A safe and fast construction method for the secondary lining of a double-sidewall pilot tunnel

By retaining temporary structures and dismantling them one by one in the double-side wall pit guide method tunnel construction, the impact of temporary support structure removal on the initial support of the tunnel is solved, safe and rapid construction of the second lining of the tunnel is achieved, and construction difficulty and disturbance are reduced. , improve construction efficiency and safety.

CN115306428BActive Publication Date: 2024-11-12CHINA RAILWAY 12TH BUREAU GRP CO LTD +3
View PDF 0 Cites 1 Cited by

Patent Information

Application Number
CN202211070649.1
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-09-02
Publication Date
2024-11-12
Estimated Expiration
2042-09-02

AI Technical Summary

Technical Problem

In the construction of double-sided wall pit guide tunnels, the removal process of the temporary support structure can easily lead to excessive deformation of the initial branch of the tunnel, and it is difficult for the prior art to achieve safe, fast and low disturbance two-line construction, especially in urban environments. There are major challenges when constructing the existing operation lines under the tunnel under the concealed tunnel on a large section.

Method used

By retaining most of the temporary structures (temporary vertical support, temporary horizontal support), the second lining construction is completed and the formwork bracket is independently erected by the retained temporary structure, and the second lining construction is carried out one by one, reducing the removal of the primary support structure During the construction process, use information technology and large-scale arm gun machines to remove the structure, simplify the construction process and reduce disturbances to the surrounding environment.

Benefits of technology

The second lining long section casting is realized, which reduces the construction difficulty of the formwork bracket system, improves construction efficiency, ensures the safety of the tunnel structure and the stability of the surrounding environment, and reduces construction cycle and secondary disturbances.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115306428B_ABST
    Figure CN115306428B_ABST
Patent Text Reader

Abstract

A safe and fast construction method for the secondary lining of a double-sidewall pilot tunnel. During the construction of the entire secondary lining, the influence of the removal of temporary structures on the primary support structure is reduced by retaining most of the temporary structures (temporary vertical supports and temporary horizontal supports), so as to achieve the casting of long sections of the secondary lining. After the construction of the secondary lining is completed, the temporary structure is removed, which effectively simplifies the construction process and reduces the secondary disturbance to the surrounding environment while ensuring the safety of the dark excavation tunnel itself. After the construction of the secondary lining of the invert and the backfill concrete of the invert is completed, the template support is independently and synchronously set up by each pilot hole using the retained temporary structure, so as to transform the large hole into a small hole, greatly reducing the overall construction difficulty of the template support system, achieving the one-time casting of the secondary lining of the arch waist and arch top, and improving the overall construction efficiency of the secondary lining. The process involved in the invention is mature and easy to operate, and has very important reference value and practical significance for the construction of similar mining tunnels in sensitive environments, especially for close-range underpasses of existing lines, important pipelines and buildings.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of tunnel construction, and in particular to a safe and rapid construction method for a secondary lining of a double-side wall pilot tunnel. Background Art

[0002] The double-sidewall pilot tunnel excavation method is generally used in dark-cut tunnel projects with poor surrounding rock, large cross-section, shallow burial depth, complex surrounding environment and high requirements for settlement control. It is often encountered that the tunnel passes under the existing building (structure) construction. The usual measures are mainly to strengthen the advance support, enhance the initial support strength of the excavated tunnel, and accelerate the initial support ring, all of which are carried out around the tunnel excavation construction. Temporary vertical supports and temporary horizontal supports, as temporary structures, need to be removed during the secondary lining construction stage. This is a high-risk operation that can easily cause excessive deformation or even collapse of the tunnel's initial support. At present, the conventional removal method of temporary supports is to remove the entire section after the completion of the inverted arch secondary lining and before the construction of the side wall and arch secondary lining. Not only can the deformation of the tunnel's initial support be unreliably controlled, but the large cross-section also brings many problems such as the construction technology and progress of the secondary lining formwork support system, resulting in an increase in the secondary lining construction period, which is not conducive to the deformation of the tunnel structure and the construction safety control, and will seriously affect the safety of the tunnel itself and the surrounding building structures. Therefore, how to complete the secondary lining construction safely, reliably, quickly and with low disturbance during tunnel construction, especially the construction of large-section dark-cut tunnels under existing operating lines in sensitive urban environments, has undoubtedly become a major technical problem that needs to be solved urgently. Summary of the invention

[0003] In order to overcome the shortcomings of the above-mentioned prior art, the present invention provides a safe and fast construction method for the secondary lining of a double-side wall pilot tunnel method tunnel. During the entire secondary lining construction, the influence of the removal of the temporary structure on the primary support structure is reduced by retaining most of the temporary structures (temporary vertical supports, temporary horizontal supports), so as to realize the casting of long sections of the secondary lining; after the construction of the secondary lining is completed, the temporary structure is removed, which effectively simplifies the construction process, and reduces the secondary disturbance to the surrounding environment while ensuring the safety of the dark excavation tunnel itself; after the construction of the secondary lining of the invert and the backfill concrete of the invert is completed, the formwork support is independently and synchronously erected through each pilot hole using the retained temporary structure, so that the large hole is converted into a small hole, which greatly reduces the overall construction difficulty of the formwork support system, realizes the one-time casting of the arch waist and arch crown secondary lining, and improves the overall construction efficiency of the secondary lining.

[0004] In order to achieve the above object, the technical solution adopted by the present invention is:

[0005] A safe and fast construction method for the secondary lining of a double-side wall pilot tunnel method, comprising the following steps:

[0006] 1) After the initial support of the dark-excavated tunnel is closed into a ring, the initial support deformation is stable, and the tunnel is cleaned up, the elevation control line of the invert backfill concrete is measured and released, and the initial support spraying concrete within the scope of the temporary vertical support ② inverted arch secondary lining ④ and inverted arch backfill ⑤ is removed manually;

[0007] 2) Adopt information construction means, combine the length of the secondary lining of the inverted arch at one time, dismantle the secondary lining of the inverted arch ④ and the temporary vertical support ② steel in the range of the backfill ⑤ of one construction section every other section or every other section, and make detailed waterproof and water-stopping measures for the retained temporary vertical support ② steel;

[0008] 3) Construct the waterproofing of the second lining ④ of the inverted arch, install the steel bars, and complete the construction of the second lining ④ of the inverted arch; roughen and clean the second lining base surface of the second lining ④ of the inverted arch, and complete the construction of the backfill ⑤ of the inverted arch;

[0009] 4) All lower pilot tunnels are equipped with full-height scaffolding⑧ at the same level and synchronously. After the full-height scaffolding⑧ of the lower pilot tunnel is erected, the information construction method is adopted, and the length is divided into the second lining construction section. The temporary cross brace③ of one construction section of the second lining⑦ of the side wall is chiseled out and the concrete is sprayed. The temporary cross brace③ steel is removed every other section or every other section, and the retained temporary cross brace③ steel is treated with detailed waterproof and water-stopping measures;

[0010] 5) All upper pilot holes are equipped with full-height scaffolding⑧ at the same level and synchronously. After the full-height scaffolding⑧ of the upper pilot hole is erected, the information construction method is adopted, combined with the length division of the second lining construction section, and the temporary vertical support ② of one construction section of the arch second lining ⑥ is chiseled out and the concrete is sprayed. The temporary vertical support ② steel is removed every other section or every other section, and the retained temporary vertical support ② steel is treated with detailed waterproof and water-stopping measures;

[0011] 6) Waterproofing and steel bar installation of side wall secondary lining ⑦ and arch secondary lining ⑥, installation of combined steel formwork and completion of secondary lining concrete pouring;

[0012] 7) When the secondary lining concrete reaches the designed strength value, the information-based construction method is used to cut and disconnect the remaining temporary vertical bracing steel sections of the secondary lining ⑥ near the arch; remove and clean the upper guide hole scaffolding ⑧ of the construction section, and then continue to cut and disconnect the remaining temporary horizontal bracing steel sections of the secondary lining ⑦ near the side wall; finally, the removal and cleaning of the lower guide hole scaffolding ⑧ is completed;

[0013] 8) Based on the on-site construction conditions, use large or extended arm blasting machines to dismantle and clean the remaining temporary vertical supports ② and temporary horizontal supports ③ from top to bottom to complete the entire tunnel civil engineering construction.

[0014] Furthermore, during the construction of the secondary lining, most of the initial supporting temporary structures (temporary vertical supports and temporary horizontal supports) are retained as much as possible, and each guide tunnel uses the temporary structures to independently set up formwork supports. After the construction of the entire section of the secondary lining is completed, the secondary lining formwork system and the remaining temporary structures are dismantled to complete the dark excavation tunnel construction safely and quickly.

[0015] Furthermore, before the construction of the second inverted arch lining ④, the temporary vertical support ②, the second inverted arch lining ④ and the inverted arch backfill ⑤ range are chiseled out and the initial support and sprayed concrete are removed, and the second inverted arch lining ④ and the inverted arch backfill ⑤ range steel is removed every other section or every other section.

[0016] Furthermore, after the construction of the secondary lining ④ and the backfill ⑤ of the inverted arch is completed, each guide tunnel is independently and synchronously set up with a full-house scaffolding ⑧, and then the temporary vertical support ②, temporary horizontal support ③, arch ⑥, and side wall ⑦ are chiseled out to initially support the spraying of concrete in the secondary lining range, and the steel sections in the secondary lining range of the arch ⑥ and side wall ⑦ are removed one or two sections later.

[0017] Furthermore, after the construction of the arch second lining ⑥ and the side wall second lining ⑦ is completed, the remaining temporary vertical support ② steel sections near the arch second lining ⑥ are cut and disconnected; then the upper guide hole scaffolding ⑧ is removed and cleaned, and then the remaining temporary horizontal support ③ steel sections near the side wall second lining ⑦ are cut and disconnected; the dismantling and cleaning work of the lower guide hole scaffolding ⑧ is completed, and finally the remaining temporary vertical support ② and the remaining temporary horizontal support ③ are removed and cleaned.

[0018] Furthermore, the temporary vertical support ② inverted arch secondary lining ④ and inverted arch backfill ⑤ are manually chiseled out to spray concrete. The chiseling height is the inverted arch backfill concrete elevation +≯30cm to ensure that there is space reserved for cutting the steel section. The chiseling height should be minimized.

[0019] Furthermore, the temporary vertical brace ② and temporary horizontal brace ③ steel sections are treated with detailed waterproofing and water-stopping measures, which generally include the following construction procedures: cleaning of steel section pollutants, welding of water-stop steel plates of customized size, applying water-swelling water-stop adhesive to the welds of the steel section water-stop steel plates, using water-swelling water-stop adhesive to close the PVC waterproof board at the root of the steel section and sticking a water-swelling water-stop strip, applying an additional waterproof layer at the root of the steel section and closing and fixing it.

[0020] Furthermore, the aforementioned method of manually chiseling away the arch second lining ⑥ and the side wall second lining ⑦ to initially support the sprayed concrete, with a chiseling height of the second lining thickness +≯30cm, ensuring the reinforcement needs of the second lining formwork and reserving space for steel cutting, and the chiseling height and width should be minimized.

[0021] Furthermore, the remaining temporary vertical supports ② and temporary horizontal supports ③ are generally dismantled in a step-by-step manner from top to bottom, including temporary vertical supports for the upper guide tunnel, temporary horizontal supports, and temporary vertical supports for the lower guide tunnel. The longitudinal dismantling length of each section should not be too long and should be controlled within 3m to ensure that the temporary vertical supports for the upper guide tunnel are not piled up on top of the temporary horizontal supports during dismantling, thereby affecting the dismantling of the temporary horizontal supports. After the current dismantling of each section is completed, the next dismantling construction will be carried out in a cycle.

[0022] Compared with the prior art, the present invention has the following advantages:

[0023] The present invention provides a safe and fast secondary lining construction method for a double-side wall pilot tunnel method tunnel. During the entire secondary lining construction, most of the temporary structures (temporary vertical supports and temporary horizontal supports) are retained to reduce the impact of temporary structure removal on the primary support structure, thereby realizing long-segment casting of the secondary lining. After the secondary lining construction is completed, the temporary structure is removed, thereby effectively simplifying the construction process, and reducing secondary disturbance to the surrounding environment while ensuring the safety of the dark-excavated tunnel itself. After the construction of the secondary lining of the invert and the backfill concrete of the invert is completed, formwork supports are independently and synchronously erected through the retained temporary structures of each pilot tunnel, so that large holes are converted into small holes, thereby greatly reducing the overall construction difficulty of the formwork support system, realizing one-time casting of the secondary lining of the arch waist and arch top, and improving the overall construction efficiency of the secondary lining.

[0024] Instruction Manual

[0025] Figure 1 It is a schematic diagram of the tunnel secondary lining construction process of the present invention.

[0026] Figure 2 It is a schematic diagram of the construction process of the secondary lining of the tunnel.

[0027] Among them, in the figure: ①-initial supporting structure; ②-temporary vertical support; ③-temporary horizontal support; ④-secondary lining of inverted arch; ⑤-backfill concrete of inverted arch; ⑥-secondary lining of arch; ⑦-secondary lining of side wall; ⑧-full house scaffolding; a-temporary vertical support within the scope of secondary lining of inverted arch and backfill concrete of inverted arch; b-temporary horizontal support within the scope of secondary lining of side wall; c-temporary vertical support within the scope of secondary lining of arch. DETAILED DESCRIPTION

[0028] The present invention is further described below in conjunction with the accompanying drawings.

[0029] like Figure 1 , 2 As shown, a safe and fast construction method for the secondary lining of a double-side wall pilot tunnel method tunnel is disclosed, which includes retaining most of the initial support temporary structures (temporary vertical supports and temporary horizontal supports) during the secondary lining construction process, and independently setting up formwork supports for each pilot tunnel using temporary structures. The temporary structures are then removed after the secondary lining construction is completed. This is a safe and fast construction technology.

[0030] (1) Before the construction of the secondary lining of the inverted arch ④, the temporary vertical support ② is removed, the primary support concrete is sprayed in the area of ​​the secondary lining of the inverted arch ④ and the backfill of the inverted arch ⑤, and the steel sections in the area of ​​the secondary lining of the inverted arch ④ and the backfill of the inverted arch ⑤ are removed one or two sections apart.

[0031] (2) After the construction of the secondary lining of the inverted arch ④ and the backfill of the inverted arch ⑤ is completed, each pilot tunnel shall be independently and synchronously set up with a full-house red scaffold ⑧, and then the temporary vertical support ②, temporary horizontal support ③, arch ⑥, and side wall ⑦ secondary lining range initial support concrete shall be removed, and the steel sections of the arch ⑥ and side wall ⑦ secondary lining range shall be removed one or two sections apart.

[0032] (3) After the construction of the arch secondary lining ⑥ and the side wall secondary lining ⑦ is completed, the remaining temporary vertical support ② steel sections near the arch secondary lining ⑥ are cut and disconnected; then the scaffolding ⑧ of each upper guide hole is dismantled and cleaned, and then the remaining temporary horizontal support ③ steel sections near the side wall secondary lining ⑦ are cut and disconnected; the scaffolding ⑧ of each lower guide hole is dismantled and cleaned, and finally the remaining temporary vertical support ② and the remaining temporary horizontal support ③ are dismantled and cleaned.

[0033] (4) A safe and rapid construction method for the secondary lining of a double-sidewall pilot tunnel, characterized in that it comprises the following steps:

[0034] 1) After the initial support of the dark-excavated tunnel is closed into a ring, the initial support deformation is stable, and the tunnel is cleaned up, the elevation control line of the invert backfill concrete is measured and released, and the initial support spraying concrete within the range of the temporary vertical support ② inverted arch secondary lining ④ and inverted arch backfill ⑤ is removed manually.

[0035] 2) Adopt information construction means, combined with the length of the secondary lining of the invert, dismantle the temporary vertical support ② steel in the scope of the secondary lining ④ and the backfill ⑤ of one construction section every other section or every other section, and make detailed waterproof and water-stopping measures for the retained temporary vertical support ② steel.

[0036] 3) Construct the waterproofing of the second lining ④ of the inverted arch, install the steel bars, and complete the construction of the second lining ④ of the inverted arch; roughen and clean the base surface of the second lining ④ of the inverted arch, and complete the concrete construction of the backfill ⑤ of the inverted arch.

[0037] 4) All lower guide tunnels shall be equipped with full-height scaffolding⑧ on the same level and synchronously. After the full-height scaffolding⑧ of the lower guide tunnel is built, the information construction method shall be adopted, and the length of the second lining construction section shall be divided. The temporary cross brace ③ of one construction section of the second lining ⑦ of the side wall shall be chiseled out and sprayed with concrete. The temporary cross brace ③ steel shall be removed every other section or every other section, and the retained temporary cross brace ③ steel shall be treated with detailed waterproofing and water-stopping measures.

[0038] 5) All upper guide tunnels shall be equipped with full-height scaffolding⑧ at the same level and synchronously. After the erection of full-height scaffolding⑧ of the upper guide tunnels is completed, the information construction means shall be adopted, combined with the length division of the second lining construction section, and the temporary vertical support ② of one construction section within the scope of the arch second lining ⑥ shall be chiseled out and sprayed with concrete, and the temporary vertical support ② steel shall be removed every other section or every other section, and the retained temporary vertical support ② steel shall be treated with detailed waterproofing and water-stopping measures.

[0039] 6) Waterproofing and reinforcement installation of side wall secondary lining ⑦ and arch secondary lining ⑥, installation of composite steel formwork and completion of secondary lining concrete pouring.

[0040] 7) When the secondary lining concrete reaches the designed strength value, information-based construction methods are used to cut and disconnect the remaining temporary vertical bracing ② steel sections of the secondary lining ⑥ near the arch; dismantle and clean the scaffolding ⑧ of the upper guide hole of the construction section, and then continue to cut and disconnect the remaining temporary horizontal bracing ③ steel sections of the secondary lining ⑦ near the side wall; finally, complete the dismantling and cleaning of the scaffolding ⑧ of each lower guide hole.

[0041] 8) Based on the on-site construction conditions, use large or extended arm blasting machines to dismantle and clean the remaining temporary vertical supports ② and temporary horizontal supports ③ from top to bottom to complete the entire tunnel civil engineering construction.

[0042] (5) The above-mentioned method of manually chiseling away the temporary vertical support ②, the secondary lining ④ of the inverted arch, and the initial support spraying concrete within the range of the inverted arch backfill ⑤ shall be such that the chiseling height shall be the inverted arch backfill concrete elevation +≯30cm to ensure that there is space reserved for cutting the steel sections. The chiseling height shall be minimized.

[0043] (6) The waterproofing and water-stopping measures for the temporary vertical brace ② and temporary horizontal brace ③ are generally detailed and include the following construction procedures: cleaning of pollutants from the steel, welding of water-stop steel plates of customized size, applying water-swelling water-stop adhesive to the welds of the water-stop steel plates, using water-swelling water-stop adhesive to seal the PVC waterproof sheet at the root of the steel and pasting a water-swelling water-stop strip, applying an additional waterproof layer at the root of the steel and sealing and fixing it.

[0044] (7) The initial spraying of concrete is done by manually chiseling away the secondary lining ⑥ of the arch and the secondary lining ⑦ of the side wall. The chiseling height is the thickness of the secondary lining + ≯30cm, which is sufficient to ensure the reinforcement of the secondary lining formwork and reserve space for cutting steel sections. The chiseling height and width should be minimized.

[0045] (8) The remaining temporary vertical supports ② and temporary horizontal supports ③ mentioned above shall be removed in a general order of dismantling the entire section from top to bottom, in order of temporary vertical supports for the upper guide tunnel, temporary horizontal supports, and temporary vertical supports for the lower guide tunnel. The length of each longitudinal segment should not be too long and should be controlled within 3 m to ensure that the temporary vertical supports for the upper guide tunnel are not piled up on top of the temporary horizontal supports during the dismantling process, thereby affecting the dismantling of the temporary horizontal supports. After the current segment dismantling is completed, the next segment dismantling construction will be carried out in a cycle.

Claims

1. A safe and fast construction method for the secondary lining of a double-sidewall pilot tunnel, characterized in that: The following steps are involved: 1) After the initial support of the dark-excavated tunnel is closed into a ring, the initial support deformation is stable, and the tunnel is cleaned up, the elevation control line of the invert backfill concrete is measured and released, and the initial support spraying concrete is removed manually within the scope of the temporary vertical support (2), the invert secondary lining (4), and the invert backfill (5); 2) Adopting information construction means, combined with the length of the secondary lining of the inverted arch constructed at one time, dismantle the steel sections of the temporary vertical support (2) of the secondary lining (4) and the inverted arch backfill (5) of one construction section at a time, and carry out detailed waterproofing and water-stopping measures on the steel sections of the temporary vertical support (2) that are retained; 3) Waterproofing and steel bar installation of the secondary lining (4) of the inverted arch are completed; the base surface of the secondary lining (4) of the inverted arch is roughened and cleaned, and the concrete construction of the backfill (5) of the inverted arch is completed; 4) All lower guide tunnels are simultaneously erected with full-height scaffolding (8). After the full-height scaffolding (8) of the lower guide tunnel is erected, an information-based construction method is used, and the length of the secondary lining construction section is divided. The temporary cross brace (3) of one construction section of the side wall secondary lining (7) is chiseled out, and concrete is sprayed. The steel of the temporary cross brace (3) is removed every other section or every other section, and the steel of the retained temporary cross brace (3) is treated with detailed waterproof and water-stopping measures; 5) A full-height scaffold (8) is set up at the same level and simultaneously in each upper pilot tunnel. After the full-height scaffold (8) of the upper pilot tunnel is set up, an information-based construction method is used, and the length of the second lining construction section is divided. A temporary vertical support (2) of a construction section within the range of the arch second lining (6) is chiseled out, and concrete is sprayed. The steel of the temporary vertical support (2) is removed every other section or every other section, and the steel of the retained temporary vertical support (2) is treated with detailed waterproof and water-stopping measures; 6) Waterproofing and steel bar installation of the side wall secondary lining (7) and arch secondary lining (6), installation of composite steel formwork and completion of secondary lining concrete pouring; 7) When the secondary lining concrete reaches the designed strength value, the steel sections of the remaining temporary vertical braces (2) of the secondary lining (6) near the arch are cut and disconnected by using information construction methods; the red scaffolding (8) of the upper guide hole of the construction section is removed and cleaned, and then the steel sections of the secondary lining (7) and the remaining temporary horizontal braces (3) near the side wall are cut and disconnected; finally, the red scaffolding (8) of each lower guide hole is removed and cleaned; 8) Based on the on-site construction conditions, a large or extended arm blasting machine is used to dismantle and clean the remaining temporary vertical supports (2) and temporary horizontal supports (3) from top to bottom to complete the entire tunnel civil engineering construction; During the construction of the secondary lining, each pilot tunnel uses temporary structures to independently set up formwork supports. After the construction of the full-section secondary lining is completed, the secondary lining formwork system and the remaining temporary structures are removed to complete the dark-excavated tunnel construction safely and quickly. Before the construction of the secondary lining (4) of the inverted arch, the temporary vertical support (2) is removed, the primary support concrete is sprayed in the area of ​​the secondary lining (4) of the inverted arch and the backfill (5) of the inverted arch, and the steel in the area of ​​the secondary lining (4) of the inverted arch and the backfill (5) of the inverted arch is removed one or two times; The temporary vertical support (2) is manually chiseled out, the secondary lining (4) of the inverted arch and the backfill (5) are initially sprayed with concrete, and space is reserved for cutting the steel sections; The temporary vertical brace (2) and temporary horizontal brace (3) steel sections are subjected to detailed waterproofing and water-stopping measures, including the following construction steps: cleaning of steel section pollutants, welding of water-stop steel plates of customized size, applying water-swelling water-stopping adhesive to the welds of the water-stop steel plates of the steel sections, using water-swelling water-stopping adhesive to close the PVC waterproofing board at the root of the steel section and pasting a water-swelling water-stopping strip, applying an additional waterproofing layer at the root of the steel section and closing and fixing it.

2. A safe and fast construction method for the secondary lining of a double-sidewall pilot tunnel according to claim 1, characterized in that: After the construction of the inverted arch secondary lining (4) and the inverted arch backfill (5) is completed, each pilot hole is independently and synchronously set up with a full-house red scaffold (8), and then the temporary vertical support (2), temporary horizontal support (3), arch secondary lining (6), and side wall secondary lining (7) are chiseled out and the initial support sprayed concrete is removed, and the arch secondary lining (6) and side wall secondary lining (7) are removed one or two sections apart.

3. A safe and fast construction method for the secondary lining of a double-sidewall pilot tunnel according to claim 1, characterized in that: After the construction of the arch secondary lining (6) and the side wall secondary lining (7) is completed, the steel sections near the arch secondary lining (6) and the remaining temporary vertical supports (2) are cut and disconnected; then the red scaffolding (8) of each upper guide hole is removed and cleaned, and then the red scaffolding (8) near the side wall secondary lining (7) and the remaining temporary horizontal supports (3) are cut and disconnected; the red scaffolding (8) of each lower guide hole is removed and cleaned, and finally the remaining temporary vertical supports (2) and the remaining temporary horizontal supports (3) are removed and cleaned.

4. A safe and fast construction method for the secondary lining of a double-sidewall pilot tunnel according to claim 1, characterized in that: The method of manually chiseling away the second lining (6) of the arch and the second lining (7) of the side wall to initially support the sprayed concrete requires reinforcement of the second lining formwork and reserved space for cutting the profiled steel.

5. The method for safe and rapid construction of the secondary lining of a double-sidewall pilot tunnel according to claim 1 is characterized in that: The remaining temporary vertical braces (2) and temporary horizontal braces (3) are removed in a step-by-step order from top to bottom, including the temporary vertical braces of the upper guide tunnel, the temporary horizontal braces, and the temporary vertical braces of the lower guide tunnel. The longitudinal length of each section is controlled within 3 m to ensure that the temporary vertical braces of the upper guide tunnel are not piled up on top of the temporary horizontal braces during the removal process. After the current section removal is completed, the next section removal construction will be carried out in a cycle.