A method for synchronous lifting and installation of equipment pipelines and large-span roof steel structures
A technology of synchronous lifting and installation methods, which is applied in building construction, building material processing, construction, etc., can solve problems such as pipeline slope not meeting design requirements, pipeline straightness not meeting requirements, etc., to improve efficiency, adjust way simple effect
Patent Information
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Publication Date
- 2022-05-24
Smart Images

Figure 1 
Figure 2
Abstract
Description
technical field
[0001] The present application relates to the field of grid installation, in particular to a method for synchronously lifting and installing equipment pipelines and large-span roof steel structures. Background technique
[0002] In order to meet the needs of current building shapes and architectural functions, large-scale public construction projects such as airports and high-speed railway stations now use long-span steel structure roofs as the top frame of the buildings.
[0003] At present, the roof steel structure is usually assembled on the ground, and the pipes inside the roof are also pre-installed in the roof and installed with the overall lifting of the roof. However, after the lifting is completed and unloaded, the roof steel structure and pipes are prone to deformation. , resulting in the straightness and slope of the pipeline not meeting the requirements.
[0004] In view of the above-mentioned related technologies, the inventor believes that afte...
Examples
Embodiment Construction
[0039] Attached to the following Figure 1-2 This application will be described in further detail.
[0040] The embodiment of the present application discloses a method for synchronously lifting and installing equipment pipelines and large-span roof steel structures. The synchronous elevation installation method includes the following steps:
[0041] S1, refer to figure 1 , first install multiple lifting towers on the ground, and the lifting towers are arranged according to the design positions; after the multiple lifting towers are installed, assemble the roof steel structure on the ground in the order of installation; while assembling the roof steel structure, The support and hanger 1 of the pipeline 2 is installed on the roof steel structure. The support and hanger 1 is prefabricated in advance. The support and hanger 1 includes a cross arm 12 and a vertical arm 11. The vertical arm 11 and the cross arm 12 are arranged perpendicular to each other. One end is welded and f...