Installation and construction method of middle support of large span grid
By using the middle support scaffolding and the high-altitude bulk method in the long-span steel structure grid, the problems of installation accuracy and overall hoisting difficulty were solved, an efficient and safe construction process was achieved, and the cost and construction period were reduced.
Patent Information
- Application Number
- CN202211113420.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-09-14
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-09-14
AI Technical Summary
The long-span steel structure grid requires high installation accuracy and the overall hoisting is difficult, resulting in low construction efficiency, high cost, long construction period, and large construction limitations, making it difficult to ensure construction quality.
The middle support scaffolding is used to erect, combined with ground pre-assembly and high-altitude closing and assembly, and the high-altitude bulk method is used to gradually complete the overall installation of the grid, reduce the overall hoisting, make flexible use of the construction site, and disperse the construction points to ensure construction safety and efficiency.
Effectively control the deformation of the grid, reduce installation errors, shorten the construction period, reduce construction costs, improve construction efficiency, ensure construction safety, and improve the overall installation quality.
Smart Images

Figure CN115288449B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to a steel structure grid, in particular to a method for installing a middle support of a large-span grid. Background Art
[0002] Large-span steel structure grids are widely used in large steel structure projects such as industrial plants, airport terminals, and stadiums. Due to the high structural rigidity, good integrity, strong earthquake resistance, and light weight of steel structure grids, they are suitable for various flat and curved buildings and can be standardized and mass-produced in factories with high production efficiency. In addition, the architectural shape of steel structure grids is light, beautiful, and generous, which is easy to handle and decorate.
[0003] However, due to the high installation precision requirements of the large-span steel structure grid, the overall hoisting is difficult and the construction quality is difficult to guarantee. At present, the traditional large-span grid structure construction methods include overall lifting method, strip and block installation method, etc., but they all have strict requirements on the construction space and structural form of the grid, the construction is limited and the efficiency is low, resulting in long construction period and high cost. Summary of the invention
[0004] The technical problem to be solved by the present invention is to provide a method for installing a middle support of a large-span grid, so as to at least achieve the purpose of improving the construction efficiency.
[0005] To solve the above problems, the technical solution adopted by the present invention is: a large-span grid middle support installation construction method, comprising the following steps:
[0006] Step 1: Set up the middle supporting scaffolding;
[0007] Along the length direction of the grid to be constructed, set up a middle supporting scaffold in the middle of the site below the grid;
[0008] Step 2: The starting units are assembled at high altitude;
[0009] The middle part of the grid is selected as the starting unit. The starting unit is divided into three parts of foundation blocks and pre-assembled on the ground. After the middle foundation block is assembled, it is first placed on the upper part of the middle supporting scaffolding. The side foundation blocks are assembled on the ground on both sides of the middle supporting scaffolding. After the assembly is completed, each is lifted by a crane and fixedly spliced with the middle foundation block after reaching the assembly docking position. The end support of the side foundation block is welded to the embedded steel plate on the top of the concrete frame column.
[0010] Step 3: Installation of the grid by high-altitude bulk method;
[0011] The grids outside the starting unit are assembled by high-altitude bulk method, and the grids of the starting unit are assembled from the middle to both sides in sequence to complete the overall installation of the grid;
[0012] Step 4: Remove the middle supporting scaffolding.
[0013] Furthermore, in step one, a layer of steel plate is laid on the portion of the bolt ball supporting the starting unit on the middle supporting scaffolding, and a hydraulic jack is used to adjust the height of the bolt ball under the bolt ball.
[0014] Furthermore, a small cross bar is provided at a spacing of 300 mm at the top of the middle supporting scaffolding, and the small cross bar is fully covered with scaffolding boards as a construction operation surface, and a steel plate is added to the scaffolding boards at the position of the bolt ball supporting the starting unit.
[0015] Furthermore, poles are set up at the edge of the construction operation surface, and two horizontal bars are connected between adjacent vertical poles to form a guardrail. The height of the guardrail is 1.5m higher than the construction operation surface.
[0016] Furthermore, after the overall installation of the grid is completed, touch-up painting is performed.
[0017] Furthermore, in step three, ground assemblers first assemble the grid to be installed into small units on the ground according to the requirements of the drawings, and then use a crane and an electric hoist to lift the small units to the corresponding positions of the installed grid, and aerial workers complete the connection between the small units and the grid.
[0018] The method of the present invention does not need to set up an overall full-floor scaffolding, but only needs to set up a local middle supporting scaffolding to effectively control the deflection of the grid, avoid installation errors caused by excessive deformation, and ensure smooth assembly and installation of the starting unit.
[0019] The use of central support scaffolding can reduce the erection and dismantling of scaffolding, reduce construction costs, improve construction efficiency, shorten construction period, and ensure safe construction.
[0020] Using the starting unit as support and the high-altitude bulk method to assemble the remaining components of the grid can make full and flexible use of the construction site, carry out construction at multiple locations simultaneously, disperse the construction work points, and effectively ensure the safety and construction period during the construction process. BRIEF DESCRIPTION OF THE DRAWINGS
[0021] The drawings herein are used to provide further explanation of the present invention and constitute a part of this application. The illustrative embodiments of the present invention and their description are used to explain the present invention and do not constitute improper limitations on the present invention.
[0022] Figure 1 It is a partial horizontal elevation diagram of the middle supporting scaffolding.
[0023] Figure 2 It is a schematic diagram of the hoisting of the starting unit.
[0024] Figure 3This is a schematic diagram of the grid after the side foundation blocks on one side are in place.
[0025] In the figure, 1-middle supporting scaffolding, 2-frame columns, 3-vertical poles, 4-horizontal poles, 5-small cross bars, 6-scaffolding boards, 7-middle foundation blocks, 8-side foundation blocks, 9-pads, and 10-crane. DETAILED DESCRIPTION
[0026] In order to make those skilled in the art better understand the present invention, the present invention is further clearly and completely described below in conjunction with the accompanying drawings and embodiments. It should be noted that, in the absence of conflict, the features in the embodiments and examples of this application can be combined with each other.
[0027] A typical embodiment of the present invention provides a method for installing a large-span truss middle support. The truss described in this embodiment is in the form of a bolt ball, and the truss is located above the frame column 2. Due to the large span and space of the truss, the cumulative error control requirements during the installation process are relatively fine, and the truss structure has extremely strict requirements on deflection. If the overall hoisting construction method is adopted, it is easy to cause the truss structure to be deformed due to uneven force, thereby affecting its internal force. In addition, the overall hoisting construction method requires the use of large hoisting equipment and an open construction site, and the use of human and material resources is overly concentrated, and the difficulty of controlling safety risks is correspondingly increased.
[0028] Combined with the actual situation on site, the overall concept of the present invention is to adopt a construction method that combines "building a local middle supporting scaffolding 1, assembling the overall hoisting foundation block on the ground, assembling the starting unit at high altitude and assembling the remaining grid by bulk method at high altitude", which can effectively utilize the construction space and human and material resources to ensure construction safety and construction period.
[0029] Mark the axis and elevation at the top of frame column 2, check the displacement of the top of frame column 2, and formally install it only after the position, size and elevation of the support points of the grid have been verified.
[0030] 1. Erection of the middle supporting scaffolding
[0031] Along the length direction of the grid to be constructed, a middle supporting scaffold 1 is set up in the middle of the site below the grid.
[0032] The starting unit is pre-assembled on the ground. Due to its large span and deadweight, a scaffolding is required for support. In the method provided by the present invention, there is no need to erect an overall full-floor scaffolding. Only the middle supporting scaffolding 1 is required to effectively control the deflection of the grid, avoid installation errors caused by excessive deformation, and ensure smooth assembly and installation of the starting unit.
[0033] A layer of steel plate is added to the bolt ball of the starting unit on the middle supporting scaffold 1 to ensure that it can support the local concentrated pressure of the grid. A hydraulic jack is used to adjust the height of the bolt ball under the bolt ball to ensure the height and horizontality of the lower chord of the grid.
[0034] In a relatively specific embodiment, the middle supporting scaffold 1 is a partial steel pipe fastener type scaffold. The material of the scaffold steel pipe is Q235A, the main body spacing of the vertical poles 3 is 1.2m×1.2m, the step distance of the horizontal poles 4 is 1.5m, the vertical poles 3 spacing at the stress node is 0.6m×0.6m, and the total height of the middle supporting scaffold 1 is 10.0m.
[0035] The soil layer under the middle supporting scaffold 1 is compacted (if the concrete floor has been completed, compaction is no longer necessary), and good drainage measures must be taken to prevent excessive water accumulation on rainy days from causing the soil layer to soften and pose a risk to the stability of the middle supporting scaffold 1. The bottom of all vertical poles 3 is laid with full-length scaffolding boards with a thickness of 50-60mm and a width of 200-300mm. The number of vertical poles 3 on each scaffolding board is not less than 2.
[0036] refer to Figure 1 , small crossbars 5 are set at the top of the middle supporting scaffold 1 with a spacing of 300mm. The small crossbars 5 are fully covered with scaffolding boards 6 as the construction operation surface, and steel plates are added to the scaffolding boards 6 at the position of the bolt ball of the starting unit. The small crossbars 5 should be encrypted at the bottom of the steel plate and the load-bearing vertical poles near the small crossbars 5 should be reinforced to ensure that the middle section of the starting unit (middle foundation block 7) can maintain the accuracy of the elevation and axis and the stability of the grid after being placed on the upper part.
[0037] Poles can be set up at the edge of the construction operation surface, and two horizontal bars are connected between adjacent vertical poles to form a guardrail. The height of the guardrail is 1.5m higher than the construction operation surface. According to the characteristics of grid installation and hoisting, the construction load of the construction operation surface is preferably 2.0kN / m 2 In addition to the full scaffolding board 6, the stacking area also needs to be covered with a layer of reinforcing steel plate or wooden board to prevent falling objects.
[0038] Scissor braces are set around and in the middle of the central supporting scaffold 1, and are continuously set from the ground to the operating surface. The inclination angle between the scissor braces and the ground is between 45° and 60°. The spacing between the middle scissor braces is not more than 5m. Vertical scissor braces are arranged separately in the load concentration area. A sweeping rod is set at the bottom of the vertical pole 3, and the sweeping rod is 200mm from the ground. It is erected according to the specifications.
[0039] A ramp for people to go up is arranged outside the middle supporting scaffold 1. The ramp is straight, 1.2m wide, and has a slope of 1:3. A rest platform is arranged in the middle. Guardrails and dense safety nets are arranged on both sides of the ramp and around the rest platform. The height is 1.2m. An anti-slip strip is arranged every 250 to 300mm on the slope.
[0040] Considering that the middle supporting scaffolding 1 may be used in the rainy season, which is a period of frequent lightning, a lightning protection grounding electrode is set up at the bottom of the middle supporting scaffolding 1 and connected to the earth. The grid structure temporarily uses the lightning protection grounding lead reserved in the concrete structure as lightning protection grounding, and uses a wire to connect to the concrete lightning protection grounding module.
[0041] (II) High-altitude assembly of the starting unit
[0042] The starting unit is installed by adopting the method of "assembling the integral hoisting foundation block on the ground and assembling the starting unit at high altitude".
[0043] refer to Figure 2 and Figure 3 , select the middle part of the grid as the starting unit, the starting unit is divided into three parts of foundation blocks for pre-assembly on the ground, the three parts of the foundation blocks are a middle foundation block 7 and two side foundation blocks 8; among them, after the middle foundation block 7 is assembled, it is first placed on the upper part of the middle supporting scaffolding 1; the remaining side foundation blocks 8 are assembled on both sides of the middle supporting scaffolding 1, and after the assembly is completed, they are lifted by a crane 10, and after arriving at the assembly docking position, they are fixedly spliced with the middle foundation block 7, and the end supports of the side foundation blocks 8 are welded to the embedded steel plates on the tops of the concrete frame columns 2.
[0044] The above method solves the problem of high installation precision requirements and overall lifting difficulty of large-span grid structures, shortens the construction period, and saves grid construction suspension fees, large crane usage fees, etc.
[0045] Taking a large-span bolt-ball truss as an example, the starting unit of the truss has a specification of 15 meters × 75 meters and is divided into three foundation blocks for pre-assembly on the ground.
[0046] When installing the grid starter unit, first find the location of the grid support, connect the corresponding bolt balls and rods, tighten the bolt connection parts in place, strictly adjust the grid position, and require the grid support offset to be strictly controlled within the allowable error. If it is installed in a factory building, the area cannot be too large (about 500 square meters). In addition, the hoisting is affected by the middle support scaffolding 1 and cannot be hoisted in place at one time. Therefore, first assemble the grid span middle foundation block 7 (the connection part of the two side foundation blocks 8) on the ground. The size is one column spacing, that is, 15m×15m, the area is 225m², and the weight is 11.77t. After the assembly is completed, hoist the center as a whole and place it on the middle support scaffolding 1. Then, install the side foundation blocks 8 on both sides on the ground. The size is 15m*30m, the area is 450m², and the weight is 23.54t. The side foundation blocks 8 are hoisted simultaneously by 4 cranes, and fixed and spliced after reaching the assembly docking position. During the assembly process, the horizontality of the lower chord of the grid and the grid axis must be strictly controlled to prevent the position of the starting unit from being offset, which will cause difficulties for subsequent construction. After the assembly is completed, the offset and deflection of the grid axis should be checked immediately and the data should be recorded. When assembling the above-mentioned foundation blocks, in order to ensure the overall elevation of the grid, prevent uneven elevations and open welding of grid rods, you can first adjust one end of the foundation block for assembly, and then slightly adjust the elevation of the other end to minimize the adjustment range.
[0047] During the ground assembly of the foundation block, multiple pads 9 are arranged under the node ball of the lower chord of the grid as temporary support points. The temporary support pads 9 are generally required to use wooden pads or steel structure pads. The height or thickness of the pads 9 should be consistent with the height of the grid support to ensure that the lower chord of the grid is on the same horizontal plane. After the assembly is completed, the installation quality should be checked, mainly to check whether the rod bolts are tightened in place, whether the rods and ball nodes meet the requirements of the drawings, to prevent installation errors, resulting in rod bending and different grid sizes, and hoisting after checking.
[0048] The lifting weight of the side foundation block 8 is 23.54t, and four cranes are used for lifting. The lifting weight of each crane is 5.89t, the crane operation radius is 6m, and the lifting height of the crane arm should be controlled within 20m. The lifting node binding position is the node ball of the lower chord of the grid.
[0049] refer to Figure 3 When the side foundation block 8 between the H~J axis and the ①~③ axis is hoisted and installed and assembled with the middle foundation block 7 on the middle supporting scaffolding 1, assemble the side foundation block 8 between the symmetrical plane H~J axis and the ④~⑥ axis to complete the installation of the entire H~J axis grid.
[0050] When the installation of the H~J axis is completed, the overall installation quality of the combined foundation block should be inspected, especially whether the deviation of the axis is consistent with the foundation axis. If the deviation is found, it should be adjusted immediately. Strictly control the deflection of the grid. In order to avoid excessive deflection of the grid, anti-deformation measures are required during the installation process. For example: artificially increase the height of the lower chord pad on the middle support scaffolding 1. Anti-deformation measures should always be maintained during installation. When the grid is assembled to complete the four column spacings, the pads in the three column spacings assembled previously can be removed, and the deflection in the three column spacings is measured (the selection of measurement points is: no less than five points for large spans, and no less than three points for small and medium spans) to see if it meets the no-load deflection requirements. This deflection is generally about 25% of the design deflection and shall not be greater than 1.15 times the design deflection.
[0051] The load-bearing part of the grid should slowly fall to the middle support scaffold 1, and the changes of the middle support scaffold 1 after being stressed should be observed. There will be 12 lower chord balls falling on the middle support scaffold 1. If tilting or settling is found, the construction should be stopped immediately. It can be used after correction and reinforcement, otherwise there will be safety hazards.
[0052] (III) Installation by high-altitude bulk method
[0053] The grid outside the starting unit is assembled using the high-altitude bulk method, and the grid is assembled from the middle to both sides in sequence based on the grid of the starting unit to complete the overall installation of the grid.
[0054] In the high-altitude bulk installation, the middle supporting scaffolding 1 is used as the dividing line, and it gradually extends from the H axis to the A axis, and the J axis to the M axis until the entire installation is completed.
[0055] The installers are divided into two work surfaces and work simultaneously. Each work surface can be divided into 2-3 groups. For example, one group assembles small units while the other performs high-altitude installation.
[0056] The installation procedure is as follows: First, the ground assemblers assemble the grid to be installed into small units on the ground according to the requirements of the drawings, and use cranes and electric hoists to lift the small units to the corresponding positions of the grids that have been installed in the air, and the aerial workers complete the connection between the small units and the grids. After all the rods are fastened in place, the tethers can be untied, the hooks can be released, and the next small unit can be installed. This process is repeated until all installation work is completed. Spread the assembly from the middle to both sides, release the assembly error to the surroundings, make full use of the construction site, carry out construction at multiple locations at the same time, and disperse the construction work points.
[0057] During the assembly process, the accuracy of the grid installation axis is inspected and controlled, and the grid deflection is monitored in real time. The error is controlled within the specification range and released to the surrounding areas, which greatly ensures the quality and safety of the grid installation and provides a data basis for subsequent roof panel construction.
[0058] After the overall installation of the grid is completed, the hydraulic jacks on the middle supporting scaffold 1 used to support the grid are slowly unloaded to ensure that the internal force of the grid structure is gradually redistributed and a stable spatial system is formed.
[0059] (IV) Grid repainting work
[0060] During the hoisting and assembly process, the steel rope hanging parts and the parts that touch the ground during pre-assembly are subject to friction, which will inevitably cause local paint film damage and fall off, affecting the service life of the grid. In addition, the connection positions between the grid chord and the bolt ball should also be painted for corrosion protection. Therefore, touch-up painting should be carried out immediately after the installation is completed, and the relevant technical specifications must be strictly followed to ensure the quality and quantity of the touch-up painting work.
[0061] When the steel surface is damaged or rusted due to rolling, cutting, welding or installation wear, it must be cleaned with sandblasting or power tools before repainting.
[0062] After painting, if the paint film is found to be cracked, wrinkled, brushed, dripping, powdered, glossy or exposed, the paint film should be scraped off, sanded with sandpaper and repainted; if bubbles, cracks, holes, peeling rust or pinhole rust, paint falling off, etc. are found, the paint film should be scraped off and surface treated, and then repainted according to regulations.
[0063] The grid acceptance is carried out in two steps. The first step is the acceptance of the grid while it is still in the hoisting state; the second step is the acceptance of the grid with independent load after hoisting and unloading.
[0064] (V) Dismantle the middle supporting scaffolding 1.
[0065] The dismantling of the middle supporting scaffolding 1 shall be carried out according to the principle of erecting first and dismantling later, erecting later and dismantling first, dismantling non-load-bearing poles first and load-bearing poles later. It shall be dismantled layer by layer from top to bottom, and it is strictly forbidden to dismantle the upper and lower layers at the same time.
[0066] The scope of protection claimed by the present invention is not limited to the above specific embodiments. For those skilled in the art, the present invention may have various deformations and changes. Any modifications, improvements and equivalent substitutions made within the concept and principle of the present invention should be included in the protection scope of the present invention.
Claims
1. A method for installing a large-span grid middle support, characterized in that: The following steps are included: Step 1: Set up the middle supporting scaffolding; Along the length direction of the grid to be constructed, set up a middle supporting scaffold in the middle of the site below the grid; The middle supporting scaffold 1 is a partial steel pipe fastener scaffold, the material of the scaffold steel pipe is Q235A, the main body spacing of the vertical pole is 1.2m×1.2m, the horizontal pole step is 1.5m, the vertical pole spacing at the stress node is 0.6m×0.6m, and the total height of the middle supporting scaffold 1 is 10.0m; the soil layer below the middle supporting scaffold 1 is compacted, and the bottom of all the vertical poles 3 are laid with full-length scaffolding boards, the thickness of the scaffolding boards is 50-60mm, the width is 200-300mm, and the number of vertical poles 3 on each scaffolding board is not less than 2; The top of the middle supporting scaffold is provided with a small cross bar at a spacing of 300 mm, and the small cross bar is fully covered with scaffolding boards as a construction operation surface. Scissor braces are set around and in the middle of the central supporting scaffolding, and are set continuously from the ground to the operating surface. The inclination angle between the scissor braces and the ground is between 45° and 60°. The spacing between the scissor braces in the middle is not more than 5m. Vertical scissor braces are arranged separately in the load concentration area. A sweeping rod is set at the bottom of the vertical pole 3. The sweeping rod is 200mm from the ground and is erected according to the specifications; The outside of the middle supporting scaffold 1 is provided with a ramp for people to go up. The ramp is a straight run type, 1.2m wide, with a slope of 1:3, and a rest platform is set in the middle. Guardrails and dense safety nets are set on both sides of the ramp and around the rest platform. The height is 1.2m, and an anti-slip strip is set every 250-300mm on the slope; Step 2: The starting units are assembled at high altitude; The specification of the starting unit is 15m×75m. The middle part grid is selected as the starting unit. The starting unit is divided into three parts of foundation blocks for pre-assembly on the ground. The three parts of the foundation blocks are a middle foundation block and two side foundation blocks. Among them, the middle foundation block is the connecting part of the two side foundation blocks. The size of the middle foundation block is one column spacing, that is, 15m×15m, the area is 225m², and the weight is 11.77t. After the middle foundation block is assembled, it is first placed on the upper part of the middle supporting scaffolding; the size of the side foundation block is 15m*30m, the area is 450m², and the weight is 23.54t. The side foundation blocks are assembled on the ground on both sides of the middle supporting scaffolding. After the assembly is completed, they are lifted by cranes and fixedly spliced with the middle foundation blocks after reaching the assembly docking position. The end supports of the side foundation blocks are welded to the embedded steel plates on the top of the concrete frame columns. A layer of steel plate is added to the bolt ball of the starting unit on the middle supporting scaffolding; a hydraulic jack is used to adjust the height of the bolt ball under the bolt ball; In order to avoid excessive deflection of the grid, anti-deformation measures are taken during the installation process. The height of the lower chord pad is artificially increased on the middle supporting scaffolding. When the grid is assembled to complete the four column spacings, the pads in the three column spacings assembled before are removed to measure whether the deflection in the three column spacings meets the no-load deflection requirements. The selection of measurement points is: no less than five points for large spans and no less than three points for small and medium spans; Step 3: Installation of the grid by high-altitude bulk method; The grids outside the starting unit are assembled by high-altitude bulk method, and the grids of the starting unit are assembled from the middle to both sides in sequence to complete the overall installation of the grid; Step 4: Remove the middle supporting scaffolding.
2. The method for installing the middle support of a large-span grid according to claim 1 is characterized in that: Poles are set up at the edge of the construction operation surface, and two horizontal bars are connected between adjacent vertical poles to form a guardrail. The height of the guardrail is 1.5m higher than the construction operation surface.
3. The method for installing the middle support of a large-span grid according to claim 1 or 2, characterized in that: After the overall installation of the grid is completed, touch-up painting is carried out.
4. The method for installing the middle support of a large-span grid according to claim 3 is characterized in that: In step three, ground assemblers first assemble the grid to be installed into small units on the ground according to the requirements of the drawings, and then use a crane and electric hoist to lift the small units to the corresponding positions of the grid that has been installed in the air, and aerial workers complete the connection between the small units and the grid.