Molds for testing melt flow

The mold design with a movable mold core and flow channel conversion module addresses the need for versatile melt fluidity testing by enabling easy cavity selection and interchangeability, improving operational efficiency.

CN115609816BActive Publication Date: 2024-12-03WANHUA CHEM GRP CO LTD
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202211344985.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2022-10-31
Publication Date
2024-12-03
Estimated Expiration
2042-10-31

AI Technical Summary

Technical Problem

Existing melt fluidity testing methods for high-fluidity thermoplastic polymers require replacing the entire movable mold assembly to accommodate different cavity specifications, leading to cumbersome operations and limited universality.

Method used

A mold design featuring a movable mold core with two cavities and a flow channel conversion module, allowing selection and connection of different cavities without replacing the entire mold assembly, facilitated by detachable connections and positioning grooves for easy interchangeability.

Benefits of technology

Enables flexible and efficient melt fluidity testing by allowing the same movable mold core to perform multiple tests without replacing the entire assembly, simplifying operations and enhancing versatility.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN115609816B_ABST
    Figure CN115609816B_ABST
Patent Text Reader

Abstract

The present invention provides a mold for testing melt fluidity, including a fixed mold assembly, a movable mold assembly and a flow channel conversion module. The fixed mold assembly includes a detachably connected fixed mold frame and a fixed mold core, the fixed mold frame is provided with a pouring port, and the fixed mold core is provided with a pouring channel connected to the pouring port; the movable mold assembly includes a detachably connected movable mold frame and a movable mold core, the movable mold frame is detachably connected to the fixed mold frame, and a first cavity and a second cavity are provided on a side surface of the movable mold core facing the fixed mold core; the flow channel conversion module is detachably connected to a side surface of the movable mold core facing the fixed mold core, and the flow channel conversion module includes a bearing plate, a cold material well and a single-sided flow channel connected to the cold material well are provided on the bearing plate, the cold material well is connected to the pouring channel, and the single-sided flow channel is connected to the first cavity or the second cavity. By adopting the present invention, the same movable mold core can be tested for different fluidity, and when replacing the movable mold core, there is no need to replace the entire movable mold assembly, and the operation is simple.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of melt fluidity testing, and in particular to a mold for testing melt fluidity. Background Art

[0002] High-fluidity thermoplastic polymers such as liquid crystal polymers are widely used in devices in the fields of electronics, information and communications. In addition to their excellent mechanical properties (heat resistance, rigidity, etc.), chemical stability, dimensional accuracy, etc., their melt has ultra-high processing fluidity during injection molding, which facilitates the molding of extremely thin parts in components, meeting people's daily needs for thin-walled, miniaturized and lightweight devices in the fields of electronics, information and communications.

[0003] It is essential to evaluate the melt fluidity of high-flow thermoplastic polymers. Currently, the indicators for measuring melt fluidity include apparent viscosity, melt index, flow length ratio, etc. Among them, in the process of testing the melt fluidity using the flow length ratio, a movable mold with a cavity is connected to a fixed mold with a flow channel running through it. The melt is injected into the cavity through the flow channel and extends a certain distance in the cavity. After cooling, a molded body is formed. The extension length of the molded body characterizes the fluidity of the melt. For melts with different fluidities, or the same melt under different injection molding processes, different cavity specifications need to be used. In the prior art, the entire movable mold needs to be replaced to achieve the purpose of replacing different cavities. The operation is cumbersome and the universality of the movable mold is not strong. Summary of the invention

[0004] In view of this, the present invention provides a mold for testing melt fluidity. Two sizes of cavities are provided on the movable mold core, and a flow channel conversion module is installed. According to the test requirements, the single-side flow channel on the flow channel conversion module is selected to be connected to one of the cavities. When the cavities of both sizes do not meet the test requirements, there is no need to replace the entire movable mold assembly. The movable mold core is removed from the movable mold frame and replaced with a new movable mold core.

[0005] The present invention provides a mold for testing melt fluidity, including a fixed mold assembly, a movable mold assembly and a flow channel conversion module. The fixed mold assembly includes a detachably connected fixed mold frame and a fixed mold core, the fixed mold frame is provided with a pouring port, and the fixed mold core is provided with a pouring channel connected to the pouring port; the movable mold assembly includes a detachably connected movable mold frame and a movable mold core, the movable mold frame is detachably connected to the fixed mold frame, and a first cavity and a second cavity are provided on a side surface of the movable mold core facing the fixed mold core; the flow channel conversion module is detachably connected to a side surface of the movable mold core facing the fixed mold core, and the flow channel conversion module includes a bearing plate, a cold material well and a single-sided flow channel connected to the cold material well are provided on the bearing plate, the cold material well is connected to the pouring channel, and the single-sided flow channel is connected to the first cavity or the second cavity.

[0006] Optionally, a receiving groove is provided on a side surface of the movable mold core facing the fixed mold core, the flow channel conversion module is detachably connected to the movable mold core in the receiving groove, and the supporting plate is flush with the movable mold core.

[0007] Optionally, a first accommodating groove is provided on a side surface of the movable mold frame facing the fixed mold frame, and the movable mold core is removably connected to the first accommodating groove.

[0008] Optionally, a first positioning groove is provided on the movable mold core; and a first positioning piece which matches and engages with the first positioning groove is movably connected to the movable mold frame.

[0009] Optionally, a second accommodating groove is provided on a side surface of the fixed mold frame facing the movable mold frame, and the fixed mold core is removably connected to the second accommodating groove.

[0010] Optionally, a second positioning groove is provided on the fixed mold core; and a second positioning piece which matches and engages with the second positioning groove is movably connected to the fixed mold frame.

[0011] Optionally, the movable mold core is provided with a first inlet and a first outlet, and a first medium flow groove connecting the first inlet and the first outlet is opened in the movable mold core; a first medium inlet and a first medium outlet are opened through the movable mold frame; after the movable mold core is connected to the movable mold frame, the first inlet is connected to the first medium inlet, and the first outlet is connected to the first medium outlet.

[0012] Optionally, the fixed mold core is provided with a second inlet and a second outlet, and a second medium flow groove connecting the second inlet and the second outlet is opened in the fixed mold core; a second medium inlet and a second medium outlet are opened through the fixed mold frame; after the fixed mold core is connected to the fixed mold frame, the second inlet is connected to the second medium inlet, and the second outlet is connected to the second medium outlet.

[0013] Optionally, the first cavity includes a first main channel, a first branch channel, a first gate and a first test channel which are connected in sequence; the first main channel is used to connect with the single-sided channel; the cross-sectional area of ​​the first branch channel gradually increases in the direction toward the first gate; the depth of the first gate is less than the depth of the first branch channel.

[0014] Optionally, the first cavity further includes: a first cold material trough, wherein opposite ends of the first cold material trough are respectively connected to the first branch channel and the first gate, and a depth of the first cold material trough is greater than a depth of the first branch channel.

[0015] Compared with the prior art, the above technical solution provided by the present invention has at least the following beneficial effects:

[0016] The mold for testing melt fluidity of the present invention can connect the runner conversion module to the first cavity or the second cavity according to the test requirements, and different fluidity tests can be performed on the same movable mold core. When both cavities on the same movable mold core do not meet the test requirements, there is no need to replace the entire movable mold assembly. The movable mold core can be removed from the movable mold frame and replaced and installed with a new movable mold core. The operation is simple and the versatility is strong. BRIEF DESCRIPTION OF THE DRAWINGS

[0017] Figure 1 A three-dimensional cross-sectional view of a mold for testing melt fluidity according to an embodiment of the present invention;

[0018] Figure 2 for Figure 1 Schematic diagram of a mold used to test melt fluidity;

[0019] Figure 3 for Figure 2 A side view of a mold shown for testing melt fluidity;

[0020] Figure 4 for Figure 1 A schematic diagram of a movable mold core of a mold for testing melt fluidity is shown;

[0021] Figure 5 for Figure 4 A side view of the movable mold core shown;

[0022] Figure 6 for Figure 4 A top view of the movable mold core shown;

[0023] Figure 7 for Figure 1 A schematic diagram of a fixed mold core of a mold for testing melt fluidity is shown;

[0024] Figure 8 for Figure 7 A top view of the fixed mold core shown;

[0025] Fig. 9 for Figure 4 A partial enlarged view of the first cavity of the movable mold core;

[0026] Fig.10 for Fig. 9 A cross-sectional view of the first cavity shown;

[0027] Fig.11 for Fig. 9 A schematic cross-sectional view of a first main flow channel of a first cavity is shown;

[0028] Fig.12 It is a molded body formed after the melt is injected into the first cavity.

[0029] Reference numerals:

[0030] 1: runner conversion module; 11: carrier plate; 12: cold material well; 13: single-side runner; 2: fixed mold frame; 21: pouring gate; 22: second positioning piece; 3: fixed mold core; 31: pouring channel; 32: second positioning groove; 33: second handrail; 4: movable mold frame; 41: first positioning piece; 5: movable mold core; 51: first cavity; 511: first main flow channel; 512: first branch flow channel; 513: first gate; 514: first test flow channel; 515: first cold material trough; 52: second cavity; 53: first positioning groove; 54: first handrail; 55: quick connector; 6: molding body. DETAILED DESCRIPTION

[0031] The embodiments of the present invention will be further described below in conjunction with the accompanying drawings. In the description of the present invention, it should be noted that the orientations or positional relationships indicated by the terms "center", "up", "down", "left", "right", "vertical", "horizontal", "inside", "outside", etc. are based on the orientations or positional relationships shown in the accompanying drawings, and are only simplified descriptions for the convenience of describing the present invention, rather than indicating or implying that the device or component referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only and cannot be understood as indicating or implying relative importance. Among them, the terms "first position" and "second position" are two different positions.

[0032] Figure 1 A three-dimensional cross-sectional view of a mold for testing melt fluidity according to an embodiment of the present invention; Figure 2 for Figure 1 Schematic diagram of a mold used to test melt fluidity; Figure 3 for Figure 2 A side view of a mold shown for testing melt fluidity; Figure 4 for Figure 1 A schematic diagram of a movable mold core of a mold for testing melt fluidity is shown; Figure 5 for Figure 4 A side view of the movable mold core shown; Figure 6 for Figure 4 A top view of the movable mold core shown; Figure 7 for Figure 1 A schematic diagram of a fixed mold core of a mold for testing melt fluidity is shown; Figure 8 for Figure 7 A top view of the fixed mold core shown; Fig. 9 for Figure 4 A partial enlarged view of the first cavity of the movable mold core; Fig.10 for Fig. 9 A cross-sectional view of the first cavity is shown.

[0033] like Figure 1-Figure 10 As shown, the mold for testing melt fluidity includes a fixed mold component, a movable mold component and a flow channel conversion module 1.

[0034] The fixed mold assembly includes a detachably connected fixed mold frame 2 and a fixed mold core 3, wherein the fixed mold frame 2 is provided with a pouring port 21, and the fixed mold core 3 is provided with a pouring channel 31 connected to the pouring port 21. The movable mold assembly includes a detachably connected movable mold frame 4 and a movable mold core 5, wherein the movable mold frame 4 is detachably connected to the fixed mold frame 2, and the movable mold core 5 is provided with a first cavity 51 and a second cavity 52 on a side surface facing the fixed mold core 3. The runner conversion module 1 is detachably connected to a side surface of the movable mold core 5 facing the fixed mold core 3, and the runner conversion module 1 includes a bearing plate 11, wherein a cold material well 12 and a single-side runner 13 connected to the cold material well 12 are provided on the bearing plate 11, wherein the cold material well 12 is connected to the pouring channel 31, and the single-side runner 13 is connected to the first cavity 51 or the second cavity 52.

[0035] When in use, according to the requirements of different melts to be tested for fluidity, the first cavity 51 or the second cavity 52 is selected for fluidity test, and the runner conversion module 1 is connected to the movable mold core 5, so that the single-sided runner 13 opened on the supporting plate 11 is connected to the selected first cavity 51 or the second cavity 52, and the fixed mold frame 2 and the movable mold frame 4 are connected. After the connection is completed, the fixed mold core 3 is abutted against the movable mold core 5 and the runner conversion module 1, and the fixed mold core 3 covers the first cavity 51, the second cavity 52, the cold material well 12 and the single-sided runner 13. An external injection molding machine is used to inject the test melt through the pouring port 21 penetrating the fixed mold frame 2 and the pouring channel 31 penetrating the fixed mold core 3. The melt flows through the pouring channel 31 to the cold material well 12 connected thereto, and then overflows through the cold material well 12 into the connected single-side flow channel 13, and finally enters the first cavity 51 or the second cavity 52 connected to the single-side flow channel 13, and flows a certain distance in the first cavity 51 or the second cavity 52. ​​After the melt is cooled and solidified, the fixed mold frame 2 and the movable mold frame 4 are disassembled, and the fixed mold core 3 is separated from the movable mold core 5. After the melt solidifies, a molded body is formed. The molded body is taken out, and the length of its extension indicates the fluidity of the corresponding melt. When the melt for testing fluidity is replaced or the injection molding process is changed, and the first cavity 51 (second cavity 52) connected to the runner conversion module 1 does not meet the test requirements, the runner conversion module 1 is removed from the movable mold core 5, and the runner conversion module 1 is rotated to connect the single-sided runner 13 with the second cavity 52 (first cavity 51), and then it is re-fixed to the movable mold core 5. When both the first cavity 51 and the second cavity 52 do not meet the test requirements, the movable mold core 5 is removed from the movable mold frame 4, and other movable mold cores that meet the test requirements are selected and reinstalled to the movable mold frame 4.

[0036] The mold of the present invention is used to test the fluidity of the melt. According to the test requirements, the flow channel conversion module 1 can be connected to the first cavity 51 or the second cavity 52, and the same movable mold core 5 can be used to perform different fluidity tests. When both cavities on the same movable mold core 5 do not meet the test requirements, there is no need to replace the entire movable mold assembly. The movable mold core 5 can be removed from the movable mold frame 4 and replaced and installed with a new movable mold core 5. The operation is simple and the versatility is strong.

[0037] In this embodiment, the movable mold frame 4 is provided with a plurality of mounting holes in the circumferential direction, and a plurality of mounting parts are fixed at corresponding positions of the fixed mold frame 2. The plurality of mounting parts are inserted into the corresponding plurality of mounting holes one by one to realize the connection between the movable mold frame 4 and the fixed mold frame 2. Figure 1 , Figure 3 As shown, the pouring port 21 runs through the center of the fixed mold frame 2 and is in the shape of a funnel. Figure 1 , Figure 7 As shown, the fixed mold core 3 is a rectangular parallelepiped as a whole, the pouring channel 31 runs through the center of the fixed mold core 3 and is connected to the pouring port 21. The cross section of the pouring channel 31 is circular, and the diameter gradually increases in the direction toward the movable mold core 5. Figure 4 As shown, the movable mold core 5 is a rectangular parallelepiped as a whole, the carrier plate 11 of the flow channel conversion module 1 is a rectangular whole, installed in the middle position of the movable mold core 5, and the extension direction is along the width direction of the movable mold core 5. The center of the carrier plate 1 is provided with the cold material well 12, and the single-sided flow channel 13 connected to the cold material well 12 is provided perpendicular to the extension direction of the carrier plate 11, and the single-sided flow channel 13 extends to the end of the carrier plate 11, and the depth of the cold material well 12 is greater than that of the single-sided flow channel 13. The depth of the side flow channel 13 allows the melt with a lowered temperature at the front end to enter the cold material well 12. After the cold material well 12 is filled, the subsequent melt with a higher temperature overflows and is injected into the single-side flow channel 13. The upper and lower ends of the carrier plate 11 symmetrically relative to the cold material well 12 are respectively penetrated with threaded holes, and two bolts are placed in the threaded holes. The corresponding positions on the movable mold core 5 are also provided with threaded holes, so that the bolts are threadedly connected with the threaded holes, thereby realizing the detachable connection between the flow channel conversion module 1 and the movable mold core 5. Figure 4 As shown, the movable mold core 5 is provided with the first cavity 51 and the second cavity 52 on the left and right sides symmetrically about the flow channel conversion module 1, and both extend along the length direction of the movable mold core 5. Figure 4 The one-side flow channel 13 is connected to the first cavity 51. When it is necessary to change from being connected to the first cavity 51 to being connected to the second cavity 52, the bolts on the carrier plate 11 are removed, and the flow channel conversion module 1 is rotated 180 degrees to make Figure 4The single-sided flow channel 13 faces the right side and is connected to the second cavity 52 on the right side, and then the bolts are tightened to reconnect the flow channel conversion module 1 and the movable mold core 5. In this embodiment, the projections of the first cavity 51 and the second cavity 52 on the movable mold core 5 are mirror-symmetrical about the flow channel conversion module 1, but the depths of the first cavity 51 and the second cavity 52 are different, and the depth of the first cavity 51 is greater than the depth of the second cavity 52. ​​According to actual application conditions, any detachable connection method can be adopted between the fixed mold frame 2 and the fixed mold core 3, between the movable mold frame 4 and the movable mold core 5, and between the flow channel conversion module 1 and the movable mold core 5, the projections of the first cavity 51 and the second cavity 52 can be the same or different, and the shape and size of the flow channel conversion module 1 can be adjusted.

[0038] Optionally, a receiving groove is provided on one side of the movable mold core 5 facing the fixed mold core 3, the flow channel conversion module 1 is detachably connected to the movable mold core 5 in the receiving groove, and the carrier plate 11 is flush with the movable mold core 5. In this arrangement, the side surface of the fixed mold core 3 facing the movable mold core 5 can remain flat, and the two are fitted or abutted.

[0039] In this embodiment, a receiving groove matching the shape and size of the supporting plate 11 is opened on the surface of the movable mold core 5, and the flow channel conversion module 1 is bolted to the movable mold core 5 in the receiving groove. After installation, the supporting plate 11 is flush with the movable mold core 5, and the height of the bolt is lower than the height of the supporting plate 11, which does not affect the abutment between the fixed mold core 3 and the movable mold core 5.

[0040] Optionally, a first receiving groove is provided on a side surface of the movable mold frame 4 facing the fixed mold frame 2, and the movable mold core 5 is removably connected to the first receiving groove. This arrangement simplifies the detachable connection between the movable mold frame 4 and the movable mold core 5, and improves the convenience of operation.

[0041] In this embodiment, if Figure 1 , Figure 2As shown, the movable mold frame 4 is provided with the first receiving groove in the middle position of the surface of one side facing the fixed mold frame 2, and the movable mold core 5 can be pulled and moved along the first receiving groove to push into or pull out of the first receiving groove, so as to realize the detachable connection between the movable mold core 5 and the movable mold frame 4. In order to facilitate the pulling and pulling of the movable mold core 5, a first handrail 54 is fixed on the outer wall of the movable mold core 5 on one side of the movable mold frame 4. In order to prevent the movable mold core 5 from slipping out of the first receiving groove, a limiting baffle can be installed on the movable mold frame 4, so that the shape of the movable mold core 5 matches the concave and convex of the limiting baffle, which can not only ensure the limiting effect on the movable mold core 5, so that the movable mold core 5 will not slip out of the first receiving groove, but also do not affect the connection between the movable mold frame 4 and the fixed mold frame 2, and the movable mold core 5 and the fixed mold core 3 are abutted.

[0042] Optionally, the movable mold core 5 is provided with a first positioning groove 53; the movable mold frame 4 is movably connected with a first positioning member 41 that matches and engages with the first positioning groove 53. In this arrangement, when the movable mold core 5 is inserted into the first receiving groove provided on the movable mold frame 4, the first positioning member 41 is inserted into the first positioning groove 53, so that the movable mold core 5 and the movable mold frame 4 are further positioned and connected.

[0043] In this embodiment, if Figure 4 As shown, the top center of the movable mold core 5 is provided with the first positioning groove 53. Figure 1 As shown, the first positioning member 41 penetrates the movable mold frame 4 to the first receiving groove for inserting the movable mold core 5, and is movably connected to the movable mold frame 4. When the movable mold core 5 needs to be inserted into the first receiving groove, the first positioning member 41 is pulled outward so that it does not hinder the insertion of the movable mold core 5. After the movable mold core 5 is inserted into the first receiving groove, the first positioning groove 53 corresponds to the position of the first positioning member 41. The first positioning member 41 is pushed inward to engage with the first positioning groove 53, and the first positioning member 41 is fixed to the movable mold frame 4, such as by bolting. According to the actual application, the opening position of the first positioning groove 53 on the movable mold core 5 can be adjusted, and the first positioning member 41 is adjusted accordingly.

[0044] Optionally, a second receiving groove is provided on a side surface of the fixed mold frame 2 facing the movable mold frame 4, and the fixed mold core 3 is removably connected to the second receiving groove. This arrangement simplifies the detachable connection between the fixed mold frame 2 and the fixed mold core 3, and improves the convenience of operation.

[0045] In this embodiment, if Figure 1 , Figure 2As shown, the fixed mold frame 2 is provided with the second receiving groove in the middle position of the surface of one side facing the movable mold frame 4, and the fixed mold core 3 can be pulled and moved along the second receiving groove to be pushed into or pulled out of the second receiving groove, so as to realize the detachable connection between the fixed mold core 3 and the fixed mold frame 2. In order to facilitate the pulling and pulling of the fixed mold core 3, a second handrail 33 is fixed on the outer wall of one side of the fixed mold core 3 exposed from the fixed mold frame 2. In order to prevent the fixed mold core 3 from slipping out of the second receiving groove, a limiting baffle can be installed on the fixed mold frame 2, so that the shape of the fixed mold core 3 matches the concave-convex of the limiting baffle, which not only ensures that the fixed mold core 3 is limited so that the fixed mold core 3 will not slip out of the second receiving groove, but also does not affect the contact between the fixed mold core 3 and the movable mold core 5 after the fixed mold frame 2 is connected with the movable mold frame 4.

[0046] Optionally, a second positioning groove 32 is provided on the fixed mold core 3; and a second positioning member 22 that matches and engages with the second positioning groove 32 is movably connected to the fixed mold frame 2. In this arrangement, when the fixed mold core 3 is inserted into the second receiving groove provided on the fixed mold frame 2, the second positioning member 22 is inserted into the second positioning groove 32, so that the fixed mold core 3 and the fixed mold frame 2 are further positioned and connected.

[0047] In this embodiment, if Figure 7 As shown, the top center of the fixed mold core 3 is provided with the second positioning groove 32. Figure 1 As shown, the second positioning member 22 penetrates the fixed mold frame 2 to the second receiving groove for inserting the fixed mold core 3, and is movably connected to the fixed mold frame 2. When the fixed mold core 3 needs to be inserted into the second receiving groove, the second positioning member 22 is pulled outward so that it does not hinder the insertion of the fixed mold core 3. After the fixed mold core 3 is inserted into the second receiving groove, the second positioning groove 32 corresponds to the position of the second positioning member 22. The second positioning member 22 is pushed inward to engage with the second positioning groove 32, and the second positioning member 22 is fixed to the fixed mold frame 2, such as by bolting. According to actual application conditions, the opening position of the second positioning groove 32 on the fixed mold core 3 can be adjusted, and the second positioning member 22 is adjusted accordingly.

[0048] Optionally, the movable mold core 5 is provided with a first inlet and a first outlet, and a first medium flow groove connecting the first inlet and the first outlet is provided in the movable mold core 5; a first medium inlet and a first medium outlet are provided through the movable mold frame 4; after the movable mold core 5 is connected to the movable mold frame 4, the first inlet is connected to the first medium inlet, and the first outlet is connected to the first medium outlet. In this arrangement, after the movable mold core 5 is connected to the movable mold frame 4, hot medium can be injected into the first medium flow groove through the first medium inlet and the first inlet, and after heat exchange with the movable mold core 5, it is discharged through the first outlet and the first medium outlet to adjust the temperature of the movable mold core 5.

[0049] In this embodiment, the movable mold frame 4 is provided with the first receiving groove, the movable mold core 5 is removably connected to the first receiving groove, the first inlet and the first outlet are both provided at one end of the movable mold core 5 inserted into the first receiving groove, and the first medium inlet and the first medium outlet are provided at corresponding positions of the movable mold frame 4. After the movable mold core 5 is inserted into the first receiving groove to a set position, the first inlet is communicated with the first medium inlet, and the first outlet is communicated with the first medium outlet. In this embodiment, Figure 4 As shown, quick connectors 55 are installed at the first inlet and the first outlet, and connecting pieces matching and connecting the quick connectors 55 are installed at the first medium inlet and the first medium outlet. After the movable mold core 5 is inserted into the first accommodating groove to the set position, the quick connector 55 at the first inlet is connected to the connecting piece at the first medium inlet, and the quick connector 55 at the first outlet is connected to the connecting piece at the first medium outlet. After connecting to the external heat medium, the heat medium enters from the first medium inlet and the first inlet, and is discharged from the first outlet and the first medium outlet after heat exchange in the first medium flow groove. The cycle is repeated to adjust the temperature of the movable mold core 5 so that the melt fluidity test can be carried out normally. According to the actual application situation, any connection method can be adopted between the first inlet and the first medium inlet, and between the first outlet and the first medium outlet, as long as the movable mold core 5 is connected to the movable mold frame 4 to facilitate their connection and enable the heat medium to circulate normally.

[0050] Optionally, the fixed mold core 3 is provided with a second inlet and a second outlet, and a second medium flow groove connecting the second inlet and the second outlet is provided in the fixed mold core 3; a second medium inlet and a second medium outlet are provided through the fixed mold frame 2; after the fixed mold core 3 is connected to the fixed mold frame 2, the second inlet is connected to the second medium inlet, and the second outlet is connected to the second medium outlet. In this arrangement, after the fixed mold core 3 is connected to the fixed mold frame 2, hot medium can be injected into the second medium flow groove through the second medium inlet and the second inlet, and after heat exchange with the fixed mold core 3, it is discharged through the second outlet and the second medium outlet to adjust the temperature of the fixed mold core 3.

[0051] In this embodiment, the fixed mold frame 2 is provided with the second receiving groove, the fixed mold core 3 is removably connected to the second receiving groove, the second inlet and the second outlet are both provided at one end of the fixed mold core 3 inserted into the second receiving groove, and the corresponding position of the fixed mold frame 2 is provided with the second medium inlet and the second medium outlet. After the fixed mold core 3 is inserted into the second receiving groove to the set position, the second inlet is connected to the second medium inlet, and the second outlet is connected to the second medium outlet. In this embodiment, quick connectors are installed at the second inlet and the second outlet, and connecting pieces matching the quick connectors are installed at the second medium inlet and the second medium outlet. After the fixed mold core 3 is inserted into the second receiving groove to the set position, the quick connector at the second inlet is connected to the connecting piece at the second medium inlet, and the quick connector at the second outlet is connected to the connecting piece at the second medium outlet. After connecting with the external heat medium, the heat medium enters from the second medium inlet and the second inlet, and is discharged from the second outlet and the second medium outlet after heat exchange in the second medium flow groove. The cycle is repeated to adjust the temperature of the fixed mold core 3 so that the melt flowability test can be carried out normally. According to the actual application, any connection method can be adopted between the second inlet and the second medium inlet, and between the second outlet and the second medium outlet, as long as the fixed mold core 3 is connected to the fixed mold frame 2 to facilitate their connection and enable the heat medium to circulate normally.

[0052] Fig. 9 for Figure 4 A partial enlarged view of the first cavity of the movable mold core; Fig.10 for Fig. 9 A cross-sectional view of the first cavity shown; Fig.11 for Fig. 9 FIG. 4 is a schematic cross-sectional view of the first main flow channel of the first cavity. Figure 9-11As shown, optionally, the first cavity 51 includes a first main channel 511, a first branch channel 512, a first gate 513 and a first test channel 514 which are connected in sequence; the first main channel 511 is used to communicate with the single-sided channel 13; the cross-sectional area of ​​the first branch channel 512 gradually increases in the direction toward the first gate 513; the depth of the first gate 513 is less than the depth of the first branch channel 512.

[0053] In this embodiment, if Fig.11 As shown, the cross section of the first main channel 511 is divided into two parts, the upper part is an inverted trapezoid with a top width of 5 mm, and the lower part is a semicircle, and the connecting parts are tangent, so that the injected melt flows better in the first main channel 511. Fig. 9 , Fig.10 As shown, the cross section of the first runner 512 is a trapezoid, and its width gradually increases in the direction toward the first gate 513, and its depth also gradually increases in the direction toward the first gate 513, so that the melt can be fully injected, wherein the maximum width is 30 mm, Fig.10 The rightmost depth of the first branch channel 512 is 2mm, the leftmost depth is 4mm, and the first main channel 511 and the first branch channel 512 have a smooth transition. The first test channel 514 is a rectangular parallelepiped groove with a depth range of 0.01-50mm, a width range of 1-50mm, and a length range of 1-300mm. In this embodiment, the first test channel 514 is preferably 0.8mm deep, 200mm long, and 20mm wide. The first gate 513 has a depth of 50-100% of the depth of the first test channel 514, a width of 20%-100% of the width of the first test channel 514, and a length range of 0.1-20mm. In this embodiment, the first gate 513 is preferably equal to the depth of the first test channel 514, the width is 80% of the width of the first test channel 514, and the length is 6mm.

[0054] like Figure 4 As shown, in this embodiment, the projections of the second cavity 52 and the first cavity 51 on the movable mold core 5 are mirror-symmetrical about the runner conversion module 1, but the depth is different. Similarly, the second cavity 52 includes a second main runner, a second branch runner, a second gate and a second test runner that are connected in sequence, and the second main runner has the same specifications as the first main runner 511, the second branch runner has the same specifications as the first branch runner 512, the second gate has the same specifications as the first gate 513, and the length and width of the second test runner are the same as those of the first test runner, but the depth is less than that of the first test runner, which is set to 0.2 mm.

[0055] According to actual application, the width of the second test flow channel may also be different from that of the first test flow channel 514 , and the length of the second test flow channel may be equal to or greater than that of the first test flow channel 514 .

[0056] Optionally, the first cavity 52 further includes a first cold material groove 515, the opposite ends of which are connected to the first branch channel 512 and the first gate 513, respectively, and the depth of the first cold material groove 515 is greater than the depth of the first branch channel 512. In this arrangement, the cooling melt entering the front end first enters the first cold material groove 515, so that the subsequent high-temperature melt overflows from the first cold material groove 515 and then enters the first test flow channel 514, thereby ensuring the accuracy of the melt fluidity test result.

[0057] In this embodiment, if Fig. 9 , Fig.10 As shown, the first cold material groove 515 is a rectangular parallelepiped, and its width is greater than the width of the first gate 513, and is the same as the width of the leftmost end of the first branch channel 512, which is set to 30mm. The depth of the first cold material groove 515 ranges from 1-50mm, and the length ranges from 1-100mm. In this embodiment, the depth is preferably 10mm, and the length is 10mm. The first main channel 511, the first branch channel 512, the first cold material groove 515, the first gate 513 and the first test channel 514 are all in a straight line. The melt flow direction does not change during the injection molding process, and its fluidity will not be affected.

[0058] Similarly, a second cold material trough is also connected between the second branch channel and the second gate of the second cavity 52 , and the specifications of the second cold material trough are the same as those of the first cold material trough 515 .

[0059] Fig.12 The molded body is formed after the melt is injected into the first cavity, such as Fig.12 As shown, the shape of the molded body 6 is the same as that of the first cavity 51 , and the shapes of the melt cooled in the pouring channel 31 , the cold material well 12 and the single-sided runner 13 are retained.

[0060] The following further describes the use of the mold for testing melt fluidity:

[0061] When in use, according to the requirements of different melts to be tested for fluidity, the first cavity 51 or the second cavity 52 is selected for fluidity test, and the runner conversion module 1 is connected to the movable mold core 5, so that the single-sided runner 13 opened on the supporting plate 11 is connected to the selected first cavity 51 or the second cavity 52, and the fixed mold frame 2 and the movable mold frame 4 are connected. After the connection is completed, the fixed mold core 3 is abutted against the movable mold core 5 and the runner conversion module 1, and the fixed mold core 3 covers the first cavity 51, the second cavity 52, the cold material well 12 and the single-sided runner 13. The test melt is injected through the pouring port 21 penetrating the fixed mold frame 2 and the pouring channel 31 penetrating the fixed mold core 3 by an external injection molding machine. The melt flows through the pouring channel 31 to the cold material well 12 connected thereto, and then overflows through the cold material well 12 into the connected single-side flow channel 13, and finally enters the first cavity 51 or the second cavity 52 connected to the single-side flow channel 13, and flows a certain distance in the first cavity 51 or the second cavity 52. ​​During the melt injection process, hot medium is injected into the first medium flow groove in the movable mold core 5 through the first medium inlet of the movable mold frame 4 and the first inlet of the movable mold core 5, and hot medium is injected into the second medium flow groove in the fixed mold core 3 through the second medium inlet of the fixed mold frame 2 and the second inlet of the fixed mold core 3, so that the movable mold core 5 and the fixed mold core 3 are kept at the set temperature. After the melt is cooled and solidified, the fixed mold frame 2 and the movable mold frame 4 are disassembled to separate the fixed mold core 3 from the movable mold core 5. After the melt solidifies, a molded body 6 is formed. The molded body 6 is taken out, and the length of the extension of the first test flow channel 514 or the second test flow channel portion thereof corresponds to the fluidity of the corresponding melt. When the melt for testing fluidity is replaced or the injection molding process is changed, and the first cavity 51 (second cavity 52) connected to the flow channel conversion module 1 does not meet the test requirements, the flow channel conversion module 1 is disassembled from the movable mold core 5, and the flow channel conversion module 1 is rotated to connect the single-side flow channel 13 with the second cavity 52 (first cavity 51), and then it is re-fixed to the movable mold core 5. When both the first cavity 51 and the second cavity 52 do not meet the test requirements, the movable mold core 5 is disassembled from the movable mold frame 4, and other movable mold cores that meet the test requirements are selected and reinstalled to the movable mold frame 4.

[0062] The mold of the present invention is used to test the fluidity of the melt. According to the test requirements, the flow channel conversion module 1 can be connected to the first cavity 51 or the second cavity 52, and the same movable mold core 5 can be used to perform different fluidity tests. When both cavities on the same movable mold core 5 do not meet the test requirements, there is no need to replace the entire movable mold assembly. The movable mold core 5 can be removed from the movable mold frame 4 and replaced and installed with a new movable mold core 5. The operation is simple and the versatility is strong.

[0063] The following are some related experiments conducted using the mold of the present invention for testing melt fluidity:

[0064] The specifications of the cavity are shown in Table 1:

[0065]

[0066] Table 1 Relevant dimensions of the cavity

[0067] Example 1

[0068] The injection molding machine selected in this embodiment is Haitian HZ1200 / 210H, and the screw diameter is 26mm. The selected materials to be tested are LCP pure resin T3400 of Thales (Nantong) Pharmaceutical Chemical Co., Ltd., Celanese 30% short glass fiber reinforced products E130i and zinite-6130L. The above three products are tested for viscosity at different shear rates using a capillary rheometer. Among them, the capillary rheometer uses the German Got tfert-RG20. The test temperature is 350°C, the capillary diameter is 1.0mm, and the aspect ratio is 40.

[0069] The viscosities at different shear rates are shown in Table 2.

[0070]

[0071] Table 2 Viscosity at different shear rates

[0072] This embodiment uses the mold to experimentally test the fluidity of different high-flow thermoplastic polymer melts under the same injection molding process under the actual production injection molding process of downstream customers, and also studies the melt flow under different injection molding processes and the sensitivity of the melt fluidity to the molding process.

[0073] Example 2

[0074] The experimental purpose of this embodiment is to test the fluidity of different high-flow thermoplastic polymer melts under the same injection molding process. The specific injection molding process is shown in Table 3.

[0075]

[0076] Table 3 Injection molding process of Example 2

[0077] This embodiment conducted an injection molding experiment under the Experiment 1 scheme. The experimental results showed that when the three high-flow thermoplastic polymer melts were injected into the first cavity 51, they were all completely filled and reached 200 mm, so it was impossible to compare. Therefore, the flow channel conversion module was rotated 180 degrees, the second cavity 52 was selected, and the experiment was conducted according to the Experiment 2 scheme. The experimental results are shown in Table 4:

[0078]

[0079] Table 4 Experiment 2 test results

[0080] Example 3

[0081] The purpose of the experiment in this example is to use the mold to study the melt flow and melt fluidity sensitivity to the molding process under different injection molding processes. The high-flow thermoplastic polymer melt selected in this example is Celanese E130i, and the molding process is shown in Table 5:

[0082]

[0083] Table 5 Injection molding process of Example 3

[0084] The specific experimental results are shown in Table 6:

[0085]

[0086]

[0087] Table 6 Experimental results of Example 3

[0088] From the above experiments, it can be seen that when preparing the 0.2mm thick molded body under different injection molding processes, the injection pressure, holding pressure and barrel temperature have the greatest influence on the fluidity of E130i; when the holding time exceeds 8s, the length of the molded body no longer increases and the gate is closed; the length of the molded body under different injection molding speeds is not much different, which shows that the injection molding speed has little effect on the fluidity.

[0089] Finally, it should be noted that the above embodiments are only used to illustrate the technical solutions of the present invention, rather than to limit it. Although the present invention has been described in detail with reference to the aforementioned embodiments, those skilled in the art should understand that they can still modify the technical solutions described in the aforementioned embodiments, or make equivalent replacements for some of the technical features therein. However, these modifications or replacements do not cause the essence of the corresponding technical solutions to deviate from the scope of the technical solutions of the embodiments of the present invention.

Claims

1. A mold for testing melt fluidity, characterized in that: Including fixed mold assembly, movable mold assembly and runner conversion module: The fixed mold assembly comprises a detachably connected fixed mold frame and a fixed mold core, the fixed mold frame is provided with a pouring port, and the fixed mold core is provided with a pouring channel communicating with the pouring port; The movable mold assembly comprises a movable mold frame and a movable mold core which are detachably connected, the movable mold frame is detachably connected to the fixed mold frame, and a first mold cavity and a second mold cavity are formed on a surface of the movable mold core facing the fixed mold core; The runner conversion module is detachably connected to a surface of the movable mold core on one side facing the fixed mold core, and the runner conversion module includes a carrier plate, a cold material well and a single-sided runner connected to the cold material well are provided on the carrier plate, the cold material well is connected to the pouring channel, and the single-sided runner is connected to the first cavity or the second cavity.

2. The mold for testing melt fluidity according to claim 1, characterized in that: A receiving groove is provided on a side surface of the movable mold core facing the fixed mold core, the flow channel conversion module is detachably connected to the movable mold core in the receiving groove, and the carrying plate is flush with the movable mold core.

3. The mold for testing melt fluidity according to claim 1 or 2, characterized in that: A first accommodating groove is provided on a side surface of the movable mold frame facing the fixed mold frame, and the movable mold core is removably connected to the first accommodating groove.

4. The mold for testing melt fluidity according to claim 3, characterized in that: The movable mold core is provided with a first positioning groove; The movable mold frame is movably connected with a first positioning piece which is matched and clamped with the first positioning groove.

5. The mold for testing melt fluidity according to claim 1 or 2, characterized in that: A second accommodating groove is provided on a side surface of the fixed mold frame facing the movable mold frame, and the fixed mold core is removably connected to the second accommodating groove.

6. The mold for testing melt fluidity according to claim 5, characterized in that: A second positioning groove is provided on the fixed mold core; The fixed mold frame is movably connected with a second positioning piece which is matched and clamped with the second positioning groove.

7. The mold for testing melt fluidity according to claim 1 or 2, characterized in that: The movable mold core is provided with a first inlet and a first outlet, and a first medium flow groove connecting the first inlet and the first outlet is opened in the movable mold core; The movable mold frame is provided with a first medium inlet and a first medium outlet; After the movable mold core is connected to the movable mold frame, the first inlet is communicated with the first medium inlet, and the first outlet is communicated with the first medium outlet.

8. The mold for testing melt fluidity according to claim 1 or 2, characterized in that: The fixed mold core is provided with a second inlet and a second outlet, and a second medium flow groove connecting the second inlet and the second outlet is opened in the fixed mold core; The fixed mold frame is provided with a second medium inlet and a second medium outlet; After the fixed mold core is connected to the fixed mold frame, the second inlet is communicated with the second medium inlet, and the second outlet is communicated with the second medium outlet.

9. The mold for testing melt fluidity according to claim 1 or 2, characterized in that: The first cavity comprises a first main flow channel, a first branch flow channel, a first gate and a first test flow channel which are connected in sequence; The first main flow channel is used to communicate with the single-side flow channel; The cross-sectional area of ​​the first runner gradually increases in a direction toward the first gate; The depth of the first gate is less than the depth of the first runner.

10. The mold for testing melt fluidity according to claim 9, characterized in that: The first cavity further comprises: A first cold material trough, wherein two opposite ends of the first cold material trough are respectively connected to the first branch channel and the first gate, and the depth of the first cold material trough is greater than the depth of the first branch channel.