A mounting assembly and a flange anti-tilt mounting method for a water electrolysis hydrogen production pipeline

By using pipe clamps and flange positioners for the installation components, the problem of experience and repeated adjustments in the installation of electrolytic hydrogen-making pipe flange is solved, and the rapid, efficient and safe flange anti-tilt installation is achieved, which improves construction Quality and efficiency.

CN115122040BActive Publication Date: 2025-02-11CHINA ELEVENTH CHEM CONSTR
View PDF 4 Cites 0 Cited by

Patent Information

Application Number
CN202210761479.5
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-06-29
Publication Date
2025-02-11
Estimated Expiration
2042-06-29

AI Technical Summary

Technical Problem

The installation of existing electrolytic water-making hydrogen pipeline flanges depends on the experience of the operator, and the repeated adjustments are highly random, which wastes time, manpower and material resources, and poses safety hazards.

Method used

An installation assembly is provided, including a pipe clamp and a flange positioner, which adjusts the horizontality of the pipe through the pipe clamp and adjusts the verticality of the flange through the flange positioner to ensure the anti-tilt installation of the flange.

Benefits of technology

It realizes the installation standards of flange set pairs, is simple to operate, is easy to use and assemble, is safe and reliable, is suitable for large-scale operations, and improves construction quality and comprehensive benefits.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115122040B_ABST
    Figure CN115122040B_ABST
Patent Text Reader

Abstract

The present invention provides a mounting assembly and a flange anti-tilt mounting method for a water electrolysis hydrogen production pipeline. The mounting assembly is used for the installation of the flange of the water electrolysis hydrogen production pipeline, and includes a pipeline clamp, including a first clamping member, a second clamping member and an adjusting member, the first clamping member and the second clamping member are connected by the adjusting member, and the first clamping member and the second clamping member are formed with a spacing for clamping the water electrolysis hydrogen production pipeline; a flange positioning member, which is connected to the pipeline clamp and formed with a positioning portion, and the positioning portion is formed with a positioning plane, and the positioning plane is used to abut with the flange to be installed at the end of the water electrolysis hydrogen production pipeline. The present invention ensures the horizontality through the pipeline clamp and the verticality of the flange through the flange positioning member, thereby meeting the installation standard of the flange of the water electrolysis hydrogen production pipeline, is simple to operate, safe and reliable, suitable for large-scale flange assembly, and the mounting assembly can be reused, saving materials and having good economy.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present application relates to the technical field of water electrolysis hydrogen production, and in particular to an installation component and a flange anti-tilt installation method for a water electrolysis hydrogen production pipeline. Background Art

[0002] The development of green hydrogen energy from water electrolysis has ushered in opportunities. At present, the technology has been industrialized. The installation of hydrogen pipelines for water electrolysis is one of the important points and difficulties in the installation of water electrolysis hydrogen production. Hydrogen is a Class A explosive and dangerous flammable gas with flammable and explosive chemical properties. The flange group must not be tilted during the installation of the hydrogen pipeline to prevent hydrogen leakage.

[0003] The conventional method of assembling flanges for horizontal pipes is as follows: the point at the top of the pipe cross section is called the 0 degree point, the point at the bottom of the pipe cross section is called the 180 degree point, and the left and right points of the pipe cross section are called the 90 degree point and the 270 degree point respectively. The flange is pre-installed at the end of the horizontal pipe, and the flange is spot welded at the 0 degree position of the pipe. Then, a plumb line is placed on the upper part of the flange to check whether the plumb line fits the flange. If there is a gap, adjust the flange inclination until the plumb line fits the flange. Then, spot weld the flange at the 180 degree point of the pipe to ensure that the verticality meets the flange inclination requirements in accordance with the specifications. Then, rotate the flange 90 degrees. At this time, the original 270 degree point of the pipe cross section is rotated to the 0 degree point, and the original 90 Rotate the flange to the 180-degree point, repeat the above steps, spot weld the original 270-degree point first, then put a plumb line on the upper part of the flange to check whether the plumb line fits the flange. If there is a gap, adjust the flange inclination until the plumb line fits the flange, and then spot weld the flange at the original 90-degree point of the pipeline to ensure that the verticality meets the requirements of the flange inclination. The verticality deviation in both directions meets the requirements, and the flange inclination can be confirmed to be qualified.

[0004] The above conventional practices all rely on the operator's experience to adjust the deviation. Repeated adjustments are highly random, wasting installation time and manpower and material resources. In addition, the deviation is different each time, which may cause safety hazards.

[0005] Therefore, it is necessary to develop a new flange anti-tilt installation method for the water electrolysis hydrogen production pipeline to solve the above-mentioned shortcomings. Summary of the invention

[0006] In view of this, in order to overcome the defects of the prior art, the present invention provides a mounting assembly and a flange anti-tilt installation method for a water electrolysis hydrogen production pipeline, which effectively solves the problem that the installation of the existing water electrolysis hydrogen production pipeline flange depends entirely on the experience of the operator, repeated adjustments are highly random, and installation time and manpower and material resources are wasted.

[0007] According to a first aspect of the present invention, there is provided a mounting assembly for mounting a flange of a water electrolysis hydrogen production pipeline, wherein the mounting assembly comprises a pipeline clamp, comprising a first clamping member, a second clamping member and an adjusting member, wherein the first clamping member and the second clamping member are connected via the adjusting member, and a spacing is formed between the first clamping member and the second clamping member for clamping the water electrolysis hydrogen production pipeline; a flange positioning member, which is connected to the pipeline clamp and has a positioning portion, wherein the positioning portion has a positioning plane, and the positioning plane is used to abut against a flange to be installed at the end of the water electrolysis hydrogen production pipeline.

[0008] Preferably, the flange positioning member further includes a rotating shaft, and the flange positioning member is pivotally connected to the pipe clamping member via the rotating shaft, so that the angle between the positioning plane of the positioning portion and the water electrolysis hydrogen production pipeline can be adjusted.

[0009] Preferably, the adjusting member comprises a first arc track and a second arc track, the first arc track is connected to the first clamping member, the second arc track is connected to the second clamping member, and the first arc track and the second arc track are connected by an adjusting bolt.

[0010] Preferably, the first clamping member and the second clamping member are both formed into a first plate-like structure, and the opposite surfaces of the two first plate-like structures are used to clamp the electrolysis water hydrogen production pipeline; the flange positioning member includes a first positioning plate and a second positioning plate, the first positioning plate and the second positioning plate are both formed with the positioning plane, the first positioning plate and the second positioning plate are both formed into a second plate-like structure, and the two second plate-like structures are respectively connected to the two first plate-like structures.

[0011] According to a second aspect of the present invention, a flange anti-tilt installation method for a water electrolysis hydrogen production pipeline is provided, wherein the flange of the water electrolysis hydrogen production pipeline is installed using the installation assembly as described above, and the flange anti-tilt installation method for the water electrolysis hydrogen production pipeline comprises adjusting the horizontality of the water electrolysis hydrogen production pipeline so that the horizontality of the water electrolysis hydrogen production pipeline meets the operating standard; clamping the water electrolysis hydrogen production pipeline by the pipe clamp; pre-installing the flange at the end of the water electrolysis hydrogen production pipeline; adjusting the angle of the positioning plane of the positioning part of the flange positioning member relative to the water electrolysis hydrogen production pipeline so that the positioning plane abuts the flange, thereby positioning the flange; welding the positioned flange to the water electrolysis hydrogen production pipeline; and disassembling the installation assembly.

[0012] Preferably, the horizontality of the water electrolysis hydrogen production pipeline is adjusted by an adjustment component, which includes an operating bracket; a channel steel placed on the operating bracket; a round steel welded to the flange plate of the channel steel; and the water electrolysis hydrogen production pipeline is used to be placed on the round steel.

[0013] Preferably, before the pipe clamp clamps the electrolysis water hydrogen production pipe, two parallel straight lines are placed on the working bracket on both sides of the electrolysis water hydrogen production pipe, and the first clamping member and the second clamping member are adjusted so that the clamping surfaces of the first clamping member and the second clamping member for clamping the electrolysis water hydrogen production pipe coincide with the corresponding parallel straight lines respectively.

[0014] Preferably, when the flange is a planar flange, the positioning plane of the flange positioning member is perpendicular to the electrolysis water hydrogen production pipeline; when the flange is a neck flange, the flange positioning member and the pipeline clamping member are rotated through a rotating shaft so that the positioning plane abuts the neck flange, and an angle corresponding to the neck of the neck flange is formed between the positioning plane and the electrolysis water hydrogen production pipeline.

[0015] Preferably, when the flange is a neck flange, before the pipe clamp clamps the water electrolysis hydrogen production pipeline, two reference lines are placed on the working bracket, the two reference lines coincide with the water electrolysis hydrogen production pipeline and the pre-installed neck flange, and the first clamping member, the second clamping member and the flange positioning member are adjusted to coincide with the two reference lines.

[0016] Preferably, the welding is spot welding.

[0017] According to the installation component and the flange anti-tilt installation method of the water electrolysis hydrogen production pipeline of the present invention, the horizontality during installation is ensured by the pipeline clamping piece of the installation component, and the verticality of the flange during installation is ensured by the flange positioning piece of the installation component, so that the installation standard of the flange pairing of the water electrolysis hydrogen production pipeline is achieved, the operation is simple, the use and assembly are convenient, safe and reliable, and it is particularly suitable for the operation of large-scale flange pairing, which improves the quality of pipeline construction and increases the comprehensive benefits of the project. It has the characteristics of fast, efficient, flexible, simple and high safety. In addition, the installation component can be reused, saves materials and has good economy.

[0018] In order to make the above-mentioned objects, features and advantages of the present application more obvious and easy to understand, preferred embodiments are specifically cited below and described in detail with reference to the attached drawings. BRIEF DESCRIPTION OF THE DRAWINGS

[0019] In order to more clearly illustrate the technical solutions of the embodiments of the present application, the drawings required for use in the embodiments will be briefly introduced below. It should be understood that the following drawings only show certain embodiments of the present application and therefore should not be regarded as limiting the scope. For ordinary technicians in this field, other related drawings can be obtained based on these drawings without paying creative work.

[0020] Figure 1 A schematic diagram showing the structure of an installation assembly according to an embodiment of the present invention is shown;

[0021] Figure 2 Another schematic structural diagram of the installation assembly according to an embodiment of the present invention is shown;

[0022] Figure 3 A schematic diagram showing the structure of an adjustment component according to an embodiment of the present invention is shown;

[0023] Figure 4 A structural schematic diagram showing a flange anti-tilt installation method for a water electrolysis hydrogen production pipeline according to an embodiment of the present invention;

[0024] Figure 5 Another structural schematic diagram showing a flange anti-tilt installation method for a water electrolysis hydrogen production pipeline according to an embodiment of the present invention;

[0025] Figure 6 Another structural schematic diagram shows a flange anti-tilt installation method for a water electrolysis hydrogen production pipeline according to an embodiment of the present invention.

[0026] Figure markings: 1-water electrolysis hydrogen production pipeline; 2-flange; 3-neck flange; 4-first clamping member; 5-second clamping member; 6-first arc track; 7-second arc track; 8-adjusting bolt; 9-connecting bolt; 10-first positioning plate; 11-second positioning plate; 12-first reference line; 13-second reference line; 14-third reference line; 15-fourth reference line; 16-fifth reference line; 17-sixth reference line; 18-channel steel; 19-first round steel; 20-second round steel; 21-rotating shaft. DETAILED DESCRIPTION

[0027] The following specific embodiments are provided to help the reader obtain a comprehensive understanding of the methods, devices and / or systems described herein. However, after understanding the disclosure of the present application, various changes, modifications and equivalents of the methods, devices and / or systems described herein will be apparent. For example, the order of operations described herein is merely an example, and is not limited to the order set forth herein, but in addition to the operations that must occur in a particular order, changes that will be apparent after understanding the disclosure of the present application may be made. In addition, in order to improve clarity and brevity, the description of features known in the art may be omitted.

[0028] The features described herein may be implemented in different forms and should not be interpreted as being limited to the examples described herein. Rather, the examples described herein have been provided only to illustrate some of the many possible ways of implementing the methods, devices and / or systems described herein that will be apparent after understanding the disclosure of the present application.

[0029] Throughout the specification, when an element (such as a layer, a region, or a substrate) is described as being “on”, “connected to”, “bound to”, “over”, or “covering” another element, it may be directly “on”, “connected to”, “bound to”, “over”, or “covering” another element, or one or more other elements may be present between them. In contrast, when an element is described as being “directly on”, “directly connected to”, “directly bound to”, “directly over”, or “directly covering” another element, there may be no other elements present between them.

[0030] As used herein, the term "and / or" includes any one of the associated listed items and any combination of any two or more items.

[0031] Although terms such as "first," "second," and "third" may be used herein to describe various members, components, regions, layers, or portions, these members, components, regions, layers, or portions are not limited by these terms. Rather, these terms are only used to distinguish one member, component, region, layer, or portion from another member, component, region, layer, or portion. Therefore, without departing from the teachings of the examples described herein, the first member, component, region, layer, or portion referred to may also be referred to as the second member, component, region, layer, or portion.

[0032] For ease of description, spatial relational terms such as "above", "upper", "below", and "lower" may be used herein to describe the relationship of one element to another element as shown in the accompanying drawings. Such spatial relational terms are intended to include different orientations of the device in use or operation in addition to the orientation depicted in the accompanying drawings. For example, if the device in the accompanying drawings is turned over, an element described as being "above" or "upper" relative to another element will subsequently be "below" or "lower" relative to the other element. Therefore, the term "above" includes both "above" and "below" orientations depending on the spatial orientation of the device. The device may also be positioned in other ways (e.g., rotated 90 degrees or in other orientations), and the spatial relational terms used herein will be interpreted accordingly.

[0033] The terms used herein are only used to describe various examples and are not used to limit the present disclosure. Unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. The terms "include", "comprise" and "have" list the stated features, quantities, operations, components, elements and / or their combinations that exist, but do not exclude the existence or addition of one or more other features, quantities, operations, components, elements and / or their combinations.

[0034] Variations in the shapes shown in the drawings may occur due to manufacturing techniques and / or tolerances. Therefore, the examples described herein are not limited to the specific shapes shown in the drawings but include variations in shapes that occur during manufacturing.

[0035] The features of the examples described herein may be combined in various ways that will be apparent after understanding the disclosure of the present application. In addition, although the examples described herein have various configurations, other configurations are possible as will be apparent after understanding the disclosure of the present application.

[0036] According to a first aspect of the present invention, there is provided a mounting assembly, such as Figure 1 and Figure 2 As shown, the installation assembly is used for installing the flange 2 of the water electrolysis hydrogen production pipeline 1, and the installation assembly includes a pipeline clamp and a flange positioning member.

[0037] In the following description, reference will be made to Figure 1 and Figure 2 The detailed structures of the pipe clamp and flange positioning member of the installation assembly are specifically described.

[0038] like Figure 1 and Figure 2As shown, in an embodiment, the pipe clamp may include a first clamping member 4, a second clamping member 5 and an adjusting member. The first clamping member 4 and the second clamping member 5 may be, for example, a rectangular plate supported by a metal material such as stainless steel or aluminum alloy. In an embodiment, the size of the rectangular plate may be, for example, 200 mm in length, 5 mm in width, and 150 mm in height. The first clamping member 4 and the second clamping member 5 can be connected by an adjusting member, and the adjusting member can include a first arc track 6 and a second arc track 7. The first arc track 6 and the second arc track 7 can be, for example, an arc structure supported by a metal material such as stainless steel or aluminum alloy. The arc structure is provided with an arc through hole along the central axis. The first arc track 6 and the second arc track 7 are connected by an adjusting bolt 8. The adjusting bolt 8 passes through the arc through hole provided by the first arc track 6 and the second arc track 7. The angle and position of the first arc track 6 and the second arc track 7 can be adjusted by locking or loosening the adjusting bolt 8. The first arc track 6 and the second arc track 7 are respectively connected to the first clamping member 4 and the second clamping member 5 by connecting bolts 9. In this way, when you want to change the spacing between the first clamping member 4 and the second clamping member 5, loosen the adjusting bolt 8, adjust the angle and position of the first arc track 6 and the second arc track 7, and then lock the adjusting bolt 8. In the embodiment, the width of the first arc track 6 and the second arc track 7 may be 24 mm, the width of the arc through hole may be 12 mm, and the adjustment bolt 8 may be, for example, a single-head M12 hexagonal bolt.

[0039] like Figure 1 , Figure 2 and Figure 6 As shown, in an embodiment, the flange positioning member may include a first positioning plate 10 and a second positioning plate 11. The first positioning plate 10 and the second positioning plate 11 may be, for example, a rectangular plate supported by a metal material such as stainless steel or aluminum alloy. In an embodiment, the size of the rectangular plate may be, for example, 100 mm in length, 5 mm in width, and 200 mm in height. The flange positioning member may also include a rotating shaft 21, and the first positioning plate 10 and the second positioning plate 11 may be connected to the first clamping member 4 and the second clamping member 5 respectively through the rotating shaft 21. The rotating shaft 21 is a structural member in the prior art, and may be, for example, a structure similar to a door shaft. The first positioning plate 10 and the second positioning plate 11 abut against the flange 2 to be installed. In this way, the first positioning plate 10 or the second positioning plate 11 are both formed with a positioning plane for abutting the flange, and the angle with the first clamping member 4 or the second clamping member 5 may be adjusted through the rotating shaft 21 to adapt to different types of flanges (for example, Figure 6As shown, when the flange is a neck flange 3, the first positioning plate 10 or the second positioning plate 11 forms an angle with the first clamping member 4 or the second clamping member 5, that is, when the flange is a planar flange, the positioning plane of the flange positioning member coincides with the planar flange, and at this time, the positioning plane is perpendicular to the electrolysis water hydrogen production pipeline 1; when the flange is a neck flange 3, the positioning plane of the flange positioning member forms an angle with the electrolysis water hydrogen production pipeline 1 to correspond to the angle of the neck of the neck flange 3).

[0040] It should be noted here that the metal materials selected for the above-mentioned components can effectively extend the life of the installation component and realize the function of multiple uses. In addition, the strength and rigidity of the installation component can also be increased.

[0041] The installation component adjusts the horizontality with the electrolysis water hydrogen production pipeline 1 through the pipeline clamp (it should be noted that the horizontality of the electrolysis water hydrogen production pipeline 1 mentioned here is the standard in the prior art. Since the electrolysis water hydrogen production pipeline 1 passes through the flammable and explosive hydrogen, the horizontality of the electrolysis water hydrogen production pipeline 1 needs to meet the operating standards), and abuts the flange 2 through the flange positioning piece to ensure the verticality of the flange 2 and the electrolysis water hydrogen production pipeline 1, thereby realizing the anti-tilt installation of the flange 2.

[0042] In addition, if Figures 3 to 6 As shown, according to the second aspect of the present invention, a flange anti-tilt installation method for a water electrolysis hydrogen production pipeline is provided, and the above-mentioned installation component is provided, and the flange 2 is installed on the water electrolysis hydrogen production pipeline 1 through the above-mentioned installation component.

[0043] The flange anti-tilt installation method of the water electrolysis hydrogen production pipeline comprises:

[0044] Adjust the horizontality of the electrolytic water hydrogen production pipeline 1 so that the horizontality of the electrolytic water hydrogen production pipeline 1 meets the operation standard;

[0045] Clamp the water electrolysis hydrogen production pipeline 1 by a pipeline clamp;

[0046] Pre-install the flange 2 at the end of the water electrolysis hydrogen production pipeline 1;

[0047] Adjust the angle of the positioning plane of the positioning part of the flange positioning member relative to the water electrolysis hydrogen production pipeline 1 so that the positioning plane abuts against the flange 2, thereby positioning the flange 2;

[0048] The positioned flange 2 is welded to the electrolytic water hydrogen production pipeline 1;

[0049] Remove the mounting assembly.

[0050] Specifically, the first step of the method for preventing the flange of the electrolytic water hydrogen production pipeline from tilting requires adjusting the level of the electrolytic water hydrogen production pipeline 1 so that the level of the electrolytic water hydrogen production pipeline 1 meets the operation standard (it should be noted here that the level of the electrolytic water hydrogen production pipeline 1 mentioned here is the standard in the prior art. Since the hydrogen passing through the electrolytic water hydrogen production pipeline 1 is flammable and explosive, the level of the electrolytic water hydrogen production pipeline 1 needs to meet the operation standard), as Figure 3 shown. In the embodiment, the level of the electrolytic water hydrogen production pipeline 1 can be adjusted by an adjustment assembly. The adjustment assembly can include an operation support (not shown), a channel steel 18, a first round steel 19, and a second round steel 20. The operation support can be, for example, a device in the prior art, and the level of the operation support meets the operation requirements of the electrolytic water hydrogen production pipeline 1. The channel steel 18 can be, for example, a steel material formed into a U-shaped structure. The first round steel 19 and the second round steel 20 can be, for example, stainless steel round steels with a diameter of 10 mm. The first round steel 19 and the second round steel 20 can be respectively welded to the two flange plates of the channel steel 18. In this way, the channel steel 18 can be placed on the operation support, the first round steel 19 and the second round steel 20 are placed away from the operation support, and then the electrolytic water hydrogen production pipeline 1 is placed on the first round steel 19 and the second round steel 20. In this way, the level of the electrolytic water hydrogen production pipeline 1 is ensured.

[0051] The second step requires clamping the electrolytic water hydrogen production pipeline 1 by a pipeline clamping member. Before clamping the electrolytic water hydrogen production pipeline 1 by the pipeline clamping member, lay wires on the operation support and place two parallel straight lines, as Figure 5 shown. In the embodiment, they can be, for example, a first reference line 12 and a second reference line 13. As shown in Figure 6, in the embodiment, they can be, for example, a third reference line 14 and a sixth reference line 17 (it should be noted here that Figure 6 shown is the installation of the necked flange 3. Therefore, a fourth reference line 15 and a fifth reference line 16 need to be additionally set. The included angles formed between the fourth reference line 15 and the fifth reference line 16 and the third reference line 14 and the sixth reference line 17 respectively can correspond to the angle of the neck of the necked flange to ensure that the necked flange 3 and the electrolytic water hydrogen production pipeline 1 meet the installation standard. In this way, corresponding to the above-mentioned first positioning plate 10 and second positioning plate 11, it is convenient for the installation of the necked flange 3). The distance between the two parallel straight lines is the same as the diameter of the electrolytic water hydrogen production pipeline 1. The pipeline clamping member is placed on the parallel straight lines, and by adjusting the first arc track 6 and the second arc track 7, the clamping surfaces of the first clamping member 4 and the second clamping member 5 are respectively made to coincide with the two parallel straight lines. In this way, the distance between the first clamping member 4 and the second clamping member 5 is adjusted to be the same as the diameter of the electrolytic water hydrogen production pipeline 1.

[0052] The third step is to pre-install the flange 2 at the end of the electrolytic water hydrogen production pipeline 1;

[0053] The fourth step is to abut the flange 2 with the flange locating piece. After the pipe clamping piece clamps the electrolysis water hydrogen production pipeline 1, the flange locating piece is close to the end of the electrolysis water hydrogen production pipeline 1 where the flange 2 needs to be installed. Then the first positioning plate 10 and the second positioning plate 11 are abutted against the flange 2 to be installed. In this way, the horizontality required for installation is ensured by the pipe clamping piece, and the verticality of the flange 2 is ensured by the flange locating piece.

[0054] Step 5: Figure 4 As shown, in the embodiment, the flange 2 is welded to the water electrolysis hydrogen production pipeline 1, and the welding can be, for example, spot welding.

[0055] Step 6: Dismantle the installation components to complete the installation. The dismantled installation components can continue to be put into use.

[0056] The flange anti-tilt installation method of the water electrolysis hydrogen production pipeline solves the problem of low efficiency and multiple flange direction adjustment when the flange 2 is installed on the water electrolysis hydrogen production pipeline 1. The flange anti-tilt installation method of the water electrolysis hydrogen production pipeline ensures the horizontality required for installation through the pipeline clamping member of the installation component, and ensures the verticality of the flange 2 through the flange positioning member of the installation component. The operation is simple, the use and assembly are convenient, and the method is safe and reliable. It is particularly suitable for large-scale flange assembly operations, improves the quality of pipeline construction, and increases the comprehensive benefits of the project. It has the characteristics of being fast, efficient, flexible, simple, and highly safe. In addition, the installation components can be reused, saving materials and being economical.

[0057] Finally, it should be noted that the above-described embodiments are only specific implementation methods of the present application, which are used to illustrate the technical solutions of the present application, rather than to limit them. The protection scope of the present application is not limited thereto. Although the present application is described in detail with reference to the above-described embodiments, ordinary technicians in the field should understand that any technician familiar with the technical field can still modify the technical solutions recorded in the above-described embodiments within the technical scope disclosed in the present application, or can easily think of changes, or make equivalent replacements for some of the technical features therein; and these modifications, changes or replacements do not make the essence of the corresponding technical solutions deviate from the spirit and scope of the technical solutions of the embodiments of the present application, and should be included in the protection scope of the present application. Therefore, the protection scope of the present application shall be subject to the protection scope of the claims.

Claims

1. A mounting assembly for mounting a flange of a water electrolysis hydrogen production pipeline, characterized in that: The installation assembly includes: A pipeline clamping member, comprising a first clamping member, a second clamping member and an adjusting member, wherein the first clamping member and the second clamping member are connected via the adjusting member, and a distance is formed between the first clamping member and the second clamping member for clamping the electrolytic water hydrogen production pipeline; A flange positioning member connected to the pipe clamping member and formed with a positioning portion, wherein the positioning portion is formed with a positioning plane, and the positioning plane is used to abut against a flange to be installed at the end of the electrolytic water hydrogen production pipeline; The adjusting member comprises a first arc track and a second arc track, the first arc track is connected to the first clamping member, the second arc track is connected to the second clamping member, and the first arc track and the second arc track are connected by an adjusting bolt; The flange positioning member further includes a rotating shaft, and the flange positioning member is pivotally connected to the pipeline clamping member via the rotating shaft, so that the angle between the positioning plane of the positioning portion and the electrolysis water hydrogen production pipeline can be adjusted; The first clamping member and the second clamping member are both formed into a first plate-like structure, and the opposite surfaces of the two first plate-like structures are used to clamp the electrolysis water hydrogen production pipeline; the flange positioning member includes a first positioning plate and a second positioning plate, and the first positioning plate and the second positioning plate are both formed with the positioning plane, and the first positioning plate and the second positioning plate are both formed into a second plate-like structure, and the two second plate-like structures are respectively connected to the two first plate-like structures.

2. A flange anti-tilt installation method for a water electrolysis hydrogen production pipeline, characterized in that: The flange of the water electrolysis hydrogen production pipeline is installed by using the installation assembly according to claim 1, and the flange anti-tilt installation method of the water electrolysis hydrogen production pipeline comprises: Adjusting the horizontality of the electrolytic water hydrogen production pipeline so that the horizontality of the electrolytic water hydrogen production pipeline meets the operation standard; Clamp the water electrolysis hydrogen production pipeline by the pipeline clamp; Pre-installing the flange at the end of the water electrolysis hydrogen production pipeline; Adjusting the angle of the positioning plane of the positioning portion of the flange positioning member relative to the water electrolysis hydrogen production pipeline so that the positioning plane abuts against the flange, thereby positioning the flange; Welding the positioned flange to the water electrolysis hydrogen production pipeline; disassembling the installation assembly; The horizontality of the electrolytic water hydrogen production pipeline is adjusted by an adjustment component, and the adjustment component includes: an operation bracket; a channel steel, which is placed on the operation bracket; a round steel, which is welded to the flange plate of the channel steel; the electrolytic water hydrogen production pipeline is used to be placed on the round steel; Before the pipe clamp clamps the water electrolysis hydrogen production pipe, two parallel straight lines are placed on the work support at both sides of the water electrolysis hydrogen production pipe, and the first clamping member and the second clamping member are adjusted so that the clamping surfaces of the first clamping member and the second clamping member for clamping the water electrolysis hydrogen production pipe respectively coincide with the corresponding parallel straight lines; When the flange is a flat flange, the positioning plane of the flange positioning member is perpendicular to the electrolysis water hydrogen production pipeline; when the flange is a neck flange, the flange positioning member and the pipeline clamping member are rotated through a rotating shaft so that the positioning plane abuts the neck flange, and an angle corresponding to the neck of the neck flange is formed between the positioning plane and the electrolysis water hydrogen production pipeline.

3. The flange anti-tilt installation method of the water electrolysis hydrogen production pipeline according to claim 2 is characterized in that: When the flange is a neck flange, before the pipe clamp clamps the water electrolysis hydrogen production pipeline, two reference lines are placed on the work bracket, the two reference lines coincide with the water electrolysis hydrogen production pipeline and the pre-installed neck flange, and the first clamping member, the second clamping member and the flange locating member are adjusted to coincide with the two reference lines.

4. The flange anti-tilt installation method of the water electrolysis hydrogen production pipeline according to claim 2 is characterized in that: The welding is spot welding.

Citation Information

Patent Citations

  • Petroleum pipeline support

    CN104913114A

  • BIM-based cylindrical steel-structured vertical skew positioning and connecting device