A tunnel support structure in strongly weathered mudstone stratum and its construction method
Through the flexible assembly of arc-shaped arch bars and the design of limit components, the problem of poor support effect caused by unstable welding of the steel arch is solved, the stability of the tunnel in strongly weathered mudstone strata is improved, and the risk of collapse is reduced.
Patent Information
- Application Number
- CN202211002380.3
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-08-22
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-08-22
AI Technical Summary
During the construction of tunnels in strongly weathered mudstone strata, due to the inconsistent curvature of the inner wall of the tunnel after the steel arch was welded and formed, some positions could not be stably contacted, resulting in poor support and increased risk of collapse.
Multiple sections of arc-shaped arch bars are used, connected through movable plug-in grooves and bumps, combined with limit components and elastic connecting rods, to achieve flexible assembly and stable compression of the arch bars, ensuring the tightness between the arch bars and the inner wall of the tunnel. touch.
The support effect of the steel arch on the inner wall of the tunnel in strongly weathered mudstone strata is improved, reducing the risk of collapse. The contact area between the arch bar and the inner wall of the tunnel is increased through fillers, which enhances stability.
Smart Images

Figure CN115263374B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of tunnel support, and in particular to a tunnel support structure in a strongly weathered mudstone formation and a construction method thereof. Background Art
[0002] With the large-scale construction of tunnel projects, the problems and challenges we encounter in the tunnel construction process have increased dramatically, and the construction risks have also become increasingly greater. Tunnels will inevitably pass through many complex strata during construction. Among them, weak surrounding rock strata are a common geological condition with low rock strength, significant deformation when disturbed, and poor bearing capacity, which brings extremely severe challenges to tunnel construction. Strongly weathered mudstone, as a typical representative of weak surrounding rock, has the unfavorable characteristics of easy disintegration and collapse when exposed to water, and has creep and long-term strength reduction, so timely drainage is required during construction.
[0003] When constructing in strongly weathered mudstone formations, the tunnel body is excavated first, and then the entrance is supported. The tunnel is then excavated inward along the entrance, and the excavated sand and gravel are discharged. Then the inner wall of the tunnel is initially supported. During the initial support process, it is necessary to spray concrete on the inner wall of the tunnel, set up steel supply racks, install anchor rods and steel mesh, and spray concrete on the mesh. After completing the initial support, the invert is excavated, and the invert is initially supported, formwork is erected, and concrete is poured. Finally, the inner wall of the tunnel is lined twice to make the inner wall of the tunnel closed into a ring.
[0004] The steel supply frame used in the initial support process needs to be cut into place in one go according to the total length of the tunnel steel arch frame, and then cold-bent into shape as a whole, and then cut into sections according to the cross-section size set in the tunnel excavation plan to form arch frame strips. Then, each section of the arch frame strip is transported to the tunnel, and each section of the arch frame strip is welded together to form an arc-shaped steel arch frame, so that the steel arch frame can be installed in the tunnel.
[0005] With respect to the above-mentioned related technologies, the inventor believes that there are the following defects: when two adjacent arch frames are welded together, in order to ensure the stability of the welding of the two adjacent arch frames, the ends of the two adjacent arch frames are often made to abut in parallel. Since it is difficult to ensure the same curvature of the inner wall of the tunnel during tunnel excavation, some parts of the welded steel arch frames cannot stably abut against the inner wall of the tunnel, resulting in poor support effect of the steel arch frames on the inner wall of the tunnel, which in turn leads to the collapse of the inner wall of the tunnel in the strongly weathered mudstone formation. Summary of the invention
[0006] In order to improve the problem of poor support effect of steel arch frames on the inner wall of a tunnel in a strongly weathered mudstone formation, the present application provides a support structure for a tunnel in a strongly weathered mudstone formation and a construction method thereof.
[0007] In the first aspect, the present application provides a tunnel support structure in a strongly weathered mudstone formation, which adopts the following technical solution:
[0008] A tunnel support structure in a strongly weathered mudstone formation comprises a plurality of arc-shaped arch bars, one end of the arch bar being provided with a groove, the length direction of the groove being consistent with the radial direction of a circle in which the arch bar is located, the other end of the arch bar being fixedly connected with a protrusion movably plugged into the groove, the protrusion being provided with a connecting hole penetrating along the width direction of the groove, a connecting rod for rotatably connecting with the connecting hole on the protrusion being provided in the groove on the arch bar, and a limiting component for limiting the rotation of the protrusion on the connecting rod toward the inner side of the arch bar being provided at the end of the arch bar.
[0009] By adopting the above technical solution, when constructing a tunnel support structure, first transport multiple arc-shaped arch bars into the tunnel, then fix one arch bar on the inner wall of the tunnel, and then splice the other arch bar with the fixed arch bar. When splicing two arch bars, first insert the protrusion on one arch bar into the groove of the other fixed arch bar, and make the connecting rod pass through the connecting hole, at this time the protrusion is rotated and connected in the groove of the arch bar. Then rotate the unfixed arch bar toward the inner wall of the tunnel, at this time the protrusion rotates in the groove, and when the unfixed arch bar abuts against the inner wall of the tunnel, stop rotating the arch bar, at this time the arch bar is stably pressed against the inner wall of the tunnel under the limiting action of the limit assembly. In this way, multiple sections of arch frame strips are assembled to form a steel arch frame, so that each section of the arch frame strip is pressed against the inner wall of the tunnel, thereby improving the supporting effect of the steel arch frame on the inner wall of the tunnel in the strongly weathered mudstone formation, making it less likely for the inner wall of the tunnel in the strongly weathered mudstone formation to collapse.
[0010] Optionally, one end of the groove close to the inner side of the arch frame bar is opened, and two connecting rods are provided. The two connecting rods are respectively vertically and elastically connected to the inner walls on both sides of the groove, and the connecting line of the two connecting rods is consistent with the width direction of the groove. The ends of the two connecting rods close to each other are provided with guide surfaces, and the guide surfaces are located on the side of the connecting rod close to the inner wall of the arch frame bar.
[0011] By adopting the above technical solution, when splicing two arch frame strips, the protrusion on one arch frame strip is first inserted into the groove from the open end of the groove of the other fixed arch frame strip. As the protrusion is inserted, the protrusion contacts the guide surfaces of the two connecting rods, and the two connecting rods are pushed to shrink in the direction away from each other through the guide surfaces. When the connecting rods are aligned with the connecting holes, the two connecting rods are automatically reset. At this time, the two connecting rods are both inserted into the connecting holes of the protrusions, and the protrusions are rotatably connected in the grooves through the two connecting rods, thereby quickly realizing the rotational connection of the two arch frame strips.
[0012] Optionally, the limiting assembly includes a ratchet fixed on the protrusion and a pawl hinged on the inner wall of the groove and adapted to be engaged with the ratchet, the center hole of the ratchet is aligned with the connecting hole, the pawl is located on the side of the connecting rod close to the outer wall of the arch bar, and the free end of the pawl is movably engaged with the ratchet.
[0013] By adopting the above technical solution, the center hole of the ratchet is aligned with the connecting hole, so that when one arch bar is driven to rotate around the end of another fixed arch bar, the ratchet rotates around the connecting rod synchronously and stably. The pawl is hingedly arranged on the inner wall of the groove and is located on the side of the connecting rod close to the outer wall of the arch bar, so that when the ratchet is stationary, the pawl can stably abut on the ratchet. Under the action of the ratchet and the pawl, the arch bar to be fixed can only rotate around the end of the fixed arch bar toward the inner wall of the tunnel, so that the arch bar can be stably pressed against the inner wall of the tunnel.
[0014] Optionally, the end face of the protrusion away from the arch bar is set as an arc surface, the center of the circle where the arc surface is located coincides with the center of the connecting hole, and when the connecting rod is inserted into the connecting hole, the arc surface of the protrusion is set to abut against the bottom wall of the groove.
[0015] By adopting the above technical solution, since the center of the circle where the arc surface is located coincides with the center of the connecting hole, when assembling the arch frame strips, it is only necessary to abut the arc surface of the protrusion on the arch frame strip to be fixed against the bottom wall of the groove on the fixed arch frame strip, and then push the protrusion into the groove, so that the connecting rod in the groove can be quickly aligned and inserted into the connecting hole of the protrusion, thereby improving the efficiency of the rotational connection between the two arch frame strips and shortening the assembly cycle of the steel supply frame.
[0016] Optionally, a grouting hole is penetrated through the inner wall of one side of the groove, a first shielding component is arranged on the arch frame bar at the opening end of the groove, and a second shielding component for covering the notch of the groove is arranged on the arch frame bar on the surrounding side of the protrusion.
[0017] By adopting the above technical solution, after the arch frame strips are assembled and positioned, grout is injected into the groove through the grouting hole, and the first shielding component and the second shielding component shield the open end and the notch of the groove to minimize the slurry overflow so that the slurry is stored in the groove. After the slurry solidifies, two adjacent arch frame strips are stably connected, so that each section of the arch frame strip can be stably connected to form a steel arch frame, thereby stably supporting the inner wall of the tunnel.
[0018] Optionally, the first shielding assembly includes two shielding plates, which are respectively vertically and elastically connected to the inner walls on both sides of the groove, and the ends of the two shielding plates close to each other are movably abutted against each other, and the ends of the two shielding plates close to each other are both provided with a slope, and the slope is located on the side of the shield away from the connecting rod.
[0019] By adopting the above technical solution, when two arch frame strips are spliced, the protrusion on one arch frame strip is first inserted into the groove from the open end of the groove of the other fixed arch frame strip, and the protrusion first contacts the inclined surfaces of the two shielding plates, and as the protrusion is inserted, the two shielding plates are pushed to shrink in the direction away from each other. When the protrusion is inserted into the groove and does not abut against the shielding plate, the free end of the shielding plate moves in the direction away from the inner wall of the groove on the same side, and at this time, the ends of the two shielding plates that are close to each other are abutted against each other, thereby realizing automatic shielding of the open end of the groove.
[0020] Optionally, the second shielding assembly includes an accordion cover and a telescopic spring arranged in the accordion cover, two ends of the telescopic spring are respectively fixed to two ends of the accordion cover, the accordion cover is sleeved on the circumferential side of the protrusion, and one end of the accordion cover is sealedly connected to one end of the arch frame bar where the protrusion is provided, and the other end is detachably connected to the notch end face of the adjacent arch frame bar where the groove is provided.
[0021] By adopting the above technical solution, one end of the accordion cover is sealed and connected to one end of the arch frame bar with a protrusion. When the telescopic spring is not compressed, the telescopic spring is in the original length state. At this time, the accordion cover can cover and protect the protrusion on the arch frame bar, and avoid the protrusion and / or ratchet from being damaged when the arch frame bar is transported as much as possible. After the two sections of the arch frame bar are spliced, the other end of the accordion cover is connected to the notch of the groove of the adjacent arch frame bar, so that the accordion cover is partially enclosed and sleeved on the splicing part of the two sections of the arch frame bar, so that when grouting is injected into the groove, the slurry can be stably stored in the groove of the arch frame bar. Due to the combined design of the accordion cover and the telescopic spring, when driving the two adjacent arch frame bars to rotate relative to each other, the accordion cover can still stably block the notch of the groove, thereby minimizing the overflow of the slurry from the notch of the groove, which not only saves the use of slurry, but also ensures the stability of the connection between the two adjacent arch frame bars.
[0022] Optionally, a first sealing strip is provided on the end surfaces of the two shielding plates abutting against each other, and a second sealing strip is provided on the end surface of the accordion cover away from the protrusion.
[0023] By adopting the above technical solution, the first sealing strip is set, so that when the two shields are in contact with each other, the ends of the shields are not easily damaged, and the gap between the two shields is also filled, so as to prevent the slurry in the groove from overflowing from the gap between the two shields as much as possible. The second sealing strip is set to improve the sealing and shielding effect of the accordion cover on the groove notch, so as to prevent the slurry in the groove from overflowing from the groove notch as much as possible.
[0024] Optionally, a filling piece for filling a gap between the arch bar and the inner wall of the tunnel is provided on the outer wall of the arch bar.
[0025] By adopting the above technical solution, the filling piece can fill the gap between the arch frame bar and the inner wall of the tunnel, thereby increasing the abutment area between the inner wall of the tunnel and the arch frame bar, so that the arch frame bar can stably support the inner wall of the tunnel, thereby making it less likely for the inner wall of the tunnel in the strongly weathered mudstone formation to collapse.
[0026] In the second aspect, the present application provides a construction method of a tunnel support structure in a strongly weathered mudstone formation, which adopts the following technical solution:
[0027] S1, initial spraying of concrete, spraying concrete on the inner wall of the tunnel and waiting for the concrete to solidify;
[0028] S2, assembling the arch frame bars, transporting multiple sections of the arch frame bars into the tunnel for assembly, driving two adjacent sections of the arch frame bars to rotate relative to each other, and locking the arch frame bars so that each section of the arch frame bars is tightly pressed against the inner wall of the tunnel;
[0029] S3, fixed connection of the arch strip, grouting is injected into the groove of the arch strip, and after the grouting solidifies, two adjacent arch strips are stably connected;
[0030] S4, installing anchor rods and steel mesh, inserting the anchor rods into the inner wall of the tunnel, and hanging the steel mesh on the arch bars and anchor rods;
[0031] S5, spraying concrete, spraying concrete onto the steel mesh, and forming a reinforced concrete layer with the steel mesh after the concrete is cured.
[0032] By adopting the above technical solution, after the inner wall of the tunnel is excavated and cleaned, concrete is first sprayed onto the inner wall of the tunnel, and after the concrete solidifies, an initial support for the inner wall of the tunnel can be formed. Then, multiple sections of arch frame strips are transported into the tunnel for assembly of the arch frame strips. When assembling the arch frame strips, first, an arch frame strip is fixedly installed at the bottom of one side of the inner wall of the tunnel through an anchor rod, and the outer wall of the arch frame strip is abutted against the inner wall of the tunnel, and the end of the arch frame strip with a groove is away from the bottom direction of the tunnel. Then, the protrusion on another arch frame strip is inserted into the groove on the fixed arch frame strip, and the arch frame strip is driven to rotate around one end of the fixed arch frame strip until the arch frame strip is tightly against the inner wall of the tunnel, and finally the two adjacent arch frame strips are locked and fixed, so that each section of the arch frame strip is tightly against the inner wall of the tunnel.
[0033] After the arch bars are assembled, grout is injected into the grooves of the arch bars. After the grout solidifies, the two adjacent arch bars are stably connected. At this time, multiple arch bars are connected to form a steel arch, which provides stable support for the inner wall of the tunnel. After the steel arch is installed, the anchor rods are inserted into the inner wall of the tunnel, and the steel mesh is hung on the arch bars and anchor rods. Concrete is sprayed on the steel mesh. After the concrete solidifies, it forms a reinforced concrete layer with the steel mesh, thereby improving the stable support for the inner wall of the tunnel in the strongly weathered mudstone formation.
[0034] In summary, the present application includes at least one of the following beneficial technical effects:
[0035] 1. The steel arch frame is mainly composed of multiple sections of arch frame bars hinged together. The angle between two adjacent sections of arch frame bars can be adjusted according to the curvature of the tunnel inner wall, so that each section of the arch frame bar is tightly pressed against the tunnel inner wall, thereby improving the supporting effect of the steel arch frame on the inner wall of the tunnel in the strongly weathered mudstone formation, making it less likely for the inner wall of the tunnel in the strongly weathered mudstone formation to collapse;
[0036] 2. The filling piece can fill the gap between the arch bar and the inner wall of the tunnel, increasing the contact area between the inner wall of the tunnel and the arch bar, so that the arch bar can stably support the inner wall of the tunnel, thereby making it less likely for the inner wall of the tunnel in the strongly weathered mudstone formation to collapse;
[0037] 3. After the arch bars are assembled and positioned, grout is injected into the groove through the grouting holes. The first shielding component and the second shielding component shield the open end and the notch of the groove to minimize the slurry overflow and keep the slurry in the groove. After the slurry solidifies, the two adjacent arch bars are stably connected, so that each section of the arch bar can be stably connected to form a steel arch, thereby stably supporting the inner wall of the tunnel. BRIEF DESCRIPTION OF THE DRAWINGS
[0038] Figure 1 It is a schematic diagram of the overall structure of a tunnel support structure in a strongly weathered mudstone formation in an embodiment of the present application.
[0039] Figure 2 It is a schematic diagram of the partial cross-sectional structure of the arch frame bar in the embodiment of the present application, which is mainly used to show the connection method between the connecting rod and the shield plate.
[0040] Figure 3 It is a schematic diagram of the structure of the arch bar, the protrusion, the second shielding component and the filling member in the embodiment of the present application.
[0041] Figure 4 It is a schematic diagram of a partial cross-sectional structure of the second shielding component in the embodiment of the present application.
[0042] Figure 5 It is a schematic flow chart of a construction method of a tunnel support structure in a strongly weathered mudstone formation in an embodiment of the present application.
[0043] Figure numerals: 1. arch bar; 2. groove; 3. protrusion; 4. connecting hole; 5. connecting rod; 61. ratchet; 62. pawl; 7. guide surface; 8. arc surface; 9. grouting hole; 10. shield plate; 11. inclined surface; 12. second shielding assembly; 121. accordion cover; 122. telescopic spring; 13. first sealing strip; 14. second sealing strip; 15. filling piece; 16. guide rod; 17. float; 18. first spring; 19. second spring; 20. conduit; 21. water-swelling waterstop strip. DETAILED DESCRIPTION
[0044] The following is combined with Figure 1-5 This application is described in further detail.
[0045] The embodiment of the present application discloses a tunnel support structure in a strongly weathered mudstone formation.
[0046] Reference Figure 1 A tunnel support structure in a strongly weathered mudstone formation includes a plurality of arc-shaped arch bars 1, which are sequentially connected to form a steel arch, and the ends of two adjacent arch bars 1 are connected by rotation, and the center of the circle where each arch bar 1 is located is located on the inner side of the steel arch. The two arch bars 1 connected by rotation can be pressed against the inner wall of the tunnel by adjusting the angle between the two arch bars 1. A filling member 15 for filling the gap between the arch bar 1 and the inner wall of the tunnel is provided on the outer wall of the arch bar 1. The filling member 15 can be an air bag or a water-swellable water stop block. In the embodiment of the present application, the filling member 15 is configured as an air bag, and the air bag is fixed to the outer wall of the arch bar 1 by waterproof adhesive.
[0047] Reference Figure 2 and Figure 3, a groove 2 is provided at one end of the arch bar 1, and a protrusion 3 movably plugged into the groove 2 is fixedly connected to the other end. The length direction of the groove 2 is consistent with the radial direction of the circle where the arch bar 1 is located, and the end of the groove 2 close to the inner side of the arch bar 1 is set as an opening. A catheter 20 is connected and fixedly connected to the airbag, and the catheter 20 is pre-buried and fixed in the arch bar 1, and the end of the catheter 20 away from the airbag is connected to the groove 2. The end face of the protrusion 3 away from the arch bar 1 is set as an arc surface 8, and the size of the protrusion 3 along the length direction of the groove 2 is the width size of the protrusion 3. In the embodiment of the present application, the width size of the protrusion 3 is smaller than the length size of the groove 2, and the length size of the protrusion 3 is greater than the depth size of the groove 2. A connecting hole 4 is provided on the protrusion 3 along the width direction of the groove 2, and a connecting rod 5 for rotatably connecting with the connecting hole 4 on the protrusion 3 is provided in the groove 2 on the arch bar 1. The connecting rod 5 can be one or more. In the embodiment of the present application, two connecting rods 5 are provided.
[0048] Reference Figure 2 and Figure 3 , mounting holes are correspondingly opened on the inner walls of both sides of the groove 2 on the arch bar 1, one end of the connecting rod 5 is located in the mounting hole, and the other end is located outside the mounting hole. A first spring 18 is arranged in the mounting hole of the arch bar 1, one end of the first spring 18 is fixedly connected to the end of the connecting rod 5, and the other end is fixedly connected to the bottom wall of the mounting hole. Under the action of the first spring 18, the connecting rod 5 is vertically and elastically connected to the inner wall of the groove 2. When the two first springs 18 are at their original length, the distance between the two connecting rods 5 and one end thereof is greater than the thickness of the protrusion 3.
[0049] In order to facilitate the insertion of the protrusion 3 into the groove 2, the connecting rod 5 can be automatically and quickly inserted into the connecting hole 4 of the protrusion 3, referring to Figure 2 and Figure 3 A guide surface 7 is provided at one end of the two connecting rods 5 close to each other, and the guide surface 7 is located on a side of the connecting rod 5 close to the inner wall of the arch bar 1.
[0050] When it is necessary to connect the ends of two adjacent arch frame strips 1 by rotation, first fix one arch frame strip 1 at the bottom of one side of the inner wall of the tunnel, and make the outer wall of the arch frame strip 1 abut against the inner wall of the tunnel, and the end of the arch frame strip 1 with the groove 2 faces away from the bottom direction of the tunnel; then insert the protrusion 3 on one arch frame strip 1 into the groove 2 from the open end of the groove 2 of the other fixed arch frame strip 1, and make the arc surface 8 of the protrusion 3 abut against the bottom wall of the groove 2 on the fixed arch frame strip 1; as the protrusion 3 is inserted, the protrusion 3 contacts the guide surfaces 7 of the two connecting rods 5, and the two connecting rods 5 are pushed to shrink in the direction away from each other through the guide surfaces 7; when the connecting rod 5 is aligned with the connecting hole 4, the two connecting rods 5 are automatically reset, and at this time, the two connecting rods 5 are both inserted into the connecting hole 4 of the protrusion 3, and the protrusion 3 is rotatably connected in the groove 2 through the two connecting rods 5, thereby quickly realizing the rotation connection of the two arch frame strips 1.
[0051] After completing the rotational connection between two adjacent arch frame bars 1, the arch frame bar 1 to be fixed is driven to rotate around one end of the fixed arch frame bar 1 toward the inner wall of the tunnel, so that the arch frame bar 1 to be fixed is pressed against the inner wall of the tunnel. In order to ensure that the arch frame bar 1 to be fixed can be stably pressed against the inner wall of the tunnel, a limit assembly is provided at the end of the arch frame bar 1 for limiting the rotation of the protrusion 3 on the connecting rod 5 toward the inner side of the arch frame bar 1.
[0052] Reference Figure 2 and Figure 3 The limiting assembly includes a ratchet 61 fixed to the protrusion 3 and a ratchet 62 hinged to the inner wall of the groove 2 and adapted to the ratchet 61. Each protrusion 3 corresponds to two ratchets 61, and the two ratchets 61 are respectively fixed to the two side walls of the protrusion 3. The center hole of the ratchet 61 is aligned with the connecting hole 4, and the aperture of the center hole of the ratchet 61 is not less than the aperture size of the connecting hole 4. In the embodiment of the present application, the aperture size of the center hole of the ratchet 61 is the same as the aperture size of the connecting hole 4.
[0053] Reference Figure 2 and Figure 3 There are two pawls 62, which correspond to the two ratchet wheels 61. The two pawls 62 are located on the side of the connecting rod 5 close to the outer wall of the arch bar 1, and one end of the pawl 62 is rotatably connected to the inner wall of the groove 2 through the rotating shaft. A torsion spring is sleeved on the rotating shaft, one torsion arm of the torsion spring is fixedly connected to the pawl 62, and the other torsion arm is fixedly connected to the inner wall of the groove 2. When the torsion spring is in an unstressed state, the end of the pawl 62 away from the rotating shaft is tilted to point to the notch direction of the groove 2 and is movably engaged with the ratchet wheel 61.
[0054] In the process of driving the projection 3 to be inserted into the groove 2, the ratchet 61 contacts the pawl 62. As the ratchet 61 approaches, the pawl 62 rotates in the direction away from the bottom wall of the groove 2 under the push of the sawtooth of the ratchet 61, and the torsion spring is twisted. When the connecting rod 5 passes through the center hole of the ratchet 61 and is inserted into the connecting hole 4 of the projection 3, the projection 3 is rotated and connected to the connecting rod 5. At this time, the pawl 62 is pressed and buckled on the sawtooth of the ratchet 61 under the drive of the torsion spring. Under the joint action of the ratchet 61 and the ratchet teeth, the end of the projection 3 located outside the groove 2 can only rotate around the connecting rod 5 toward the inner wall of the tunnel, so that the arch frame bar 1 to be fixed can rotate and press against the inner wall of the tunnel, and at the same time, the arch frame bar 1 to be fixed can be pre-locked and fixed on one end of the fixed arch frame bar 1.
[0055] In order to ensure that the arch frame bar 1 to be fixed can be stably pressed against the inner wall of the tunnel, refer to Figure 2 and Figure 3A grouting hole 9 is provided on the inner wall of one side of the groove 2, and slurry can be injected into the groove 2 through the grouting hole 9. After the slurry solidifies, the two sections of the arch bar 1 are stably connected, and at this time, the arch bar 1 can be stably pressed against the inner wall of the tunnel.
[0056] Since one end of the groove 2 is open, Figure 2 and Figure 3 A first shielding assembly is provided at the open end of the groove 2 on the arch bar 1. The first shielding assembly includes two shielding plates 10. Embedding grooves are provided on the inner walls on both sides of the groove 2. The two embedded grooves are aligned and arranged. Second springs 19 are arranged in the two embedded grooves. The ends of the two shielding plates 10 that are away from each other are respectively slidably arranged in the two embedded grooves and fixedly connected to one end of the corresponding second spring 19. The end of the second spring 19 that is away from the shielding plates 10 is fixedly connected to the groove bottom wall of the embedded groove. The two shielding plates 10 are respectively vertically and elastically connected to the inner walls on both sides of the groove 2 through the corresponding second springs 19. The second spring 19 is always in a compressed state. The ends of the two shielding plates 10 that are close to each other are movably abutted under the action of the two second springs 19. The ends of the two shielding plates 10 that are close to each other are each provided with an inclined surface 11, and the inclined surface 11 is located on the side of the shielding plates 10 that is away from the connecting rod 5.
[0057] When the two shielding plates 10 are disposed in contact with each other, in order to improve the sealing performance of the two shielding plates 10 to the opening end of the groove 2, refer to Figure 2 and Figure 3 The first sealing strip 13 is provided on the end surfaces of the two shields 10 that abut against each other. The first sealing strip 13 is set as a rubber strip. The rubber strip is bonded and fixed to the end of the shield 10 away from the second spring 19, so that when the two shields 10 abut against each other, the end of the shield 10 is not easily damaged, and the gap between the two shields 10 is also filled. Water-swelling water stop strips 21 are bonded to both ends of the rubber strip on the shield 10 through waterproof glue.
[0058] Since the notch of the groove 2 is open, in order to cover the notch of the groove 2, refer to Figure 3 and Figure 4, a second shielding assembly 12 for covering the notch of the groove 2 is provided on the arch bar 1 on the peripheral side of the protrusion 3. The second shielding assembly 12 includes an accordion cover 121 and a telescopic spring 122 arranged in the accordion cover 121, the accordion cover 121 is sleeved on the peripheral side of the protrusion 3, and one end of the accordion cover 121 is sealed and connected to the end of the arch bar 1 provided with the protrusion 3. The air hood is arranged in a double layer, the telescopic spring 122 is located in the interlayer of the accordion cover 121, and a plurality of telescopic springs 122 are arranged, and a plurality of telescopic springs 122 are arranged in the interlayer of the accordion cover 121 at intervals, and the two ends of the telescopic spring 122 are respectively fixed to the two ends of the accordion cover 121. When the telescopic spring 122 is at its original length, the arc surface 8 of the protrusion 3 is located in the accordion cover 121, and the accordion cover 121 can cover the protrusion 3 and the ratchet 61, thereby preventing the protrusion 3 and / or the ratchet 61 from being damaged.
[0059] Reference Figure 3 and Figure 4 A bolt is provided on the end of the accordion cover 121 away from the protrusion 3, and a threaded hole matching the bolt thread is provided on the end surface of the arch frame bar 1 provided with the groove 2. When it is necessary to rotatably connect one arch frame bar 1 with another fixed arch frame bar 1, it is only necessary to compress the accordion cover 121 to expose the protrusion 3, and then rotatably connect the protrusion 3 to the connecting rod 5. At this time, the accordion cover 121 is elastically pressed against the notch of the groove 2 under the drive of the telescopic spring 122, and then the bolt is tightened and fixed on the notch end surface of the groove 2 through the threaded hole. At this time, the accordion cover 121 can effectively cover the notch of the groove 2.
[0060] In order to further improve the sealing performance between the end surface of the accordion cover 121 and the end surface of the groove 2, refer to Figure 3 and Figure 4 The second sealing strip 14 is arranged on the end surface of the bellows cover 121 away from the protrusion 3. The second sealing strip 14 is in a closed ring shape and is made of a damping material. The second sealing strip 14 is fixed to the end surface of the bellows cover 121 away from the protrusion 3 by waterproof adhesive. When the bellows cover 121 is tightened and fixed to the notch end surface of the groove 2 by bolts, the second sealing strip 14 can seal and fill the gap between the end surface of the bellows cover 121 and the notch end surface of the groove 2.
[0061] When the ends of two adjacent arch frame strips 1 are rotated and connected, the arch frame strip 1 to be fixed is rotated around one end of the fixed arch frame strip 1, so that the arch frame strip 1 to be fixed is pressed against the inner wall of the tunnel. At this time, the arch frame strip 1 to be fixed is pre-fixed under the joint action of the ratchet 61 and the pawl 62. Then, slurry is injected into the groove 2 through the grouting hole 9, the first shielding component shields the open end of the groove 2, and the second shielding component 12 shields the notch of the groove 2 to minimize the overflow of slurry. The slurry can fill the groove 2 and the cavity of the airbag. At this time, the airbag expands, and the expanded airbag can fill the gap between the outer wall of the arch frame strip 1 and the inner wall of the tunnel, so that the arch frame strip 1 is pressed against the inner wall of the tunnel. After the slurry in the groove 2 solidifies, the two adjacent arch frame strips 1 are stably connected, so that each section of the arch frame strip 1 can be stably connected to form a steel arch, thereby stably supporting the inner wall of the tunnel.
[0062] Since the slurry in the airbag cannot be bonded to the inner wall of the tunnel after solidification, Figure 2 and Figure 3 A sliding hole is formed through the end wall of the groove 2 near the outer end of the arch bar 1, and a guide rod 16 is slidably penetrated at the sliding hole on the end wall of the groove 2. The length direction of the guide rod 16 is consistent with the length direction of the groove 2, and the sliding direction of the guide rod 16 is also consistent with the length direction of the groove 2. A floating block 17 is vertically fixed to one end of the guide rod 16 in the groove 2, and the floating block 17 can be a lightweight foam board, a lightweight cardboard, or a lightweight plastic board. A flexible needle is bonded to the peripheral wall of the guide rod 16, and the needle is tilted in the direction away from the groove 2. The material of the needle is spring steel, and the cross-sectional area of the end of the needle away from the guide rod 16 is smaller than the cross-sectional area of the end of the needle close to the guide rod 16. The length of the needle is greater than the wall thickness of the end wall of the groove 2, and when the guide rod 16 slides on the end wall of the groove 2, the end of the needle away from the guide rod 16 is always located outside the groove 2.
[0063] When the slurry is injected into the airbag, as the slurry is injected, the slurry pushes the guide rod 16 to move toward the outside of the arch bar 1 through the floating block 17. At this time, after the end of the needle close to the guide rod 16 moves to the outside of the sliding hole, the end of the needle away from the guide rod 16 rotates in the direction away from the guide rod 16. As the slurry is continuously injected, the slurry enters the airbag. When the airbag expands, it is squeezed by the inner wall of the tunnel and the outer wall of the arch bar 1, and the airbag extends toward the direction close to the needle. When the airbag contacts the needle, the needle pierces the airbag, and the slurry in the airbag overflows and adheres to the inner wall of the tunnel. At this time, the space between the inner wall of the tunnel and the outer wall of the arch bar 1 is filled with slurry and broken airbags. After the slurry solidifies, the broken airbags and slurry can enhance the adhesion between the arch bar 1 and the inner wall of the tunnel, so that the arch bar 1 is stably fixed on the inner wall of the tunnel.
[0064] The implementation principle of a tunnel support structure in a strongly weathered mudstone stratum according to an embodiment of the present application is as follows: multiple sections of arch frame bars 1 are transported into the tunnel for assembling the arch frame bars 1. When assembling the arch frame bars 1, one arch frame bar 1 is first fixed to the bottom of one side of the inner wall of the tunnel, and the outer wall of the arch frame bar 1 is abutted against the inner wall of the tunnel, and one end of the arch frame bar 1 with a groove 2 is facing away from the bottom direction of the tunnel; then a protrusion 3 on one arch frame bar 1 is inserted into the groove 2 from the open end of the groove 2 of another fixed arch frame bar 1, and the arc surface 8 of the protrusion 3 is abutted against the bottom wall of the groove 2 on the fixed arch frame bar 1.
[0065] As the protrusion 3 is inserted, the protrusion 3 contacts the guide surfaces 7 of the two connecting rods 5, and the two connecting rods 5 are pushed to shrink in the direction away from each other through the guide surfaces 7; when the connecting rods 5 are aligned with the connecting holes 4, the two connecting rods 5 are automatically reset. At this time, the two connecting rods 5 are both inserted into the connecting holes 4 of the protrusion 3, and the protrusion 3 is rotatably connected to the groove 2 through the two connecting rods 5. The first shielding component shields the open end of the groove 2, and the second shielding component 12 shields the notch of the groove 2.
[0066] Then, the arch bar 1 is driven to rotate around one end of the fixed arch bar 1 until the arch bar 1 is pressed against the inner wall of the tunnel, and the limit assembly is used to limit the arch bar 1 from rotating in the direction away from the inner wall of the tunnel. After the assembly of two adjacent arch bars 1 is completed, grouting is injected into the groove 2 of the arch bar 1 through the grouting hole 9. As the slurry is injected, the slurry pushes the guide rod 16 toward the outside of the arch bar 1 through the floating block 17. At this time, after the end of the needle close to the guide rod 16 moves to the outside of the sliding hole, the end of the needle away from the guide rod 16 rotates in the direction away from the guide rod 16.
[0067] As the slurry is continuously injected, the slurry enters the airbag, and when the airbag expands, it is squeezed by the inner wall of the tunnel and the outer wall of the arch bar 1, and the airbag extends toward the needle. When the airbag contacts the needle, the needle punctures the airbag, and the slurry in the airbag overflows and adheres to the inner wall of the tunnel. At this time, the space between the inner wall of the tunnel and the outer wall of the arch bar 1 is filled with slurry and broken airbags.
[0068] After the slurry solidifies, the broken airbags and slurry can enhance the adhesion between the arch frame strip 1 and the inner wall of the tunnel, so that the arch frame strip 1 is stably fixed on the inner wall of the tunnel, and two adjacent sections of the arch frame strip 1 are also stably connected. Multiple sections of the arch frame strip 1 are assembled in sequence to form a steel arch frame, so that the steel arch frame stably supports the inner wall of the tunnel.
[0069] The embodiment of the present application also discloses a construction method of a tunnel support structure in a strongly weathered mudstone formation.
[0070] Reference Figure 5 The construction method of a tunnel support structure in a strongly weathered mudstone stratum comprises the following steps:
[0071] S1, initial spraying of concrete, spraying concrete on the inner wall of the tunnel and waiting for the concrete to solidify;
[0072] S2, assembling the arch frame strips 1, transporting multiple sections of the arch frame strips 1 into the tunnel for assembly, driving two adjacent sections of the arch frame strips 1 to rotate relative to each other, and locking the arch frame strips 1 so that each section of the arch frame strips 1 is pressed against the inner wall of the tunnel;
[0073] S3, fixed connection of the arch bar 1, grouting is injected into the groove 2 of the arch bar 1, and after the grout solidifies, two adjacent sections of the arch bar 1 are stably connected;
[0074] S4, installing anchor rods and steel mesh, inserting the anchor rods into the inner wall of the tunnel, and hanging the steel mesh on the arch bar 1 and the anchor rods;
[0075] S5, spraying concrete, spraying concrete onto the steel mesh, and forming a reinforced concrete layer with the steel mesh after the concrete is solidified.
[0076] The implementation principle of the construction method of a tunnel support structure in a strongly weathered mudstone formation of the present application embodiment is as follows: after excavating and cleaning the inner wall of the tunnel, concrete is first sprayed onto the inner wall of the tunnel, and after the concrete solidifies, an initial support for the inner wall of the tunnel can be formed. Then, multiple sections of arch frame strips 1 are transported into the tunnel for assembly of the arch frame strips 1. When assembling the arch frame strips 1, an arch frame strip 1 is first fixedly installed at the bottom of one side of the inner wall of the tunnel through an anchor rod, and the outer wall of the arch frame strip 1 is abutted against the inner wall of the tunnel, and one end of the arch frame strip 1 with a groove 2 is away from the bottom direction of the tunnel. Then, the protrusion 3 on another arch frame strip 1 is inserted into the groove 2 on the fixed arch frame strip 1, and the arch frame strip 1 is driven to rotate around one end of the fixed arch frame strip 1 until the arch frame strip 1 is tightly against the inner wall of the tunnel, and finally the two adjacent arch frame strips 1 are locked and fixed, so that each section of the arch frame strip 1 is tightly against the inner wall of the tunnel.
[0077] After the assembly of the arch frame strip 1 is completed, grout is injected into the groove 2 of the arch frame strip 1. After the grout solidifies, the two adjacent sections of the arch frame strip 1 are stably connected. At this time, multiple sections of the arch frame strip 1 are connected to form a steel arch frame, so that the steel arch frame stably supports the inner wall of the tunnel. After the installation of the steel arch frame is completed, the anchor rod is inserted into the inner wall of the tunnel, and the steel mesh is hung on the arch frame strip 1 and the anchor rod, and concrete is sprayed on the steel mesh. After the concrete solidifies, it forms a reinforced concrete layer with the steel mesh, thereby improving the stable support of the inner wall of the tunnel in the strongly weathered mudstone formation.
[0078] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A tunnel support structure in a strongly weathered mudstone formation, comprising a plurality of arc-shaped arch bars (1), characterized in that: A groove (2) is provided at one end of the arch bar (1), the length direction of the groove (2) is consistent with the radial direction of the circle where the arch bar (1) is located, and a protrusion (3) movably plugged into the groove (2) is fixedly connected to the other end of the arch bar (1), and a connecting hole (4) is provided on the protrusion (3) along the width direction of the groove (2). A connecting rod (5) for rotatably connecting to the connecting hole (4) on the protrusion (3) is provided in the groove (2) on the arch bar (1), and a limit assembly for limiting the rotation of the protrusion (3) on the connecting rod (5) toward the inner side of the arch bar (1) is provided at the end of the arch bar (1); One end of the groove (2) close to the inner side of the arch bar (1) is open, and two connecting rods (5) are provided. The two connecting rods (5) are respectively vertically and elastically connected to the inner walls on both sides of the groove (2), and the connecting line of the two connecting rods (5) is consistent with the width direction of the groove (2). The ends of the two connecting rods (5) close to each other are both provided with a guide surface (7), and the guide surface (7) is located on the side of the connecting rod (5) close to the inner wall of the arch bar (1); The limiting assembly comprises a ratchet (61) fixedly connected to the protrusion (3) and a pawl (62) hinged on the inner wall of the groove (2) and adapted to be engaged with the ratchet (61), the center hole of the ratchet (61) being aligned with the connecting hole (4), the pawl (62) being located on a side of the connecting rod (5) close to the outer wall of the arch bar (1), and the free end of the pawl (62) being movably engaged with the ratchet (61); The end surface of the protrusion (3) away from the arch bar (1) is arranged as an arc surface (8), the center of the circle where the arc surface (8) is located coincides with the center of the connecting hole (4), and when the connecting rod (5) is inserted into the connecting hole (4), the arc surface (8) of the protrusion (3) is arranged to abut against the bottom wall of the groove (2); A grouting hole (9) is provided through the inner wall of one side of the groove (2); a first shielding component is provided on the arch bar (1) at the open end of the groove (2); and a second shielding component (12) for covering the notch of the groove (2) is provided on the arch bar (1) at the peripheral side of the protrusion (3); The first shielding assembly comprises two shielding plates (10), the two shielding plates (10) being respectively vertically and elastically connected to the inner walls on both sides of the groove (2), the ends of the two shielding plates (10) being close to each other being movably abutted against each other, the ends of the two shielding plates (10) being close to each other being both provided with an inclined surface (11), the inclined surface (11) being located on a side of the shielding plate (10) away from the connecting rod (5); The second shielding assembly (12) comprises an accordion cover (121) and a telescopic spring (122) arranged in the accordion cover (121), the two ends of the telescopic spring (122) being respectively fixedly connected to the two ends of the accordion cover (121), the accordion cover (121) being sleeved around the convex block (3), and one end of the accordion cover (121) being sealedly connected to one end of the arch frame bar (1) provided with the convex block (3), and the other end being detachably connected to the notch end face of the adjacent arch frame bar (1) provided with the groove (2).
2. A tunnel support structure in strongly weathered mudstone strata according to claim 1, characterized in that: A first sealing strip (13) is provided on the end surfaces of the two shielding plates (10) that abut against each other, and a second sealing strip (14) is provided on the end surface of the accordion cover (121) that is away from the protrusion (3).
3. The tunnel support structure in strongly weathered mudstone strata according to claim 1 is characterized by: A filling piece (15) for filling the gap between the arch bar (1) and the inner wall of the tunnel is arranged on the outer wall of the arch bar (1).
4. A construction method of a tunnel support structure in a strongly weathered mudstone formation, based on a tunnel support structure in a strongly weathered mudstone formation as claimed in any one of claims 1 to 3, characterized in that: The following steps are involved: S1, initial spraying of concrete, spraying concrete on the inner wall of the tunnel and waiting for the concrete to solidify; S2, assembling the arch frame strips (1), transporting multiple sections of the arch frame strips (1) into the tunnel for assembly, driving two adjacent sections of the arch frame strips (1) to rotate relative to each other, and under the joint action of the ratchet wheel (61) and the ratchet teeth, the end of the protrusion (3) located outside the groove (2) can only rotate around the connecting rod (5) towards the inner wall of the tunnel, so that the arch frame strip (1) to be fixed can be rotated and pressed against the inner wall of the tunnel, and at the same time, the arch frame strip (1) to be fixed can be pre-locked and fixed on one end of the arch frame strip (1) that has been fixed; each section of the arch frame strip (1) is pressed against the inner wall of the tunnel; S3, fixed connection of the arch bar (1), grouting is injected into the groove (2) of the arch bar (1), and after the grouting solidifies, two adjacent arch bars (1) are stably connected; S4, installing anchor rods and steel mesh, inserting the anchor rods into the inner wall of the tunnel, and hanging the steel mesh on the arch bar (1) and the anchor rods; S5, spraying concrete, spraying concrete onto the steel mesh, and forming a reinforced concrete layer with the steel mesh after the concrete is solidified.
Citation Information
Patent Citations
Joint device suitable for tunnel arching automatic assembling and installation method of joint device
CN106545349A
Concrete filling device for roadway steel support
CN111502702A