A differentiated statistical method for the development and construction of domestic and foreign distribution networks
By establishing differentiated statistical collection templates and scientific models and quantifying the influencing factors, the problem of instability of existing statistical methods has been solved, the comprehensive reflection of differentiation of domestic and foreign distribution networks has been achieved and the construction plan has been adjusted, and the statistical results have been improved. Stability and accuracy.
Patent Information
- Application Number
- CN202110526414.8
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-05-14
- Publication Date
- 2024-11-19
- Estimated Expiration
- 2041-05-14
AI Technical Summary
The existing differentiated statistical methods fail to influence the influence of differentiated factors through scientific and reasonable models and quantify the influence of differentiated factors, resulting in unstable statistical results and difficult to meet social needs.
Establish a differentiated statistical collection template for the development and construction of domestic and foreign distribution networks, collect data in a classified manner, extract key factors, and adjust the construction plan of the distribution network through scientific and reasonable models and quantify the influence of differentiated factors.
Through integrated analysis and hierarchical analysis methods, the differentiation of urban distribution networks at home and abroad is fully reflected, and managers are helped to adjust the construction plan, improving the stability and accuracy of statistical results.
Abstract
Description
Technical Field
[0001] The present invention relates to the field of electric power technology, and more specifically, to a differentiated statistical method for the development and construction of domestic and foreign distribution networks. Background Art
[0002] The distribution network has developed and constructed rapidly in the past 20 years, but its morphological structure has not changed much, mainly changing from the traditional radial type to the segmented connection type. In the future, it will develop into a multi-layer, multi-ring, and multi-state complex network. The traditional distribution network is a primary form, with the goal of providing geographical full coverage of user loads and providing a basic service platform. The modern distribution network is an intermediate form, with the goal of providing reliable, efficient, and high-quality power supply services and providing a high-quality service platform. The future distribution network will be an advanced form, with the goal of providing green, intelligent, and customizable power supply services and providing an intelligent service platform. With the change of form, the control capability of the distribution network will gradually improve, and the resource coordination capability will be significantly enhanced to better meet the complex load Demand. At present, the distribution system is in the transition stage from modern to future development. In the actual operation of distribution networks at home and abroad, the operating parameters of distribution networks are affected by many factors. In order to reduce the gap in distribution network development and construction, it is often necessary to conduct statistics on the differences between domestic and foreign distribution networks. The existing differentiated statistical methods only conduct statistics on the data of various differences, but fail to use scientific and reasonable models and quantify the influence of various factors that affect the differences. As a result, the statistical results have certain instability and are difficult to meet the needs of society. Therefore, a differentiated statistical method for the development and construction of domestic and foreign distribution networks is needed to solve the above problems. Summary of the invention
[0003] In order to overcome the above-mentioned defects of the prior art, the present invention provides a differentiated statistical method for the development and construction of domestic and foreign distribution networks. The technical problem to be solved by the present invention is that the existing differentiated statistical method only counts the differentiated data, but does not use a scientific and reasonable model to quantify the influence of various factors affecting the differentiation, which makes the statistical results have a certain instability and is difficult to meet the needs of society.
[0004] To achieve the above purpose, the present invention provides the following technical solution: a differentiated statistical method for the development and construction of domestic and foreign distribution networks, comprising the following steps:
[0005] S1. Establish differentiated statistical collection templates for the development and construction of domestic and international distribution networks.
[0006] S2. By using the differentiated statistical collection template for domestic and foreign distribution network construction established in S1, the development history of domestic and foreign distribution networks and the basic data of domestic and foreign distribution networks are collected by classification.
[0007] S3. Analyze the collected domestic and foreign distribution network data separately, extract and record the key factors that lead to construction differences.
[0008] S4. Classify the key factors that lead to construction differentiation, and match and operate each key factor by splitting and integrating. Then, use a scientific and reasonable model to quantify the influence of each factor that affects the differentiation, analyze the reasons for the existence of each factor, and adjust the subsequent construction plan of the distribution network accordingly.
[0009] As a further solution of the present invention: the establishment of the differentiated statistical collection template for the development and construction of domestic and foreign distribution networks in S1 includes the following contents:
[0010] Create an Excel table, which is divided into two major items, one is for domestic distribution network construction data collection, and the other is for foreign distribution network construction data collection. After completion, save it as a differentiated statistical table for the development and construction of domestic and foreign distribution networks.
[0011] As a further solution of the present invention: the domestic distribution network construction data collection and the foreign distribution network construction data collection both include development history collection, grid structure collection, distribution automation collection, power supply reliability collection, energy grid construction collection, grid operation data collection, information support construction collection and value creation construction collection.
[0012] As a further solution of the present invention: the power grid structure collection includes distribution network geographical connection map, line information, voltage level power substation information and planned power grid information data; the energy grid construction collection includes transformer quantity, line number and line length indicators; the value creation construction collection includes electricity sales, power loss, electricity purchase and sales fees, electricity fee management, power grid investment, power supply quality, business expansion and registration, asset profit and human resources indicators; the power grid operation data includes safety level, light load operation, heavy load operation and high loss operation indicators; the value creation construction collection includes economic development collection, land resources collection, population resources collection and electricity customers collection.
[0013] As a further solution of the present invention: S2 uses the differentiated statistical collection template for the construction of domestic and foreign distribution networks established in S1 to classify and collect the development history of domestic and foreign distribution networks and the basic data of domestic and foreign distribution networks, including the following contents:
[0014] Combining the development history of distribution networks at home and abroad, we then collected big data on the grid structure, distribution automation and power supply reliability of Tokyo, Singapore, Paris, Shanghai, Xiamen and Suzhou. We then processed the collected data to remove duplicate and redundant data, and then classified the remaining data and filled it into the corresponding areas of the above Excel table.
[0015] As a further solution of the present invention: the analysis of the domestic and foreign power distribution network data in S3 includes the following contents:
[0016] According to the information filled in the differentiated statistical table of domestic and foreign distribution network development and construction, the corresponding charts are generated, the key information of the basic data of the distribution network is extracted, and the differentiation model is constructed from top to bottom. A comparative analysis is conducted based on the current situation and the differences between domestic and foreign distribution networks. The differentiation model mainly compares and analyzes the direct factors of area, boundary, and number of power points from a horizontal perspective, and then draws them on the GIS layer through automatic drawing technology, giving different graphic features to different grids to intuitively reflect the differences. At the same time, a deeper comparative analysis is conducted on the horizontal factors of power supply range, power supply radius, power substation distribution, overall spatial distribution of regional loads, and distribution form of main corridors between substations, and the difference factors that affect the differentiation of domestic and foreign distribution networks are obtained.
[0017] As a further solution of the present invention: S4 analyzes the reasons for the existence of each factor and the negative impact coefficient of each factor on each city distribution network, then compares the impact coefficients of all factors to obtain statistical results, and adjusts the construction plan of the city distribution network according to the statistical results.
[0018] As a further solution of the present invention: the method for determining the influence of the differentiation factor in S4 includes the following contents:
[0019] After integrating and analyzing various differentiated data, some factors are split into controllable factors and uncontrollable factors. Then the controllable factors in the domestic data are run in the uncontrollable factors of the foreign data respectively, and then the controllable factors in the domestic data are run in the uncontrollable factors of the domestic data respectively, and a variety of different permutations and combinations of controllable and uncontrollable factors are obtained. By statistically analyzing these results, a set of optimal operating data is obtained, and then based on the hierarchical analysis method, the distribution network model constructed and the influence of various factors that affect the differentiation are quantified.
[0020] As a further solution of the present invention: the differentiated analysis in S3 is based on the hierarchical analysis method, and the energy efficiency evaluation index system is constructed based on the standard "GB31367 Guidelines for Energy Efficiency Evaluation of Medium and Low Voltage Distribution Networks", and the weights of individual indicators are determined. Then, according to the scoring standards of each indicator in the relevant guidelines, the analyzed domestic and foreign distribution network information is input to obtain the final scoring result.
[0021] As a further solution of the present invention: the controllable factors include distribution network development automation, distribution automation, power supply reliability, power supply mode and energy grid construction structure, and the uncontrollable factors include user differences and environmental differences.
[0022] The beneficial effects of the present invention are:
[0023] 1. After integrating and analyzing various differentiated data, the present invention splits some factors into controllable factors and uncontrollable factors, and then respectively runs the controllable factors in the domestic data in the uncontrollable factors in the foreign data, and then respectively runs the controllable factors in the domestic data in the uncontrollable factors in the domestic data, and obtains a variety of different permutation and combination results of controllable factors and uncontrollable factors. By statistically analyzing these results, a set of optimal operation data is obtained, and then based on the hierarchical analysis method, the constructed distribution network model and the influence of various factors that quantify the influence of the differentiation, the differentiation of the development and construction of urban distribution networks at home and abroad can be comprehensively and systematically reflected. By analyzing the various factors that lead to differentiation, and then by analyzing the reasons for the existence of each factor and the negative impact coefficient of each factor on each urban distribution network, the influence coefficients of all factors are compared with each other to obtain statistical results, so that management personnel can adjust the construction plan of the urban distribution network according to the statistical results;
[0024] 2. The present invention establishes an Excel table and divides the table into two major items, one is for collecting data on domestic distribution network construction, and the other is for collecting data on foreign distribution network construction. The data is then divided into development history collection, grid structure collection, distribution automation collection, power supply reliability collection, energy grid construction collection, grid operation data collection, information support construction collection and value creation construction collection. When personnel need to collect domestic and foreign data information, they can directly use the established differentiated statistical tables for the development and construction of domestic and foreign distribution networks to fill in, thereby facilitating the rapid collection of domestic and foreign development data by personnel. DETAILED DESCRIPTION
[0025] The technical solutions in the embodiments of the present invention are described clearly and completely below. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of them. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.
[0026] A differentiated statistical method for the development and construction of domestic and foreign distribution networks includes the following steps:
[0027] S1. Establish differentiated statistical collection templates for the development and construction of domestic and international distribution networks.
[0028] S2. By using the differentiated statistical collection template for domestic and foreign distribution network construction established in S1, the development history of domestic and foreign distribution networks and the basic data of domestic and foreign distribution networks are collected by classification.
[0029] S3. Analyze the collected domestic and foreign distribution network data separately, extract and record the key factors that lead to construction differences.
[0030] S4. Classify the key factors that lead to construction differentiation, and match and operate each key factor by splitting and integrating. Then, use a scientific and reasonable model to quantify the influence of each factor that affects the differentiation, analyze the reasons for the existence of each factor, and adjust the subsequent construction plan of the distribution network accordingly.
[0031] S1 The establishment of differentiated statistical collection templates for the development and construction of domestic and foreign distribution networks in China includes the following contents:
[0032] Create an Excel table, which is divided into two major items, one is for domestic distribution network construction data collection, and the other is for foreign distribution network construction data collection. After completion, save it as a differentiated statistical table for the development and construction of domestic and foreign distribution networks.
[0033] The data collection of domestic distribution network construction and the data collection of foreign distribution network construction both include development history collection, grid structure collection, distribution automation collection, power supply reliability collection, energy grid construction collection, grid operation data collection, information support construction collection and value creation construction collection.
[0034] The grid structure data collected includes the geographical connection map of the distribution network, line information, voltage level power substation information and planned grid information data; the energy grid construction data includes the number of transformers, the number of lines and the line length indicators; the value creation construction data includes electricity sales volume, power loss, electricity purchase and sales fees, electricity fee management, grid investment, power supply quality, business expansion reporting, asset profit and human resources indicators; the grid operation data includes safety level, light load operation, heavy load operation and high loss operation indicators; the value creation construction data includes economic development collection, land resource collection, population resource collection and electricity customer collection.
[0035] In S2, the differentiated statistical collection template for domestic and foreign distribution network construction established in S1 is used to classify and collect the development history of domestic and foreign distribution networks and the basic data of domestic and foreign distribution networks, including the following contents:
[0036] Combining the development history of distribution networks at home and abroad, we then collected big data on the grid structure, distribution automation and power supply reliability of Tokyo, Singapore, Paris, Shanghai, Xiamen and Suzhou. We then processed the collected data to remove duplicate and redundant data, and then classified the remaining data and filled it into the corresponding areas of the above Excel table.
[0037] According to the investigation, the current status of Tokyo's distribution network construction is as follows: the power supply area is 715 square kilometers, the maximum load in 2015 was 15.24 million kilowatts, the transmission and distribution line loss rate was below 5%, the medium-voltage distribution network mostly adopts a ring network structure and radial operation, the 6.6 kV overhead network adopts a six-segment three-connection method, the 6.6 kV cable network adopts a single-ring network connection method between stations, the distribution transformer adopts an amorphous alloy transformer and a small-capacity multi-point mode, and the low-voltage power grid adopts a grid power supply mode. In the mid-1980s, Tokyo achieved full coverage of distribution automation. The distribution automation solution mainly adopts a distributed / centralized hybrid method, and the fault location is distributed, relying on the cooperation of circuit breakers and switches to automatically complete the positioning on site, and then the main station uses remote control to restore power supply. During accident handling and normal maintenance, the operation time of load switches is greatly shortened. In 2015, the power supply reliability rate in Tokyo's core area reached 99.999%, and the average power outage time per household was 5 minutes. The rapid improvement stage of power supply reliability was in the 1980s, and it dropped rapidly from 98 minutes to 8 minutes within five years, and increased rapidly from less than "4 nines" (corresponding to a power outage time of 53 minutes) to close to "5 nines" (corresponding to a power outage time of 5 minutes).
[0038] The current status of Singapore's distribution network construction is as follows: Singapore's power supply area is about 714 square kilometers, with a maximum load of 6639MW in 2015. The distribution network is 22 kilovolts and below, using a complex lotus petal grid and a large number of high-tech equipment. It adopts a closed-loop operation mode, and the distribution network fully adopts differential protection to achieve fault isolation. The automation signal adopts cable shield layer carrier transmission. The distribution network management and support system implements professional centralized management of the distribution network, integrated operation of distribution network equipment operation and user services. Since 2007, Singapore's power supply reliability has reached 99.999%. In 2015, the power supply reliability rate reached 99.9999%, and the average power outage time per household was only 0.7 minutes. Singapore emphasizes the technical level and safety and reliability of power grid equipment, has first-class equipment and technical support, and uses generators and other non-stop operation methods to reduce user power outage time. At the same time, it implements maintenance strategies based on equipment status, extends maintenance cycles, and implements simultaneous maintenance of user-side and power equipment, greatly shortening planned maintenance time.
[0039] The current status of the construction of the Paris distribution network is as follows: the power supply area of the power grid in the core area of Paris is about 105 square kilometers. In 2015, the maximum power supply load reached 3 million kilowatts. The distribution network consists of three levels: 225 kV, 20 kV, and 380 / 220 V. It adopts the N-2 reliability standard. The high-voltage network adopts a double-ring network structure, and the medium-voltage network adopts a spindle-shaped grid structure. The power supply of the switchgear is "hand in hand" and has high reliability. The urban area of Paris is all cable lines, and the substations are fully buried or semi-buried, which is environmentally friendly and saves space resources, but the investment cost is high. The Paris urban distribution network emphasizes the reliability and design margin of the medium-voltage grid and primary equipment, but the level of automation and intelligence of the distribution network is relatively low. Fault indicator technology is mostly used, and there are a large number of old equipment in operation. In 2015, the power supply reliability rate in the core area of Paris was 99.995%, and the average power outage time per household was 21 minutes.
[0040] The current status of Shanghai's distribution network construction is: the power supply area is 6341km2, which is the area with the highest load density in China. Among them, the A+ and A-class areas are the core areas with a total area of 752km2. In 2019, Shanghai's full-caliber power supply reliability rate reached 99.9991%, and the average power outage time per household was 4.6 minutes.
[0041] The main gaps and shortcomings with advanced foreign cities are mainly reflected in the following points:
[0042] (1) The grid structure still needs to be continuously optimized and improved
[0043] Singapore, Paris and Tokyo have fully built their target grids and met the N-2 standard. The 110kV power grid in Shanghai's central urban area has not yet fully built its target chain structure grid. The 10kV load transfer capacity in some areas is insufficient and has not met the multi-connection requirements. In some areas, there is a single power source, and some transformers and lines still have heavy overload problems, which have not yet fully met the N-2 standard.
[0044] (2) Some equipment is not of high quality
[0045] Compared with world-class cities, especially Singapore's high-end equipment, Shanghai's equipment and technology level are relatively backward. Some distribution equipment and cables have been in operation for a long time. The quality of distribution network equipment is uneven and defects are frequent. The core area still has a non-low resistance grounding system, which makes it difficult to meet the safe operation requirements of the growing capacitive current.
[0046] (3) Uninterrupted power supply operations need to be further strengthened
[0047] Compared with Tokyo, there is still much room for improvement in the rate of non-stop operations in Shanghai's distribution network. Complex and comprehensive non-stop operations are not carried out in depth. Most of Shanghai's non-stop operations are simple operations. In 2017, Shanghai carried out 6,239 non-stop operations on 10 kV urban distribution networks, with a non-stop operation rate of 81.02%, improving power supply reliability by 0.063%. During the same period, Tokyo had 100% full coverage of non-stop operations and fully carried out bypass and other operations.
[0048] The development goals of Shanghai's distribution network are:
[0049] The construction of a world-class urban distribution network will be carried out in steps: the first year will be the stage of filling in the gaps, during which optimization and transformation of grid equipment will be carried out, distribution automation and intelligent construction will be promoted, with a focus on improving power supply reliability and power quality; the second year will be the stage of tackling tough problems and improvement, during which distribution automation construction will be deepened, new technologies will be promoted in an all-round way, new energy and distributed power sources will be fully absorbed, and intelligent coordinated interaction between source, grid and load will be realized, with a focus on improving the efficiency of smart services; the third year will be the stage of catching up with the first-class level, with management improvement, deepening the construction of the country's first intelligent distribution network technology center, promoting the construction of a smart power supply service system, completing the construction of a power supply service command center, and applying Internet+ and new technologies of "cloud, big data, and mobile Internet" to realize the operation and management of distribution networks in all regions, all businesses, and all processes, with a focus on improving the efficiency of operation and management; by the fourth year, Shanghai will have fully built a world-class urban distribution network characterized by "safety, reliability, economy, efficiency, greenness, and low carbon, and intelligent interaction."
[0050] The current status of Xiamen's distribution network construction is as follows: the city's land area is 1,699 square kilometers, with a permanent population of 3.94 million. There are 19 220kV substations, which surround the Xiamen sea area to form a trunk ring network and a local radiation structure. The island's power grid forms a "DC and AC" double-chain structure through four channels and eight loops. Ring networks are formed in their respective areas outside the island and are interconnected through connecting lines. There are 68 110kV substations, forming a power grid framework dominated by chain and double radiation.
[0051] The main gaps and shortcomings with advanced foreign cities are mainly reflected in the following points:
[0052] (1) The reliability of power supply is far behind that of world-class cities and domestic advanced cities
[0053] In 2018, the power supply reliability rate of Xiamen power grid A+ area was 99.9865%, and the average power outage time per household was 71.4 minutes. During the same period, the power supply reliability rate of Tokyo core area was 99.999%, and the average power outage time per household was 5 minutes. The power supply reliability still lags behind that of first-class international cities such as Singapore, Tokyo, and Paris. Planned power outages for maintenance accounted for 70%, and the low-voltage power supply reliability statistics were not achieved.
[0054] (2) The grid structure still needs to be continuously optimized and improved
[0055] Xiamen City has not yet fully built the target grid. The 110kV and 35kV power grids mainly adopt chain and radial structures. The 10kV overhead network is mainly composed of overhead single interconnection and multi-segment moderate interconnection. The 10kV cable network is mainly composed of switchgear and single ring network connection. Tokyo has fully built the target grid and reached the N-2 standard. The medium-voltage distribution network mostly adopts a ring network structure and radial operation. The distribution network structure in the core area of Tokyo is simple. The 6.6kV overhead network adopts a six-segment three-interconnection method, and the 6.6kV cable network adopts a single ring network connection method between stations.
[0056] (3) The level of some equipment needs to be further improved
[0057] Compared with world-class cities, distribution network equipment and automation terminal brands are diversified, and the average operating life of equipment is relatively short, basically within 15 years. Almost all distribution network equipment in Singapore and Paris is supplied by internationally renowned companies such as Alstom, Schneider, and Siemens, with an operating life of up to 30 years.
[0058] The development goals of Xiamen's distribution network are:
[0059] (1) Overall Objectives
[0060] Build a world-class urban distribution network that is "safe and reliable, high-quality and efficient, green and low-carbon, and intelligent and interactive", and fully realize a world-class urban distribution network with "ten hundred percent" as the benchmark, and the core elements such as power supply reliability, economic operation level, power quality, asset utilization efficiency, clean energy absorption capacity, and market competitiveness reach the international advanced level.
[0061] The “ten hundred percents” are 100% satisfaction of power supply capacity, 100% realization of N-1 of 110kV substations on Xiamen Island, 100% standardization of 10kV grid, 100% realization of N-1 of 10kV feeders, 100% completion of transformation of high-fault lines and heavily overloaded distribution transformers, 100% insulation of overhead lines, 100% restoration of power before emergency repairs for lifeline users, 100% absorption of clean energy, 100% coverage of distribution automation, and 100% coverage of status detection of distribution network main equipment.
[0062] (2) Construction objectives
[0063] Based on the overall goal, Xiamen City has proposed construction goals in four aspects: comprehensively improving the distribution network structure level, improving the technical level of distribution network equipment, improving the lean operation and maintenance level of the distribution network, and improving the intelligent interactive service level of the distribution network.
[0064] 1) Comprehensively improve the structure of distribution network
[0065] First, carry out special planning for distribution networks, implement the "grid and unitization" planning concept, complete the preparation of special planning reports for world-class urban distribution networks, and use planning to guide the construction and development of distribution networks. Second, improve the structure of distribution networks. According to the requirements of differentiated grid planning, build clear, orderly, simple and flexible target grids in different regions. The standardization rate of high-voltage grid structures reaches 95%, and the standardization rate of medium-voltage grid structures reaches 100%. Third, improve power supply capacity, optimize load distribution, form sufficient load transfer capacity, orderly adjust the power supply radius of medium-voltage distribution networks, improve the effective connection rate of grids, improve power supply capacity and adaptability of power grids, and build a balanced and reliable distribution network. Fourth, improve construction standards, build "one-step, shortest path, safe and reliable" power channels and sites, form a cooperative situation of "the government is responsible for cable trench construction, and the power company is responsible for obtaining cable funds", and increase the average capacity of distribution and transformation households.
[0066] 2) Improve the technical level of distribution network equipment
[0067] First, upgrade equipment technology. In the first year, we will fully complete the typhoon and lightning protection transformation of overhead lines, and the flood prevention and control of low-lying and underground distribution stations. In the second year, we will complete the transformation of all old switchgear with safety hazards, and the application rate of primary and secondary integrated equipment in new projects will be 100%. Second, we will improve equipment quality control, improve the technical standard system, improve construction standards, and improve the quality supervision system. In the third year, we will achieve 100% coverage of random inspections of 28 types of equipment and materials, establish a quality problem analysis mechanism for equipment in the distribution network, improve the application of supplier quality assessment, and achieve closed-loop control of equipment quality. Third, we will promote green energy conservation and new technologies. Based on the status of Xiamen's distribution network, we will select composite insulated crossarms, environmentally friendly gas insulated metal-enclosed switchgear, and S13 three-dimensional wound core distribution transformers as appropriate to carry out pilot applications of new technologies in applicable scenarios.
[0068] 3) Improve the lean operation and maintenance level of distribution networks
[0069] First, we will innovate the operation and maintenance model. In 2017, we will build a power supply service command center, achieve a 100% integration rate for distribution team operation and maintenance, and a 100% integration rate for marketing and distribution terminals. We will improve the grid-based emergency repair system and deepen the policy of “restore power before repairing”. The average time for emergency repairs to arrive at the scene will decrease by 10% year by year, and the time for medium-voltage emergency repairs will decrease by 15% year by year. Second, we will improve the level of economic operation and steadily improve the level of line loss management. By 2020, the qualified rate of 10kV branch line loss and voltage division line loss in A+ / A area will reach 100%, and the reliability assessment of the entire distribution network will be completed. Third, we will improve the ability to operate without power outages. In 2017, we will achieve a 100% coverage rate of live operation areas, a 98% rate of planned maintenance of overhead lines in 2020, and a 99% rate of non-stop operation for business expansion.
[0070] 4) Improve the level of intelligent interactive services in distribution networks
[0071] First, speed up the construction of distribution automation, and achieve 100% coverage of distribution automation in the whole city in 2017. In 2020, a new generation of intelligent distribution automation master station will be built, the online rate of distribution automation terminals will reach more than 97%, and the correct rate of FA action will reach 95%. Second, improve the level of informatization, the graphical topology connectivity rate of the production management system will reach 100%, and the distribution data will be 100% connected, enhance the full life cycle management effect of distribution network equipment, and the life span compliance rate of retired main equipment of the distribution network will reach more than 95%. The intelligent power supply service command platform will be built and put into operation. Third, intelligent operation and inspection will be carried out, and the "three remote" monitoring of important nodes, low-voltage switch monitoring of the substation area, environmental monitoring of important distribution station buildings, and monitoring of important cable channels will be fully realized to improve the observable and measurable level of the distribution network. Fourth, strengthen the interactive service system, 100% of distributed power sources will be fully consumed, and a 0.9-kilometer electric vehicle charging radius service circle will be built.
[0072] The current status of Suzhou's distribution network construction is as follows: ultra-high voltage AC / DC hybrid access as support, 500 kV as the backbone grid, 7 220 kV sub-grids operating in coordination, and 110 kV and below smart distribution networks developing in a coordinated manner. As of the end of 2019, Suzhou Power Grid had 545 substations of 35 kV and above (with a total substation capacity of 118,486 MVA), 23,821 10 (20) kV distribution stations (switch stations); 1,433 transmission lines of 35 kV and above (12,599 km), and 7,642 distribution lines of 10 (20) kV (51,907 km).
[0073] The main gaps and shortcomings with advanced foreign cities are mainly reflected in the following points:
[0074] (1) The level of power distribution automation needs to be improved
[0075] Suzhou's distribution automation has not achieved full coverage. Lines in areas above Class A use "three patrols" for distribution automation construction, and the level of practicality needs to be improved. Japan uses all on-site line automation, supports remote signaling and remote control, and more than 20% of switches have remote control functions. It also realizes GIS-based electrical equipment status information management and control, with a distribution automation coverage rate of 100%. Paris has a large number of fault indicators with communication functions, which only collect necessary data, and the fault information is sent directly to SCADA, achieving full automation coverage for all lines.
[0076] (2) The distribution network wiring structure is simple and its reliability needs to be further improved
[0077] Suzhou's distribution network cable lines mainly use double-ring networks and single-ring networks, and overhead lines mainly use multi-segment multi-connection and multi-segment single connection. Singapore's 22kV distribution network adopts petal-shaped connection centered on the substation and closed-loop operation. Backup connections (1-3) are set between the petals of different power substations and open-loop operation. Tokyo's 22kV is mostly cable network, mainly used in high-load density areas, using single-ring network, double-shot, and triple-shot 6kV power grids, multi-segment moderately connected cable networks, and multi-segment moderately connected overhead networks in suburbs. Paris' 20kV distribution network mainly adopts double-ring or triple-ring networks, and the reliability of the medium-voltage distribution network is relatively high.
[0078] 3. Development goals
[0079] (1) Overall Objectives
[0080] Implement the "three-step" strategic goal: take the lead in basically building a strong and intelligent power grid in the first year, build a comprehensive strong and intelligent power grid in the third year, and basically build a world-class urban distribution network that is "safe, reliable, high-quality, efficient, green, low-carbon, and intelligent and interactive" in the fifth year, fully support economic development and serve the society and people's livelihood, and accumulate experience and provide demonstration for Jiangsu Company's transformation of distribution network development mode and improvement of operation and management level.
[0081] (2) Construction objectives
[0082] Based on the overall goal, Suzhou City has proposed construction goals in four aspects: grid optimization, equipment transformation, lean operation and maintenance, and intelligent interaction.
[0083] 1) Grid optimization
[0084] By 2020, the "N-1" pass rate of high-voltage distribution networks in cities above Class C will be 100%, and the grid structure standardization rate will reach 98%. The "N-1" pass rate and grid structure standardization rate of medium-voltage distribution networks in cities above Class C will both reach 95%. The average power supply radius of medium-voltage distribution lines in A+, A, and B areas will not exceed 3 kilometers, and in other areas will not exceed 5 kilometers. The average power supply radius of low-voltage distribution lines in A+ and A areas will not exceed 150 meters, in Class B areas will not exceed 250 meters, in Class C areas will not exceed 400 meters, and in Class D areas will not exceed 500 meters.
[0085] 2) Equipment transformation
[0086] First, streamline equipment types and select equipment with mature technology, no (low) maintenance, low loss, and scalable functions to meet the requirements of intelligence, versatility, and durability. Second, optimize equipment sequences, carry out upgrades and renovations of existing equipment and construction of incremental distribution networks. Third, standardize equipment selection, strengthen the construction of equipment quality control system, and achieve full coverage of testing of main equipment and major components.
[0087] 3) Lean Operation and Maintenance
[0088] By 2020, the company's operation and maintenance indicators will reach world-class levels: 100% isolation of user faults, 100% coverage of non-stop operations, 100% coverage of mobile operations, 99.99% comprehensive voltage qualification rate, 10kV branch line loss rate below 4%, fault shutdown rate below 0.5 times / 100km / year, and power supply quality complaints below 0.02 times / 10,000 households.
[0089] 4) Intelligent interaction
[0090] First, to achieve full coverage of distribution automation system. By 2020, distribution automation coverage will be 100%, feeder automation in Class A+ areas will be 100%, remote control success rate will be no less than 98%, and line fault self-healing success rate will be 95%; second, to achieve full coverage of intelligent power supply service command system. The construction of intelligent power supply service command system will be completed in 2017, and the whole province will be covered in 2018. By 2020, mobile operation application will be 100% covered, and RFID identification of distribution network main equipment will be 100% covered; third, to achieve friendly interaction among "source, network and load". By 2020, 100% distributed power supply of new energy demonstration projects will be connected, 100% electricity will be consumed, and 100% power-on rate of electric vehicle charging and swapping stations and decentralized charging piles will be achieved; the customer repair positioning rate will be above 98%, and the automatic analysis rate and accuracy of power outage range will be above 98%.
[0091] S3 China's domestic and overseas power distribution network data analysis includes the following:
[0092] According to the information filled in the differentiated statistical table of domestic and foreign distribution network development and construction, the corresponding charts are generated, the key information of the basic data of the distribution network is extracted, and the differentiation model is constructed from top to bottom. A comparative analysis is conducted based on the current situation and the differences between domestic and foreign distribution networks. The differentiation model mainly compares and analyzes the direct factors of area, boundary, and number of power points from a horizontal perspective, and then draws them on the GIS layer through automatic drawing technology, giving different graphic features to different grids to intuitively reflect the differences. At the same time, a deeper comparative analysis is conducted on the horizontal factors of power supply range, power supply radius, power substation distribution, overall spatial distribution of regional loads, and distribution form of main corridors between substations, and the difference factors that affect the differentiation of domestic and foreign distribution networks are obtained.
[0093] In S4, the reasons for the existence of each factor and the negative impact coefficient of each factor on each city's distribution network are analyzed, and then the impact coefficients of all factors are compared with each other to obtain statistical results, and the construction plan of the urban distribution network is adjusted according to the statistical results.
[0094] The method for calculating the influence of differentiation factors in S4 includes the following:
[0095] After integrating and analyzing various differentiated data, some factors are split into controllable factors and uncontrollable factors. Then the controllable factors in the domestic data are run in the uncontrollable factors of the foreign data respectively, and then the controllable factors in the domestic data are run in the uncontrollable factors of the domestic data respectively, and a variety of different permutations and combinations of controllable and uncontrollable factors are obtained. By statistically analyzing these results, a set of optimal operating data is obtained, and then based on the hierarchical analysis method, the distribution network model constructed and the influence of various factors that affect the differentiation are quantified.
[0096] The differentiated analysis in S3 is based on the hierarchical analysis method. It constructs an energy efficiency evaluation index system based on the standard "GB31367 Guidelines for Energy Efficiency Evaluation of Medium and Low Voltage Distribution Networks", determines the weights of individual indicators, and then inputs the analyzed domestic and foreign distribution network information according to the scoring standards of each indicator in the relevant guidelines to obtain the final scoring results.
[0097] Controllable factors include distribution network development automation, distribution automation, power supply reliability, power supply mode and energy grid construction structure, while uncontrollable factors include user differences and environmental differences.
[0098] Finally, a few points should be explained: Although the present invention has been described in detail above with general descriptions and specific embodiments, on the basis of the present invention, the above embodiments are only used to illustrate the technical solution of the present invention, rather than to limit it; although the present invention has been described in detail with reference to the aforementioned embodiments, ordinary technicians in this field should understand that they can still modify the technical solutions recorded in the aforementioned embodiments, or replace some or all of the technical features therein with equivalents; and these modifications or replacements do not make the essence of the corresponding technical solutions deviate from the scope of the technical solutions of the embodiments of the present invention.
Claims
1. A differentiated statistical method for the development and construction of domestic and foreign distribution networks, characterized by: The following steps are involved: S1. Establish a differentiated statistical collection template for the development and construction of domestic and foreign distribution networks; S2. By using the differentiated statistical collection template for the construction of domestic and foreign distribution networks established in S1, the development history of domestic and foreign distribution networks and the basic data of domestic and foreign distribution networks are collected by classification; the establishment of the differentiated statistical collection template for the development and construction of domestic and foreign distribution networks in S1 includes the following contents: Create an Excel spreadsheet, which is divided into two major items: one is for domestic distribution network construction data collection, and the other is for foreign distribution network construction data collection. After the completion, save it as a differentiated statistical table for the development and construction of domestic and foreign distribution networks; The domestic distribution network construction data collection and foreign distribution network construction data collection both include development history collection, grid structure collection, distribution automation collection, power supply reliability collection, energy grid construction collection, grid operation data collection, information support construction collection and value creation construction collection; The grid structure data includes the geographical connection diagram of the distribution network, line information, voltage level power substation information and planned grid information data; the energy grid construction data includes the number of transformers, the number of lines and the line length indicators; the value creation construction data includes the electricity sales volume, power loss, electricity purchase and sales fees, electricity fee management, grid investment, power supply quality, business expansion and registration, asset profit and human resources indicators; the grid operation data includes safety level, light load operation, heavy load operation and high loss operation indicators; the value creation construction data includes economic development data, land resource data, population resource data and electricity customer data; In S2, the development history of domestic and foreign distribution networks and basic data of domestic and foreign distribution networks are collected by classification using the differentiated statistical collection template for domestic and foreign distribution network construction established in S1, including the following contents: Combined with the development history of distribution networks at home and abroad, we then collected big data on the grid structure, distribution automation and power supply reliability of Tokyo, Singapore, Paris, Shanghai, Xiamen and Suzhou, and then processed the collected data to remove duplicate and redundant data. The remaining data was then classified and filled into the corresponding areas of the above Excel table. S3. Analyze the collected domestic and foreign distribution network data, extract and record the key factors that lead to construction differentiation; The S3 domestic and foreign power distribution network data analysis includes the following: Generate corresponding charts based on the information filled in the differentiated statistical tables of domestic and foreign distribution network development and construction, extract key information of distribution network basic data, build a differentiated model from top to bottom, and conduct comparative analysis based on the current situation and differences between domestic and foreign distribution networks. The differentiated model mainly compares and analyzes the direct factors of area, boundary, and number of power points from a horizontal perspective, and then draws on the GIS layer through automatic drawing technology, giving different graphic features to different grids to intuitively reflect the differences. At the same time, conduct a deeper comparative analysis of the horizontal factors of power supply range, power supply radius, power substation distribution, overall spatial distribution of regional loads, and distribution of main corridors between substations, and obtain the differential factors that affect the differentiation of domestic and foreign distribution networks. The analysis in S3 is based on the analytic hierarchy process, and the energy efficiency evaluation index system is constructed based on the standard "GB / T31367-2015 Guidelines for Energy Efficiency Evaluation of Medium and Low Voltage Distribution Networks", and the weight of each index is determined. Then, according to the scoring standards of each index in the relevant guidelines, the analyzed domestic and foreign distribution network information is input to obtain the final scoring result; S4. Classify the key factors that lead to construction differentiation, and match and operate each key factor by splitting and integrating. First, use a scientific and reasonable model to quantify the influence of each factor that affects differentiation, then analyze the reasons for the existence of each factor, and adjust the subsequent construction plan of the distribution network accordingly.
2. According to claim 1, a differentiated statistical method for the development and construction of domestic and foreign distribution networks is characterized by: In S4, it is necessary to analyze the reasons for the existence of each factor and the negative impact coefficient of each factor on each city distribution network, and then compare the impact coefficients of all factors to obtain statistical results, and adjust the construction plan of the city distribution network according to the statistical results.
3. According to claim 1, a differentiated statistical method for the development and construction of domestic and foreign distribution networks is characterized by: The S4 includes the following: After integrating and analyzing various differentiated data, some factors are split into controllable factors and uncontrollable factors. Then, the controllable factors in the domestic data are respectively run in the uncontrollable factors of the foreign data, and then the controllable factors in the domestic data are respectively run in the uncontrollable factors of the domestic data, to obtain a variety of different permutations and combinations of controllable and uncontrollable factors. By statistically analyzing these results, a set of optimal operating data is obtained. Then, based on the hierarchical analysis method, the constructed distribution network model and the influence of various factors that quantify the impact of differentiation, the reasons for the existence of each factor are analyzed.
4. A differentiated statistical method for the development and construction of domestic and foreign distribution networks according to claim 3, characterized in that: The controllable factors include distribution network development automation, distribution automation, power supply reliability, power supply mode and energy grid construction structure, and the uncontrollable factors include user differences and environmental differences.