Method for operating a plant for the continuous preparation of isocyanates

Through the two-stage adiabatic-isothermal process mode and appropriate pressure and temperature control, the problems of by-product formation and sediment accumulation in isocyanate preparation are solved, the yield and economy are improved, and the stable operation of the device is achieved.

CN115397808BActive Publication Date: 2024-10-11COVESTRO DEUTSCHLAND AG
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202180032066.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Priority Date
2020-05-15
Filing Date
2021-05-12
Publication Date
2024-10-11
Estimated Expiration
2041-05-12

AI Technical Summary

Technical Problem

In the existing isocyanate preparation method, the external temperature adjustment of the reactor leads to the formation of by-products and the accumulation of sediments, resulting in a decrease in yield and an increase in economic costs, and the heat exchanger device increases investment costs.

Method used

Adopting a two-stage adiabatic-isothermal process mode, by conducting an adiabatic reaction in the first reaction chamber and an isothermal reaction in the second reaction chamber, the pressure is used to adjust the reaction temperature, combined with appropriate starting pressure and temperature control, to ensure that the device recovers from the interruption state. The target state is running.

Benefits of technology

It effectively reduces by-product formation and sediment accumulation, improves productivity and device reliability, reduces economic costs, and avoids additional investment costs.

✦ Generated by Eureka AI based on patent content.
Patent Text Reader

Abstract

The invention relates to a method for operating a plant for the continuous preparation of isocyanates, the continuous preparation being carried out in the liquid phase by reacting a primary amine A with phosgene P in the presence of a solvent L, while maintaining a stoichiometric excess of phosgene based on the amino group of the primary amine, using a first adiabatically operated reaction chamber and a second isothermally operated reaction chamber. The method is characterized by the use of a combination of measures, in particular maintaining a sufficiently high start-up pressure and a sufficiently high start-up temperature, in order to bring the plant back from a production interruption state to a target state, normal operation.
Need to check novelty before this filing date? Find Prior Art

Description

[0001] The invention relates to a method for operating a plant for the continuous preparation of isocyanates by reacting a primary amine A with phosgene P in the liquid phase in the presence of a solvent L, using a first adiabatically operated reaction chamber and a second isothermally operated reaction chamber, while maintaining a stoichiometric excess of phosgene based on the amino group of the primary amine. The method is characterized by the use of a combination of measures, in particular the maintenance of a sufficiently high start-up pressure and a sufficiently high start-up temperature, in order to bring the plant back from a production interruption (e.g. after a shutdown for maintenance, due to a lack of raw materials or due to a lack of demand for the isocyanate produced in the plant) to the target state, normal operation.

[0002] Isocyanates are prepared in large quantities and are used primarily as starting materials for the preparation of polyurethanes. They are mostly prepared by reacting the corresponding amines with phosgene, using a stoichiometric excess of phosgene. The reaction of amines with phosgene can be carried out in the gas phase or in the liquid phase, the reaction being carried out discontinuously or continuously. The phosgenation reaction - in the case of gas phase phosgenation, after so-called quenching of the gaseous reaction products first formed - produces a liquid phase comprising the desired isocyanate.

[0003] The preparation of organic isocyanates from primary amines and phosgene has been described in many cases; purely by way of example, reference may be made to the following documents:

[0004] DE-A-34 03 204 describes a continuous process for preparing organic polyisocyanates in which elevated temperatures of 100 to 220° C. are established at a pressure of 5 to 100 bar in a reaction which is carried out partly in a cycle.

[0005] DE-A-17 68 439 describes a process for the continuous preparation of organic isocyanates, in which the starting materials amine and phosgene are firstly preheated and the preheated components are then combined under elevated pressure in a reaction zone and reacted under isothermal conditions, ie with heat exchange with the environment.

[0006] DE-A-102 22 968 describes a process for the continuous preparation of polyisocyanates by reaction of primary amines with phosgene, the reaction being carried out in a cascade of temperature-adjustable reaction tubes of different sizes.

[0007] EP 1 873 142 A1 describes a three-stage process mode in which the pressure between the first stage of the mixer and the second stage of the first phosgenation reactor remains the same or increases, and in the third stage, in the device for separating the phosgene, the pressure is lower than in the second stage. The reaction can be run adiabatically or isothermally.

[0008] Of industrial interest are aromatic isocyanates, such as methylene diphenylene diisocyanate (hereinafter MMDI - "monomeric MDI"), mixtures of MMDI and polymethylene polyphenylene polyisocyanates (the latter being higher homologues of MMDI, hereinafter referred to as PMDI, "polymeric MDI") or toluene diisocyanate (TDI), and aliphatic isocyanates, such as 1,5-pentamethylene diisocyanate (PDI), 1,6-hexamethylene diisocyanate (HDI) or isophorone diisocyanate (IPDI). In addition, isocyanates having benzyl isocyanate groups are also important, and mention may be made here of xylylene diisocyanate (XDI) in particular. The present invention relates in particular to the preparation of methylene diphenylene diisocyanate and polymethylene polyphenylene polyisocyanates (hereinafter collectively referred to as MDI).

[0009] In most known processes, thermostatic reactors are used in various variants (jacket heating, heating via heat exchangers or special reactor internals) to establish the desired reaction temperature. However, in the synthesis of isocyanates by phosgenation of amines, external temperature control of the reactor is often a problem, since high temperatures on the reactor wall surfaces promote or even lead to the formation of by-products, which then have an adverse effect on the yield and / or product properties. In addition, deposits then form in the reactor, which requires regular shutdowns and cleaning of the reactor. However, this leads to a loss of productivity of the device and thus to economic disadvantages. In addition, the heat exchanger device causes additional investment costs, which likewise worsens the economic viability of the process. In order to solve these problems, a two-stage process mode is proposed in EP 1 616 857 A1, in which In the first phase a) The amine and phosgene are reacted in an adiabatically carried out reaction, wherein the reaction temperature is limited to values ​​of 100 to 220° C. by deliberately establishing an absolute pressure in the reactor to values ​​of 8 to 50 bar by means of reduced pressure and maintaining the temperature at values ​​of 100 to 220° C. until a phosgene conversion of at least 80% is achieved, and then In the second phase b)The reaction mixture from the first stage is depressurized to an absolute pressure of 1 to 15 bar and the reaction is continued at a temperature of 90 to 240° C., usually with heat supply. This process mode can be referred to as an adiabatic-isothermal process mode. It is important for the described process that the reaction temperature in the adiabatically operated reactor (100° C. to 220° C., preferably 115° C. to 180° C., particularly preferably 120° C. to 150° C.) is regulated by the pressure in the reactor. This regulation by pressure is carried out by controlled decompression by opening a valve installed on the reactor, whereby a portion of the reaction mixture escapes from the reactor (see paragraph

[0016] ). The reaction mixture leaving the adiabatically operated reactor is further reacted under isothermal conditions in a second stage and is depressurized therein to a pressure below that of the first stage (see paragraph

[0019] ). At the outlet of the isothermally operated reactor, a gas phase and a liquid phase containing the isocyanate are removed therefrom, respectively.

[0010] European patent application EP 3 653 605 A1 relates to a process for preparing isocyanates by reaction of primary amines with phosgene, comprising I) providing an amine solution and regulating its temperature in a heat exchanger, II) providing a phosgene solution and regulating its temperature in a heat exchanger, III) mixing the amine solution with the phosgene solution in a mixing unit, followed by IV) further reaction in an adiabatically operated reaction zone and separation of the gas phase formed as a result of the chemical reaction in a separation zone, V) decompression of the remaining liquid phase, VI) further reaction of the liquid phase remaining after decompression in an indirectly heated reaction zone, and VII) separation of the isocyanate from the reaction solution obtained there, wherein the temperature in the reaction zone and the separation zone is regulated by setting a target value for the temperature of the reaction mixture from step III) in the range of 110° C. to 145° C. and by using the actual temperature of the reaction mixture from step III) measured continuously or at intervals to control the temperature of the primary amine solution provided in step I) and / or the temperature of the phosgene solution provided in step II) by means of the heat exchangers respectively used for regulating the temperatures of these solutions.

[0011] European patent application EP 3 653 604 A1 relates to a process for preparing isocyanates by reaction of primary amines with phosgene, comprising I) providing an amine solution, II) providing a phosgene solution, III) mixing the amine solution with the phosgene solution in a mixing unit, then IV) further reacting in an adiabatically operated reaction zone and separating off the gas phase formed as a result of the chemical reaction in a separation zone, V) subjecting the remaining liquid phase to two to three-stage decompression, VI) further reacting the liquid phase remaining after the last decompression stage in an indirectly heated reaction zone and VII) separating off the isocyanate from the reaction solution obtained there.

[0012] The quality of a process for preparing isocyanates is defined on the one hand by the content of unwanted by-products in the process product. On the other hand, the quality of a process is defined by the fact that the entire process from startup, production in normal operation to shutdown of the process can be run without technical production interruptions and without problems requiring intervention in the process, and without losses of raw materials, intermediates or end products. Against this background, international patent application WO 2015 / 144658 A1 relates to a process for preparing isocyanates by phosgenating the corresponding amines, wherein problems caused by the formation of deposits in the equipment of the reaction section during the start-up (start-up) and shutdown (shutdown) of the process are avoided by process technology measures, in particular by ensuring a large excess of phosgene relative to the amine to be phosgenated during the critical startup and shutdown steps of the process. For this purpose, a continuous process for preparing isocyanates by reacting the corresponding amines with phosgene in an inert solvent is proposed, wherein the steps (A) startup of the continuous production, (B) continuous production and (C) shutdown of the continuous production are carried out successively, wherein in step (A)

[0013] The mixing zone and the reaction zone downstream thereof are first (i) at least partly charged only with an inert solvent and then heated to the desired reaction temperature and then additionally charged with phosgene but no amine, or (ii) at least partly charged with an inert solvent and phosgene but no amine and then heated to the desired reaction temperature;

[0014] Only then are the amine and also further phosgene and further inert solvent supplied continuously to the reaction zone via the mixing zone;

[0015] And wherein in step (C), firstly only the supply of amine is terminated while phosgene and inert solvent are continuously supplied to stop continuous production. This document does not introduce the characteristics of the two-stage adiabatic-isothermal process mode in detail.

[0016] However, experience has shown that the knowledge gained from the "conventional" phosgenation process cannot be simply transferred to the two-stage adiabatic-isothermal process mode. The present invention is based on the following knowledge: In the two-stage adiabatic-isothermal phosgenation process, a number of factors must be met simultaneously in order to achieve a problem-free start-up. These include, in particular, a sufficiently high start-up pressure and a sufficiently high (but not too high) start-up temperature.

[0017] In view of these insights, the present invention provides the following:

[0018] A method for operating a plant for the continuous preparation of isocyanates by reaction of a primary amine A with phosgene P in the liquid phase in the presence of a solvent L, maintaining a stoichiometric excess of phosgene based on the amino group of the primary amine,

[0019] in The device With the following Device part :

[0020] (I) First mixing equipment , which is configured to mix a primary amine A and a solvent L to form an amine solution AL,

[0021] (II) Second mixing equipment , which is configured to mix phosgene P and solvent L to form a phosgene solution PL,

[0022] (III) The third mixing equipment , which is configured to mix the amine solution and the phosgene solution into a reaction mixture,

[0023] (IV) First reaction chamber , which is configured for adiabatic reaction of the reaction mixture, and downstream of the reaction chamber reduced pressure room , which is configured to form a first liquid phase and a first gas phase (wherein the reaction chamber and the decompression chamber are arranged in (a) two different devices, namely First Reactor and First pressure relief device or (b) in its entirety First Reactor a common device),

[0024] (V) (In the case of (a): second ) a decompression device configured to decompress the first liquid phase to form a second liquid phase and a second gas phase (= a decompression chamber of the apparatus part (V) arranged in a dedicated device),

[0025] (VI) Second reaction chamber , which is configured for the isothermal reaction of the second liquid phase to form a third liquid phase and a third gas phase (= second reactor),

[0026] (VII) for obtaining isocyanate from the third liquid phase Post-processing unit ;

[0027] in The method In the target state (normal operation), the amine solution is included with the target concentration of amine in the amine solution c(A) 目标 and target flow rate ṁ(AL) of amine solution 目标 and phosgene solution with the target concentration of phosgene in the phosgene solution c(P) 目标 and target flow rate of phosgene solution ṁ(PL) 目标 Continuous reaction,

[0028] The target flow rate of the amine solution is given by the target flow rate of the amine ṁ(A) 目标 and the first target flow rate of solvent ṁ(LA) 目标 It is concluded that

[0029] The target flow rate of phosgene solution is given by the target flow rate of phosgene ṁ(P) 目标and the second target flow rate of solvent ṁ(LP) 目标 It is concluded that

[0030] And among them

[0031] Starting from a state where no amine solution is supplied to the third mixing device (i.e. the instantaneous flow rate ṁ(AL) of the amine solution is equal to zero, so the production of isocyanate is interrupted), the following steps are performed to reach the target state:

[0032] (i) Continuous Supply

[0033] (a) a phosgene solution from a second mixing device at a temperature of 100° C. to 125° C., preferably 100° C. to 105° C., with a target concentration c(P) 目标 and target flow rate ṁ(PL) 目标 , and (at the same time, before, or after)

[0034] (b) solvent (without amine) from the first mixing device at a temperature of 70°C to 100°C, preferably 90°C to 95°C, at a first target flow rate ṁ(LA) 目标

[0035] into the third mixing device and from there through the first reaction chamber, the decompression chamber, the decompression device and the second reaction chamber into the post-treatment unit,

[0036] (ii) At a target flow rate less than amine ṁ(A) 目标 Amine start-up flow rate ṁ(A) 启动 the continuous supply of amine to the first mixing device is started, and moreover the solvent stream established in step (i)(b) flows through the first mixing device and thus forms an amine solution, so that the temperature of the amine solution leaving the first mixing device is in the range of 85° C. to 105° C., preferably 95° C. to 100° C., and the temperature of the reaction mixture leaving the third mixing device is obtained in the range of 130° C. to 145° C., preferably 138° C. to 142° C. (=start-up temperature), wherein the point in time for starting the continuous supply of amine A to the first mixing device is selected such that when the amine solution and the phosgene solution come into contact with one another for the first time in the third mixing device, the pressure in the reduced pressure chamber of the apparatus part (IV) is in the range of 16 bar to 25 bar, preferably 16 bar to 20 bar (=start-up pressure),

[0037] (iii) Change the amine flow rate from ṁ(A) 启动 Increase to ṁ(A) 目标(stage by stage or continuously), and at the same time lowering the temperature of the phosgene solution removed from the second mixing device to a value of 0° C. to 10° C., preferably 0° C. to 5° C., so that the temperature of the reaction mixture leaving the third mixing device remains within the range set in step ii) and the pressure in the reduced pressure chamber of plant part (IV) is increased to a value of 20 bar to 30 bar, preferably 20 bar to 25 bar,

[0038] (iv) After reaching the target amine flow rate (i.e., ṁ(A) = ṁ(A) 目标 ):

[0039] The temperature of the amine solution removed from the first mixing device is reduced to a value of 50° C. to 80° C., preferably 50° C. to 60° C., so that under the target conditions the temperature of the reaction mixture leaving the third mixing device is in the range of 125° C. to 135° C., preferably 128° C. to 132° C., and the pressure in the reduced pressure chamber of the apparatus part (IV) is maintained at 20 bar to 30 bar, preferably 20 bar to 25 bar.

[0040] Here and below, all pressures are to be understood as absolute pressures.

[0041] According to the invention, phosgene is used in a "stoichiometric excess" based on the amino groups of the primary amines. Theoretically, 1 mol of phosgene reacts with 1 mol of primary amino groups. Thus, an excess of x% phosgene relative to the primary amino groups corresponds to The molar ratio n (Phosgene) / n (-NH2) n = amount of substance), i.e., for example, in the case of a 40% excess of phosgene 1.40 or, for example, in the case of a 120% excess of phosgene 2.2.

[0042] Below first Brief summary Various possible embodiments of the present invention.

[0043] In a first embodiment of the present invention, which can be combined with all other embodiments, in step (i)

[0044] The temperature of the phosgene solution is set to a value between 100°C and 105°C, and

[0045] The temperature of the solvent is set to a value of 90°C to 95°C;

[0046] wherein in step (ii)

[0047] When the amine solution and the phosgene solution first come into contact with one another in the third mixing device, the pressure in the reduced pressure chamber of the apparatus part (IV) is 16 to 20 bar;

[0048] The temperature of the amine solution leaving the first mixing device occurs at 95°C to 100°C, and

[0049] The temperature of the reaction mixture obtained leaving the third mixing device is 138° C. to 142° C.;

[0050] and wherein in step (iii)

[0051] the temperature of the phosgene solution removed from the second mixing device is reduced to a value between 0°C and 5°C, and

[0052] The pressure in the reduced pressure chamber of the device part (IV) is increased to a value of 20 to 25 bar;

[0053] and wherein in step (iv)

[0054] the temperature of the amine solution removed from the first mixing device is reduced to a value of 50° C. to 60° C.,

[0055] Under target conditions, the temperature of the reaction mixture leaving the third mixing device occurs between 128°C and 132°C, and

[0056] The pressure in the reduced pressure chamber of the apparatus part (IV) is maintained at 20 to 25 bar.

[0057] In a second embodiment of the invention, which can be combined with all other embodiments, the pressure in the reduced pressure chamber of the apparatus part (IV) established in step (iii) is greater than the pressure in the reduced pressure chamber of the apparatus part (IV) in which the continuous supply of amine to the first mixing device is started in step (ii).

[0058] In a third embodiment of the invention, which is an alternative to the fourth embodiment described below, but can otherwise be combined with all other embodiments, the reaction chamber and the decompression chamber of apparatus part (IV) are arranged in two different devices (first reactor and first decompression device).

[0059] In a fourth embodiment of the invention, which is an alternative to the aforementioned third embodiment but can otherwise be combined with all other embodiments, the reaction chamber and the decompression chamber of device part (IV) are arranged in a common device (which in its entirety constitutes the first reactor).

[0060] In a fifth embodiment of the invention, which can be combined with all other embodiments, in step (ii), the pressure in the reduced pressure chamber of apparatus part (IV) is adjusted by degassing phosgene, by adding an inert gas, in particular nitrogen, and / or by adding hydrogen chloride.

[0061] In a sixth embodiment of the invention, which is a special embodiment of the fifth embodiment, the pressure in the reduced pressure chamber of apparatus part (IV) is adjusted by adding hydrogen chloride, wherein hydrogen chloride is withdrawn from the first, second and / or third gas phase.

[0062] In a seventh embodiment of the invention, which is an alternative to the eighth and ninth embodiments described below, but which can otherwise be combined with all other embodiments, step (i)(b) is carried out simultaneously with step (i)(a).

[0063] In an eighth embodiment of the invention, which is an alternative to the seventh embodiment described above and the eighth embodiment described below, but otherwise combinable with all other embodiments, the performance of step (i)(b) begins before step (i)(a).

[0064] In a ninth embodiment of the invention, which is an alternative to the seventh and eighth embodiments described above, but which can otherwise be combined with all other embodiments, the performance of step (i)(b) begins after step (i)(a).

[0065] In a tenth embodiment of the present invention, which can be combined with all other embodiments, the post-processing unit comprises

[0066] a first distillation apparatus configured to separate a fourth gaseous phase containing phosgene from the third liquid phase to obtain a fourth liquid phase depleted in phosgene,

[0067] a second distillation apparatus configured to separate a fifth gaseous phase containing the solvent from the fourth liquid phase to obtain a fifth liquid phase depleted in phosgene and solvent, and

[0068] - A third distillation apparatus configured to obtain the isocyanate from the fifth liquid phase.

[0069] In an eleventh embodiment of the present invention, which can be combined with all other embodiments, after reaching the target state (and after the device has been running at the target state for a period of time), the continuous reaction of the amine solution and the phosgene solution is interrupted, wherein the following steps are performed for interruption:

[0070] (v) increasing the temperature of the phosgene solution and the temperature of the amine solution without changing the flow rates of the phosgene solution and the amine solution relative to the target state;

[0071] (vi) when the temperature of the reaction mixture leaving the third mixing device reaches > 135°C to 140°C:

[0072] stopping supplying amine to the first mixing device, maintaining supplying solvent to the first mixing device, and maintaining supplying phosgene solution to the second mixing device;

[0073] (vii) stopping the supply of phosgene to the second mixing device, maintaining the supply of solvent to the second mixing device and maintaining the supply of solvent to the first mixing device;

[0074] (viii) after the phosgene concentration in the solvent leaving the second mixing device has fallen below a previously determined limit concentration:

[0075] stopping the supply of solvent to the second mixing device; and

[0076] (viii) stopping the supply of solvent to the first mixing device.

[0077] In a twelfth embodiment of the present invention, which is a specific embodiment of the eleventh embodiment, in step (v), the temperature of the phosgene solution is increased to a value of 100°C to 125°C, wherein the temperature of the amine solution is increased to a value of 100°C to 125°C.

[0078] In a thirteenth embodiment of the invention, which is a specific embodiment of the eleventh and twelfth embodiments, in step (vi), the supply of amine is stopped as soon as the temperature of the reaction mixture leaving the third mixing device is >135°C to 137°C.

[0079] In a fourteenth embodiment of the present invention, which can be combined with all other embodiments, the primary amine is selected from methylene diphenylene diamine (thereby obtaining methylene diphenylene diisocyanate), polymethylene polyphenylene polyamines (thereby obtaining polymethylene polyphenylene polyisocyanates), a mixture of methylene diphenylene diamine and polymethylene polyphenylene polyamines (thereby obtaining a mixture of methylene diphenylene diisocyanate and polymethylene polyphenylene polyisocyanates), toluenediamine (thereby obtaining toluene diisocyanate), xylylenediamine (thereby obtaining xylylenediisocyanate), 1,5-pentanediamine (thereby obtaining 1,5-pentanediisocyanate), 1,6-hexamethylenediamine (thereby obtaining 1,6-hexamethylenediisocyanate), isophoronediamine (thereby obtaining isophorone diisocyanate) and naphthalene diamine (thereby obtaining naphthalene diisocyanate).

[0080] The above brief description and other possible embodiments of the present invention will be explained in more detail below.Here, unless otherwise specified or clearly derived from the context, all embodiments can be combined with each other arbitrarily.

[0081] Run the device in target state (normal operation)

[0082] Before further describing the features of the production start-up according to the invention, the operation of the device in the target state (= conventional operation) is first described in more detail. As is obvious to a person skilled in the art, many aspects described below also apply to the start-up operating state (e.g. the type of equipment used or the temperature control method of the reactants). In order to avoid unnecessary repetition, these aspects will not be described in further detail hereafter.

[0083] Once the amine solution flow rate ṁ(A) reaches ṁ(AL) 目标 = ṁ(A) 目标 + ṁ(LA) 目标 (wherein for the concentration c(A) of amine A in the amine solution AL, c(A) = c(A) 目标 ), that is, the target state is reached. The process for preparing isocyanate in the target state comprises the following steps (the process steps described below with Arabic numbers ((1), (2), etc.) are carried out in the parts of the apparatus with corresponding Roman numbers ((I), (II), etc.):

[0084] (1) With the help of First mixing equipment providing a solution of a primary amine A corresponding to an isocyanate in a solvent L;

[0085] (2) With the help of Second mixing equipment providing a solution of phosgene P in a solvent L;

[0086] (3) In The third mixing equipment The primary amine solution provided in step (1) and the phosgene solution provided in step (2) are mixed to form a reaction mixture having a temperature of 125° C. to 135° C., preferably 128° C. to 132° C., maintaining a stoichiometric excess of phosgene based on the amino groups of the primary amine, preferably 40% to 200% of theory, particularly preferably 40% to 120% of theory, very particularly preferably 50% to 100% of theory, and very particularly preferably 50% to 75% of theory;

[0087] (4) passing the liquid reaction mixture obtained in step (3) through a first reaction chamber and through a first decompression chamber of apparatus part (IV) downstream of the first reaction chamber to form a first liquid phase and a first gas phase at a pressure of 20 to 30 bar, preferably 20 to 25 bar, wherein the first reaction chamber and the decompression chamber are neither heated nor cooled (i.e. both are operated adiabatically);

[0088] (5) The first liquid phase taken out from the decompression chamber in step (4) is placed in the apparatus part (V) Pressure relief equipment decompressing the medium (in a single stage or in multiple stages) to form a second liquid phase and a second gas phase;

[0089] (6) passing the second liquid phase obtained after decompression in step (5) through Second reaction chamber , forming a third liquid phase (containing isocyanate and solvent) and a third gas phase (containing hydrogen chloride and phosgene and usually also containing a certain proportion of evaporated solvent), wherein the second reaction chamber is indirectly heated, i.e. isothermally operated;

[0090] (7) Post-processing unit The third liquid phase obtained in step (6) is post-treated to recover the solvent and obtain isocyanate.

[0091] Since the decompression chamber of the apparatus part (IV) is "downstream" of the first reaction chamber, which in the terminology of the invention also means an open fluid connection of the two zones, and since the first reaction chamber and the decompression chamber of the apparatus part (IV) are also "unheated and uncooled" (= adiabatic process mode), the temperature occurring at each point in the first reaction chamber and the decompression chamber of the apparatus part (IV) is, at a given temperature of the reaction mixture from step (3), essentially - apart from heat losses due to imperfect insulation of the equipment used - determined by the reaction enthalpy of the chemical process occurring (this will be explained in detail below). The pressure established is also primarily determined by the chemical process occurring. However, a pressure retaining valve for the gas phase formed and a level control for the liquid phase are preferably provided in the decompression chamber of the apparatus part (IV) in order to be able to reliably ensure a pressure within the above-mentioned range (20 bar to 30 bar, preferably 20 bar to 25 bar). Therefore, the temperature in step (4) ultimately depends on the temperature of the reaction mixture supplied to this step.

[0092] Step 1), Provides amine solution for phosgenation, can be carried out by all methods known from the prior art. The amine to be used is determined by the desired isocyanate. The process according to the invention is suitable in principle for preparing any aromatic, aliphatic and araliphatic isocyanates. Preference is given to using the process according to the invention to prepare methylene diphenylene diisocyanate (from methylene diphenylene diamine), polymethylene polyphenylene polyisocyanates (from polymethylene polyphenylene polyamines), mixtures of methylene diphenylene diisocyanate and polymethylene polyphenylene polyisocyanates (these mixtures are also referred to below as MDI and the starting amine mixtures as MDA), toluene diisocyanate (from toluene diamine), xylylene diisocyanate (from xylylene diamine), 1,5-pentamethylene diisocyanate (from 1,5-pentamethylene diamine), 1,6-hexamethylene diisocyanate (from 1,6-hexamethylene diisocyanate), isophorone diisocyanate (from isophorone diamine) and naphthalene diisocyanate (from naphthalene diamine), particular preference being given to methylene diphenylene diisocyanate, mixtures of methylene diphenylene diisocyanate and polymethylene polyphenylene polyisocyanates and toluene diisocyanate. The process according to the invention is very particularly preferably suitable for preparing methylene diphenylene diisocyanate and mixtures of methylene diphenylene diisocyanate and polymethylene polyphenylene polyisocyanate. Methylene diphenylene diisocyanate is also known as diamines of the diphenylmethane series. Polymethylene polyphenylene polyisocyanates are also known as polyamines of the diphenylmethane series.

[0093] Processes for preparing the amines mentioned are known to the person skilled in the art, so that no further explanation is required at this point.

[0094] In step (1), the amine to be phosgenated is dissolved in a solvent. As the first mixing device required for this purpose, a mixing device known to those skilled in the art can be used. A mixing tube having a static mixer (usually also referred to as a static mixer) as an internal component is particularly suitable. Here, suitable solvents available according to the present invention are solvents that are inert under reaction conditions, such as monochlorobenzene, dichlorobenzene (especially ortho-isomers), dioxane, toluene, xylene, methylene chloride, perchloroethylene, trichlorofluoromethane or butyl acetate. The solvent is preferably substantially free of isocyanate (striving for a mass ratio of <100 ppm) and substantially free of phosgene (striving for a mass ratio of <100 ppm), which should be noted when using a circulating stream. Therefore, it is preferred to work by the method described in EP 1 854 783 A2. The solvent can be used alone or as any mixture of the solvents mentioned as an example. Preferably, monochlorobenzene (MCB) or o-dichlorobenzene (ODB) is used, and monochlorobenzene (MCB) is very particularly preferred.

[0095] The temperature of the resulting amine solution is predetermined to be 50° C. to 80° C., particularly preferably 50° C. to 60° C. In principle, this can be achieved by appropriate temperature control of the starting material amine and the solvent, taking into account the dissolution enthalpy. In particular, however, in addition to the temperature control of the starting materials mentioned, it is preferred according to the invention to provide a heat exchanger downstream of the mixing of the amine and the solvent, which enables the amine solution to be adjusted in a targeted manner to the desired temperature in the mentioned range, so that it can be heated or cooled depending on the temperature immediately after the mixing of the starting materials. Suitable for this are the heat exchangers known to the person skilled in the art, such as, in particular, tube bundle heat exchangers and plate heat exchangers.

[0096] Taking into account the amine concentration in the solution provided in step (1), the mass proportion of the primary amine based on the total mass of the solution is preferably adjusted to a value of 25% to 50%, in particular 30% to 45%.

[0097] Step 2), Provide phosgene solution required for phosgenation , which can likewise be carried out by all methods known from the prior art. The same mixing equipment and solvents as described above for the primary amines are suitable. It is particularly preferred that the primary amine in step (1) and the phosgene in step (2) are each dissolved in the same solvent, i.e. very particularly preferably in MCB. Methods for preparing phosgene are known to those skilled in the art, so that no further explanation is required at this point.

[0098] The temperature of the resulting phosgene solution is predetermined to be 0° C. to 10° C., preferably 0° C. to 5° C. In principle, this can be achieved by appropriate temperature control of the starting material phosgene and the solvent, taking into account the dissolution enthalpy. However, in particular in addition to the temperature control of the starting materials mentioned, it is preferred according to the invention to provide a heat exchanger downstream of the mixing of phosgene and solvent, which enables the phosgene solution to be adjusted to the desired temperature in the above-mentioned range in a targeted manner, so that it can be heated or cooled depending on the temperature immediately after the mixing of the starting materials. Suitable for this are the same heat exchangers as described above for the primary amines.

[0099] Taking into account the phosgene concentration in the solution provided in step (2), the mass proportion of phosgene based on the total mass of the solution is preferably adjusted to a value of 45% to 90%, in particular 55% to 80%.

[0100] In step (3), Mixing the primary amine solution provided in step (1) and the phosgene solution provided in step (2). Mixing devices known per se to the person skilled in the art, such as static or dynamic mixers, are suitable as the third mixing device required for this purpose. Static mixers are characterized by the absence of movable parts, and here in particular mixing tubes (often also referred to as static mixers) or nozzles with static mixers as internal components may be mentioned. In contrast, dynamic mixers contain movable parts, such as agitator elements. In particular, the rotor-stator systems known from EP 0 830 894 A1 and EP 2 077 150 A1 may also be mentioned here. Dynamic mixers, in particular dynamic mixers of the rotor-stator type, are preferably used in the present invention.

[0101] The third mixing device of step (3) is preferably neither heated nor cooled, which means that the temperature of the obtained reaction mixture is determined only by the mixing enthalpy and the enthalpy of the reaction that has already started in the mixing device. The conveying pipe for the reaction mixture between the outlet of the third mixing device and the inlet in the first reaction chamber is also preferably neither heated nor cooled, but is preferably insulated.

[0102] According to the invention, during the mixing in step (3), a stoichiometric excess of phosgene, based on the amino group of the primary amine, is maintained, preferably from 40% to 200% of theory, particularly preferably from 40% to 120% of theory, very particularly preferably from 50% to 100% of theory, very very particularly preferably from 50% to 75% of theory.

[0103] In step (4) (in addition to the chemical reaction already started in the third mixing device) the reaction for forming the isocyanate takes place First main part , more precisely in Adiabatic conditions This means that the reaction mixture is neither heated nor cooled during the reaction as it passes through step (4). The equipment used is insulated against heat losses, so that the temperature development is determined by the reaction enthalpy of the reaction taking place.

[0104] Without wishing to be bound by theory, it is assumed that multiple reactions are carried out simultaneously in step (4) (and partially in step (3) already). The primary amine reacts with phosgene to form the known intermediate carbamoyl chloride (exothermic reaction). The hydrogen chloride released here reacts with the amine not yet converted to form amine hydrochloride (exothermic reaction), which dissolves in the solvent used (endothermic reaction). The cleavage of the carbamoyl chloride into the desired isocyanate and hydrogen chloride also partially occurs in step (4) (endothermic reaction). The change in temperature depends on the interaction of all these reactions. Usually, only a slight change in temperature is observed in step (4), which indicates that the exothermic reaction and the endothermic reaction maintain a "balance". In any case, a first gas phase is formed in the reaction in step (4), which is separated from the remaining first liquid phase in the first decompression chamber of the device part (IV).

[0105] (a) According to the present invention, two separate devices can be used as the first reaction chamber and the decompression chamber of the device part (IV), in which case, in the terminology of the present invention, the device comprising the first reaction chamber is referred to as the first reactor, and the device comprising the first decompression chamber is referred to as the first decompression device. Suitable as the first decompression device is a gas-liquid separation container (also referred to as a gas separator) known per se to those skilled in the art.

[0106] (b) According to the invention, it is also possible and preferred to arrange the first reaction chamber and the first decompression chamber in a common apparatus, which is then referred to as the first reactor in its entirety in the terminology of the invention.

[0107] Whether variant (a) or variant (b) is used, a suitable first reactor is a conventional phosgenation reactor known to those skilled in the art, such as, in particular, a vertically arranged tubular reactor (tubular reactor; if the aspect ratio is relatively small, also referred to as a tower reactor or reactor tower). Such a reactor can also be operated as a bubble column. In order to reduce the residence time distribution, the first reaction chamber arranged in the first reactor can be segmented by internal components known to those skilled in the art. The reaction mixture obtained in step (3) preferably flows through the first reactor from bottom to top. In the preferred case (b), the first decompression chamber is the gas space in the upper region of the first reactor, from which the first liquid phase and the first gas phase are taken out separately.

[0108] Whether variant (a) or (b) is used, phase separation occurs spontaneously.

[0109] In step (5), the first liquid phase obtained in step (4) is subjected to Single-stage or multi-stage decompression , more precisely preferably to a pressure of 1.0 bar to 20 bar, and in the case of multi-stage decompression, the gas phase obtained in the last stage is measured, which is referred to as the second gas phase in the terminology of the present invention. Suitable (in case (a): second) decompression equipment is a gas-liquid separation container (also called a gas separator) known per se to those skilled in the art. In the case of multi-stage decompression in step (5), a corresponding number of such gas separators are connected in series, wherein in the terminology of the present invention, the entirety of all series-connected gas-liquid separation containers constitutes the decompression equipment of the device part (V). Here, a gas phase containing hydrogen chloride and unconverted phosgene is formed in each stage. In the multi-stage decompression, the liquid phase obtained after the first stage decompression is the raw material for the second stage, and so on.

[0110] The gas-liquid separation vessel provided for decompression (for final decompression in case of multi-stage decompression) and the second (indirectly heated) reaction chamber of step (6) may be arranged in a common apparatus. An example of a possible embodiment is described below.

[0111] In step (6), the second liquid phase obtained in step (5) is placed in the second reaction chamber. Further reaction , forming a third liquid phase containing the desired isocyanate and a third gas phase (containing hydrogen chloride and phosgene) ("isothermal process mode"). This can be carried out in a heatable reactor known to the person skilled in the art. Particularly suitable for this purpose are (vertically arranged) tube bundle reactors. Here, the second liquid phase can be conducted through the interior of the tubes of the tube bundle reactor (tube interior space) or through the space between the tubes of the tube bundle reactor, which space is bounded to the outside by the reactor wall surrounding the tube bundle (tube exterior space). The heating medium - thermal oil, salt melt, steam, etc. - is then conducted through the respective other space, so that it does not come into material contact with the liquid process product to be converted (indirect heating). In this case, the second liquid phase obtained in step (4) preferably flows from top to bottom through the vertically arranged tube bundle reactor. In this preferred embodiment of the invention, the gas-liquid separation container provided for the decompression of step (5) / for the final decompression stage of step (5) is integrated in the device in which the second reaction chamber of step (5) is arranged, and the gas-liquid phase separation is then carried out in the top cover at the top of the tube bundle reactor.

[0112] In step (7), in the post-processing unit Post-processing the third liquid phase obtained in step (6) , separating the desired isocyanate and recovering the solvent. This step can be carried out by methods known per se from the prior art and generally comprises Take off Phosgenation , Solvent separation and Final purification Preferably, the third liquid phase is firstly freed as completely as possible from dissolved phosgene in a first distillation apparatus (the so-called "dephosgeneration column"), which is separated off as a fourth gaseous phase, thereby obtaining a phosgene-depleted liquid phase. No. Four liquid phases This is preferably freed as completely as possible from the solvent in a second distillation apparatus (the so-called "solvent column") (which is separated as Fifth gas phase ), thereby obtaining a phosgene- and solvent-depleted Fifth liquid phase The recovered phosgene and solvent are advantageously recycled.

[0113] The fifth liquid phase is subjected to final purification in the third distillation apparatus, which includes homologue separation if necessary. Depending on the type of isocyanate, final purification may also include isomer separation. In a preferred embodiment, the present invention relates to the preparation of methylene diphenylene diisocyanate and a mixture of methylene diphenylene diisocyanate and polymethylene polyphenylene polyisocyanate. In this case, the fifth liquid phase, which preferably contains a mixture of all crude isocyanates (homologues and isomers), is first supplied to a distillation homologue separation (so-called "polymer separation"), thereby forming a distillate consisting of methylene diphenylene diisocyanate (which contains at most trace amounts of polymethylene polyphenylene polyisocyanate) and a bottom product consisting of polymethylene polyphenylene polyisocyanate and methylene diphenylene diisocyanate (wherein the proportion of methylene diphenylene diisocyanate is reduced compared to the fifth liquid phase corresponding to the amount of methylene diphenylene diisocyanate distilled out in the homologue separation). The distillate consisting of methylenediphenylene diisocyanate is freed from low-boiling and high-boiling impurities in at least one further distillation step and separated into different isomeric fractions. The isomer separation preferably comprises obtaining a fraction of 4,4'-methylenediphenylene diisocyanate and a fraction of a mixture of 2,4'-methylenediphenylene diisocyanate and 4,4'-methylenediphenylene diisocyanate. Step (7), which is only briefly outlined here, is described in detail in the prior art; for example, reference may be made to WO 2017 / 050776 A1.

[0114] In steps (4), (5) and (6), gas phases (i.e., the first, second and third gas phases) containing hydrogen chloride and phosgene and optionally entrained solvent are formed. Preferably, these gas phases are also subjected to an aftertreatment to recover valuable products. The aftertreatment is particularly used to separate phosgene and hydrogen chloride from each other and to separate impurities, and can be carried out, for example, by absorbing the phosgene in a solvent or by separating by distillation after compression and liquefaction. The resulting hydrogen chloride gas is suitable for further oxidation to chlorine, which is required for the preparation of the phosgene required for step (2). The oxidation can be carried out electrolytically or catalytically with oxygen (the so-called Deacon process). As will be explained below, a portion of the recovered hydrogen chloride can also be used to establish a start-up pressure. The recovered phosgene, optionally containing a solvent, can be used in step (2).

[0115] In any case, it is expedient to bring the gas phases formed in steps (4), (5) and (6) to a common pressure and combine before work-up.

[0116] In principle, this can be achieved by decompressing all gas phases to the lowest pressure (ie to the pressure of the third gas phase obtained in step (6)) or even lower pressure and then further purifying. This treatment method is preferred, especially in the case of work-up by absorption.

[0117] Start production (transfer the device to the target state)

[0118] The startup process of the present invention needs to start from a state where no amine solution is supplied to the third mixing device (i.e., the instantaneous flow rate ṁ(AL) of the amine solution is equal to zero, so the production of isocyanate is interrupted), and perform the steps (i) to (iv) described above to reach the target state (for converting the device to the conventional operation explained above). In this case, in a preferred embodiment,

[0119] In step (i)

[0120] · setting the temperature of the phosgene solution to a value between 100°C and 105°C, and

[0121] Set the temperature of the solvent to a value between 90°C and 95°C;

[0122] In step (ii), the process is carried out such that:

[0123] When the amine solution and the phosgene solution first come into contact with one another in the third mixing device, the pressure in the reduced pressure chamber of the apparatus part (IV) is 16 to 20 bar;

[0124] The temperature of the amine solution leaving the first mixing device occurs at 95°C to 100°C, and

[0125] The temperature of the reaction mixture obtained leaving the third mixing device is 138° C. to 142° C.;

[0126] In this case, in step (iii), the process is carried out in such a way that:

[0127] the temperature of the phosgene solution removed from the second mixing device is reduced to a value between 0°C and 5°C, and

[0128] The pressure in the reduced pressure chamber of the device part (IV) is increased to a value of 20 to 25 bar;

[0129] and wherein finally in step (iv) it is run such that:

[0130] the temperature of the amine solution removed from the first mixing device is reduced to a value of 50° C. to 60° C.,

[0131] Under target conditions, the temperature of the reaction mixture leaving the third mixing device occurs between 128°C and 132°C, and

[0132] The pressure in the reduced pressure chamber of the apparatus part (IV) is maintained at 20 to 25 bar.

[0133] For the pressure in the reduced pressure chamber of the plant part (IV) established in step (iii), a value is preferably selected which is greater than the pressure in the reduced pressure chamber at which the continuous supply of amine to the first mixing device was initiated in step (ii). This ensures that the reaction does not stop even if the excess phosgene decreases due to a continuous increase in the concentration of the aniline solution supplied.

[0134] Depending on the pressure and temperature conditions selected in step (ii), the dissolved phosgene is partially converted from the liquid phase into the gaseous state (outgassing). As a result, the pressure in the decompression chamber of the device part (IV) increases. In the method according to the invention, it is provided that the amine solution and the phosgene solution only come into contact with each other for the first time in the third mixing device when the pressure in the decompression chamber of the device part (IV) is between 16 bar and 25 bar, preferably between 16 bar and 20 bar (starting pressure). For this purpose, the residence time of the amine solution from the beginning of the supply of amine to the first mixing device until the amine solution first reaches the third mixing device must be taken into account, which is easy to determine for a given device. In addition to the pressure established by the given boundary conditions without taking any special measures, the pressure in the decompression device part (IV) can also be established by adding an inert gas (in particular nitrogen) and / or by adding hydrogen chloride. Here, hydrogen chloride can advantageously be taken from the first, second and / or third gas phase, wherein, if necessary, this hydrogen chloride can also originate from an earlier production period for the preparation of isocyanates (intermediate storage in a suitable storage container).

[0135] After step (iv) has been performed, the apparatus is in normal operation and can continue to operate until the next production interruption as described above.

[0136] Stop production (transition the device from the target state to a state where the device stops operating)

[0137] Any continuous production must be interrupted from time to time, possibly because the demand for the product produced decreases or because work needs to be done on the plant (maintenance, repairs, etc.). For this purpose, it is preferred within the scope of the present invention to proceed as follows:

[0138] Without changing the flow rates of the phosgene solution and the amine solution relative to the target state (normal operation), the temperature of the phosgene solution and the amine solution is first increased. The effect achieved thereby is to avoid a temperature drop after the third mixing device, which could lead to contamination of the reactor. The temperature of the phosgene solution is increased from its target value of 0°C to 10°C for normal operation to a value preferably of 100°C to 125°C. The temperature of the amine solution is preferably increased from its target value of 50°C to 80°C for normal operation to a value preferably of 100°C to 125°C. As a result, the temperature of the reaction mixture leaving the third mixing device is increased from its target value of 125°C to 135°C under normal operation to a higher value. When a temperature of >135°C to 140°C, preferably >135°C to 137°C, is reached, the further supply of amine is interrupted, however, during this period the solvent flow rate into the third mixing device via the first mixing device is continued, wherein this flow rate can also be higher or lower, in particular higher than in normal operation (to adjust the temperature at the outlet of the third mixing device). The temperature at the outlet of the third mixing device decreases with increasing dilution of the amine solution. The temperature is preferably maintained in the range of 115°C to 125°C.

[0139] In order to flush the equipment used and react the amine still present therein, after shutting down the amine supply, the phosgene solution is also continuously supplied through the second mixing device, the third mixing device and the equipment downstream thereof for a certain time, preferably a time of 15 minutes to 3 hours, for example a time of 20 minutes. After this time has passed, the phosgene supply is also interrupted, and only the solvent for diluting / flushing the phosgene solution still present in the equipment is pumped into the third mixing device through the second mixing device and pumped into the equipment downstream thereof from the equipment. Once the phosgene is fully replaced (i.e., reaching the limit concentration determined in advance), the metered addition of the solvent through the second mixing device is interrupted. Thereafter (especially 10 minutes to 20 minutes, for example 15 minutes later), the solvent supply via the first mixing device is also interrupted.

[0140] The extent to which the plant must be depleted of phosgene depends on the circumstances. In the case of relatively brief interruptions in production without work being done on the plant parts that conduct phosgene, it is generally not necessary to completely replace the phosgene. If the plant is to be out of operation for a longer period or if work is to be done on the plant parts that conduct phosgene, the phosgene must of course be completely replaced or decomposed by subsequent cleaning steps, for example by reaction with ammonia.

[0141] The invention is explained in more detail below with reference to exemplary embodiments.

[0142] Example:

[0143] The percentage concentration data are percentages by mass, based on the total mass of the respective material stream. For the definition of phosgene excess, see the previous description.

[0144] The example was carried out in a small-scale plant, in which an amine solution consisting of about 11.6 kg / h of MDA and about 27 kg / h of MCB from a first mixing device was mixed with a phosgene solution from a second mixing device in a dynamic mixer (third mixing device) with an excess of about 60% phosgene under target conditions, and the resulting mixture was supplied to an adiabatically operated bubble column reactor (adiabatically operated reaction chamber, first reactor). The product mixture from the bubble column reactor was decompressed in two decompression devices (the first decompression device corresponds to the decompression chamber of the plant part (IV), the second decompression device corresponds to the plant part (V)), and the liquid phase obtained was supplied to a falling film evaporator (isothermally operated reaction chamber, second reactor). The liquid phase formed therein was supplied to a distillation column, in which MDI was formed as a bottom stream and a gas phase containing phosgene and hydrogen chloride was formed as a top stream. The gas phase formed in the two decompression devices was combined with the gas phase.

[0145] Example 1 (Comparison - Starting pressure too low):

[0146] A 60% phosgene solution is prepared by mixing monochlorobenzene (MCB) and phosgene and conveyed from the second mixing device to the third mixing device at a mass flow rate of ṁ = 51.4 kg / h and a temperature of 120°C. MCB heated to 95°C is subsequently conveyed via the first mixing device to the third mixing device at a mass flow rate of ṁ = 30 kg / h. Then the supply of MDA to the second mixing device and from there to the third mixing device is started. An amine solution temperature of 100°C is established. Start-up is carried out with an amine solution concentration of 25% (corresponding to an amount of about 9.7 kg / h of MDA and about 28.9 kg / h of MCB). After about 7 minutes, the amine solution reaches the third mixing device and the reaction begins. The pressure in the decompression chamber at this point in time (=start pressure) is 15 bar. Due to the start of the reaction, the temperature at the outlet of the third mixing device increases from 100°C to 135°C within 5 minutes. Once the temperature stopped rising, the concentration of the amine solution was increased to 30% (corresponding to an amount of about 11.6 kg / h of MDA and about 27 kg / h of MCB). Due to this change, the temperature at the outlet of the third mixing device increased to 140°C. The pressure in the decompression chamber increased to 20 bar.

[0147] Subsequently, the temperature of the phosgene solution was reduced from 120°C to 0°C within 90 minutes, taking into account the temperature at the outlet of the third mixing device (which should not fall below 135°C). About 10 minutes after the start of the temperature reduction of the phosgene solution, the phosgene excess was reduced stepwise from 210% to 60% by continuously increasing the mass flow rate and concentration of the amine solution (final value was about 60 kg / h amine solution, concentration was 30%). At the same time, the pressure in the decompression chamber was increased to 26 bar. The reduction of the phosgene excess (while maintaining the temperature at the outlet of the third mixing device at least 135°C) lasted for about 60 minutes.

[0148] A decrease in gas production in the reduced pressure chamber was also observed during the reduction of the phosgene excess. At a pressure of 24 bar in the reduced pressure chamber and a phosgene excess of about 60%, the temperature at the outlet of the third mixing device dropped (which indicates that the reaction had "rested"). In order to avoid contamination of the reactor, the experiment had to be terminated.

[0149] Example 2 (Comparative - the starting pressure is high enough, but the temperature at the outlet of the third mixing device is too high):

[0150] A 60% phosgene solution is prepared by mixing monochlorobenzene (MCB) and phosgene and conveyed from the second mixing device to the third mixing device at a mass flow rate of ṁ = 51.4 kg / h and a temperature of 120°C. MCB heated to 80°C is subsequently conveyed via the first mixing device to the third mixing device at a mass flow rate of ṁ = 30 kg / h. Then the supply of MDA to the second mixing device and from there to the third mixing device is started. An amine solution temperature of 95°C is established. Start-up is carried out with an amine solution concentration of 25% (corresponding to an amount of about 9.7 kg / h of MDA and about 28.9 kg / h of MCB). After about 7 minutes, the amine solution reaches the third mixing device and the reaction begins. Before the start of the reaction, the pressure in the decompression chamber is 15 bar and is appropriately increased to 20 bar (= starting pressure) by adding nitrogen before the first contact between MDA and phosgene. As a result of the start of the reaction, the temperature at the outlet of the third mixing device increases from 100°C to 135°C within 5 minutes. Once the temperature stopped rising, the concentration of the amine solution was increased to 30% (corresponding to an amount of about 11.6 kg / h of MDA and about 27 kg / h of MCB). Due to this change, the temperature at the outlet of the third mixing device increased to 140°C. The pressure in the decompression chamber increased to 26 bar within 10 minutes due to the progress of the reaction.

[0151] Subsequently, the temperature of the phosgene solution was reduced from 120°C to 0°C within 90 minutes, irrespective of the temperature at the outlet of the third mixing device. About 10 minutes after the start of the temperature reduction of the phosgene solution, the phosgene excess was reduced stepwise from 210% to 60% by continuously increasing the mass flow rate and concentration of the amine solution (final value was about 60 kg / h amine solution, concentration of 30%). The reduction of the phosgene excess (again irrespective of the temperature at the outlet of the third mixing device) lasted for about 30 minutes. The temperature at the outlet of the third mixing device increased to 150°C, which was accompanied by increased solids formation and coating of the inner walls of the reactor with solids. The experiment was terminated to avoid further contamination of the reactor.

[0152] Example 3 (according to the invention - the starting pressure is high enough and the temperature at the outlet of the third mixing device is within a suitable range):

[0153] A 60% phosgene solution is prepared by mixing monochlorobenzene (MCB) and phosgene and conveyed from the second mixing device to the third mixing device at a mass flow rate of ṁ = 51.4 kg / h and a temperature of 120°C. MCB heated to 80°C is subsequently conveyed via the first mixing device to the third mixing device at a mass flow rate of ṁ = 30 kg / h. Then the supply of MDA to the second mixing device and from there to the third mixing device is started. An amine solution temperature of 95°C is established. Start-up is carried out with an amine solution concentration of 25% (corresponding to an amount of about 9.7 kg / h of MDA and about 28.9 kg / h of MCB). After about 7 minutes, the amine solution reaches the third mixing device and the reaction begins. Before the start of the reaction, the pressure in the decompression chamber is 15 bar and is appropriately increased to 20 bar (= starting pressure) by adding nitrogen before the first contact between MDA and phosgene. As a result of the start of the reaction, the temperature at the outlet of the third mixing device increases from 100°C to 135°C within 5 minutes. Once the temperature stopped rising, the concentration of the amine solution was increased to 30% (corresponding to an amount of about 11.6 kg / h of MDA and about 27 kg / h of MCB). Due to this change, the temperature at the outlet of the third mixing device increased to 140°C. The pressure in the decompression chamber increased to 26 bar within 10 minutes due to the progress of the reaction.

[0154] Subsequently, taking into account the temperature at the outlet of the third mixing device (which should be maintained at about 140°C), the temperature of the phosgene solution was reduced from 120°C to 0°C within 90 minutes. About 10 minutes after the temperature of the phosgene solution began to decrease, the phosgene excess was gradually reduced from 210% to 60% by continuously increasing the mass flow rate and concentration of the amine solution (final value was about 60 kg / h amine solution, concentration was 30%). The reduction of the phosgene excess (while maintaining the temperature at the outlet of the third mixing device at about 140°C) lasted for about 30 minutes.

[0155] After reaching a 60% phosgene excess, the temperature of the amine solution was reduced from 95°C to 55°C within 30 minutes. Under these conditions (amine solution temperature 55°C, phosgene solution temperature 0°C, phosgene excess 60%, pressure in the reduced pressure chamber 26 bar), the temperature of the reaction mixture at the outlet of the third mixing device was established to be 130°C. The plant was thus in the target state. The time from the start-up until the target state was reached was about 4 hours.

Claims

1. A process for operating a plant for the continuous preparation of isocyanates by reaction of a primary amine A with phosgene P in the liquid phase in the presence of a solvent L, maintaining a stoichiometric excess of phosgene based on the amino group of the primary amine, The device comprises the following device parts: (I) a first mixing device configured to mix a primary amine A and a solvent L into an amine solution AL, (II) a second mixing device configured to mix phosgene P and solvent L to form a phosgene solution PL, (III) a third mixing device configured to mix the amine solution and the phosgene solution into a reaction mixture, (IV) a first reaction chamber configured for adiabatic reaction of the reaction mixture, and a reduced pressure chamber downstream of the reaction chamber configured for forming a first liquid phase and a first gas phase, (V) a decompression device for decompressing the first liquid phase to form a second liquid phase and a second gas phase, (VI) a second reaction chamber configured for isothermal reaction of the second liquid phase to form a third liquid phase and a third gas phase, (VII) a post-treatment unit for obtaining isocyanate from the third liquid phase; The method comprises, in a target state, The target concentration of amine in the amine solution is c(A) 目标 and target flow rate of amine solution and phosgene solution with the target concentration of phosgene in the phosgene solution c(P) 目标 Target flow rate of phosgene solution Continuous reaction, The target flow rate of the amine solution is determined by the target flow rate of the amine and the first target flow rate of the solvent It is concluded that The target flow rate of phosgene solution is determined by the target flow rate of phosgene and the second target flow rate of the solvent It is concluded that And among them Starting from a state where no amine solution is supplied to the third mixing device, the following steps are performed to reach the target state: (i) Continuous Supply (a) Phosgene solution from the second mixing device at a temperature of 100°C to 125°C with a target concentration c(P) 目标 and target traffic and (b) the solvent from the first mixing device, at a temperature of 70°C to 100°C, at a first target flow rate into the third mixing device and from there through the first reaction chamber, the decompression chamber, the decompression device and the second reaction chamber into the post-treatment unit, (ii) At a target flow rate less than that of the amine The starting flow rate of amine a continuous supply of amine to the first mixing device is started, through which the solvent stream established in step (i)(b) flows and thus forms an amine solution, such that the temperature of the amine solution leaving the first mixing device is between 85° C. and 105° C., and the temperature of the reaction mixture obtained leaving the third mixing device is between 130° C. and 145° C., wherein the point in time for starting the continuous supply of amine to the first mixing device is selected such that, when the amine solution and the phosgene solution first come into contact with one another in the third mixing device, the pressure in the reduced pressure chamber of the apparatus part (IV) is between 16 bar and 25 bar, (iii) changing the flow rate of the amine step by step or continuously from Increase to and at the same time reducing the temperature of the phosgene solution removed from the second mixing device to a value of 0° C. to 10° C., so that the temperature of the reaction mixture leaving the third mixing device is maintained at 130° C. to 145° C. and the pressure in the reduced pressure chamber of apparatus part (IV) is 20 bar to 30 bar, (iv) After reaching the target flow rate of amine, The temperature of the amine solution removed from the first mixing device is reduced to a value of 50°C to 80°C, so that under the target conditions the temperature of the reaction mixture leaving the third mixing device is between 125°C and 135°C and the pressure in the decompression chamber of device part (IV) is maintained at 20 bar to 30 bar.

2. The method according to claim 1, In step (i), The temperature of the phosgene solution is set to a value between 100°C and 105°C, and The temperature of the solvent is set to a value of 90°C to 95°C; and wherein in step (ii) When the amine solution and the phosgene solution first come into contact with one another in the third mixing device, the pressure in the reduced pressure chamber of the apparatus part (IV) is 16 to 20 bar; The temperature of the amine solution leaving the first mixing device occurs at 95°C to 100°C, and The temperature of the reaction mixture obtained leaving the third mixing device is 138° C. to 142° C.; and wherein in step (iii) the temperature of the phosgene solution removed from the second mixing device is reduced to a value between 0°C and 5°C, and The pressure in the reduced pressure chamber of the device part (IV) is increased to a value of 20 to 25 bar; and wherein in step (iv) the temperature of the amine solution removed from the first mixing device is reduced to a value of 50° C. to 60° C., Under target conditions, the temperature of the reaction mixture leaving the third mixing device occurs between 128°C and 132°C, and The pressure in the reduced pressure chamber of the apparatus part (IV) was maintained at 20 to 25 bar.

3. A process according to claim 1 or 2, wherein the pressure in the reduced pressure chamber of the apparatus part (IV) established in step (iii) is greater than the pressure in the reduced pressure chamber of the apparatus part (IV) in which the continuous supply of amine to the first mixing device is started in step (ii).

4. The method according to any one of claims 1 or 2, wherein the reaction chamber and the decompression chamber of device part (IV) are arranged in two different devices.

5. The method according to claim 1, wherein the reaction chamber and the decompression chamber of apparatus part (IV) are arranged in a common device.

6. The process according to claim 1 , wherein in step (ii), the pressure in the reduced pressure chamber of apparatus part (IV) is adjusted by degassing phosgene, by adding an inert gas and / or by adding hydrogen chloride.

7. The process according to claim 6, comprising adjusting the pressure in the reduced pressure chamber of apparatus part (IV) by adding hydrogen chloride, wherein hydrogen chloride is withdrawn from the first, second and / or third gas phase.

8. The method according to any one of claims 1 or 2, wherein step (i)(b) is performed simultaneously with step (i)(a).

9. The method according to any one of claims 1 or 2, wherein step (i)(b) is performed before step (i)(a).

10. The method according to any one of claims 1 or 2, wherein the performance of step (i)(b) begins after step (i)(a).

11. The method according to any one of claims 1 or 2, wherein the post-processing unit comprises a first distillation apparatus configured to separate a fourth gaseous phase containing phosgene from the third liquid phase to obtain a fourth liquid phase depleted in phosgene, a second distillation apparatus configured to separate a fifth gaseous phase containing the solvent from the fourth liquid phase to obtain a fifth liquid phase depleted in phosgene and solvent, and - A third distillation apparatus configured to obtain the isocyanate from the fifth liquid phase.

12. The method according to claim 1 , wherein after reaching the target state, the continuous reaction of the amine solution with the phosgene solution is interrupted, wherein the following steps are performed for interruption: (v) increasing the temperature of the phosgene solution and the temperature of the amine solution without changing the flow rates of the phosgene solution and the amine solution relative to the target state; (vi) when the temperature of the reaction mixture leaving the third mixing device reaches >135°C and ≤140°C: stopping the supply of amine to the first mixing device, maintaining the supply of solvent to the first mixing device and maintaining the supply of phosgene solution to the second mixing device; (vii) stopping the supply of phosgene to the second mixing device, maintaining the supply of solvent to the second mixing device and maintaining the supply of solvent to the first mixing device; (viii) after the phosgene in the solvent leaving the second mixing device has fallen below a previously determined limit concentration: stopping the supply of solvent to the second mixing device; and (viii) Stopping the supply of solvent to the first mixing device.

13. The process according to claim 12, wherein in step (v) the temperature of the phosgene solution is increased to a value of 100 to 125°C and wherein the temperature of the amine solution is increased to a value of 100 to 125°C.

14. The process according to claim 12, wherein in step (vi), the supply of amine is stopped once the temperature of the reaction mixture leaving the third mixing device is >135°C and ≤137°C.

15. The process according to any one of claims 1 or 2, wherein the primary amine is selected from the group consisting of methylene diphenylene diamine, polymethylene polyphenylene polyamines, mixtures of methylene diphenylene diamine and polymethylene polyphenylene polyamines, toluenediamine, xylylenediamine, 1,5-pentanediamine, 1,6-hexamethylenediamine, isophoronediamine, and naphthalenediamine.