Full membrane wall waste heat boiler
Through the full-film wall structure, the problems of strong smoke bonding and complex construction are solved, and the smoke temperature reduction and waste heat are effectively utilized, the construction process is simplified and the smoke dust is improved. Collection efficiency.
Patent Information
- Application Number
- CN202010466562.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2020-05-28
- Publication Date
- 2024-11-12
- Estimated Expiration
- 2040-05-28
AI Technical Summary
When handling high-temperature flue gas, existing waste heat boilers have strong smoke bonding and are prone to block the flue. They are complex in construction, have long cycles, many equipment and components, and are strictly supervised, making it difficult to effectively reduce cooling and utilize waste heat.
The waste heat boiler with a full film wall structure divides multiple stroke spaces through the film wall, so that the flue gas can be turned at least 180 degrees during the flow process, increasing the stroke, facilitating the smoke and dust settlement, and passing through the membrane wall and steam drum The overall structure reduces the need for brackets and simplifies on-site construction.
Effectively prevent flue blockage, improve smoke collection efficiency, simplify the construction process, reduce investment and land occupation, and achieve effective reduction of flue gas temperature and utilization of waste heat.
Smart Images

Figure CN113739585B_ABST
Abstract
Description
Technical Field
[0001] The present invention relates to the technical field of waste heat boilers, and in particular to a membrane wall waste heat boiler for cooling high-temperature flue gas and utilizing waste heat. Background Art
[0002] As the equipment for cooling high-temperature flue gas and utilizing waste heat in the main process, the waste heat boiler is usually composed of steel structure, steam drum, heat exchange surface, lower drum, riser, downcomer, ash hopper and other parts. The system is complex, with many equipment components, difficult on-site construction and a long construction period.
[0003] Generally, waste heat boilers are divided into high-temperature waste heat boilers and medium- and low-temperature waste heat boilers according to the inlet flue gas temperature. As special equipment, especially the pressure-bearing parts, the manufacturing, installation and welding quality requirements are high, and the supervision is also very strict.
[0004] For example, for zinc oxide rotary kiln oxygen, although the flue gas temperature is only 600-700℃, the dust in the flue gas is very large, with a content of up to 50-100g / m 3 , contains some zinc oxide dust, a small amount of incompletely oxidized zinc powder needs to be further oxidized, the dust contains low melting point alkali salts NaCL and KCL up to 30%, and the dust has very strong adhesion.
[0005] In the current process route, there is generally no flue cooling device after the rotary kiln, and only an air cooling device is used. Since the low-melting-point alkali salts NaCl and KCl in the dust are not completely cooled above 500°C, they have strong adhesion and can easily adhere to the flue and block it.
[0006] Although there are a small number of waste heat boilers used for cooling, their furnace walls are masonry structures and are also prone to adhesion. Summary of the invention
[0007] The object of the present invention is to provide a multi-pass integral full-membrane wall waste heat boiler suitable for high-temperature flue gas with high smoke temperature, smoke gas requiring reoxidation, large smoke dust volume and strong dust viscosity.
[0008] To achieve the above-mentioned purpose, the present invention provides a full membrane wall waste heat boiler, comprising a membrane wall forming a furnace body, a steam drum located at the top of the furnace body, an ash hopper located at the bottom of the furnace body, and a downcomer and an upcomer connecting the steam drum and the membrane wall; the membrane wall comprises a front wall membrane wall, a rear wall membrane wall, two side wall membrane walls and at least one partition wall membrane wall located inside the furnace body; the front wall membrane wall is provided with a smoke inlet, and the rear wall membrane wall is provided with a smoke outlet; the partition wall membrane wall divides the inner cavity of the furnace body into two or more travel spaces that allow the smoke to make at least one 180-degree turn during the process of flowing from the smoke inlet to the smoke outlet.
[0009] Preferably, the upper edges of the membrane walls on both sides are bent toward the direction where the steam drum is located and then connected to the steam drum to form the top of the furnace body, and the pipes thereof are connected to the steam drum.
[0010] Preferably, for the partition membrane wall where the smoke channel is located below, the height of the lower connecting pipe is gradually reduced so that the flow area of the smoke channel is gradually reduced.
[0011] Preferably, a partition membrane wall is provided inside the furnace body, and the partition membrane wall divides the inner cavity of the furnace body into two travel spaces, and the smoke passages of the first travel space and the second travel space are located below the partition membrane wall;
[0012] Alternatively, at least two partition membrane walls are provided inside the furnace body, and the partition membrane walls divide the inner cavity of the furnace body into multiple travel spaces, wherein the smoke passages of the first travel space and the second travel space are located below the first partition membrane wall, and the smoke passages between the remaining travel spaces are alternately located above and below each partition membrane wall.
[0013] Preferably, the front end wall membrane wall, the rear end wall membrane wall, and the partition wall membrane wall are respectively provided with upper connecting pipes; the upper connecting pipes are provided with multiple riser pipes connected to the steam drum, wherein the plane area where the riser pipes of the front end wall membrane wall, the rear end wall membrane wall, and the partition wall membrane wall where the flue gas channel is located are located is closed by a sealing plate.
[0014] Preferably, the riser first extends upward and then communicates with the steam drum in a form of gradually converging upward.
[0015] Preferably, the upper connecting pipes of the front wall membrane wall and the rear wall membrane wall respectively include a first upper connecting pipe located below the opening area and a second upper connecting pipe located above the opening area, the first upper connecting pipe and the second upper connecting pipe are connected through a plurality of vertical pipes located in the opening area, and the second upper connecting pipe is connected to the steam drum through a rising pipe.
[0016] Preferably, the downcomer includes a downcomer main pipe located at both ends of the steam drum, and a downcomer branch pipe connected to the downcomer main pipe; the downcomer branches of the front end membrane wall, the rear end membrane wall, the two side membrane walls and the partition membrane wall are respectively connected to their lower connecting pipes.
[0017] Preferably, the descending main pipe is arranged vertically, and the descending branches of the front wall membrane wall, the rear wall membrane wall, the two side wall membrane walls and the partition wall membrane wall are symmetrically distributed left and right with the descending branch pipe as the center, and each of the descending branch pipes is connected to the corresponding lower connecting pipe after being bent.
[0018] Preferably, the descending branches of the front membrane wall, the rear membrane wall, and the membrane walls on both sides are respectively bent downward at the ends of the furnace body and are connected to the corresponding lower connecting pipes.
[0019] Preferably, the descending branch pipe of the partition membrane wall is first bent downward at the end of the furnace body, then bent toward the corresponding lower connecting pipe of the partition membrane wall, and then extended from the outside of the two side membrane walls, and then connected with the lower connecting pipe of the partition membrane wall.
[0020] Preferably, the lower connecting pipes of the membrane walls on both sides are provided with a plurality of support components distributed at intervals, so as to fix the boiler on the civil engineering platform through the support components.
[0021] Preferably, the membrane walls on both sides are provided with adjustment detection holes and / or manholes corresponding to each travel space.
[0022] The full membrane wall waste heat boiler provided by the present invention adopts a full membrane wall structure, and its furnace body and internal stroke partition components all adopt membrane walls. During operation, the flue gas enters the furnace body from the flue gas inlet, flows along the path defined by the stroke space, and is discharged from the flue gas outlet. During the flow of the flue gas, the smoke dust is not easy to adhere, which prevents the flue from being blocked, and can effectively reduce the flue gas temperature and utilize the waste heat. Moreover, since the flue gas makes at least one 180-degree turn during the flow, the stroke can be doubled or multiplied, which facilitates the sedimentation of the smoke dust and improves the smoke dust collection efficiency. In addition, from a structural point of view, the membrane wall forms the main part of the furnace body. The steam drum is located on the top of the furnace body and is supported by the membrane wall. The steam drum and the membrane wall together constitute the furnace body. Components such as the downcomer can also effectively support the furnace body. The membrane wall, steam drum and various pipelines that make up the furnace body are connected to each other to form an integral structure. There is no need to set up conventional boiler supports and other components. Except for the ash hopper that can be connected on site, all other components can be manufactured, installed and tested by the boiler factory and then transported to the site as a whole. The on-site construction workload is small, and the boiler structure is simple and compact, with low investment and small footprint.
[0023] In a preferred embodiment, the membrane walls on both sides are provided with adjustment detection holes and / or manholes corresponding to each travel space. By providing multiple adjustment detection holes in the high temperature section of the boiler, air can be naturally replenished to re-oxidize the unoxidized dust such as zinc powder. BRIEF DESCRIPTION OF THE DRAWINGS
[0024] Figure 1 A schematic diagram of the main structure of a full-membrane wall waste heat boiler disclosed in an embodiment of the present invention;
[0025] Figure 2 for Figure 1 The internal process diagram of the full membrane wall waste heat boiler is shown;
[0026] Figure 3 It is a structural schematic diagram of the front wall membrane type wall;
[0027] Figure 4 is a schematic structural diagram of the first partition membrane wall;
[0028] Figure 5 is a schematic structural diagram of the second partition membrane wall;
[0029] Figure 6 It is a structural schematic diagram of the third partition membrane wall;
[0030] Figure 7 It is a structural schematic diagram of the rear end membrane wall;
[0031] Figure 8 is a schematic cross-sectional view of a furnace body;
[0032] Fig. 9 for Figure 8 A partial enlarged view of the middle A area;
[0033] Fig.10 for Figure 8 A partial enlarged view of the B area;
[0034] Fig.11 for Figure 8 A partial enlarged view of area C in the middle.
[0035] In the figure:
[0036] 1. Steam drum 2. Membrane wall 2-1. Pipeline 2-2. Flat steel 3. Downcomer 4. Ash hopper 5. Front wall membrane wall 6. Rear wall membrane wall 7. Both side walls membrane wall 8. First partition wall membrane wall 9. Second partition wall membrane wall 10. Third partition wall membrane wall 11. Flue gas inlet 12. Flue gas outlet 13-1. Downcomer main pipe 13-2. Downcomer branch pipe 14. Lower connecting pipe 15. Support component 16. Civil engineering platform 17. Adjustment detection hole 18. Manhole 19. Upper connecting pipe 19-1. First upper connecting pipe 19-2. Second upper connecting pipe 20. Vertical pipe 21. Rising pipe 22. Sealing plate DETAILED DESCRIPTION
[0037] In order to enable those skilled in the art to better understand the solution of the present invention, the present invention is further described in detail below in conjunction with the accompanying drawings and specific implementation methods.
[0038] In this article, the terms "upper, lower, inside, outside" and the like are established based on the positional relationships shown in the drawings. The corresponding positional relationships may also change depending on the drawings, and therefore cannot be understood as absolute limitations on the scope of protection; moreover, relational terms such as "first" and "second" and the like are merely used to distinguish one component from another with the same name, and do not necessarily require or imply any actual relationship or order between these components.
[0039] Please refer to Figure 1 , Figure 2 , Figure 1 A schematic diagram of the main structure of a full-membrane wall waste heat boiler disclosed in an embodiment of the present invention; Figure 2 for Figure 1 The internal process diagram of the full membrane wall waste heat boiler is shown.
[0040] As shown in the figure, in a specific embodiment, the waste heat boiler provided by the present invention is a full membrane wall structure, which is mainly composed of four parts: a steam drum 1, a membrane wall 2, a downcomer 3, and an ash hopper 4. The membrane wall 2 and the steam drum 1 together form the furnace body of the waste heat boiler, the steam drum 1 is located at the top of the furnace body, the ash hopper 4 is located at the bottom of the furnace body, and the downcomer 3 is used to connect the two ends of the steam drum 1 with the membrane wall 2.
[0041] Specifically, the membrane wall 2 includes a front wall membrane wall 5, a rear wall membrane wall 6, two side wall membrane walls 7, and a first partition wall membrane wall 8, a second partition wall membrane wall 9, and a third partition wall membrane wall 10 located inside the furnace body. The membrane wall 2 is a tube panel formed by welding a plurality of pipes 2-1 and flat steels 2-2 located between the pipes (see Fig.10 ), usually, its pipes 2-1 are parallel to each other and spaced a certain distance apart, and the pipes 2-1 are connected to each other by flat steel 2-2. When in use, cooling water is introduced into the pipe 2-1, so it is also called a water-cooled wall. The heat absorbed by the pipe 2-1 and the flat steel 2-2 can be quickly given to the cooling water inside. The cooling water inside the pipe 2-1 automatically rises after being heated, and enters the steam drum 1 through the riser 21. The cooling water with a lower temperature in the steam drum 1 will automatically drop to the bottom of the steam drum, and then enter the lower connecting pipe of the membrane wall 2 from the downcomer 3 at the bottom of the steam drum, and enter the various pipes 2-1 of the membrane wall itself from the lower connecting pipe 14 to absorb heat again. Such a cycle operation can continuously cool the flue gas in the furnace body. At the same time, since the cooling water reaches a certain high temperature, it can be used for other purposes to realize the reuse of the waste heat of the flue gas.
[0042] The entire furnace body is roughly in the shape of a hollow rectangular parallelepiped. The upper edges of the membrane walls 7 on both sides are bent toward the direction of the steam drum 1 located in the central position and then connected to the steam drum 1 to form a "human" shaped furnace top. The pipes 2-1 of the membrane walls 7 on both sides are directly connected to the steam drum 1, and the flat steels 2-2 of the membrane walls 7 on both sides are directly connected to the steam drum 1.
[0043] A rectangular flue gas inlet 11 is provided in the upper half of the front wall membrane wall 5, and a rectangular flue gas outlet 12 is provided in the upper half of the rear wall membrane wall 6; the first partition membrane wall 8, the second partition membrane wall 9 and the third partition membrane wall 10 are parallel to each other and spaced a certain distance apart, wherein the upper part of the first partition membrane wall 8 is sealedly connected to the inner wall of the furnace body, and the lower part is spaced appropriately from the bottom of the furnace body to form a flue gas passage, allowing high-temperature flue gas to pass through; the upper part of the second partition membrane wall 9 is spaced appropriately from the inner wall of the furnace body to form a flue gas passage, allowing high-temperature flue gas to pass through, and the lower part extends all the way to the bottom of the furnace body; the upper part of the third partition membrane wall 10 is sealedly connected to the inner wall of the furnace body, and the lower part is spaced appropriately from the bottom of the furnace body to form a flue gas passage, allowing high-temperature flue gas to pass through.
[0044] In this way, three partition membrane walls divide the inner cavity of the furnace body into four independent cavities, and the flue gas can reciprocate four strokes inside the boiler. In the process of flowing from the flue gas inlet to the flue gas outlet, the flue gas makes the first 90-degree turn at the flue gas inlet, the first 180-degree turn between the first stroke and the second stroke, the second 180-degree turn between the second stroke and the third stroke, the third 180-degree turn between the third stroke and the fourth stroke, and the second 90-degree turn at the flue gas outlet, a total of two 90-degree and three 180-degree turns, and the flue gas flow path is similar to a continuous "S" shape, thus having a longer stroke.
[0045] The downcomer 3 includes a main downcomer 13-1 located at both ends of the steam drum 1, and a downcomer branch 13-2 connected to the main downcomer 13-1. The front end membrane wall 5, the rear end membrane wall 6, the two side membrane walls 7 and the downcomer branch 13-2 of each partition membrane wall are respectively connected to their lower connecting pipes 14.
[0046] The descending main pipe 13-1 is arranged vertically, and the descending branches 13-2 of the front wall membrane wall 5, the rear wall membrane wall 6, the two side wall membrane walls 7 and the partition membrane wall are respectively symmetrically distributed left and right with the descending main pipe 13-1 as the center, and each descending branch pipe 13-2 is connected to the corresponding lower connecting pipe 14 after being bent.
[0047] Specifically, the two descending branch pipes 13-2 of the front wall membrane wall 5 are bent downward 90 degrees at the front end of the furnace body, and then extend vertically downward. After reaching the bottom, they are bent 90 degrees in the direction perpendicular to the front wall membrane wall 5, and are connected to the two ends of the lower connecting pipe 14 of the front wall membrane wall 5.
[0048] The two descending branch pipes 13-2 of the rear end wall membrane wall 6 are bent downward 90 degrees at the rear end of the furnace body, and then extend vertically downward. After reaching the bottom, they are bent 90 degrees in the direction perpendicular to the rear end wall membrane wall 6, and are connected to the two ends of the lower connecting pipe 14 of the rear end wall membrane wall.
[0049] The lower connecting pipe 14 of the membrane walls 7 on both sides is divided into two parts, front and back. Taking the lower connecting pipe 14 whose length corresponds to the first stroke and the second stroke as an example, its two descending branch pipes 13-2 are respectively bent downward 90 degrees at the front end of the furnace body, and then extend vertically downward. After reaching the bottom, they are bent 90 degrees in the direction perpendicular to the front end membrane wall 5, and are connected with one end of the lower connecting pipe 14. The other end of this lower connecting pipe 14 is closed. It can be seen from the figure that the connection mode between the lower connecting pipe 14 and the descending pipe 3 corresponding to the third stroke and the fourth stroke of the membrane walls 7 on both sides is largely symmetrical with the connection mode between the lower connecting pipe 14 and the descending pipe 3 corresponding to the first stroke and the second stroke, and will not be described again.
[0050] The two descending branch pipes 13-2 of the first partition membrane wall 8 are bent downward by 90 degrees at the front end of the furnace body, and then extend vertically downward. After reaching the height of the lower connecting pipe 14 of the first partition membrane wall 8, they are bent 90 degrees in the direction perpendicular to the front wall membrane wall 5, and then extend backward from the outside of the two side wall membrane walls 7. After reaching the position of the lower connecting pipe 14 of the first partition membrane wall 8, they are bent 90 degrees toward the inside of the furnace body and connected with the two ends of the lower connecting pipe 14 of the first partition membrane wall 8.
[0051] The two descending branch pipes 13-2 of the second partition membrane wall 9 are bent downward 90 degrees at the rear end of the furnace body, and then extend vertically downward. After reaching the height of the lower connecting pipe 14 of the second partition membrane wall 9, they are bent 90 degrees in the direction perpendicular to the rear end wall membrane wall 6, and then extend forward from the outside of the two side wall membrane walls 7. After reaching the position of the lower connecting pipe 14 of the second partition membrane wall 9, they are bent 90 degrees toward the inside of the furnace body and connected with the two ends of the lower connecting pipe 14 of the second partition membrane wall 9.
[0052] The two descending branches 13-2 of the third partition membrane wall 10 are bent 90 degrees downward at the rear end of the furnace body, and then extend vertically downward. After reaching the height of the lower connecting pipe 14 of the second partition membrane wall 10, they are bent 90 degrees in a direction perpendicular to the rear end wall membrane wall 6, and then extend forward from the outside of the two side wall membrane walls 7. After reaching the position of the lower connecting pipe 14 of the third partition membrane wall 10, they are bent 90 degrees inside the furnace body and connected with the two ends of the lower connecting pipe 14 of the third partition membrane wall 10. Of course, the front half of the two descending branches of the second partition membrane wall 9 and the third partition membrane wall 10 can also share the same branch pipe, and after the second 90-degree bend, they are divided into two paths and connected with their respective lower connecting pipes 14.
[0053] When viewed from the side, the main descending pipes 13-1 and the descending branch pipes 13-2 located at the front and rear ends of the furnace body are generally located in the same plane. When viewed from the front or rear ends, the descending branch pipes 13-2 located on both sides of the furnace body are also generally located in the same plane.
[0054] The boiler as a whole adopts a vertical support structure, and the lower connecting pipes 14 of the membrane walls 7 on both sides are provided with a plurality of support components 15 distributed at intervals, and the plurality of support components 15 are directly fixed on the civil engineering platform 16.
[0055] In addition, the membrane walls 7 on both sides are provided with adjustment detection holes 17 and manholes 18 corresponding to the first stroke, the second stroke, and the third stroke. Taking the first stroke as an example, two adjustment detection holes 17 and one manhole 18 are provided on both sides. In the height direction, one of the adjustment detection holes 17 is located at an upper position, and the other adjustment detection hole 17 is located at a lower position. The manhole 18 is located near the bottom of the furnace body, and its size is larger than the two adjustment detection holes 17. The adjustment detection holes 17 and the manhole 18 are usually in a closed state and can be opened when needed. By setting a plurality of adjustment detection holes 17 in the high-temperature section of the boiler, air can be naturally replenished to re-oxidize the unoxidized dust such as zinc powder. The manhole 18 can allow staff to enter the furnace body for inspection, maintenance and other operations.
[0056] The specific structures of the front wall membrane wall 5, the first partition wall membrane wall 8, the second partition wall membrane wall 9, the third partition wall membrane wall 10 and the rear wall membrane wall 6 are described in more detail below.
[0057] like Figure 3As shown, the front end wall membrane wall 5 is provided with an upper connecting pipe 19, and the upper connecting pipe 19 includes a first upper connecting pipe 19-1 located below the opening area and a second upper connecting pipe 19-2 located above the opening area. The first upper connecting pipe 19-1 is connected to the second upper connecting pipe 19-2 through a plurality of vertical pipes 20 located in the opening area. The upper ends of the membrane wall pipes 2-1 on both sides of the opening area are connected to the second upper connecting pipe 19-2, and the lower ends are connected to the first upper connecting pipe 19-1. The second upper connecting pipe 19-2 is connected to the steam drum 1 through the rising pipe 21. The rising pipe 21 first extends upward in the "human" shaped area, and then is connected to the bottom of the steam drum 1 in the form of gradually gathering upward. The plane area where the rising pipe 21 is located is closed by a sealing plate 22 ( Figure 1 In order to clearly show the connection relationship between the riser 21 and the downcomer 3 and the steam drum 1, some sealing plates are not shown. The sealing plate 22 is marked. A steel plate can be generally used as the sealing plate 22 . The sealing plate 22 can transfer heat to the riser 21 .
[0058] like Figure 4 As shown, the first partition membrane wall 8 is provided with an upper connecting pipe 19, the lower end of the membrane wall pipe 2-1 is connected to the lower connecting pipe 14, and the upper end is connected to the upper connecting pipe 19, the upper connecting pipe 19 is connected to the steam drum 1 through the riser 21, the riser 21 first extends upward in the "human" shaped area, and then is connected to the bottom of the steam drum in the form of gradually converging upward, the plane area where the riser 21 is located is closed by the sealing plate 22, and an appropriate distance is left between the lower connecting pipe 14 and the bottom of the furnace body to form a flue gas channel.
[0059] like Figure 5 As shown, the second partition membrane wall 9 is provided with an upper connecting pipe 19, the lower end of the membrane wall pipe 2-1 of which is connected to the lower connecting pipe 14, and the upper end is connected to the upper connecting pipe 19. The upper connecting pipe 19 is connected to the steam drum 1 through the riser 21. The riser 21 first extends upward for a long distance, and then is connected to the bottom of the steam drum 1 in the form of gradually converging upward in the "human" shaped area. The plane area where the riser 21 is located is not completely closed by the sealing plate 22 to form a flue gas channel. Only the sealing plates 22 are partially provided on both sides to control the flow area of the flue gas through holes. The lower connecting pipe 14 is located at the bottom of the furnace body to prevent the flue gas from passing through the lower part of the second partition membrane wall 9.
[0060] like Figure 6As shown, the third partition membrane wall 10 is provided with an upper connecting pipe 19, the lower end of the membrane wall pipe 2-1 is connected to the lower connecting pipe 14, and the upper end is connected to the upper connecting pipe 19, the upper connecting pipe 19 is connected to the steam drum 1 through the riser 21, the riser 21 first extends upward in the "human" shaped area, and then is connected to the bottom of the steam drum 1 in the form of gradually converging upward, the plane area where the riser 21 is located is closed by the sealing plate 22, and an appropriate distance is left between the lower connecting pipe 14 and the bottom of the furnace body to form a flue gas channel.
[0061] The structure of the third partition membrane wall 10 is substantially the same as that of the first partition membrane wall 8, except that the height of the lower connecting pipe 14 of the third partition membrane wall 10 is lower than that of the lower connecting pipe 14 of the first partition membrane wall 8, so as to reduce the flow area of the flue gas passage. On the one hand, because the flue gas temperature at the rear of the boiler drops, the flue gas volume under working condition will be reduced, and on the other hand, the flue gas flow rate can be increased to enhance heat transfer.
[0062] like Figure 7 As shown, the rear end wall membrane wall 6 is provided with an upper connecting pipe 19, and the upper connecting pipe 19 includes a first upper connecting pipe 19-1 located below the opening area and a second upper connecting pipe 19-2 located above the opening area. The first upper connecting pipe 19-1 is connected to the second upper connecting pipe 19-2 through a plurality of vertical pipes 20 located in the opening area. The upper ends of the membrane wall pipes 2-1 on both sides of the opening area are connected to the second upper connecting pipe 19-2, and the lower ends are connected to the first upper connecting pipe 19-1. The second upper connecting pipe 19-2 is connected to the steam drum 1 through a riser 21. The riser 21 first extends upward in the "human" shaped area, and then is connected to the bottom of the steam drum 1 in the form of gradually converging upward. The plane area where the riser 21 is located is closed by a sealing plate 22, and its structure is substantially the same as that of the front end wall membrane wall 5.
[0063] Please refer to Figure 8 , Fig. 9 , Fig.10 , Fig.11 , Figure 8 is a schematic cross-sectional view of a furnace body; Fig. 9 for Figure 8 A partial enlarged view of the middle A area; Fig.10 for Figure 8 A partial enlarged view of the B area; Fig.11 for Figure 8 A partial enlarged view of area C in the middle.
[0064] As shown in the figure, the first partition membrane wall 8, the second partition membrane wall 9 and the third partition membrane wall 10 divide the inner cavity of the furnace body into four independent cavities. The membrane wall 2 is a tube screen welded by a plurality of pipes 2-1 and flat steels 2-2 located between the pipes. The widths of the first partition membrane wall 8, the second partition membrane wall 9 and the third partition membrane wall 10 are slightly smaller than the width of the furnace body. The side wall membrane walls 7 are discontinuously divided into four parts in the length direction. The two ends of each partition membrane wall are respectively connected to the ends of the segmented side wall membrane walls 7 through "V"-shaped flat steels 2-2. The side wall membrane walls 7 are connected to the front end wall membrane wall 5 and the rear end wall membrane wall 6 through oblique flat steels 2-2, thereby forming a closed structure on all sides.
[0065] When the boiler is running, the high-temperature flue gas enters the first stroke of the waste heat boiler from the flue gas inlet 11 of the front wall membrane wall 5; the flue gas runs downward, crosses through the flue gas channel between the ash hopper 4 and the first partition wall membrane wall 8, and enters the second stroke of the waste heat boiler upward; then crosses through the upper flue gas channel of the second partition wall membrane wall 9, and enters the third stroke of the waste heat boiler downward; then crosses through the flue gas channel between the ash hopper 4 and the third partition wall membrane wall 10, and enters the fourth stroke of the waste heat boiler upward; finally, it leaves the waste heat boiler through the flue gas outlet 12 of the rear wall membrane wall 6.
[0066] During the return process of the flue gas in the waste heat boiler, the flue gas temperature gradually decreases, and the large particles of dust in the flue gas will settle into the ash hopper 4 and be discharged from the ash discharge port at the bottom of the ash hopper 4.
[0067] In order to effectively enhance the emission of large dust particles, the flue gas operating flow rate is controlled below 4m / s during the first and second strokes, and is controlled at around 7m / s during the third and fourth strokes.
[0068] The above embodiments are only preferred solutions of the present invention and are not limited thereto. On this basis, targeted adjustments can be made according to actual needs to obtain different implementation methods. For example, the number of strokes is determined comprehensively according to the process temperature reduction parameter requirements and the on-site configuration conditions. Two strokes, three strokes, five strokes or even more strokes can be set. Since there are many possible implementation methods, they will not be explained one by one here.
[0069] Since the flue gas makes at least one 180-degree turn during its flow, the travel distance can be doubled or multiplied, which facilitates the settling of smoke and improves the efficiency of smoke collection. In addition, from a structural point of view, the membrane wall 2 forms the main part of the furnace body, the drum 1 is located at the top of the furnace body and is supported by the membrane wall 2. The drum 1 and the membrane wall 2 together constitute the furnace body, and the downcomer 3 and the riser 21 and other components can also effectively support the furnace body. The membrane wall 2, the drum 1 and various pipelines that constitute the furnace body are connected to each other to form an integral structure. There is no need to set up conventional boiler brackets and other components. Except for the ash hopper 4 that can be docked on site, all can be manufactured, installed and tested by the boiler factory and then transported to the site as a whole. The on-site construction is small, and the boiler structure is simple and compact, with low investment, which can significantly save floor space.
[0070] The full membrane wall waste heat boiler provided by the present invention is introduced in detail above. Specific examples are used in this article to illustrate the principle and implementation of the present invention. The description of the above embodiments is only used to help understand the core idea of the present invention. It should be pointed out that for ordinary technicians in this technical field, without departing from the principle of the present invention, several improvements and modifications can be made to the present invention, and these improvements and modifications also fall within the scope of protection of the claims of the present invention.
Claims
1. Full membrane wall waste heat boiler, It is characterized in that The invention comprises a membrane wall (2) for forming a furnace body, a steam drum (1) located at the top of the furnace body, an ash hopper (4) located at the bottom of the furnace body, and a downcomer (3) and an upcomer (21) connecting the steam drum (1) and the membrane wall (2); the membrane wall (2) comprises a front wall membrane wall (5), a rear wall membrane wall (6), two side wall membrane walls (7), and at least one partition wall membrane wall located inside the furnace body; the front wall membrane wall (5) is provided with a smoke inlet (11), and the rear wall membrane wall (6) is provided with a smoke outlet (12); the partition wall membrane wall divides the furnace body cavity into two or more travel spaces so that the smoke makes at least one 180-degree turn during the process of flowing from the smoke inlet to the smoke outlet; The length direction of the steam drum extends from one end of the flue gas inlet to one end of the flue gas outlet. The upper edges of the two side wall membrane walls (7) are bent in the direction of the steam drum (1) and then connected to the steam drum (1) to form the top of the furnace body. The pipeline (2-1) is connected to the steam drum (1). The front wall membrane wall (5), the rear wall membrane wall (6), and the partition wall membrane wall are respectively provided with upper connecting pipes (19). The upper connecting pipe (19) is provided with a plurality of rising pipes (21) connected to the steam drum (1), wherein the plane area where the rising pipes (21) of the front wall membrane wall (5), the rear wall membrane wall (6), and the partition wall membrane wall with the flue gas passage located below are located is closed by a sealing plate (22), and the rising pipes (21) first extend upward and then are connected to the steam drum (1) in the form of gradually converging upward.
2. The full membrane wall waste heat boiler according to claim 1, It is characterized in that For the partition membrane wall with the smoke passage located below, the height of the lower connecting pipe (14) is gradually reduced, so that the flow area of the smoke passage is gradually reduced.
3. The full membrane wall waste heat boiler according to claim 1, It is characterized in that A partition membrane wall is provided inside the furnace body, and the partition membrane wall divides the inner cavity of the furnace body into two travel spaces, and the smoke passages of the first travel space and the second travel space are located below the partition membrane wall; Alternatively, at least two partition membrane walls are provided inside the furnace body, and the partition membrane walls divide the inner cavity of the furnace body into a plurality of travel spaces, wherein the smoke passages of the first travel space and the second travel space are located below the first partition membrane wall (8), and the smoke passages between the remaining travel spaces are alternately located above and below each partition membrane wall.
4. The full membrane wall waste heat boiler according to claim 1, It is characterized in that The upper connecting pipes (19) of the front wall membrane wall (5) and the rear wall membrane wall (6) respectively include a first upper connecting pipe (19-1) located below the opening area and a second upper connecting pipe (19-2) located above the opening area, the first upper connecting pipe (19-1) and the second upper connecting pipe (19-2) being connected via a plurality of vertical pipes (20) located in the opening area, and the second upper connecting pipe (19-2) being connected to the steam drum (1) via a riser (21).
5. The full membrane wall waste heat boiler according to claim 1, It is characterized in that The downcomer (3) comprises a downcomer main pipe (13-1) located at both ends of the steam drum, and a downcomer branch pipe (13-2) connected to the downcomer main pipe (13-1); the downcomer branch pipes (13-2) of the front wall membrane wall (5), the rear wall membrane wall (6), the two side wall membrane walls (7) and the partition wall membrane wall are respectively connected to their lower connecting pipes (14).
6. The full membrane wall waste heat boiler according to claim 5, It is characterized in that The descending main pipe (13-1) is arranged vertically, and the descending branch pipes (13-2) of the front wall membrane wall (5), the rear wall membrane wall (6), the two side wall membrane walls (7) and the partition wall membrane wall are respectively symmetrically distributed with the descending main pipe (13-1) as the center, and each of the descending branch pipes (13-2) is connected to the corresponding lower connecting pipe (14) after being bent.
7. The full membrane wall waste heat boiler according to claim 6, It is characterized in that The descending branch pipes (13-2) of the front wall membrane wall (5), the rear wall membrane wall (6), and the two side wall membrane walls (7) are respectively bent downward at the ends of the furnace body and are connected to the corresponding lower connecting pipes (14).
8. The full membrane wall waste heat boiler according to claim 7, It is characterized in that The descending branch pipe (13-2) of the partition membrane wall is first bent downward at the end of the furnace body, then bent toward the corresponding lower connecting pipe (14) of the partition membrane wall, and then extends from the outer sides of the two side membrane walls (7), and then communicates with the lower connecting pipe (14) of the partition membrane wall.
9. The full membrane wall waste heat boiler according to any one of claims 1 to 8, It is characterized in that The lower connecting pipe (14) of the membrane walls (7) on both sides is provided with a plurality of support components (15) distributed at intervals, so that the boiler can be fixed on the civil engineering platform (16) through the support components (15).