A method for adjusting the periodic rotation plan of three-phase three-wire electric energy meters
Through linear fitting and clustering analysis, predicting industry expansion data, calculating workload deviations, and dynamically adjusting the electricity meter cycle rotation plan, the uneven workload distribution problem caused by the superposition of electricity meter rotation and industry expansion, achieving a more balanced and Accurate rotation schedule.
Patent Information
- Application Number
- CN202111190985.5
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2021-10-13
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2041-10-13
AI Technical Summary
In the prior art, there is a problem of uneven workload distribution after the periodic rotation of the power meter and the expansion of the industry, resulting in uneven rotation work arrangements.
By obtaining historical industry expansion data for the past few years, using linear fit to predict the company's annual industry expansion, combining cluster analysis to predict the average daily industry expansion per month, and calculating the average daily workload for the whole year and month Deviation, dynamically adjust the cycle rotation plan of the power meter to ensure balanced workload distribution.
It effectively solves the problem of uneven distribution of workload after the periodic rotation of the electricity meter and the new installation of the industry, avoids unreasonable adjustments caused by too many or too few working days in individual months, and improves the accuracy and balance of the rotation plan.
Smart Images

Figure CN113902307B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a method for adjusting a periodic rotation plan of a three-phase three-wire electric energy meter, and belongs to the technical field of methods for adjusting a periodic rotation plan of an electric energy meter. Background Art
[0002] According to the management requirements of electric energy meters, the longest use time of electric energy meters from calibration and delivery to dismantling and recycling shall not exceed 6 years. For example, if an electric energy meter is qualified and delivered in May 2011, then by May 2017, the marketing system will generate monthly electric energy meter cycle rotation work orders based on the service life of the electric energy meter, and the grassroots team needs to carry out the rotation plan according to the work orders. Due to the uneven distribution of the calibration and installation time of the electric energy meter, the rotation work arrangement of the electric energy meter in the later period will also be uneven. In addition, due to the uncertainty of the distribution of the number of new business expansions in that year, it is very likely that the phenomenon of business expansion and new installation and cycle rotation will appear.
[0003] The invention patent with the prior art application number CN103018706B discloses a method and system for predicting the rotation cycle of smart electric energy meters, wherein the method includes: selecting a training sample set from the fault information of multiple smart electric energy meters; determining and determining the initial mean value of the rotation cycle of the smart electric energy meters produced by manufacturer k installed in region j based on the training sample set to judge whether to update the initial weight coefficient; if so, updating the corresponding initial weight coefficient based on the judgment result to determine the rotation cycle mean value of the smart electric energy meters produced by manufacturer k installed in region j; if not, determining the initial mean value as the rotation cycle mean value of the smart electric energy meters produced by manufacturer k installed in region j. The embodiment of the present invention realizes the prediction of the rotation cycle of the smart electric energy meters in a targeted manner.
[0004] The prior art has problems such as uneven workload distribution after the periodic rotation of electric energy meters and the superposition of business expansion and new installation. Therefore, the present invention provides a method and system for adjusting the periodic rotation plan of three-phase three-wire electric energy meters to solve the above problems. Summary of the invention
[0005] In order to solve the above technical problems, the present invention provides a method and system for adjusting a periodic rotation plan of a three-phase three-wire electric energy meter.
[0006] The technical solution of the present invention is as follows:
[0007] A method for adjusting a three-phase three-wire electric energy meter periodic rotation plan comprises the following steps:
[0008] S1: Obtain the historical business expansion data of recent years, and predict the company's annual business expansion volume in the predicted year through linear fitting of the data;
[0009] S2: Based on the historical business expansion data, the average daily business expansion volume of each month in each year is calculated, and the average daily business expansion volume of each month in each subsequent year is predicted by clustering method to obtain the average daily business expansion volume of each month in the predicted year;
[0010] S3: Calculate the average daily business expansion volume for each year based on historical business expansion data;
[0011] S4: According to the relationship between the average daily business expansion of each month in the predicted year and the total business expansion of the company in the predicted year, combined with the cycle rotation plan of the year, the annual electricity meter cycle rotation plan is adjusted.
[0012] In step S1, the year of historical business expansion data is used as the independent variable, and the total business expansion of each year of historical business expansion data is used as the dependent variable. A linear regression equation is obtained through regression training, and then the year of the predicted year is substituted into the linear regression equation to obtain the company's annual business expansion total for the predicted year.
[0013] In step S2, cluster analysis is performed on the daily average business expansion quantity in the same month of each year in the historical business expansion data to obtain the range of the maximum probability of the daily average business expansion quantity of each month, and obtain the value closest to the predicted value from the range.
[0014] Step S4 includes the following steps:
[0015] S41: Multiply the average daily business expansion of each month in the forecast year by the number of working days in each month in the forecast year to calculate the total monthly workload of the forecast year;
[0016] S42: Calculate the average daily workload of the entire year of the forecast year and the average daily workload of each month of the forecast year;
[0017] S43: Calculate the difference between the annual average daily workload of the predicted year and the monthly average daily workload of the predicted year to obtain the deviation of the monthly average daily workload of the predicted year;
[0018] S44: multiplying the deviation of the monthly average daily workload of the predicted year by the number of working days in the corresponding month to obtain the monthly deviation of the predicted year;
[0019] S45: Adjust the annual electricity meter cycle rotation plan based on the monthly deviation results of the predicted year.
[0020] In step S41, the total amount of work = the number of business expansion work + the number of periodic rotations / 2, where the number of periodic rotations is the number of business expansions 6 years before the predicted year and month.
[0021] In step S45, the monthly deviation result f is set,
[0022] S451. Determine whether the workload of the i-th month needs to be adjusted according to the value of f. If so, further determine whether the deviation result f of the i+1th month can be adjusted. If so, adjust part of the workload of the i+1th month to the i-th month and update the deviation results f of the i-th month and the i+1th month; otherwise, determine whether the deviation result f of the i+2th month can be adjusted. If so, adjust part of the workload of the i+2th month to the i-th month and the i+1th month and update the deviation results f of the i-th, i+1-th and i+2-th months;
[0023] Repeat step S451 until the workload of all months is adjusted.
[0024] In step S451, it is determined whether the difference result f of the i-th month is less than 0. If not, it is further determined whether the deviation result f of the i+1-th month is greater than 0. If so, the deviation results of the i-th month and the i+1-th month are summed and evenly distributed, and the deviation results f of the i-th month and the i+1-th month are updated;
[0025] In step S451, it is determined whether the deviation result f of the i-th month is less than 0. If so, it is further determined whether the deviation result f of the i+1th month is greater than 0. If so, the deviation results of the i-th month and the i+1th month are summed. If the sum is greater than 0, the deviation result f of the i+1th month is updated to the sum value, and the deviation result f of the i-th month is updated to 0. If the deviation result f of the i+1th month is less than 0, it is further determined whether the deviation result f of the i+2th month is greater than 0. If so, the deviation results of the i, i+1 and i+2th months are summed. The deviation results are summed and it is determined whether the sum is greater than 0. If the sum is greater than 0, the deviation results f of the i-th month and the i+1-th month are updated to 0 and the deviation result f of the i+2-th month is updated to the sum. If the sum is less than 0, the deviation results f of the i+1-th month and the i+2-th month are updated to 0 and the deviation result f of the i-th month is updated to the sum. If the deviation result f of the i+2-th month is less than 0, the deviation result f of the i-th month is updated to the sum of the i-th month and the i+1-th month, and then the deviation result f of the i+1-th month is updated to 0.
[0026] The adjustable amount f is less than or equal to the period rotation number / 2.
[0027] Let the i+1th month be the ith month, and repeat step S451 until the workload of all months is adjusted.
[0028] The present invention has the following beneficial effects:
[0029] The present invention obtains the average daily workload by dividing the total annual workload by the number of working days in the whole year, and then calculates the monthly deviation by the deviation of the average daily workload, and then adjusts the workload according to the monthly deviation, thereby solving the problem of uneven workload distribution after the cycle rotation of the electric energy meter and the superposition of business expansion and new installation. At the same time, the actual workload is calculated by using the actual working days of each month to avoid the problem of unreasonable workload distribution after adjustment caused by too many or too few working days in individual months.
[0030] The present invention obtains the predicted annual business expansion amount through the linear regression method, which can effectively avoid the influence of abnormal business expansion amount in individual months on the model;
[0031] The present invention obtains the distribution relationship between the business expansion data of each month through the cluster analysis method, so that when there is a deviation in the annual business expansion forecast quantity, it will not have a huge impact on the relative relationship between the monthly data, thereby ensuring the accuracy of the adjustment of the periodic rotation plan. BRIEF DESCRIPTION OF THE DRAWINGS
[0032] Figure 1 is a flow chart of the method of the present invention;
[0033] Figure 2 A logic relationship diagram for adjusting the periodic rotation plan of an electric energy meter according to the present invention;
[0034] Figure 3 This is a statistical chart of the business expansion quantity in the past five years in Example 2 of the present invention;
[0035] Figure 4 This is a forecast chart of business expansion quantity in each month of 2019 for a certain area in Example 2 of the present invention;
[0036] Figure 5 This is a statistical chart of monthly deviations in a certain area in 2019 in Example 2 of the present invention;
[0037] Figure 6 This is a monthly rotation strategy diagram for a certain area in 2019 in Example 2 of the present invention;
[0038] Figure 7 This is a data comparison chart of a certain area in Example 2 of the present invention after the monthly rotation adjustment in 2019. DETAILED DESCRIPTION
[0039] The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments.
[0040] Embodiment 1:
[0041] like Figure 1 -As shown, a method for adjusting a three-phase three-wire electric energy meter periodic rotation plan in this embodiment includes the following steps:
[0042] S1: Obtain historical business expansion data and predict the company's annual business expansion volume in the forecast year through linear fitting of the data;
[0043] S2: Based on the historical business expansion data, the average daily business expansion workload of each month is calculated, and then the average daily business expansion volume of each month in the predicted year is predicted using the clustering method;
[0044] S3: Calculate the average daily workload of business expansion for each year based on historical business expansion data;
[0045] S4: According to the relationship between the average daily business expansion of each month in the predicted year and the total business expansion of the company in the predicted year, combined with the cycle rotation plan of the year, the annual electricity meter cycle rotation plan is adjusted.
[0046] Furthermore, in step S1, the year of historical business expansion data is used as the independent variable, and the total business expansion of each year of historical business expansion data is used as the dependent variable. A linear regression equation is obtained through regression training, and then the predicted year is substituted into the linear regression equation to obtain the predicted annual total business expansion.
[0047] Furthermore, in step S3, cluster analysis is performed on the average business expansion quantity in the same month of each year in the historical business expansion data to obtain the range of the most likely occurrence of the daily average business expansion quantity in each month, and obtain the value closest to the predicted value from the range.
[0048] Further, step S4 includes the following steps:
[0049] S41: Total workload per month in the forecast year;
[0050] S42: Calculate the average daily workload of the entire year of the forecast year and the average daily workload of each month of the forecast year;
[0051] S43: Calculate the difference between the annual average daily workload of the predicted year and the monthly average daily workload of the predicted year to obtain the deviation of the monthly average daily workload of the predicted year;
[0052] S44: multiplying the deviation of the monthly average daily workload of the predicted year by the number of working days in the corresponding month to obtain the monthly deviation of the predicted year;
[0053] S45: Adjust the annual electricity meter cycle rotation plan based on the monthly deviation results of the predicted year.
[0054] Furthermore, in step S41, the total amount of work = the number of business expansion work + the number of periodic rotations / 2, and the number of periodic rotations is the number of business expansions 6 years before the predicted year and month.
[0055] Further, in step S45, the monthly deviation result f is assumed to be
[0056] S451. Determine whether the workload of the i-th month needs to be adjusted according to the value of f. If so, further determine whether the deviation result f of the i+1th month can be adjusted. If so, adjust part of the workload of the i+1th month to the i-th month and update the deviation results f of the i-th month and the i+1th month; otherwise, determine whether the deviation result f of the i+2th month can be adjusted. If so, adjust part of the workload of the i+2th month to the i-th month and the i+1th month and update the deviation results f of the i-th, i+1-th and i+2-th months;
[0057] Repeat step S451 until the workload of all months is adjusted.
[0058] Further, in step S451, it is determined whether the difference result f of the i-th month is less than 0. If not, it is further determined whether the deviation result f of the i+1th month is greater than 0. If so, the deviation results of the i-th month and the i+1th month are summed and evenly distributed, and the deviation results f of the i-th month and the i+1th month are updated;
[0059] In step S451, it is determined whether the deviation result f of the i-th month is less than 0. If so, it is further determined whether the deviation result f of the i+1th month is greater than 0. If so, the deviation results of the i-th month and the i+1th month are summed. If the sum is greater than 0, the deviation result f of the i+1th month is updated to the sum value, and the deviation result f of the i-th month is updated to 0. If the deviation result f of the i+1th month is less than 0, it is further determined whether the deviation result f of the i+2th month is greater than 0. If so, the deviation results of the i, i+1 and i+2th months are summed. The deviation results are summed and it is determined whether the sum is greater than 0. If the sum is greater than 0, the deviation results f of the i-th month and the i+1-th month are updated to 0 and the deviation result f of the i+2-th month is updated to the sum. If the sum is less than 0, the deviation results f of the i+1-th month and the i+2-th month are updated to 0 and the deviation result f of the i-th month is updated to the sum. If the deviation result f of the i+2-th month is less than 0, the deviation result f of the i-th month is updated to the sum of the i-th month and the i+1-th month, and then the deviation result f of the i+1-th month is updated to 0.
[0060] Furthermore, the adjustable amount f is less than or equal to the number of periodic rotations / 2.
[0061] Furthermore, in step S451, the i+1th month is set as the ith month, and step S451 is repeated until the workload of all months is adjusted.
[0062] Embodiment 2:
[0063] This embodiment takes the forecast year 2019 as an example.
[0064] A method for adjusting a three-phase three-wire electric energy meter periodic rotation plan comprises the following steps:
[0065] S1: Get historical business expansion data from 2014 to 2018: Y 2014 , Y 2015 , Y 2016 , Y 2017 , Y 2018 (like Figure 3 As shown), by linear fitting of the data Y 2019 '=kX+A,prediction data Y 2019 ',
[0066] Import Figure 3 The Y 2014 , Y 2015 , Y 2016 , Y 2017 , Y 2018 After training the data, we can obtain k=38.7, A=-77752.2,
[0067] When X is 2019, the forecast value Y for the annual business expansion in 2019 can be obtained. 2019 '.
[0068] After obtaining the business expansion data for the whole year of 2019, 2019 ' Divide by the number of working days in 2019 D 2019 The average daily business expansion for the whole year of 2019 can be obtained.
[0069]
[0070] The business expansion data for the five years from 2014 to 2018 were counted on a monthly basis, and combined with the actual number of working days in each month, the business expansion numbers were converted into the average daily workload for each month of each year.
[0071]
[0072] Where i represents the year, and its value range is 2014-2018, and j represents the month, and its value range is January-December. ij represents the number of business expansions in the jth month of the i-th year, D ij represents the number of working days in the jth month of the i-th year, m ij It represents the average daily business expansion in the jth month of the i-th year.
[0073] Cluster analysis is performed on the daily average business expansion data of the same month in the past five years to obtain the range of values with the highest probability of the daily average business expansion of a certain month in the past five years. The closest prediction value is obtained from the range as the daily average business expansion of that month in 2019. Taking the data from January 2014 to 2018 as an example, the daily average business expansion from January 2014 to 2018 is: m 20141 、m 20151 、m 20161 、m20171 、m 20181 The forecast value of daily business expansion in 2019 is m 20191 ', m 20141 、m 20151 、m 20161 、m 20171 、m 20181 Sort the five numbers.
[0074] The sorting results are:
[0075] a 1 >a 2 >a 3 >a 4 >a 5
[0076] in,
[0077] a 1 =max(m 20141 、m 20151 、m 20161 、m 20171 、m 20181 )
[0078] a 5 =min(m 20141 、m 20151 、m 20161 、m 20171 、m 20181 ),
[0079] Secondly, the five sorted data are grouped into three and the average is taken one by one in the form of sliding difference:
[0080]
[0081]
[0082]
[0083] Finally, the three means and five data are used to calculate the variance:
[0084]
[0085]
[0086]
[0087] D k =min(D 1 , D 1 , D 3 ),
[0088] The mean corresponding to the minimum variance This is the forecast value of the average daily business expansion in January 2019.
[0089]
[0090] When m 2019j 'After confirmation, multiply it by the number of working days in the corresponding month of 2019 D 2019j , you can get the number of business expansion jobs in 2019 M 2019j ,like Figure 4 As shown, it provides a reference for the reasonable adjustment of the rotation plan in the later cycle.
[0091] During the rotation process, the high-voltage electric energy meter cycle rotation data generated at the beginning of the year was first counted on a monthly basis.
[0092] L 2019 =[L 20191 L 20192 … L 201911 L 201912 ]
[0093] Then, based on the actual workload, the number of new installations and cycle rotations in 2019 was unified and added up to form the total monthly workload.
[0094] W 2019j =M 2019j +L 2019j / 2,
[0095] The value of j ranges from 1 to 12, representing 12 months. The average daily workload w can be obtained by dividing the number of work per month by the number of working days in the corresponding month. 2019j ,
[0096]
[0097] The average daily workload for the whole year of 2019 is:
[0098]
[0099] When 2019j and After determination, the difference can reflect the relationship between the average daily workload of each month in 2019 and the average workload of the whole year in a certain area. A negative difference means that the workload of the month is lower than the average of the whole year, and a positive difference means that the workload of the month is higher than the average of the whole year.
[0100]
[0101] Multiply the monthly average daily workload deviation by the number of corresponding working days in the month to get the monthly workload deviation, such as Figure 5 Shown
[0102] ΔW j =Δw j ×D 2019j ;
[0103] Assume that the monthly deviation result is f, and take any three consecutive months of data f j 、f j+1 、f j+2 For example,
[0104] like Figure 2 As shown, according to the value of f, it is determined whether the workload of the i-th month needs to be adjusted. If adjustment is required, it is further determined whether the deviation result f of the i+1th month can be adjusted. If so, part of the workload of the i+1th month is adjusted to the i-th month and the deviation results f of the i-th and i+1th months are updated; otherwise, it is determined whether the deviation result f of the i+2th month can be adjusted. If so, part of the workload of the i+2th month is adjusted to the i-th month and the i+1th month and the deviation results f of the i-th, i+1 and i+2th months are updated; repeat step Step S451 is performed until the workload of all months is adjusted; whether the deviation result f from the i-th month is less than 0, if not, whether the deviation result f from the i+1th month is greater than 0, if so, sum and evenly distribute the deviation results of the i-th month and the i+1th month, and update the deviation results f from the i-th month and the i+1th month; whether the deviation result f from the i-th month is less than 0, if so, further judge whether the deviation result f from the i+1th month is greater than 0, if so, sum and evenly distribute the deviation results of the i-th month and the i+1th month Sum the results. If the sum is greater than 0, update the deviation result f of the i+1th month to the sum value, and update the deviation result f of the i+2th month to 0. If the deviation result f of the i+1th month is less than 0, further determine whether the deviation result f of the i+2th month is greater than 0. If so, sum the deviation results of the i, i+1 and i+2th months and determine whether the sum is greater than 0. If the sum is greater than 0, update the deviation results f of the i+1th month and the i+1th month to 0 and update the deviation result f of the i+2th month to the sum. If the sum is less than 0, update the deviation result f of the i+1th month and the i+2th month to 0 and update the deviation result f of the i+1th month to the sum value; if the deviation result f of the i+2th month is less than 0, update the deviation result f of the i+1th month to the sum value of the i+1th month and the i+1th month, and then update the deviation result f of the i+1th month to 0; the adjustable amount f is less than or equal to the number of period rotations / 2; let the i+1th month be the i+1th month, and repeat step S451 until the workload of all months is adjusted. The adjusted result is as follows: Figure 6-7 As shown;
[0105] Since only the workload of periodic rotation can be adjusted dynamically, when the monthly workload deviation is used as the adjustment quantity, when ΔW j >L 2019j / 2, the adjustment amount should be L 2019j / 2, that is
[0106] The above descriptions are merely embodiments of the present invention and are not intended to limit the patent scope of the present invention. Any equivalent structure or equivalent process transformation made using the contents of the present invention specification and drawings, or directly or indirectly applied in other related technical fields, are also included in the patent protection scope of the present invention.
Claims
1. A method for adjusting a three-phase three-wire electric energy meter periodic rotation plan, characterized in that: The following steps are included: S1: Obtain the historical business expansion data of recent years, and predict the company's annual business expansion volume in the predicted year through linear fitting of the data; S2: Based on the historical business expansion data, the average daily business expansion volume of each month in each year is calculated, and the average daily business expansion volume of each month in each subsequent year is predicted by clustering method to obtain the average daily business expansion volume of each month in the predicted year; S3: Calculate the average daily business expansion volume for each year based on historical business expansion data; S4: According to the relationship between the average daily business expansion of each month in the forecast year and the total business expansion of the company in the forecast year, combined with the cycle rotation plan of the year, adjust the annual electricity meter cycle rotation plan; Step S4 includes the following steps: S41: Total workload per month in the forecast year; S42: Calculate the average daily workload of the entire year of the forecast year and the average daily workload of each month of the forecast year; S43: Calculate the difference between the annual average daily workload of the predicted year and the monthly average daily workload of the predicted year to obtain the deviation of the monthly average daily workload of the predicted year; S44: multiplying the deviation of the monthly average daily workload of the predicted year by the number of working days in the corresponding month to obtain the monthly deviation of the predicted year; S45: adjusting the annual electric energy meter cycle rotation plan according to the monthly deviation results of the predicted year; In step S41, the total amount of work = the number of business expansion work + the number of periodic rotations / 2, where the number of periodic rotations is the number of business expansions 6 years before the predicted year and month; The amount of business expansion work is equal to the average daily business expansion volume in each month of the predicted year multiplied by the number of working days in the corresponding month.
2. A method for adjusting a three-phase three-wire electric energy meter periodic rotation plan according to claim 1, characterized in that: In step S1, the year of historical business expansion data is used as the independent variable, and the total business expansion of each year of historical business expansion data is used as the dependent variable. A linear regression equation is obtained through regression training, and then the year of the predicted year is substituted into the linear regression equation to obtain the company's annual business expansion total for the predicted year.
3. A method for adjusting a three-phase three-wire electric energy meter periodic rotation plan according to claim 1, characterized in that: In step S2, cluster analysis is performed on the daily average business expansion quantity in the same month of each year in the historical business expansion data to obtain the range of the maximum probability of the daily average business expansion quantity of each month, and obtain the value closest to the predicted value from the range.
4. A method for adjusting a three-phase three-wire electric energy meter periodic rotation plan according to claim 1, characterized in that: In step S45, the monthly deviation result f is set, S451. Determine whether the workload of the i-th month needs to be adjusted according to the value of f. If so, further determine whether the deviation result f of the i+1th month can be adjusted. If so, adjust part of the workload of the i+1th month to the i-th month and update the deviation results f of the i-th month and the i+1th month; otherwise, determine whether the deviation result f of the i+2th month can be adjusted. If so, adjust part of the workload of the i+2th month to the i-th month and the i+1th month and update the deviation results f of the i-th, i+1-th and i+2-th months; Repeat step S451 until the workload of all months is adjusted.
5. A method for adjusting a three-phase three-wire electric energy meter period rotation plan according to claim 4, characterized in that: In step S451, it is determined whether the difference result f of the i-th month is less than 0. If not, it is further determined whether the deviation result f of the i+1-th month is greater than 0. If so, the deviation results of the i-th month and the i+1-th month are summed and evenly distributed, and the deviation results f of the i-th month and the i+1-th month are updated; In step S451, it is determined whether the deviation result f of the i-th month is less than 0. If so, it is further determined whether the deviation result f of the i+1th month is greater than 0. If so, the deviation results of the i-th month and the i+1th month are summed. If the summed result is greater than 0, the deviation result f of the i+1th month is updated to the summed value, and the deviation result f of the i-th month is updated to 0. If the deviation result f of the i+1th month is less than 0, it is further determined whether the deviation result f of the i+2th month is greater than 0. If so, the deviation results of the i-th, i+1-th and i+2-th months are summed and it is determined whether the summed value is greater than 0. If the summed value is greater than 0, the deviation results f of the i-th month and the i+1th month are updated to 0 and the deviation result f of the i+2th month is updated to the summed value. If the summed value is less than 0, the deviation results f of the i+1th month and the i+2th month are updated to 0 and the deviation result f of the i+2th month is updated to the summed value. If the deviation result f of the i+2th month is less than 0, the deviation result f of the i-th month is updated to the sum of the i-th month and the i+1th month, and then the deviation result f of the i+1th month is updated to 0.
6. A method for adjusting a three-phase three-wire electric energy meter periodic rotation plan according to claim 4, characterized in that: The adjustable amount f is less than or equal to the number of periodic rotations / 2.
7. A method for adjusting a three-phase three-wire electric energy meter period rotation plan according to claim 4, characterized in that: Let the i+1th month be the ith month, and repeat step S451 until the workload of all months is adjusted.