A construction device for initial positioning of tunnel arch and use method thereof
By using the servo motor-driven displacement and adjustment mechanism in tunnel arch construction, combined with the cylinder and clamping mechanism, rapid multi-directional adjustment and docking of the arch is achieved, solving the problems of high labor intensity and low efficiency in existing construction methods. , significantly shortening the construction time.
Patent Information
- Application Number
- CN202210483094.7
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-05-05
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-05-05
AI Technical Summary
The existing tunnel arch construction method results in high labor intensity, low work efficiency and long construction time for construction personnel, which affects the tunnel construction period.
A construction device including a displacement mechanism and an adjustment mechanism driven by a servo motor is designed. The servo motor drives the screw rod to perform circular motion, and the cylinder drives the arch frame for multi-directional adjustment. The clamping mechanism realizes the rapid docking and coupling of the arch frame. fixed.
It significantly reduces the labor intensity of construction personnel, improves work efficiency, shortens construction time, and improves the construction efficiency of the initial positioning of the tunnel arch.
Smart Images

Figure CN114961794B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of initial positioning of a tunnel arch, and in particular to a construction device and a use method for initial positioning of a tunnel arch. Background Art
[0002] A highway tunnel refers to a passage built underground for cars to travel. The main building of a highway tunnel is generally composed of a tunnel body, lining and portal. In areas where the tunnel entrance is prone to collapse, an open tunnel is also built. The design of a highway tunnel usually starts with a scheme design, and then the specific design of the tunnel's plane and longitudinal section, clearance, lining, etc. The scheme design of a highway tunnel is based on an investigation of the topography, geology, meteorology, hydrology, social and natural environment of the area where the tunnel is located, as well as relevant laws and regulations. It comprehensively considers the overall layout of the tunnel; makes a rough estimate of the amount of work to be done in tunnel construction; conducts a serious analysis of the safety of tunnel construction; fully estimates the purpose and long-term planning of the tunnel; and conducts a comprehensive evaluation of the impact on the environment, so as to determine a plan for tunnel construction that is economical in investment, technically reasonable, and profitable.
[0003] During tunnel construction, due to the low strength of soft rock in the tunnel, after the tunnel is excavated, arch frames must be quickly used for support and reinforcement construction. The construction steps of the arch frames are as follows: first, a construction vehicle needs to be prepared at the construction location, and both sides of the construction vehicle have two construction platforms of different heights. Secondly, five groups of more than a dozen construction workers are asked to stand on the construction platforms located on both sides and the top of the construction vehicle, and then five arch frames are lifted up by the shoulders of the construction workers at the same time. Finally, the adjacent arch frames are connected by bolts to complete the initial positioning of the tunnel arch frames. The purpose is to prevent landslide disasters during tunnel construction. The above-mentioned construction method of the arch frames not only has high labor intensity and low work efficiency for the construction workers, but also the whole construction process is long, which is easy to affect the construction period of the tunnel. Summary of the invention
[0004] Based on the existing arch construction method, not only is the labor intensity high and work efficiency low for construction workers, but the entire construction process is long, which easily affects the tunnel construction period. The present invention proposes a construction device and a method for using it for the initial positioning of a tunnel arch.
[0005] The present invention proposes a construction device and a method for using the initial positioning of a tunnel arch frame, comprising a construction vehicle, both sides of which are fixedly mounted with bottom plates, wherein four of the bottom plates are grouped in pairs and are symmetrical with respect to the axis of the construction vehicle, a first step for walking up and down is fixedly mounted on the upper surface of the bottom plate, a first work station plate for construction is fixedly connected to the outlet end of the first step, a second step for walking up and down is fixedly mounted on the upper surface of the first step, a second work station plate for construction is fixedly mounted on the outlet end of the second step, a third work station plate for construction is fixedly mounted on the upper surface of the construction vehicle through a bracket, a displacement mechanism is fixedly mounted on the upper surfaces of the first work station plate, the second work station plate and the third work station plate, and the displacement mechanism comprises a servo motor, and the servo motor drives the arch frame to perform linear motion along its length;
[0006] An adjustment mechanism is fixedly installed above the displacement mechanism, and the adjustment mechanism includes a first cylinder and a second cylinder. The first cylinder drives the arch frame to move along the width direction of the construction vehicle, and the second cylinder drives the arch frame to move along the left and right direction of the construction vehicle.
[0007] A clamping mechanism is fixedly installed on one side of the adjustment mechanism, and the clamping mechanism includes a third cylinder and two clamping blocks. The two clamping blocks are driven by the third cylinder to contact the grooves of the arch frame from the front and back sides of the arch frame to clamp the arch frame.
[0008] Preferably, the displacement mechanism also includes a support plate, the lower surfaces of the multiple support plates are fixedly connected to the upper surfaces of the first work station plate, the second work station plate and the third work station plate, respectively, the servo motor is fixedly installed on the upper surface of the support plate, and the upper surfaces of the first work station plate, the second work station plate and the third work station plate are all fixedly installed with limit blocks, the cross-section of the limit block is U-shaped, the front inner wall and the rear inner wall of the limit block are both provided with a first slide groove, and the upper surface of the limit block is provided with symmetrically distributed second slide grooves.
[0009] Preferably, the output shaft of the servo motor is fixedly installed with a screw rod through a coupling, the outer surface of the screw rod is threadedly connected with a slider, the outer surface of the slider is slidably connected to the inner wall of the limit block, the inner walls of the first slide groove and the second slide groove are both slidably sleeved with the outer surface of the slider, the back side of the slider is fixedly connected with a connecting block, the outer surface of the connecting block is arc-shaped, and the arc surface of the connecting block is fixedly connected to an arc cylinder.
[0010] Preferably, one end of the piston rod of the arc-shaped cylinder is fixedly connected to a mounting block, the first cylinder is hinged on the left side of the front face of the mounting block through a pin shaft, the upper surface of the mounting block is hinged with a first swing plate and a second swing plate through a pin shaft, the first swing plate is located on the left side of the second swing plate, the lower surface of the mounting block is hinged with a third swing plate and a fourth swing plate through a pin shaft, the third swing plate is located on the left side of the fourth swing plate, wherein the first swing plate and the third swing plate are symmetrically distributed with the axis of the mounting block as the center of symmetry, and the second swing plate and the fourth swing plate are symmetrically distributed with the axis of the mounting block as the center of symmetry.
[0011] Preferably, the opposing surfaces of the first swing plate and the third swing plate are hinged to the outer surface of the shell of the second cylinder through pins, the opposing surfaces of the second swing plate and the fourth swing plate are hinged to the outer surface of the shell of the second cylinder through pins, one end of the piston rod of the first cylinder is fixedly connected with a T-shaped sliding block, the opposing surfaces of the first swing plate and the third swing plate are slidably connected to the outer surface of the sliding block, and the second cylinder is located above the sliding block.
[0012] Preferably, one end of the piston rod of the second cylinder is fixedly connected to a T-block, a clamping box is fixedly installed on the front of the T-block, a movable groove is opened on the right surface of the clamping box, the two clamping blocks are slidably sleeved on the inner wall of the movable groove, and the two clamping blocks are symmetrically distributed with the axis of the clamping box as the center of symmetry.
[0013] Preferably, the repelling surfaces of the two clamping blocks are hinged with a first connecting plate through a pin, one end of the first connecting plate is hinged with a symmetrically distributed second connecting plate through a pin, wherein each two opposite surfaces of the second connecting plates are fixedly connected with a reinforcing block, one end of the piston rod of the third cylinder is fixedly connected with a fixing block, the outer surface of the fixing block is hinged with a side surface of the second connecting plate through a pin, and another side surface of the second connecting plate is hinged with the outer surface of the shell of the third cylinder through a pin.
[0014] Preferably, a mounting groove is opened at the center of the rear inner wall of the movable groove, a guide rod is fixedly connected to the inner wall of the mounting groove, one end of the guide rod passes through and extends to the interior of the clamping box, and one end of the guide rod is slidably sleeved with a guide sleeve.
[0015] Preferably, the outer surface of the guide sleeve is hinged with a symmetrically distributed third connecting plate through a pin, one end of the third connecting plate is hinged with a symmetrically distributed fourth connecting plate through a pin, one end of the fourth connecting plate is fixedly connected to the outer surface of the second connecting plate, both side surfaces of the clamping box are fixedly connected with symmetrically distributed positioning blocks, the positioning blocks are located on the outside of the second connecting block, a connecting pin is hinged between the positioning block and the second connecting plate, and one end of the connecting pin passes through the reinforcement block.
[0016] Preferably, a construction device for initial positioning of a tunnel arch frame and an operating method of the use method are provided, and the specific operating method is as follows: step 1, first clamp the arch frame, the piston rod of the third cylinder extends, driving the second connecting plate to swing toward the outside of the clamping box with the axis of the connecting pin as the center of the circle, and the arch frame is clamped by the clamping block driven by the first connecting plate, and at the same time, the fourth connecting plate is hinged with the third connecting plate, and the third connecting plate is hinged with the guide plate, driving the guide sleeve to slide downward along the axis of the guide rod, wherein, since two clamping mechanisms are arranged on the third station plate, the length of the arch frame clamped on the third station plate is half of the length of the arch frame used by the first station plate, and the arch frame lengths used by the first station plate and the second station plate are consistent;
[0017] Step 2: Adjust the construction position of the arch frame. The servo motor drives the lead screw to make a circular motion. Since the lead screw is threadedly connected to the slider, and the slider is respectively slidably sleeved with the inner wall of the first slide groove and the second slide groove, the lead screw drives the slider to move left and right along the length direction of the construction vehicle while rotating. At the same time, the arch frame is adjusted left and right over a long distance through the displacement mechanism.
[0018] Step 3: The arc cylinder works to drive the mounting block to move in an arc shape along the arc track of the arc cylinder. At the same time, the arc cylinder is used to adjust the height of the arch frame in an arc shape.
[0019] Step 4: The first cylinder works to drive the first swing plate, the second swing plate, the third swing plate and the fourth swing plate to swing with the axis of the pin shaft connected to them as the center of the circle. When the first cylinder drives the first swing plate, the second swing plate, the third swing plate and the fourth swing plate to swing, it drives the second cylinder to swing along the width direction of the construction vehicle and drives the second cylinder to adjust the height. At the same time, the arch frame is adjusted forward and backward in an arc through the first cylinder.
[0020] Step 5: The piston rod of the second cylinder performs telescopic movement, driving the T-block and the clamping box to perform short-distance left-right adjustment along the length direction of the construction vehicle;
[0021] Step six, connect the adjacent arch frames through the above steps two to five, and fix the arch frames with bolts.
[0022] The beneficial effects of the present invention are:
[0023] 1. By setting up the displacement mechanism, the servo motor drives the lead screw to make circular motion. Since the lead screw is threadedly connected to the slider, and the slider is slidably sleeved with the inner walls of the first slide groove and the second slide groove respectively, the lead screw drives the slider to move left and right along the length direction of the construction vehicle while rotating. At the same time, the displacement mechanism can achieve the effect of long-distance left and right adjustment of the arch frame.
[0024] 2. By setting up the adjustment mechanism, the first cylinder works to drive the first swing plate, the second swing plate, the third swing plate and the fourth swing plate to swing with the axis of the pin shaft connected to them as the center of the circle, and when the first cylinder drives the first swing plate, the second swing plate, the third swing plate and the fourth swing plate to swing, it drives the second cylinder to swing along the width direction of the construction vehicle and drives the second cylinder to adjust the height. At the same time, the arch frame is adjusted forward and backward in an arc through the first cylinder, and the piston rod of the second cylinder performs telescopic movement, which drives the T-block and the clamping box to make a short-distance left and right adjustment along the length direction of the construction vehicle.
[0025] 3. By setting up the clamping mechanism, the arch frame is clamped by the third cylinder in the mechanism driving the clamping block, and then the arch frame is adjusted in multiple directions through the displacement mechanism and the adjustment mechanism, so that adjacent arch frames are connected, and the arch frame is fixed by bolts. Compared with the existing construction method, the arch frame construction device of the present invention not only greatly reduces the labor intensity of construction personnel and has high work efficiency, but also the construction time of the present invention is short. BRIEF DESCRIPTION OF THE DRAWINGS
[0026] Figure 1 A schematic diagram of a construction device and a method of use for initial positioning of a tunnel arch;
[0027] Figure 2 A three-dimensional diagram of a limit block structure of a construction device and a method of use for initial positioning of a tunnel arch;
[0028] Figure 3 A servo motor structure stereogram of a construction device and a method of using the device for initial positioning of a tunnel arch;
[0029] Figure 4 A three-dimensional diagram of the second cylinder structure of a construction device and a method of using the device for initial positioning of a tunnel arch;
[0030] Figure 5 A three-dimensional diagram of a clamping block structure of a construction device and a method of using the same for initial positioning of a tunnel arch;
[0031] Figure 6 An exploded diagram of a clamping box structure for a construction device and a method of use for initial positioning of a tunnel arch;
[0032] Figure 7 A three-dimensional diagram of a T-block structure of a construction device and a method of use for initial positioning of a tunnel arch;
[0033] Figure 8 A construction device and a method for using the construction device for initial positioning of a tunnel arch Figure 7 A magnified view of the structure in the middle.
[0034] In the figure: 1, construction vehicle; 2, bottom plate; 3, first step; 4, second step; 5, first station plate; 6, second station plate; 7, third station plate; 8, servo motor; 81, support plate; 82, limit block; 83, first slide; 84, second slide; 85, screw rod; 86, slider; 87, connecting block; 88, arc cylinder; 9, first cylinder; 91, mounting block; 92, first swing plate; 93, second swing plate; 94, third swing plate; 95, fourth swing plate; 96 , sliding block; 10, second cylinder; 11, third cylinder; 1101, T-block; 1102, clamping box; 1103, moving groove; 1104, first connecting plate; 1105, second connecting plate; 1106, reinforcing block; 1107, fixing block; 1108, mounting groove; 1109, guide rod; 11010, guide sleeve; 11011, third connecting plate; 11012, fourth connecting plate; 11013, positioning block; 11014, connecting pin; 12, clamping block. DETAILED DESCRIPTION
[0035] The technical solutions in the embodiments of the present invention will be described clearly and completely below in conjunction with the drawings in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, rather than all the embodiments.
[0036] Reference Figure 1-8A construction device and a method for using the initial positioning of a tunnel arch frame include a construction vehicle 1, bottom plates 2 are fixedly installed on both sides of the construction vehicle 1, four bottom plates 2 are grouped in pairs and are symmetrical with the axis of the construction vehicle 1, a first step 3 for walking up and down is fixedly installed on the upper surface of the bottom plate 2, a first work station plate 5 for construction is fixedly connected to the outlet end of the first step 3, a second step 4 for walking up and down is fixedly installed on the upper surface of the first step 3, a second work station plate 6 for construction is fixedly installed at the outlet end of the second step 4, and the upper surface of the construction vehicle 1 is supported by a support The frame is fixedly installed with a third work station plate 7 for construction. When the tunnel is under construction, five arch frames are required inside to support the inner wall of the tunnel to prevent the surrounding rock from loosening. The first work station plate 5, the second work station plate 6 and the third work station plate 7 of the present invention are used together to form five construction stations corresponding to the construction stations of the arch frame, which is convenient for installing the arch frame in the tunnel. The upper surfaces of the first work station plate 5, the second work station plate 6 and the third work station plate 7 are fixedly installed with a displacement mechanism, and the displacement mechanism includes a servo motor 8, which drives the arch frame to move linearly along its length;
[0037] An adjustment mechanism is fixedly installed above the displacement mechanism, and the adjustment mechanism includes a first cylinder 9 and a second cylinder 10. The first cylinder 9 drives the arch frame to move along the width direction of the construction vehicle 1, and the second cylinder 10 drives the arch frame to move along the left and right direction of the construction vehicle 1;
[0038] A clamping mechanism is fixedly installed on one side of the adjustment mechanism, and the clamping mechanism includes a third cylinder 11 and two clamping blocks 12. The third cylinder 11 drives the two clamping blocks 12 to contact the grooves of the arch frame from the front and back of the arch frame to clamp the arch frame.
[0039] Furthermore, in order to realize the long-distance left-right movement of the arch frame, the displacement mechanism also includes a support plate 81, the lower surfaces of the multiple support plates 81 are fixedly connected to the upper surfaces of the first work station plate 5, the second work station plate 6 and the third work station plate 7, respectively, and the servo motor 8 is fixedly installed on the upper surface of the support plate 81. The support plate 81 and the servo motor 8 are used in conjunction with each other to limit the installation position of the servo motor 8. The upper surfaces of the first work station plate 5, the second work station plate 6 and the third work station plate 7 are all fixedly installed with limit blocks 82. When the servo motor 8 in the displacement mechanism drives the arch frame to move left and right along the length direction of the construction vehicle 1, the limit blocks 82 are set to guide and limit the movement direction of the displacement mechanism. The cross-section of the limit block 82 is U-shaped, and the front inner wall and the rear inner wall of the limit block 82 are both provided with first slide grooves 83, and the upper surface of the limit block 82 is provided with symmetrically distributed second slide grooves 84.
[0040] Furthermore, in order to achieve arc-type height adjustment of the arch frame, the output shaft of the servo motor 8 is fixedly installed with a screw rod 85 through a coupling. The outer surface of the screw rod 85 is threadedly connected with a slider 86. The outer surface of the slider 86 is slidably connected to the inner wall of the limit block 82. The inner walls of the first slide groove 83 and the second slide groove 84 are both slidably sleeved with the outer surface of the slider 86. The servo motor 8 converts electrical energy into mechanical energy to drive the screw rod 85 to perform circular motion. Since the screw rod 85 is threadedly connected to the slider 86, the slider 86 is slidably sleeved with the inner walls of the first slide groove 83 and the second slide groove 84 respectively. The movable sleeve connection is formed, so when the screw rod 85 rotates, it drives the slider 86 to move left and right along the length direction of the construction vehicle 1. The movement range of the slider 86 driven by the screw rod 85 belongs to the prior art and will not be described in detail here. The back of the slider 86 is fixedly connected with a connecting block 87, and the outer surface of the connecting block 87 is in an arc shape. The arc surface of the connecting block 87 is fixedly connected with an arc cylinder 88. The slider 86, the connecting block 87 and the arc cylinder 88 are used together. When the slider 86 is moving, the arc cylinder 88 is driven by the connecting block 87 to move with the slider 86.
[0041] By setting up the displacement mechanism, the servo motor 8 drives the lead screw 85 to make a circular motion. Since the lead screw 85 is threadedly connected to the slider 86, and the slider 86 is slidably sleeved with the inner walls of the first slide groove 83 and the second slide groove 84 respectively, the lead screw 85 drives the slider 86 to move left and right along the length direction of the construction vehicle 1 while rotating. At the same time, the displacement mechanism can achieve the effect of long-distance left and right adjustment of the arch frame.
[0042] Furthermore, in order to realize the arc-type front and rear adjustment, one end of the piston rod of the arc cylinder 88 is fixedly connected to a mounting block 91, and the arc cylinder 88 is used in conjunction with the mounting block 91. When the arc cylinder 88 is working, it drives the mounting block 91 to make an arc motion along the arc track of the arc cylinder 88. The first cylinder 9 is hinged to the left side of the front face of the mounting block 91 through a pin shaft, and the upper surface of the mounting block 91 is hinged to the first swing plate 92 and the second swing plate 93 through the pin shaft, respectively. The first swing plate 92 is located on the left side of the second swing plate 93, and the lower surface of the mounting block 91 is hinged to the third swing plate 94 and the fourth swing plate 95 through the pin shaft. The movable plate 94 is located on the left side of the fourth swing plate 95, wherein the first swing plate 92 and the third swing plate 94 are symmetrically distributed with the axis of the mounting block 91 as the center of symmetry, and the second swing plate 93 and the fourth swing plate 95 are symmetrically distributed with the axis of the mounting block 91 as the center of symmetry. Because the first swing plate 92, the second swing plate 93, the third swing plate 94 and the fourth swing plate 95 are respectively arranged on the upper surface and the lower surface of the mounting block 91 through the pin shaft, when the first cylinder 9 is working, the first swing plate 92, the second swing plate 93, the third swing plate 94 and the fourth swing plate 95 will swing with the axis of the pin shaft connected to each of them as the center of the circle.
[0043] Furthermore, in order to achieve short-distance left-right adjustment of the arch frame, the surfaces of the first swing plate 92 and the third swing plate 94 are hinged to the outer surface of the shell of the second cylinder 10 through a pin shaft, and the surfaces of the second swing plate 93 and the fourth swing plate 95 are hinged to the outer surface of the shell of the second cylinder 10 through a pin shaft. When the first cylinder 9 drives the first swing plate 92, the second swing plate 93, the third swing plate 94 and the fourth swing plate 95 to swing, it drives the second cylinder 10 to swing along the width direction of the construction vehicle 1 and drives The second cylinder 10 is used for height adjustment. One end of the piston rod of the first cylinder 9 is fixedly connected to a T-shaped sliding block 96. The opposite surfaces of the first swing plate 92 and the third swing plate 94 are slidably connected to the outer surface of the sliding block 96. The second cylinder 10 is located above the sliding block 96. The first cylinder 9 is used in conjunction with the sliding block 96. When the piston rod of the first cylinder 9 is extended, the sliding block 96 is driven to slide on the opposite surfaces of the first swing plate 92 and the third swing plate 94, and at the same time drives the first swing plate 92 and the third swing plate 94 to swing.
[0044] By setting the adjustment mechanism, the first cylinder 9 is put into operation to drive the first swing plate 92, the second swing plate 93, the third swing plate 94 and the fourth swing plate 95 to swing with the axis of the pin shaft connected to each of them as the center of the circle, and when the first cylinder 9 drives the first swing plate 92, the second swing plate 93, the third swing plate 94 and the fourth swing plate 95 to swing, it drives the second cylinder 10 to swing along the width direction of the construction vehicle 1, and drives the second cylinder 10 to adjust the height. At the same time, the arch frame is adjusted forward and backward in an arc through the first cylinder 9, and the piston rod of the second cylinder 10 performs telescopic movement, which drives the T-block 1101 and the clamping box 1102 to perform short-distance left and right adjustment along the length direction of the construction vehicle 1.
[0045] Furthermore, in order to guide and limit the movement direction of the clamping block 12 in the movable groove 1103, one end of the piston rod of the second cylinder 10 is fixedly connected to the T-block 1101, and the front of the T-block 1101 is fixedly installed with a clamping box 1102. The second cylinder 10 is used in conjunction with the T-block 1101, and the piston rod of the second cylinder 10 performs telescopic movement, driving the T-block 1101 and the clamping box 1102 to adjust left and right along the length direction of the construction vehicle 1. A movable groove 1103 is provided on the right side surface of the clamping box 1102, and the two clamping blocks 12 are slidably sleeved on the inner wall of the movable groove 1103, wherein the two clamping blocks 12 are symmetrically distributed with the axis of the clamping box 1102 as the center of symmetry, and the movable groove 1103 is used in conjunction with the clamping block 12 to guide and limit the movement direction of the clamping block 12 in the movable groove 1103.
[0046] Furthermore, in order to achieve clamping of the arch frame, the repelling surfaces of the two clamping blocks 12 are hinged with a first connecting plate 1104 through a pin, and one end of the first connecting plate 1104 is hinged with a symmetrically distributed second connecting plate 1105 through a pin, wherein the opposite surfaces of each two second connecting plates 1105 are fixedly connected with a reinforcing block 1106, and one end of the piston rod of the third cylinder 11 is fixedly connected with a fixing block 1107, and the outer surface of the fixing block 1107 is hinged with a side surface of the second connecting plate 1105 through a pin, and another side surface of the second connecting plate 1105 is hinged with the outer surface of the shell of the third cylinder 11 through a pin. Since the clamping block 12 and the first connecting plate 1104, the first connecting plate 1104 and the second connecting plate 1105, and the second connecting plate 1105 and the third cylinder 11 are all hinged with pins, they are movably connected. Therefore, when the piston rod of the third cylinder 11 performs telescopic movement, it drives the clamping block 12 to clamp the arch frame.
[0047] Furthermore, in order to guide the movement direction of the guide sleeve 11010, an installation groove 1108 is opened at the center of the rear inner wall of the movable groove 1103, and the inner wall of the installation groove 1108 is fixedly connected with a guide rod 1109. The installation groove 1108 and the guide rod 1109 are used in conjunction with each other to limit and fix the installation position of the guide rod 1109. One end of the guide rod 1109 passes through and extends to the interior of the clamping box 1102. One end of the guide rod 1109 is slidably sleeved with the guide sleeve 11010. The guide rod 1109 and the guide sleeve 11010 are used in conjunction with each other to guide the movement direction of the guide sleeve 11010.
[0048] Furthermore, the outer surface of the guide sleeve 11010 is hinged with a symmetrically distributed third connecting plate 11011 through a pin shaft, and one end of the third connecting plate 11011 is hinged with a symmetrically distributed fourth connecting plate 11012 through a pin shaft, and one end of the fourth connecting plate 11012 is fixedly connected to the outer surface of the second connecting plate 1105, and both side surfaces of the clamping box 1102 are fixedly connected with symmetrically distributed positioning blocks 11013, and the positioning blocks 11013 are located on the outside of the second connecting block 87. A connecting pin shaft 11014 is hinged between the positioning block 11013 and the second connecting plate 1105, and one end of the connecting pin shaft 11014 passes through the reinforcing block 1106. The steps for clamping the arch frame are as follows: the piston rod of the third cylinder 11 extends to drive the The second connecting plate 1105 swings toward the outside of the clamping box 1102 with the axis of the connecting pin 11014 as the center of the circle, and drives the clamping block 12 to clamp the arch frame through the first connecting plate 1104. At the same time, the fourth connecting plate 11012 is hinged with the third connecting plate 11011, and the third connecting plate 11011 is hinged with the guide plate, driving the guide sleeve 11010 to slide downward along the axis of the guide rod 1109. The length of the arch frame clamped on the third workstation plate 7 is half of the length of the arch frame used by the first workstation plate 5, and the arch frame lengths used by the first workstation plate 5 and the second workstation plate 6 are the same. The reason is that two clamping mechanisms are arranged on the third workstation plate 7, so the length of the arch frame clamped by the two clamping mechanisms is equal to the length of the arch frame used by the first workstation plate 5.
[0049] By setting up the clamping mechanism, the third cylinder 11 in the mechanism drives the clamping block 12 to clamp the arch frame, and then the displacement mechanism and the adjustment mechanism are used to adjust the arch frame in multiple directions, so that adjacent arch frames can be connected, and the arch frame is fixed by bolts. Compared with the existing construction method, the arch frame construction device of the present invention not only greatly reduces the labor intensity of construction personnel and has high work efficiency, but also the construction time of the present invention is short.
[0050] Working principle: Step 1, first clamp the arch frame, the piston rod of the third cylinder 11 extends, driving the second connecting plate 1105 to swing toward the outside of the clamping box 1102 with the axis of the connecting pin 11014 as the center, and the clamping block 12 is driven by the first connecting plate 1104 to clamp the arch frame. At the same time, the fourth connecting plate 11012 is hinged with the third connecting plate 11011, and the third connecting plate 11011 is hinged with the guide plate, driving the guide sleeve 11010 to slide downward along the axis of the guide rod 1109. Since two clamping mechanisms are provided on the third station plate 7, the length of the arch frame clamped on the third station plate 7 is half of the length of the arch frame used by the first station plate 5, and the arch frame lengths used by the first station plate 5 and the second station plate 6 are consistent;
[0051] Step 2: Adjust the construction position of the arch frame. The servo motor 8 drives the screw rod 85 to make a circular motion. Since the screw rod 85 is threadedly connected to the slider 86, and the slider 86 is respectively slidably sleeved with the inner walls of the first slide groove 83 and the second slide groove 84, the screw rod 85 drives the slider 86 to move left and right along the length direction of the construction vehicle 1 while rotating. At the same time, the arch frame is adjusted left and right over a long distance through the displacement mechanism.
[0052] Step 3: The arc cylinder 88 works, driving the mounting block 91 to move in an arc shape along the arc track of the arc cylinder 88. At the same time, the arc cylinder 88 adjusts the height of the arch frame in an arc shape.
[0053] Step 4: The first cylinder 9 works to drive the first swing plate 92, the second swing plate 93, the third swing plate 94 and the fourth swing plate 95 to swing with the axis of the pin shaft connected to each of them as the center of the circle. When the first cylinder 9 drives the first swing plate 92, the second swing plate 93, the third swing plate 94 and the fourth swing plate 95 to swing, it drives the second cylinder 10 to swing along the width direction of the construction vehicle 1 and drives the second cylinder 10 to adjust the height. At the same time, the arch frame is adjusted forward and backward in an arc through the first cylinder 9;
[0054] Step 5: The piston rod of the second cylinder 10 performs telescopic movement, driving the T-block 1101 and the clamping box 1102 to perform short-distance left-right adjustment along the length direction of the construction vehicle 1;
[0055] Step six, connect the adjacent arch frames through the above steps two to five, and fix the arch frames with bolts.
[0056] The above description is only a preferred specific implementation manner of the present invention, but the protection scope of the present invention is not limited thereto. Any technician familiar with the technical field can make equivalent replacements or changes according to the technical scheme and inventive concept of the present invention within the technical scope disclosed by the present invention, which should be covered by the protection scope of the present invention.
Claims
1. A construction device for initial positioning of a tunnel arch, comprising a construction vehicle (1), characterized in that: Base plates (2) are fixedly mounted on both side surfaces of the construction vehicle (1), wherein four base plates (2) are arranged in groups of two and are symmetrical with respect to the axis of the construction vehicle (1); a first step (3) for walking up and down is fixedly mounted on the upper surface of the base plate (2); a first work station plate (5) for construction is fixedly connected to the outlet end of the first step (3); a second step (4) for walking up and down is fixedly mounted on the upper surface of the first step (3); a second work station plate (6) for construction is fixedly mounted on the outlet end of the second step (4); a third work station plate (7) for construction is fixedly mounted on the upper surface of the construction vehicle (1) via a bracket; a displacement mechanism is fixedly mounted on the upper surfaces of the first work station plate (5), the second work station plate (6) and the third work station plate (7), and the displacement mechanism comprises a servo motor (8), and the servo motor (8) drives the arch frame to perform linear motion along its length; An adjustment mechanism is fixedly installed above the displacement mechanism, and the adjustment mechanism comprises a first cylinder (9) and a second cylinder (10), the first cylinder (9) drives the arch frame to move along the width direction of the construction vehicle (1), and the second cylinder (10) drives the arch frame to move along the left and right direction of the construction vehicle (1); A clamping mechanism is fixedly installed on one side of the adjustment mechanism, and the clamping mechanism comprises a third cylinder (11) and two clamping blocks (12), and the third cylinder (11) drives the two clamping blocks (12) to contact the grooves of the arch frame from the front and back sides of the arch frame to clamp the arch frame; One end of the piston rod of the second cylinder (10) is fixedly connected to a T-block (1101), and a clamping box (1102) is fixedly installed on the front of the T-block (1101). A movable groove (1103) is provided on the right surface of the clamping box (1102), and the two clamping blocks (12) are slidably sleeved on the inner wall of the movable groove (1103), wherein the two clamping blocks (12) are symmetrically distributed with the axis of the clamping box (1102) as the symmetry center, and the repelling surfaces of the two clamping blocks (12) are hinged with a first connecting plate (1104) through a pin shaft, and one end of the first connecting plate (1104) is hinged with a symmetrically distributed second connecting plate (1105) through a pin shaft, wherein every two of the second connecting plates (1105) are relatively The surfaces of the movable groove (1103) are fixedly connected with a reinforcing block (1106), one end of the piston rod of the third cylinder (11) is fixedly connected with a fixing block (1107), the outer surface of the fixing block (1107) is hinged to the surface of one side of the second connecting plate (1105) through a pin, and the other side surface of the second connecting plate (1105) is hinged to the outer surface of the shell of the third cylinder (11) through a pin, a mounting groove (1108) is opened at the center of the rear inner wall of the movable groove (1103), the inner wall of the mounting groove (1108) is fixedly connected with a guide rod (1109), one end of the guide rod (1109) passes through and extends to the interior of the clamping box (1102), and one end of the guide rod (1109) is slidably sleeved with a guide sleeve (11010); The outer surface of the guide sleeve (11010) is hinged with a symmetrically distributed third connecting plate (11011) through a pin shaft, and one end of the third connecting plate (11011) is hinged with a symmetrically distributed fourth connecting plate (11012) through a pin shaft, and one end of the fourth connecting plate (11012) is fixedly connected to the outer surface of the second connecting plate (1105), and both side surfaces of the clamping box (1102) are fixedly connected with symmetrically distributed positioning blocks (11013), and the positioning blocks (11013) are located on the outside of the second connecting block (87), and a connecting pin shaft (11014) is hinged between the positioning block (11013) and the second connecting plate (1105), and one end of the connecting pin shaft (11014) passes through the reinforcing block (1106).
2. A construction device for initial positioning of a tunnel arch according to claim 1, characterized in that: The displacement mechanism further comprises a support plate (81), the lower surfaces of the plurality of support plates (81) are respectively fixedly connected to the upper surfaces of the first work station plate (5), the second work station plate (6) and the third work station plate (7), the servo motor (8) is fixedly mounted on the upper surface of the support plate (81), the upper surfaces of the first work station plate (5), the second work station plate (6) and the third work station plate (7) are all fixedly mounted with a limit block (82), the cross section of the limit block (82) is U-shaped, the front inner wall and the rear inner wall of the limit block (82) are both provided with a first slide groove (83), and the upper surface of the limit block (82) is provided with a symmetrically distributed second slide groove (84).
3. A construction device for initial positioning of a tunnel arch according to claim 2, characterized in that: The output shaft of the servo motor (8) is fixedly mounted with a screw rod (85) through a coupling, the outer surface of the screw rod (85) is threadedly connected with a slider (86), the outer surface of the slider (86) is slidably connected to the inner wall of the limit block (82), the inner walls of the first slide groove (83) and the second slide groove (84) are both slidably sleeved with the outer surface of the slider (86), the back of the slider (86) is fixedly connected with a connecting block (87), the outer surface of the connecting block (87) is in an arc shape, and the arc surface of the connecting block (87) is fixedly connected with an arc cylinder (88).
4. A construction device for initial positioning of a tunnel arch according to claim 3, characterized in that: One end of the piston rod of the arc-shaped cylinder (88) is fixedly connected to a mounting block (91); the first cylinder (9) is hinged to the left side of the front face of the mounting block (91) through a pin shaft; the upper surface of the mounting block (91) is hinged to a first swing plate (92) and a second swing plate (93) through a pin shaft, respectively; the first swing plate (92) is located on the left side of the second swing plate (93); the lower surface of the mounting block (91) is hinged to a third swing plate (94) and a fourth swing plate (95) through a pin shaft, respectively; the third swing plate (94) is located on the left side of the fourth swing plate (95); the first swing plate (92) and the third swing plate (94) are symmetrically distributed with the axis of the mounting block (91) as the symmetry center; the second swing plate (93) and the fourth swing plate (95) are symmetrically distributed with the axis of the mounting block (91) as the symmetry center.
5. A construction device for initial positioning of a tunnel arch according to claim 4, characterized in that: The opposing surfaces of the first swing plate (92) and the third swing plate (94) are hinged to the outer surface of the shell of the second cylinder (10) through a pin shaft, and the opposing surfaces of the second swing plate (93) and the fourth swing plate (95) are hinged to the outer surface of the shell of the second cylinder (10) through a pin shaft. One end of the piston rod of the first cylinder (9) is fixedly connected to a T-shaped sliding block (96), and the opposing surfaces of the first swing plate (92) and the third swing plate (94) are slidably connected to the outer surface of the sliding block (96), and the second cylinder (10) is located above the sliding block (96).
6. According to claim 5, an operation method of a construction device for initial positioning of a tunnel arch frame, the operation method is as follows: step 1, first clamp the arch frame, the piston rod of the third cylinder (11) extends, driving the second connecting plate (1105) to swing toward the outside of the clamping box (1102) with the axis of the connecting pin (11014) as the center of the circle, and the clamping block (12) is driven by the first connecting plate (1104) to clamp the arch frame, and at the same time, the fourth connecting plate (1105) is driven to move the clamping block (12) ... 012) is hinged with the third connecting plate (11011), and the third connecting plate (11011) is hinged with the guide plate, driving the guide sleeve (11010) to slide downward along the axis of the guide rod (1109), wherein since the third station plate (7) is provided with two clamping mechanisms, the length of the arch frame clamped on the third station plate (7) is half of the length of the arch frame used by the first station plate (5), and the length of the arch frame used by the first station plate (5) and the second station plate (6) is consistent; Step 2: Adjust the construction position of the arch frame. The servo motor (8) drives the screw rod (85) to make a circular motion. Since the screw rod (85) is threadedly connected to the slider (86), and the slider (86) is respectively slidably sleeved with the inner wall of the first slide groove (83) and the second slide groove (84), the screw rod (85) drives the slider (86) to move left and right along the length direction of the construction vehicle (1). At the same time, the arch frame is adjusted left and right over a long distance through the displacement mechanism. Step 3: The arc cylinder (88) works to drive the mounting block (91) to move in an arc shape along the arc track of the arc cylinder (88). At the same time, the arc cylinder (88) performs arc-shaped height adjustment on the arch frame; Step 4: The first cylinder (9) operates to drive the first swing plate (92), the second swing plate (93), the third swing plate (94) and the fourth swing plate (95) to swing with the axis of the pin shaft connected to them as the center of the circle. When the first cylinder (9) drives the first swing plate (92), the second swing plate (93), the third swing plate (94) and the fourth swing plate (95) to swing, it drives the second cylinder (10) to swing along the width direction of the construction vehicle (1) and drives the second cylinder (10) to adjust the height. At the same time, the arch frame is adjusted forward and backward in an arc through the first cylinder (9); Step 5: The piston rod of the second cylinder (10) performs telescopic movement, driving the T-block (1101) and the clamping box (1102) to perform short-distance left-right adjustment along the length direction of the construction vehicle (1); Step six, connect the adjacent arch frames through the above steps two to five, and fix the arch frames with bolts.
Citation Information
Patent Citations
Trolley for tunnel arch centre operation
CN108167003A
Operation rack for tunnel supporting construction
CN113074005A