A method for treating deep deformation of ballasted track subgrade in operating railway
Through the steps of I-beam rail buckling, pile foundation construction and load-bearing plate backfilling, the problem of deep deformation of the ballasted track subgrade was solved, efficient remediation was achieved, the project cost and construction period were reduced, and the maintenance of the ballasted track line was satisfied. need.
Patent Information
- Application Number
- CN202211269131.0
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2022-10-17
- Publication Date
- 2024-10-29
- Estimated Expiration
- 2042-10-17
AI Technical Summary
It is difficult for existing technology to effectively solve the problem of deep deformation of ballasted track subgrade under operating conditions, especially when the skylight operation time is limited, the construction period is long, and the cost is high. The existing solutions cannot meet the maintenance needs of ballasted track lines.
The methods of I-beam rail buckling, pile foundation construction, easel beam erection, ballast and subgrade excavation, load-bearing plate construction and backfilling are used to adjust the track geometry by constructing pile foundations and load-bearing plate structures at the lower part of the track structure. Realize the control of deep deformation of ballasted track subgrade.
It provides an efficient and convenient method for remediating deep deformation of ballasted track subgrade in operating railways, which can completely remediate deep deformation of ballasted track subgrade under operating conditions, reduces project cost and construction period, and meets the maintenance needs of ballasted track lines.
Smart Images

Figure CN115434191B_ABST
Abstract
Description
Technical Field
[0001] The invention belongs to the technical field of railway tracks, and in particular relates to a method for regulating deep deformation of a ballasted track subgrade of an operating railway. Background Art
[0002] At present, affected by complex geological factors and environmental factors such as expansive rock and collapsible loess, the expansion or settlement of railway subgrade and deep foundation causes the continuous arching or settlement of track structure. In order to ensure normal operation, the railway equipment management department needs to carry out maintenance and repair operations frequently, which greatly increases the maintenance and repair costs. Some work points with serious deformation are also subject to speed limits, which seriously interferes with the normal operation order. In recent years, some relatively effective remediation measures have been proposed for the deep deformation of ballastless track subgrade or foundation. The deep soil under the track structure can be replaced by mechanical or manual operation, or the pile-slab structure scheme can be used to eliminate the influence of deep soil deformation on the track structure. However, for ballasted track, since the roadbed is a loose ballast material, it is easy to become unstable, and the above schemes are difficult to apply. At the same time, the skylight operation time of most ballasted track lines in my country is a "V"-shaped skylight, that is, the skylight time of the up and down lines is different. Therefore, it is of great significance to propose an effective method for remediation of deep deformation of ballasted track subgrade under operating conditions.
[0003] Prior art CN108951307A discloses a method for treating the arching of ballastless track subgrade. Its technical solution can only replace the shallow layer of ballastless track subgrade under operating conditions, and cannot solve the problem of replacing the deep layer of ballasted track subgrade. Prior art CN112012051A discloses a method for treating the deformation of ballastless track. Its technical solution has a large amount of excavation and replacement engineering, support engineering, difficulty and safety risk. Since most ballastless tracks under operating conditions do not have the conditions for large-scale mechanical equipment to operate, the second technical solution can only use manual work, which increases the construction period, and then leads to long-term operation of the line, and the project cost is large. Moreover, this solution also cannot solve the impact of deep deformation of ballasted track subgrade.
[0004] The prior art CN113605152A discloses a structure, method and application of a deep replacement roadbed for a dark excavation pile-row roadbed. This technical solution cannot meet the maintenance work window time requirements of ballasted track lines. At the same time, since the pile-row mainly relies on manual excavation, the amount of work is large, and it is not applicable to work sites with a deformation layer exceeding 10 meters or a shallow groundwater level. Therefore, how to overcome the above defects, provide a method for regulating the ballastless track roadbed under operating conditions, and solve the problem of deep replacement of ballasted track roadbed, has become a topic to be solved in this technical field. Summary of the invention
[0005] In order to overcome the shortcomings of the above-mentioned prior art, the present invention provides a method for treating deep deformation of ballasted track subgrade in an operating railway, which specifically adopts the following technical solutions:
[0006] A method for treating deep deformation of ballasted track subgrade of an operating railway comprises the following steps:
[0007] S1. Construction preparation steps;
[0008] S2. I-beam rail buckling step, used to support and limit the track structure;
[0009] S3. Pile foundation construction step, used to construct pile foundation between the shoulder and the line, which is used to support the temporary beam and subsequent bearing plate;
[0010] S4. Beam erection steps;
[0011] S5. Ballast and roadbed excavation step, used to remove the ballast under the temporary beam and excavate the roadbed;
[0012] S6. Steps for constructing the bearing plate and longitudinal beams, which are used to construct the bearing plate and connect it to the pile foundation;
[0013] S7. Roadbed and ballast backfilling steps;
[0014] S8. Steps for removing the temporary beam and I-beam;
[0015] S9. Line maintenance steps.
[0016] Furthermore, the S1. construction preparation step specifically includes:
[0017] The length of the section for erecting a single temporary beam and removing the roadbed is divided to determine the specific location of the pile foundation; the section length is 16m or 24m.
[0018] Further, the step S2. I-beam rail buckling specifically includes:
[0019] In the roadbed excavation section, a plurality of I-beams are respectively installed below the track and between two adjacent sleepers, and a plurality of through holes are opened on the upper surfaces of both ends of the I-beams;
[0020] Below the two ends of the I-beam, square wood sleepers and sleeper piers are respectively arranged from top to bottom to support the I-beam;
[0021] The track rails are fixedly connected to the I-beams.
[0022] Further, the S3. pile foundation construction step specifically includes:
[0023] After the I-beam rail buckling step is completed, the temporary beam pile foundation and the temporary piers between the lines are constructed by manual digging or mechanical drilling;
[0024] The length of the temporary beam pile foundation needs to penetrate the deep deformation layer to the stable soil layer or rock layer. The diameter of the circular pile or the side length of the square pile of the temporary beam pile foundation section is 1.5m-1.8m, and the distance between adjacent temporary beam pile foundations is 6m-8m;
[0025] The length of the temporary piers between lines is 3m-4m, the pile diameter is optimized and determined according to the line spacing, the diameter of the circular piles or the side length of the square piles of the temporary piers between lines is 1.5m-1.8m, and the spacing between adjacent temporary piers between lines is 6m-10m.
[0026] Furthermore, the step of S4. erecting the temporary beam includes:
[0027] Temporary beams are respectively erected on both sides of the track, and the temporary beams are erected on the top of the temporary beam pile foundation, and the extension direction of the temporary beam is parallel to the extension direction of the track;
[0028] A plurality of connecting pieces are arranged on the side of the temporary beam, the plane where the connecting pieces are located is perpendicular to the extension direction of the track, one side of the connecting piece is vertically welded to the side of the temporary beam, the spacing between two adjacent connecting pieces is the same as the spacing between the track sleepers, and the connecting piece is provided with a plurality of through holes at equal intervals from top to bottom;
[0029] The two ends of the I-beam are respectively fixed to the porous connecting piece of the temporary beam on one side through connecting pieces, so as to achieve the fixation of the temporary beam and the I-beam.
[0030] Furthermore, the connecting member includes a horizontally arranged base and a vertically arranged connecting plate, which are fixedly connected or integrally formed;
[0031] The base is provided with a plurality of through holes, which correspond to the positions of the plurality of through holes provided on the upper surface of one end of the I-beam, respectively, so that the base can be fixed to the upper surface of the I-beam by means of bolts and nuts passing through the through holes;
[0032] The connecting plate is provided with a plurality of through holes corresponding to a part of the plurality of through holes of the connecting sheet, and the connecting plate can be fixedly connected to the connecting sheet by means of bolts and nuts passing through the through holes.
[0033] Further, the step of S5. removing ballast and roadbed comprises:
[0034] The ballast and part of the roadbed soil are excavated, and the thickness of the excavated part of the roadbed soil is 2m-3m.
[0035] Furthermore, the S6. construction of the bearing plate and the longitudinal beam specifically includes:
[0036] The longitudinal beam is erected on the top of two adjacent piles, and the extension direction of the longitudinal beam is parallel to the extension direction of the track. The longitudinal beams are erected on both sides of the track;
[0037] The bearing plate is set up on the top of the longitudinal beam and below the track, and a 20cm-40cm empty layer is reserved at the bottom of the bearing plate.
[0038] Furthermore, the S7. roadbed and ballast backfill specifically includes:
[0039] After backfilling graded crushed stone on the top of the bearing plate to the original roadbed top surface elevation, backfill the ballast bed.
[0040] Furthermore, the S9. line maintenance step specifically includes: tamping the ballast bed with a large machine.
[0041] The present invention provides an efficient and convenient method for treating deep deformation of ballasted track subgrade in operation. Under operation conditions, pile foundation and bearing plate structure can be constructed under the ballast track structure, and the geometric state of the track can be adjusted to achieve thorough treatment of deep deformation of the ballasted track subgrade. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 is a flow chart of the method of the present invention;
[0043] Figure 2 It is a top view of the I-beam after being fastened to the rail of the present invention;
[0044] Figure 3 It is a side view of the I-beam after the rail is buckled according to the present invention;
[0045] Figure 4 It is a cross-sectional schematic diagram of the pile foundation and temporary supporting piers for construction of temporary beams of the present invention;
[0046] Figure 5 This is a schematic diagram of the plan of setting up a temporary beam according to the present invention;
[0047] Figure 6 It is a schematic diagram of the cross section of the roadbed of the present invention. DETAILED DESCRIPTION
[0048] The present invention will be further described below in conjunction with the accompanying drawings. The following examples are only used to more clearly illustrate the technical solution of the present invention, and cannot be used to limit the scope of protection of the present invention. It should be pointed out that the following detailed descriptions are all exemplary and are intended to provide further explanation of the present application.
[0049] Unless otherwise specified, all technical and scientific terms used herein have the same meanings as those generally understood by those of ordinary skill in the art to which this application belongs. It should be noted that the terms used herein are only for the purpose of describing specific embodiments and are not intended to limit the exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular form is also intended to include the plural form. In addition, it should be understood that when the terms "comprising" and / or "including" are used in this specification, it indicates the presence of features, steps, operations, devices, components and / or combinations thereof.
[0050] The embodiment of the present invention discloses a method for remediating deep deformation of ballasted track subgrade in an operating railway. The method first uses an I-beam buckle beam to support and limit the track structure, and then constructs pile foundations between the shoulders and the lines. The pile foundations are used to support temporary beams and subsequent load-bearing plates. After the pile foundation construction is completed, temporary beams are erected, and then the ballast below the temporary beams is removed, the subgrade is excavated, the load-bearing plates are constructed and connected to the pile foundations, and finally the ballast is backfilled. The scope of remediation should be reasonably divided into construction sections according to the operating conditions. After the pile-slab structure construction of all construction sections is completed, the line is tamped and maintained. For the specific construction process, please refer to the attached Figure 1 shown.
[0051] Each step is described below.
[0052] Construction preparation.
[0053] Re-measure the deformation of the line to determine the scope of the renovation. At the same time, based on the renovation of the line, reasonably divide the length of the single temporary beam erection and roadbed excavation section, and then determine the specific location of the pile foundation. The length of the single renovation section can be determined in combination with the length of the temporary beam, which can generally be selected as 16m or 24m.
[0054] I-beam rail clip.
[0055] The track structure is reinforced by using I-beams to buckle the rails to ensure the safety of the line. During the pile foundation construction, if the line sinks, the I-beams can ensure the safety of the line. Since the I-beams require a small bearing capacity, the I-beams can be considered to be temporarily supported by sleepers.
[0056] See attached Figure 2 , Attachment Figure 3 As shown, in the roadbed excavation section, a plurality of I-beams are installed below the track and between two adjacent sleepers, and a plurality of through holes are opened on the upper surfaces of both ends of the I-beams; below both ends of the I-beams, square wood sleepers and sleeper piers are arranged from top to bottom to support the I-beams; the track rails are fixedly connected to the I-beams.
[0057] Pile foundation construction.
[0058] See attached Figure 4As shown, after the construction of the I-beam rail clip is completed, the temporary beam pile foundation and temporary piers between the lines are constructed by manual digging or mechanical drilling.
[0059] In addition to providing support for the temporary beam, the temporary beam pile foundation must also consider the use requirements of the pile-board structure under normal driving conditions after renovation. Its size should be designed according to the roadbed, foundation properties and driving conditions. The length of the pile foundation must penetrate the deep deformation layer to the stable soil or rock layer. The cross-sectional size of the pile foundation and the pile spacing must meet the strength and deformation requirements. It is generally recommended that the diameter of the round pile or the side length of the square pile be 1.5-1.8m, and the pile spacing be 6-8m.
[0060] Temporary piers between lines are designed only considering the supporting function during the renovation process. The pile length is generally 3-4m, and the pile diameter is optimized according to the line spacing. Generally, the diameter of round piles or the side length of square piles is 1.5-1.8m, and the recommended pile spacing is 6-10m.
[0061] Erection of temporary beams.
[0062] After the pile foundation and temporary piers between the lines are constructed, temporary beams are erected to support and limit the track. Temporary beams are erected on both sides of the track, and the temporary beams are erected on the top of the temporary beam pile foundation. The extension direction of the temporary beam is parallel to the extension direction of the track; multiple connecting pieces are arranged on the side of the temporary beam, and the plane where the connecting piece is located is perpendicular to the extension direction of the track. One side of the connecting piece is vertically welded to the side of the temporary beam, and the spacing between two adjacent connecting pieces is the same as the spacing between the track sleepers. The connecting piece is provided with multiple through holes at equal intervals from top to bottom; the two ends of the I-beam are fixed to the porous connecting piece of the corresponding side of the temporary beam through connecting pieces, so as to achieve the fixation of the temporary beam and the I-beam. The connecting member includes a horizontally arranged base and a vertically arranged connecting plate, which are fixedly connected or integrally formed; a plurality of through holes are provided on the base, which correspond to the positions of a plurality of through holes provided on the upper surface of one end of the I-beam, respectively, and the base can be fixed to the upper surface of the I-beam by means of bolts and nuts passing through the through holes; a plurality of through holes are provided on the connecting plate, which correspond to the positions of a part of the plurality of through holes of the connecting plate, and the connecting plate can be fixedly connected to the connecting plate by means of bolts and nuts passing through the through holes.
[0063] As attached Figure 5 The figure shows the plan layout of a temporary beam with a single length of 16m, which is rectified in three steps.
[0064] Ballast and roadbed removal.
[0065] After the temporary beam is erected, small machinery is used to remove the ballast and a certain thickness of roadbed soil. The excavation thickness is determined according to the subsequent bearing plate thickness, which is generally 2-3m.
[0066] Construction of load-bearing plates and longitudinal beams.
[0067] After the roadbed is excavated and leveled, the steel bars are tied, the formwork is erected, and the longitudinal beam and the bearing plate are constructed in sequence. The longitudinal beam is erected on the top of two adjacent piles, and the extension direction of the longitudinal beam is parallel to the extension direction of the track. The bearing plate is erected on the top of the longitudinal beam and is located below the track. A 20-40cm hollow layer is reserved at the bottom of the bearing plate to avoid the impact of the expansion of the lower soil on the bearing plate.
[0068] Backfill of roadbed and ballast.
[0069] After backfilling graded crushed stone on the top of the bearing plate to the original roadbed top surface elevation, backfill the ballast bed.
[0070] Remove the temporary beams and I-beams.
[0071] All temporary beams and I-beams were removed, and the cross section of the roadbed after renovation is as shown in the attached figure. Figure 6 As shown. According to the step-by-step situation of the renovated sections, repeat steps (2) to (8) to complete the renovation of other sections.
[0072] Line maintenance.
[0073] After all work in the renovation area is completed, the roadbed will be compacted by large machines to ensure that the line geometry meets normal driving requirements.
[0074] The present invention can construct pile foundation and bearing plate structure under the ballast track structure under operating conditions, and adjust the geometric state of the track to achieve thorough treatment of deep deformation of the ballasted track subgrade.
[0075] The above is only a preferred embodiment of the present invention. It should be pointed out that for ordinary technicians in this technical field, several improvements and modifications can be made without departing from the technical principles of the present invention. These improvements and modifications should also be regarded as the protection scope of the present invention.
Claims
1. A method for treating deep deformation of ballasted track subgrade in an operating railway, characterized in that: The method for treating deep deformation of ballasted track subgrade of an operating railway comprises the following steps: S1. Construction preparation steps; S2. I-beam rail fastening step is used to support and limit the track structure, specifically including: In the roadbed excavation section, a plurality of I-beams are respectively installed below the track and between two adjacent sleepers, and a plurality of through holes are opened on the upper surfaces of both ends of the I-beams; Below the two ends of the I-beam, square wood sleepers and sleeper piers are respectively arranged from top to bottom to support the I-beam; The track rails are fixedly connected to the I-beams; S3. Pile foundation construction steps are used to construct pile foundations between the shoulder and the line. The pile foundations are used to support the temporary beam and subsequent bearing plate, including: After the I-beam rail buckling step is completed, the temporary beam pile foundation and the temporary piers between the lines are constructed by manual digging or mechanical drilling; The length of the temporary beam pile foundation needs to penetrate the deep deformation layer to the stable soil layer or rock layer. The diameter of the circular pile or the side length of the square pile of the temporary beam pile foundation section is 1.5m-1.8m, and the distance between adjacent temporary beam pile foundations is 6m-8m; The length of the temporary piers between the lines is 3m-4m, the pile diameter is optimized according to the line spacing, the diameter of the temporary pier cross-section round pile or square pile side length between the lines is 1.5m-1.8m, and the spacing between adjacent temporary piers between the lines is 6m-10m; S4. Steps for erecting temporary beams, specifically including: Temporary beams are respectively erected on both sides of the track, and the temporary beams are erected on the top of the temporary beam pile foundation, and the extension direction of the temporary beam is parallel to the extension direction of the track; A plurality of connecting pieces are arranged on the side of the temporary beam, the plane where the connecting pieces are located is perpendicular to the extension direction of the track, one side of the connecting piece is vertically welded to the side of the temporary beam, the spacing between two adjacent connecting pieces is the same as the spacing between the track sleepers, and the connecting piece is provided with a plurality of through holes at equal intervals from top to bottom; Fixing the two ends of the I-beam to the connecting piece of the corresponding side beam through connecting pieces, thereby fixing the beam and the I-beam; S5. Ballast and roadbed excavation step, used to remove the ballast under the temporary beam and excavate the roadbed; S6. The steps for constructing the bearing plate and longitudinal beams are used to connect the bearing plate and the pile foundation, including: The longitudinal beam is erected on the top of two adjacent piles on the shoulder, and the extension direction of the longitudinal beam is parallel to the extension direction of the track; the longitudinal beams are erected on both sides of the track respectively; The bearing plate is set on the top of the longitudinal beam and located below the track, and a 20cm-40cm empty layer is reserved at the bottom of the bearing plate; S7. Roadbed and ballast backfilling steps; S8. Steps for removing the temporary beam and I-beam; S9. Line maintenance steps.
2. The method for treating deep deformation of ballasted track subgrade in an operating railway according to claim 1, characterized in that: The S1. construction preparation step specifically includes: The length of the section for erecting a single temporary beam and removing the roadbed is divided to determine the specific location of the pile foundation; the section length is 16m or 24m.
3. The method for treating deep deformation of ballasted track subgrade in an operating railway according to claim 1, characterized in that: The connecting member comprises a horizontally arranged base and a vertically arranged connecting plate, which are fixedly connected or integrally formed; The base is provided with a plurality of through holes, which correspond to the positions of the plurality of through holes provided on the upper surface of one end of the I-beam, respectively, so that the base can be fixed on the upper surface of the I-beam by means of bolts and nuts passing through the through holes; The connecting plate is provided with a plurality of through holes corresponding to a part of the plurality of through holes of the connecting sheet, and the connecting plate can be fixedly connected to the connecting sheet by means of bolts and nuts passing through the through holes.
4. The method for treating deep deformation of ballasted track subgrade in an operating railway according to claim 1, characterized in that: The step of removing ballast and roadbed in S5 includes: The ballast and part of the roadbed soil are excavated, and the thickness of the excavated part of the roadbed soil is 2m-3m.
5. The method for treating deep deformation of ballasted track subgrade in an operating railway according to claim 1, characterized in that: The S7. roadbed and ballast backfill specifically includes: After backfilling graded crushed stone on the top of the bearing plate to the original roadbed top surface elevation, backfill the ballast bed.
6. The method for treating deep deformation of ballasted track subgrade in an operating railway according to claim 1, characterized in that: The S9. line maintenance step specifically includes: tamping the ballast bed with a large machine.
Citation Information
Patent Citations
Treatment method for ballastless track roadbed arching
CN108951307A
Ballastless track deformation treatment method
CN112012051A
Deep roadbed replacement structure and method by underground excavation of row piles, and application
CN113605152A
Grouting, rectification and lifting method for transition section between embankment and abutment of rail