Multi-point prefabricated component installation platform and installation method
By designing a multi-point prefabricated parts installation platform in construction, using steel formwork, support frame and electric hoist, the relay between the tower crane and the lifting system is achieved, solving the problems of long-term occupation of tower cranes and inaccurate manual fine adjustment, and improving the Installation efficiency and safety.
Patent Information
- Application Number
- CN202110149629.2
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-02-03
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2041-02-03
AI Technical Summary
During the installation of existing prefabricated parts, the tower crane takes up a long time and the manual fine adjustment is not accurate, which can easily cause installation errors, affect construction efficiency, and may lead to personnel injury or structural damage.
Design a multi-point prefabricated installation platform, including steel formwork, support frame, truss and electric hoists, lift the prefabricated parts to a designated position through tower cranes, use electric hoists and hoists to achieve precise installation and inter-layer movement, and reduce tower crane occupation Time and manual fine adjustment steps.
It improves the efficiency and safety of prefabricated parts installation, ensures installation accuracy, reduces secondary rework, and improves construction efficiency.
Smart Images

Figure CN112796531B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a multi-point prefabricated component installation platform and an installation method, belonging to the technical field of building construction. Background Art
[0002] The existing floor positioning installation of the vertical structure of prefabricated parts relies on the tower crane to lift the prefabricated parts to the location to be installed. The commander coordinates the tower crane driver to control the tower crane to position the installation position through the intercom. The fine adjustment is mainly based on the rough adjustment, the workers manually push and pull the prefabricated parts for positioning and installation. When the position of the prefabricated parts is adjusted to the predetermined position, the tower crane lowers the prefabricated parts, and then manually reinforces the diagonal bracing of the prefabricated parts and the positioning and reinforcement of the vertical channel steel. Only after all the prefabricated parts are reinforced and installed can the tower crane loosen the rope to install the next prefabricated part. This process will always take up the tower crane's time. If the tower crane driver and the commander do not cooperate well, it may also cause injuries to personnel or the prefabricated parts may collide with the surrounding steel bars and formwork, damaging the structure. In addition, the manual fine adjustment of the process is difficult to ensure the accurate installation of the prefabricated parts, which is easy to cause the prefabricated parts to have too large installation errors, resulting in secondary rework, reducing construction efficiency, and is not conducive to the promotion of prefabricated parts on site. Summary of the invention
[0003] The purpose of the present invention is to provide a multi-point prefabricated component installation platform and installation method with simple structure, low cost and convenient operation, so as to overcome the shortcomings of the prior art.
[0004] In order to achieve the above-mentioned purpose, the present invention adopts the following technical scheme: a multi-point prefabricated component installation platform, including a constructed wall, a steel formwork is fixedly installed on the upper part of the constructed wall by tension bolts, a support frame is fixedly connected to the top of the steel formwork, a truss is fixedly connected to the top of the support frame to form a support platform, a walking trolley that can move along the truss is provided on the truss, and an electric hoist is connected to the bottom of the walking trolley.
[0005] Furthermore, one side of the constructed wall is fixedly connected to a column through a wall connecting piece, a pair of fixed pulleys are installed on the top of the column, a steel wire rope is wound around the pair of fixed pulleys, one end of the steel wire rope is connected to the top of the steel formwork, and the other end thereof is connected to a winch.
[0006] Furthermore, the top of the column is higher than the top of the steel formwork.
[0007] At the same time, the present invention also provides a multi-point prefabricated component installation method based on the multi-point prefabricated component installation platform, comprising the following steps:
[0008] Step 1: First, install the steel formwork on the upper part of the constructed wall by tension bolts, then fix the connecting support frame on the top of the steel formwork, and fix the connecting truss on the top of the support frame to form a support platform;
[0009] Step 2: Set a trolley on the truss that can move along the truss, and connect an electric hoist to the bottom of the trolley;
[0010] Step 3: Pour the concrete of the wall to be constructed between the steel formworks. When the concrete of the wall to be constructed reaches the designed strength, lift the prefabricated parts to the floor where the wall to be constructed is located by the tower crane and unload them. Then, lift the prefabricated parts by the electric hoist and control the traveling trolley to move the prefabricated parts to the designated position for installation.
[0011] In the above method, after the installation of the prefabricated parts is completed, the tension bolts on the steel formwork are removed, and then the winch is started. The steel formwork at the other end of the wire rope and the support platform fixedly connected to the steel formwork are driven by the winch to move upward to the upper layer for installing the prefabricated parts on the upper layer. This cycle can be repeated to complete the installation of prefabricated parts in the entire building.
[0012] Due to the adoption of the above technical solution, the present invention has the following advantages:
[0013] ① The support platform and electric hoist form a lifting system, which forms a relay with the tower crane to transfer the prefabricated parts on the tower crane to the lifting system. This can save the time of occupying the tower crane, facilitate the installation of prefabricated parts at multiple points, and improve the efficiency of installing prefabricated parts;
[0014] ②Fix the support platform on the steel formwork, use the high-strength steel formwork for support, and use the positioning principle of the steel formwork to control the spacing of the support frame, which can save the steps of rough adjustment of prefabricated parts and improve construction efficiency;
[0015] ③ Use the electric hoist lifting system to adjust the position, which makes the positioning more reliable and safe, ensuring the safety of the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0016] Figure 1 It is a front view of the structural schematic diagram of the present invention;
[0017] Figure 2 It is a top view of the structural schematic diagram of the present invention. DETAILED DESCRIPTION
[0018] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0019] Embodiments of the present invention: Please refer to Figure 1 and Figure 2 A multi-point prefabricated component installation platform includes a constructed wall 1, a steel formwork 2 is fixedly installed on the upper part of the constructed wall 1 by tension bolts, a support frame 4 is fixedly connected to the top of the steel formwork 2, a truss 9 is fixedly connected to the top of the support frame 4 to form a support platform, a walking trolley 7 that can move along the truss 9 is provided on the truss 9, and an electric hoist 8 is connected to the bottom of the walking trolley 7. A column 3 is fixedly connected to one side of the constructed wall 1 through a wall connecting member 11, a pair of fixed pulleys 5 are installed on the top of the column 3, a steel wire rope 6 is wound around the pair of fixed pulleys 5, one end of the steel wire rope 6 is connected to the top of the steel formwork 2, and the other end is connected to a winch 10. The top of the column 3 is higher than the top of the steel formwork 2 to ensure that the steel formwork 2 can be lifted to the upper layer. The traveling trolley 7 and the electric hoist 8 used in the present invention are both purchased, and their models can be selected according to the weight of the prefabricated part 13, as long as the prefabricated part 13 can be smoothly moved or lifted.
[0020] When installing prefabricated parts using the above-mentioned multi-point prefabricated part installation platform, the following steps can be adopted:
[0021] Step 1: First, the steel formwork 2 is fixedly installed on the upper part of the constructed wall 1 by tension bolts, and then the support frame 4 is fixedly connected to the top of the steel formwork 2, and the truss 9 is fixedly connected to the top of the support frame 4 to form a support platform;
[0022] Step 2: A traveling trolley 7 that can move along the truss 9 is arranged on the truss 9, and an electric hoist 8 is connected to the bottom of the traveling trolley 7;
[0023] Step three: pour the concrete of the wall 12 to be constructed between the steel formworks 2. When the concrete of the wall 12 to be constructed reaches the designed strength, lift the prefabricated component 13 to the floor where the wall 12 to be constructed is located by the tower crane and unload it. Then, lift the prefabricated component 13 by the electric hoist 8, and control the traveling trolley 7 to move the prefabricated component 13 to the designated position for installation.
[0024] When the prefabricated parts 13 are installed, the tension bolts on the steel formwork 2 are removed, and then the winch 10 is started. The winch 10 drives the steel formwork 2 at the other end of the wire rope 6 and the support platform fixedly connected to the steel formwork 2 to move upward to the upper layer for installing the prefabricated parts 13 of the upper layer. This cycle is repeated to complete the installation of the prefabricated parts 13 in the entire building.
Claims
1. A multi-point prefabricated component installation method based on a multi-point prefabricated component installation platform, the multi-point prefabricated component installation platform comprising a constructed wall (1), a steel template (2) is fixedly installed on the upper part of the constructed wall (1) by tension bolts, a support frame (4) is fixedly connected to the top of the steel template (2), a truss (9) is fixedly connected to the top of the support frame (4), forming a support platform, the truss (9) is provided with a walking trolley (7) that can move along the truss (9), The bottom of the walking trolley (7) is connected to an electric hoist (8); one side of the constructed wall (1) is fixedly connected to a column (3) through a wall connecting member (11); a pair of fixed pulleys (5) are installed on the top of the column (3); a steel wire rope (6) is wound around the pair of fixed pulleys (5); one end of the steel wire rope (6) is connected to the top of the steel template (2), and the other end is connected to the winch (10); the top of the column (3) is higher than the top of the steel template (2); it is characterized in that The following steps are involved: Step 1: First, a steel formwork (2) is fixedly installed on the upper part of the constructed wall (1) by means of tension bolts, and then a support frame (4) is fixedly connected to the top of the steel formwork (2), and a truss (9) is fixedly connected to the top of the support frame (4) to form a support platform; Step 2: The truss (9) is provided with a walking trolley (7) that can move along the truss (9), and an electric hoist (8) is connected to the bottom of the walking trolley (7); Step 3: pour concrete of the wall to be constructed (12) between the steel formworks (2). When the concrete of the wall to be constructed (12) reaches the designed strength, the prefabricated component (13) is hoisted to the floor where the wall to be constructed (12) is located by a tower crane and then unloaded. Then, the prefabricated component (13) is hoisted by an electric hoist (8), and the traveling trolley (7) is controlled to move the prefabricated component (13) to a designated position for installation.
2. The multi-point prefabricated component installation method according to claim 1, characterized in that: When the prefabricated parts (13) are installed, the tension bolts on the steel formwork (2) are removed, and then the winch (10) is started. The winch (10) drives the steel formwork (2) at the other end of the steel wire rope (6) and the support platform fixedly connected to the steel formwork (2) to move upward to the upper layer for installing the prefabricated parts (13) of the upper layer. This cycle is repeated to complete the installation of the prefabricated parts (13) in the entire building.