Single-span overall floating installation construction method for trestle superstructure

By adopting a single-span overall floating installation method in the construction of water bridges, and using the support and jack on the barge to assemble and install the upper structure of the trestle bridge as a whole, the problems of slow construction progress and major weather-affected problems in the existing technology are solved, and the problem of slow construction progress and heavy weather is realized. Fast and efficient construction and turnover use.

CN115404781BActive Publication Date: 2024-11-22ROAD & BRIDGE INT CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202210975702.6
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-08-15
Publication Date
2024-11-22
Estimated Expiration
2042-08-15

AI Technical Summary

Technical Problem

In the existing construction methods of water bridges, the installation and disassembly of the upper structure of the trench bridge leads to slow construction progress, and is greatly affected by uncertain factors such as weather and wind and waves. Especially when the scale is large or the construction period is tight, it is difficult to meet the rapid development. Construction requirements.

Method used

A single-span overall floating installation and construction method is adopted for the trest superstructure. By erecting a bracket and a jack on the barge, the entire superstructure is assembled into a whole, and the crane and winch are used to assemble and adjust the position on land to synchronize the steel pipes. Pile insertion and structural installation realize the rapid installation and removal of the superstructure.

Benefits of technology

It greatly improves construction efficiency, shortens the water construction time, reduces the risk of being affected by weather and wind and waves, and quickly turns around to use or remove the trestle when needed, significantly improving construction speed and efficiency.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115404781B_ABST
    Figure CN115404781B_ABST
Patent Text Reader

Abstract

The present invention relates to a method for floating installation of a single-span upper structure of a trestle, wherein a support is set up on a barge, and a crane is used on a dock to assemble a single-span upper structure of the trestle into a whole on the barge support, and the trestle is transported to one side of the trestle by ship, and the whole-span upper structure of the trestle on the ship is lifted to a level higher than the pile top bearing beam by a jack, and then the barge is moved to the middle of the bridge span, and the jack returns oil to drop the Bailey beam onto the pile top bearing beam, thereby completing the installation of the single-span upper structure of the trestle. The present invention transfers the assembly operation of the upper structure of the trestle from water to land, and the construction time on water is short. The driving of the steel pipe piles of the trestle and the assembly of the upper structure can be constructed simultaneously, and the upper structure of the trestle can be installed as a whole with a single span, and the construction speed is fast and the efficiency is high.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge construction, relates to the construction of a steel trestle used for water bridge construction, and specifically relates to a single-span integral floating installation construction method for a trestle superstructure. Background Art

[0002] The trestle is a temporary structure for underwater bridge construction, which runs through the entire process of bridge construction. The trestle includes a substructure and a superstructure, such as Figure 1 , Figure 2 As shown, the lower structure of the pier includes steel pipe piles 1 inserted into the water, and a load-bearing beam 2 is set on the steel pipe piles in the transverse direction of the bridge; the upper structure has many design components, including a Bailey beam 3 set on the load-bearing beam in the longitudinal direction of the bridge, a plurality of transverse distribution beams 4 are set on the Bailey beam in the transverse direction of the bridge, a plurality of longitudinal distribution beams 5 are set on the transverse distribution beams in the longitudinal direction of the bridge, a bridge deck 6 is laid on the longitudinal distribution beam, and guardrails 7 are usually arranged on both sides of the bridge deck.

[0003] There are usually two methods for trestle construction: the fishing method and the pile-first method. The fishing method uses crawler cranes and other lifting equipment in conjunction with a vibrating hammer to vibrate and sink piles. The lifting equipment also installs the superstructure at the same time, and the construction is carried out span by span from the shore into the water. The pile-first method uses a pile-driving ship or other piling equipment to first sink piles in the water, and then install the superstructure. In these two construction methods, each component of the trestle superstructure needs to be installed one by one, and also needs to be dismantled one by one when the trestle is dismantled. For trestle with large scale or tight construction period, or when the trestle needs to be used in rotation, the construction progress is too slow; in addition, the above methods all require long-term water operations, which are greatly affected by uncertain factors such as weather or wind and waves. Summary of the invention

[0004] The purpose of the present invention is to solve the above problems and provide a method for the overall floating installation construction of a single-span superstructure of a pier, so as to improve the construction efficiency and reduce the time of water operations.

[0005] The technical solution of the present invention is as follows:

[0006] A single-span overall floating installation construction method for a pier superstructure is characterized by comprising the following steps:

[0007] (1) The barge is moored at the dock, and a set of brackets is set up at both ends of the barge. Each set of brackets includes two steel pipe brackets. The two steel pipe brackets are arranged in parallel in the transverse direction of the ship. Two supports are set up on the top of each steel pipe bracket. A joist is set up on the top of the supports on the two brackets. A jack is set up between the two supports on each bracket. The bottom of the jack is supported on the bracket, and the top is facing the bottom surface of the joist.

[0008] (2) While the steel pipe piles of the low trestle are being driven, a crane is used to assemble a span of the trestle superstructure on the bracket into a whole; the Bailey beam of the trestle superstructure is supported on the cushion beam and is temporarily connected and fixed to the cushion beam;

[0009] (3) After the steel pipe piles of the trestle substructure are driven and the load-bearing beams are installed, the barge is towed to one side of the trestle and the direction of the barge is adjusted so that the trestle superstructure on the barge is in the direction of the bridge; the temporary connection between the Bailey beam and the cushion beam is released, and the four jacks on the two sets of brackets are started simultaneously to lift the entire span of the trestle superstructure to a height higher than the load-bearing beam at the top of the pile;

[0010] (4) Move the barge to the middle of the bridge span and adjust the position of the barge so that the superstructure of the trestle is located directly above the designed installation position; slowly return the oil to the jack to drop the Bailey beam onto the pile top load-bearing beam, install the Bailey beam limit device, and complete the installation of the superstructure of the one-span trestle.

[0011] The present invention transfers the assembly work of the upper structure of the trestle from the water to the land, assembles it into a whole, and ships it to the place for installation. The steel pipe piles of the trestle can be driven and the upper structure assembled simultaneously, with fast construction speed and high efficiency. The water construction time is short, and the uncertainties caused by water construction can be reduced. When the trestle needs to be used in a turnover manner, the whole span can be dismantled and transported by this method, which can also greatly improve the turnover efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0012] Figure 1 This is a schematic diagram of the longitudinal structure of the trestle;

[0013] Figure 2 This is a schematic diagram of the transverse structure of the trestle;

[0014] Figure 3 It is a schematic diagram of the upper structure of the whole-span trestle for ship transportation according to the present invention in the along-bridge direction;

[0015] Figure 4 It is a transverse schematic diagram of the upper structure of the whole-span trestle for shipping of the present invention;

[0016] Figure 5 It is a schematic diagram along the bridge after the upper structure of a trestle bridge is installed as a whole. DETAILED DESCRIPTION

[0017] like Figure 3 , Figure 4 , Figure 5 As shown, the construction process of the present invention is as follows:

[0018] (1) The beam transport barge 8 is docked at the dock, and a set of brackets 9 are respectively set up at both ends of the barge, each set of brackets includes two steel pipe brackets, the two steel pipe brackets are arranged in parallel in the transverse direction of the ship, and two supports 10 are set up on the top of each steel pipe bracket, and a joist 11 is set up on the top of the supports on the two brackets; a jack 12 is set between the two supports on each bracket, and the bottom of the jack is supported on the bracket, and the top is directly opposite to the bottom surface of the joist beam;

[0019] (2) While the steel pipe piles 1 of the trestle are being driven, a crane is used to assemble a span of the trestle superstructure on the bracket 9 into a whole; the Bailey beam of the trestle superstructure is supported on the cushion beam 11 and is temporarily connected and fixed to the cushion beam;

[0020] (3) After the steel pipe piles 1 of the trestle substructure are driven and the load-bearing beams 2 are installed, the barge 8 is towed to one side of the trestle and the direction of the barge 8 is adjusted so that the trestle superstructure on the boat is in the direction of the bridge; at this time, the height of the joist beam 11 is lower than the height of the load-bearing beam on the pile top; the temporary connection between the Bailey beam and the cushion beam is released, and the four jacks 12 on the two sets of brackets are started simultaneously, and the entire span of the trestle superstructure is lifted to a height higher than the load-bearing beam 2 on the pile top through the joist beam 11;

[0021] (4) Move the barge to the middle of the bridge span where the superstructure is to be installed, and adjust the position of the barge so that the superstructure of the trestle is located directly above the designed installation position; slowly return the oil to the jack to drop the Bailey beam 3 onto the pile top load-bearing beam 2, install the Bailey beam limit device, and complete the installation of the superstructure of the trestle span.

[0022] When the present invention is implemented, a winch 13 can be fixedly installed on the barge in advance at the four corners of the barge. When the barge moves to the middle of the bridge span and the position of the barge is adjusted, the traction ropes 14 of the four winches 13 are respectively connected to the four steel pipe piles 1 of each span, and the steel pipe piles are used as anchor piles. The traction ropes are tightened or loosened by the four winches respectively, and the position of the barge is accurately adjusted. After the barge position is adjusted in place, the barge position is fixed.

[0023] After the installation of the superstructure of one span of the trestle is completed, the barge returns to the dock to assemble, transport and install the next span. When the construction period is tight, multiple barges can be used to assemble, transport and install the superstructure of the trestle at the same time to speed up the construction progress.

[0024] The trestle dismantling method is the reverse process of the above-mentioned installation method. When the trestle needs to be rotated, the above-mentioned barge can be used to dismantle the entire span of the trestle superstructure as a whole and transport it to the next trestle installation location.

Claims

1. A method for the overall floating installation of a single-span trestle superstructure, characterized in that: The following steps are involved: (1) The barge is moored at the dock, and a set of brackets is set up at both ends of the barge. Each set of brackets includes two steel pipe brackets. The two steel pipe brackets are arranged in parallel in the transverse direction of the ship. Two supports are set up on the top of each steel pipe bracket. A joist is set up on the top of the supports on the two steel pipe brackets. A jack is set up between the two supports on each steel pipe bracket. The bottom of the jack is supported on the steel pipe bracket, and the top is directly opposite to the bottom surface of the joist. (2) While the steel pipe piles of the trestle are being driven, a crane is used to assemble a span of the trestle superstructure on the bracket into a whole; the Bailey beam of the trestle superstructure is supported on the joist beam and is temporarily connected and fixed to the joist beam; (3) After the steel pipe piles of the trestle substructure are driven and the load-bearing beams are installed, the barge is towed to one side of the trestle and the direction of the barge is adjusted so that the trestle superstructure on the barge is along the direction of the bridge; the temporary connection between the Bailey beam and the supporting beam is released, and the four jacks on the two sets of brackets are started simultaneously to lift the entire span of the trestle superstructure to a height higher than the load-bearing beam at the top of the pile; (4) Move the barge to the middle of the bridge span and adjust the position of the barge so that the superstructure of the trestle is directly above the designed installation position; The jack slowly returns oil, drops the Bailey beam onto the load-bearing beam on the top of the pile, installs the Bailey beam limit device, and completes the installation of the superstructure of a span trestle.

2. The single-span integral floating installation construction method for the superstructure of a pier according to claim 1 is characterized in that: A winch is fixedly installed on the barge at each of the four corners of the barge. When adjusting the position of the barge, the traction ropes of the four winches are connected to the four steel pipe piles of each span respectively. The steel pipe piles are used as anchor piles. The traction ropes are tightened or loosened by the four winches respectively to accurately adjust the position of the barge. After the barge is adjusted into place, the position of the barge is fixed.