The refrigeration equipment comprises: A heat exchange tube, which is placed in the cold storage tank (27) to cool the water after spraying; The refrigerator (20) has two ends of its refrigerant channel connected to the two ends of the heat exchange tube to form a circulation loop for conveying the cooled refrigerant into the heat exchange tube; and two ends of its water channel are connected to the cooling tower (18) pipeline to form a circulation loop for cooling the refrigerant passing through the refrigerant channel.

4. A cold storage water / ice type steam jet water ring vacuum unit according to claim 3, characterized in that: It also includes a plurality of cold energy storage tanks, each of which is connected to the cold storage tank (27) through a pipeline and is used to store excess low-temperature water or ice-water mixture in the cold storage tank (27).

5. The cold storage water / ice type steam jet water ring vacuum unit according to claim 4, characterized in that: Two stages of booster pumps are connected in series between the vacuum tank (1) and the uppermost condenser, and each of the booster pumps is connected to a steam drum (29) pipeline.

6. The cold storage water / ice type steam jet water ring vacuum unit according to claim 5, characterized in that: Between two adjacent condensers, a jet pump is connected to the connecting pipelines of the two condensing chambers of the upper condenser, and each of the jet pumps is connected to the pipeline of the steam drum (29).

7. The cold storage water / ice type steam jet water ring vacuum unit according to claim 5, characterized in that: The bottom of the lowermost condenser is connected to the cold storage tank (27), and the cold storage tank (27) serves as its water storage tank.

8. A cold storage water / ice type steam jet water ring vacuum unit according to claim 5, 6 or 7, characterized in that: A water ring vacuum pump is arranged on a pipeline connecting the exhaust port of the bottom condenser with the outside, and the pipeline is connected with the water circuit of the water ring vacuum pump.

9. The cold storage water / ice type steam jet water ring vacuum unit according to claim 8, characterized in that: The exhaust port of the C2 condenser (12) and the air inlet of the C3 condenser (25) are connected via two parallel pipelines, and the two pipelines are connected to a S4A jet pump (24) and a S4B jet pump (7) respectively.