Micro-disturbance sinking construction method for caisson in soft upper and hard lower water-rich strata
By combining the undrained and drained sinking methods, MJS construction method piles are used to realize the self-weight sinking of the caisson in the upper soft and lower hard strata, solving the problems of low construction efficiency and poor economy, ensuring construction safety and quality, and avoiding ground Disadvantages of poor uplift and piling effects.
Patent Information
- Application Number
- CN202210447950.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-04-27
- Publication Date
- 2024-10-15
- Estimated Expiration
- 2042-04-27
AI Technical Summary
Under the conditions of soft and hard water-rich strata at the top and bottom, the existing caisson sinking construction methods have problems such as low construction efficiency, long construction period, difficulty in correcting deviations, and poor economy. Especially when entering the boulder-bearing water layer, the traditional water-stop structure It is easy to cause the ground to bulge and the pile formation effect is poor.
Using a method that combines the undrained sinking method and the drained sinking method, the caisson is sunk through the crane grab and flushing and suction equipment in the initial stage. After entering the conglomerate pressurized water layer, an MJS jet grouting pile water-stop structure is constructed. MJS construction method piles are used. Reinforce the weathered sandstone layer, control the internal pressure, ensure that the caisson sinks under its own weight, and prevent water seepage from the phreatic layer through bentonite mud.
It improves construction efficiency, reduces construction difficulty and cost, enhances construction safety, avoids the problems of ground deformation and poor pile formation caused by traditional water-stop structures, and shortens the construction period.
Smart Images

Figure CN114776305B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the field of caisson sinking construction, and in particular relates to a micro-disturbance sinking construction method for a caisson in a soft upper and hard lower water-rich stratum. Background Art
[0002] Using caisson as the starting and receiving structure of pipe jacking project helps to improve the safety and economy of the project. With the gradual development of pipe jacking project, it has shown the characteristics of long distance, large diameter and high burial depth. However, due to the constraints of geological conditions, surrounding environment and construction methods, the sinking problem of caisson structure has become the key to restricting the progress of the overall project. In complex geological formations, it is usually adopted to increase the caisson counterweight to make the caisson sink, but this method has the disadvantages of slow sinking, long construction period, difficult correction and poor economy. The soft upper and hard lower water-rich formation is a typical complex structural geology, see Figure 3 , from top to bottom, it is divided into surface water layer 4, silty clay layer 5, gravel confined water layer 6, and weathered sandstone layer 7. In such geological conditions, the caisson sinking construction is usually carried out by combining drainage and non-drainage. Drainage construction must be carried out when entering the gravel confined water layer. Drainage construction requires the construction of a water-stop structure outside the caisson to prevent the confined water from entering the caisson. Usually, the drainage sinking water-stop structure is constructed by high-pressure rotary jet piles, TRD ground-connected walls and other methods, but the construction cost of TRD ground-connected walls is high and the economy is poor. Although the high-pressure rotary jet pile construction efficiency is high and the economy is good, as the depth of soil burial increases, the air lift efficiency will decrease. When the gap between the soil and the nozzle is blocked, the increase in the pressure in the foundation will reduce the injection efficiency, and even cause the ground to rise, endangering the safety of buildings around the construction site. Therefore, how to adopt a caisson sinking construction method with little disturbance to surrounding structures, strong controllability, high construction efficiency and good economy under the geological conditions of soft soil on the upper part and hard weathered sandstone layer on the lower part needs to be solved urgently. Summary of the invention
[0003] The purpose of the present invention is to provide a micro-disturbance sinking construction method for a caisson in a soft upper and hard lower water-rich stratum to solve the problems existing in the prior art.
[0004] The technical solution for achieving the above-mentioned purpose includes the following contents.
[0005] A micro-disturbance sinking construction method for caissons in water-rich strata with soft upper part and hard lower part, wherein a non-drainage sinking method is used above the gravel pressure water layer, and a drainage sinking method is used for the gravel pressure water layer, wherein the non-drainage sinking method comprises the steps of mechanical soil grabbing and air mud suction: in the initial stage of caisson sinking, a crane grab is used to directly dig the soil at the bottom of the well to form a pot bottom and sink by the deadweight of the caisson; when water seeps into the surface water layer into the caisson, causing the mechanical soil grabbing to be difficult, flushing and suction equipment is used to discharge mud nearby through pipelines; the drainage sinking method comprises the steps of constructing a water-stop curtain, injecting mud to isolate water, and mechanically breaking rock and sinking after drainage: a circle of MJS rotary jet piles is driven on the outside of the caisson to block the gravel pressure water layer outside the circle, The MJS reinforcement body goes downward into the weathered sandstone layer. The upward elevation of the MJS reinforcement body is not lower than the top of the gravel pressure water layer. Bentonite mud is injected between the outer wall of the caisson and the submerged layer to prevent the submerged layer from seeping downward along the outer wall of the caisson. The water in the caisson is drained, and the weathered sandstone layer is broken by a small pickaxe until the caisson sinks into place by its own weight. After acceptance, the bottom sealing construction is carried out.
[0006] Furthermore, the pile diameter of the MJS method is 1.2-1.8m, and the bite is 0.3-0.5m.
[0007] Furthermore, the MJS piles are reinforced upwards to a height of 1m above the top of the gravel confined water layer.
[0008] Further, the MJS piles were reinforced downwards to a depth of 0.8-1.2 m into the weathered sandstone layer.
[0009] Furthermore, the flushing and suction equipment is at least 4m below the groundwater level.
[0010] Compared with the prior art, the present invention has the following obvious outstanding substantive features and significant advantages:
[0011] 1. The present invention uses a caisson micro-disturbance sinking construction method to effectively improve the caisson sinking construction efficiency in soft upper and hard lower strata, reduce the construction difficulty, enhance the construction safety and ensure the construction quality;
[0012] 2. When encountering weathered sandstone layers where it is impossible to sink the caisson without drainage, drainage is required to cooperate with the pickaxe to break the rock and sink. In order to prevent large deformation of the surrounding soil due to drainage operations, MJS method piles are first used as the caisson water-stopping structure, which overcomes the shortcomings of traditional water-stopping structures such as high-pressure jet grouting piles that easily cause ground uplift and poor pile formation. MJS method piles control the pressure in the ground through jet forced slurry discharge, which can effectively curb surface deformation, control the impact of the sinking process on the surrounding environment, and ensure the safety of the caisson sinking;
[0013] 3. The present invention relies on the caisson's own gravity to drive the caisson to sink, thus avoiding the increase in construction cost and the restriction on construction progress caused by the weight pressing method and the external auxiliary sinking process, saving construction time and reducing construction cost. BRIEF DESCRIPTION OF THE DRAWINGS
[0014] Figure 1 This is a flowchart of the caisson micro-disturbance sinking construction according to an embodiment of the present invention;
[0015] Figure 2 It is a flow chart of the MJS method pile construction method of an embodiment of the present invention;
[0016] Figure 3 It is a schematic diagram of the caisson structure and the stratum cross-section structure according to an embodiment of the present invention.
[0017] In the figure, 1. caisson; 2. bentonite slurry; 3. MJS pile; 4. surface water layer; 5. silty clay layer; 6. gravel pressure water layer; 7. weathered sandstone layer; 8. groundwater level. DETAILED DESCRIPTION
[0018] The present invention is specifically described below with reference to the embodiments.
[0019] See also Figures 1 to 3 This embodiment provides a method for sinking a caisson under the geological conditions of soft upper and hard water-rich strata, including two stages of construction. The first stage is before the caisson 1 enters the gravel confined water layer 6, and the undrained sinking construction is adopted. Figure 1 , including the following steps:
[0020] Step 1: Chisel off the blade foot cushion and brick formwork before sinking. The cushion removal should be carried out symmetrically from the inside to the outside, and the broken bricks in the well should be cleaned up with a crane grab. Draw a measuring ruler on the walls around the caisson 1 and set up a horizontal indicator ruler;
[0021] Step 2: Before digging the caisson, the caisson blade feet are excavated manually and layered at the same time. The excavated soil is first concentrated in the center, and the caisson is allowed to sink gradually, so that the caisson blade feet are buried in the soil layer, the center of gravity of the caisson is lowered, and a large tilt of the caisson is avoided;
[0022] Step 3: During construction, four observation points are set up on the caisson wall for continuous tracking measurement, at least once every hour under normal circumstances. The average of the sinking amounts of the four measurement points is used as the sinking amount of the caisson each time, and the point with the largest sinking amount is used as the reference and the height difference of each point is subtracted from the sinking amounts of other points to guide the corrective sinking construction;
[0023] Step 4, the soil excavation method for the initial 4m sinking of the caisson is to use a crane grab to dig the soil at the bottom of the well to form a pot bottom sinking. The construction machinery mainly uses a 50t crawler crane to grab the soil and sink it, equipped with a 1.2m3 volume grab. The soil excavation by the crane grab should be carried out symmetrically to make it sink evenly, and the height difference of the soil surface in the bin should not exceed 50cm. When the crane grabs the soil, the depth of the pot bottom should not be deeper than 1.0m. The bottom of the caisson pot should be excavated evenly, and when the caisson deviation reaches 1 / 4 of the allowable deviation value, it must be corrected;
[0024] Step 5. When the water level is greater than 4m and the grab cannot take soil underwater, use special flushing and suction equipment to excavate and sink the soil. Arrange the flushing and suction equipment, and the mud sucked out by air suction is discharged to the nearby mud pool through pipes. During the sinking process, control the water level in the well to reduce buoyancy and ensure the sinking of the caisson. When using an air suction device, the water discharge is large. In order to maintain the balance of water levels inside and outside the well and prevent the pressure difference between the inside and outside due to the lowering of the water level in the well, a sufficient number of water pumps are equipped on site to continuously inject water into the well to maintain the water head height in the well;
[0025] When the caisson sinks to the gravel confined water layer, the groundwater gushes out under pressure and the flow rate is too large. The air suction device cannot work normally. The caisson sinking construction enters the second stage, using drainage sinking construction. Figure 2 , including building a water-stop curtain, injecting mud to isolate water, and mechanically breaking rocks and sinking after drainage. The specific steps are as follows:
[0026] Step 1: Pile foundation positioning. According to the pile center design requirements, determine the position of MJS pile 3, lay out the line, and dig trenches along the line;
[0027] Step 2, hole drilling. Use a main machine to drill the hole by itself or a special hole drilling machine to drill the hole. Lay a walkway board horizontally on the top of the trench to ensure flatness. After the drilling rig is in place, level and center the pile driver, adjust the verticality of the pile driver, ensure that the casing is consistent with the pile position, and the deviation is no more than 50mm. Put in the outer casing at the same time; the hole drilling depth is 1~2m greater than the designed pile depth. During the hole drilling process, the number of outer casing sections should be recorded in detail to ensure the drilling depth and verticality are controlled at 1 / 150;
[0028] Step 3, lower the drill pipe. Check the operation of the equipment and ensure that the main machine is in place under normal working condition. Start zeroing after the rack is placed stably. After the hole is guided to the designed depth, remove the casing and lower the MJS drill pipe section by section to the designed elevation. When lowering the drill pipe, check whether the sealing ring of each section of the drill pipe is intact. If there is any defect, replace it in time; connect the data cable, various pipelines, drill bit and underground pressure monitoring display, confirm that the drill bit is zeroed when there is no load, and ensure the pipeline connection is sealed so that there is no air in the pipe. Lower the drill pipe to the designed depth in the guide hole. If it is difficult to lower the drill pipe during the process, turn on the drilling water for normal drilling. It is strictly forbidden to force the drill pipe down when it is difficult to lower it;
[0029] Step 4, parameter setting. After the drill bit reaches the predetermined depth, start zeroing, so that the "0" scale of the power head, the nozzle, and the white line on the drill rod are in the same straight line, and then set various process parameters, including swing angle, extraction speed, number of revolutions, etc. After setting, start construction;
[0030] Step 5, fixed position spraying. First, start the backflow of water and air. When confirming that the slurry discharge is normal, open the mud discharge valve, turn on the high-pressure cement pump and the main air compressor. To ensure the construction quality of the bottom of the pile, first use water to spray upwards 50cm, the pressure is 10MPa, and the spraying time is 3min. Then switch the water to cement slurry, and start the upward spraying construction after the drill rod is lowered into place again;
[0031] Step 6, spraying and lifting. When turning on the high-pressure cement pump, the pressure should not be too high, and should be gradually increased until the specified pressure is reached. After reaching the specified pressure and confirming that the underground pressure is normal, you can start to lift it. When water is switched to cement slurry, the pressure will rise automatically, and the pressure can be adjusted only when there is a sudden change in pressure. Closely monitor the underground pressure during construction. When the pressure is abnormal, the size of the slurry discharge valve must be adjusted in time to control the underground pressure within a safe range. The spraying process should be carried out continuously without interruption. In the event of a drilling rig failure or poor mud discharge, the spraying should be stopped immediately;
[0032] Step 7, drill pipe disassembly. After lifting a drill pipe, the drill pipe needs to be disassembled after the cement slurry is switched to water. First release the pressure and then switch the cement slurry to water. When the pressure of the cement slurry pump tends to decrease, it means that the water flow has reached the nozzle position. At this time, turn off the cement slurry pump, main air, backdraft air and backdraft water flow;
[0033] Step 8: Drilling rig relocation. To ensure the pile top elevation and quality, stop jetting when the slurry nozzle is raised to 10 cm above the designed pile top elevation. After removing the drill rod, flush and maintain the drill rod, high-pressure grouting pump, and pipeline in time.
[0034] Step 9, inspection and acceptance of MJS pile 3;
[0035] Step 10, drain the water in the well, use a small pickaxe to break the rock layer, and inject bentonite slurry 2 between the outer wall of the caisson and the surface phreatic layer 4 to block the downward seepage of the phreatic layer groundwater along the outer wall of the well and reduce the sinking resistance of the caisson until the caisson sinks into place. When the caisson sinks to nearly 2m from the design elevation, the sinking speed of the caisson should be slowed down, mainly to correct the deviation, and pay close attention to the sinking speed of the caisson to prevent over-sinking, so that the caisson 1 can sink smoothly to the design elevation. After the caisson reaches the elevation, the sinking amount does not exceed 10mm within 8 hours before the concrete bottom can be sealed.
[0036] The following table is the MJS construction parameter table.
[0037] Serial number content parameter Serial number content parameter 1 Pile diameter 1600mm 9 Cutting water pressure 10~30MPa 2 Water-cement ratio 0.7—1 10 Pile Angle Error Control ≤1 / 150 3 Cement slurry pressure 40MPa 11 Increase speed 40, 20min / m 4 Cement slurry flow rate 90L / min 12 Step travel 25mm 5 Main air pressure 0.7~1.05MPa 13 Stride lifting time 60、30s 6 Main air flow <![CDATA[1.0~2.0m 3 / min]]> 14 Speed 3~4rpm 7 Backflow water pressure 0~20MPa 15 Intraterrestrial pressure 1.3~1.6 coefficient 8 Backflow water flow 0~60L / min 16 Cement content 40%
[0038] The MJS pile construction adopted in this embodiment overcomes the shortcomings of traditional water-stopping structures such as high-pressure jet grouting piles that easily cause ground uplift and poor pile formation effect. The caisson is driven to sink by its own gravity, which improves the construction efficiency and saves the construction period. Compared with the existing technology, the sinking construction of the caisson in this embodiment under the same geological conditions requires About 40 days The construction method of this embodiment was actually used for 25 days, and the effect of saving construction time was obvious.
[0039] The textual description and diagrams of this embodiment belong to the description of the examples of the present invention. Obviously, the present invention is limited to the embodiments described, and various changes can be made according to the purpose of the present invention. Any changes, modifications, combinations, substitutions, and simplifications made according to the spirit and principle of the technical solution of the present invention should be considered as equivalent replacement methods. As long as they meet the purpose of the present invention and do not deviate from the purpose of the present invention, they are the same or similar to the micro-disturbance sinking construction method of the caisson in the soft upper and hard lower water-rich strata of the present invention, and they all belong to the protection scope of the present invention.
Claims
1. A micro-disturbance sinking construction method for a caisson in a soft upper and hard water-rich stratum, characterized in that: The soft upper and hard lower water-rich strata are divided into surface phreatic layer, silty clay layer, gravel confined water layer and weathered sandstone layer from top to bottom. The undrained sinking method is used above the gravel confined water layer, and the drained sinking method is used for the gravel confined water layer. The undrained sinking method includes the steps of mechanical soil grabbing and air mud suction: in the early stage of caisson sinking, a crane grab is used to directly dig the soil at the bottom of the well to form a pot bottom and sink by the deadweight of the caisson. When the surface phreatic layer seeps into the caisson, making it difficult to mechanically grab the soil, flushing and suction equipment is used to discharge mud nearby through pipes; the drained sinking method includes constructing a water-stop curtain, injecting mud to isolate water, and mechanically breaking rocks and sinking after drainage. The specific steps are as follows: a circle of MJS rotary jet piles is driven on the outside of the caisson to block the gravel confined water layer outside the circle, The MJS reinforcement body goes downward into the weathered sandstone layer. The upward elevation of the MJS reinforcement body is not lower than the top of the gravel pressure water layer. Bentonite mud is injected between the outer wall of the caisson and the submerged layer to prevent the submerged layer from seeping downward along the outer wall of the caisson. The water in the caisson is drained, and the weathered sandstone layer is broken by a small pickaxe until the caisson sinks into place under its own weight. After acceptance, the bottom sealing construction is carried out.
2. The micro-disturbance sinking construction method for caisson in soft upper and hard lower water-rich strata according to claim 1 is characterized in that: The pile diameter of MJS method is 1.2-1.8m, and the bite is 0.3-0.5m.
3. The micro-disturbance sinking construction method for caisson in soft upper and hard lower water-rich strata according to claim 1 is characterized in that: The upward reinforcement elevation of the MJS pile exceeds the top of the gravel pressure water layer by 1m.
4. The micro-disturbance sinking construction method for caisson in soft upper and hard lower water-rich strata according to claim 1 is characterized in that: The MJS piles are reinforced downwards to a depth of 0.8-1.2 m into the weathered sandstone layer.
5. The micro-disturbance sinking construction method for caisson in soft upper and hard lower water-rich strata according to claim 1 is characterized in that: The flushing and suction equipment is at least 4m below the groundwater level.
Citation Information
Patent Citations
Water inlet pump chamber and method
CN102383442A
Open caisson construction method
CN107142955A
Construction method of underwater large-depth open caisson penetrating through hard and difficult-to-break soil layer
CN109339084A
High-pressure-bearing underwater shield entrance and exit hole soil body reinforcing method
CN113482626A
Open caisson clamping pile breaking structure
CN215367361U