Bamboo-joint vacuum preloaded drainage board and construction method

By using bamboo-type drainage boards in vacuum preloading technology, combined with the staggered or surrounding structure of horizontal drainage boards and vertical drainage pipes, the problem of vacuum attenuation caused by blockage of drainage boards in vacuum preloading is solved, and the foundation is significantly improved. The reinforcement effect achieves better drainage consolidation effect.

CN116043816BActive Publication Date: 2024-10-29TIANJIN UNIV
View PDF 2 Cites 0 Cited by

Patent Information

Application Number
CN202310030358.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-01-10
Publication Date
2024-10-29
Estimated Expiration
2043-01-10

AI Technical Summary

Technical Problem

When vacuum preloading is used to treat ultra-soft soil foundations, conventional drainage slabs are prone to siltation, which causes vacuum attenuation and affects the reinforcement effect. Existing technology has not yet effectively solved the problem of vacuum attenuation caused by horizontal drainage and siltation.

Method used

Bamboo-type drainage boards are used to connect vertical drainage pipes through horizontal drainage boards to form a staggered or surrounding structure. They are fixed with hand joints and connecting nuts to simplify installation, overcome blockage problems, and achieve effective horizontal drainage and vacuum. degree transfer.

Benefits of technology

It significantly improves the reinforcement effect, enhances the drainage consolidation effect, solves the problem of vacuum degree attenuation, achieves better foundation reinforcement effect, and the device is simple and easy to use.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116043816B_ABST
    Figure CN116043816B_ABST
Patent Text Reader

Abstract

The present invention relates to a bamboo-joint drain board, comprising a drain pipe, a drain board single board, a hand-shaped joint and a connecting nut. Holes matching the connecting nut are provided at different positions on the side of the drain pipe, and the drain board single board is fixedly connected to the drain pipe through the hand-shaped joint and the connecting nut; the connecting nut is hollow and connected to one end of the hand-shaped joint. The present invention also relates to a construction accessory for the bamboo-joint drain board, comprising a casing and a casing base, and the casing can be detachably connected to the casing base. The present invention also provides a construction method thereof.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a novel bamboo-joint vacuum pre-pressed drainage board, which is used for treating a deep and ultra-soft soil foundation with a water content exceeding 75%. Background Art

[0002] With the development of economy, the contradiction of land shortage for urban infrastructure construction in coastal areas has become increasingly prominent. Therefore, a wave of land reclamation has been set off in major cities. The dredged soil formed by channel dredging is often used as the foundation for land reclamation. The treatment and disposal of dredged silt from rivers, lakes and seas has become the main bottleneck restricting my country's ecological construction and sustainable economic development. Therefore, large-scale silt treatment projects have been carried out one after another, and the vacuum preloading method, as a relatively mature reinforcement method, is widely used in the reinforcement of ultra-soft soil foundations with a water content of more than 75%.

[0003] Kjellman et al. first proposed the vacuum preloading method to solve the reinforcement problem of ultra-soft soil foundation. The vacuum preloading soft soil foundation treatment technology was introduced into my country in the 1980s. After continuous improvement and innovation, vacuum preloading technology has been widely used in the field of soft soil foundation treatment. In engineering practice, common vacuum preloading technologies include: direct discharge vacuum preloading, vacuum preloading combined with pile loading preloading, vacuum preloading combined with electroosmosis, temperature vacuum preloading, double-layer filter tube sandless cushion vacuum preloading, deep gas pressure splitting vacuum preloading and gas injection boosting vacuum preloading technology.

[0004] The essence of vacuum preloading treatment of soft soil foundation is the consolidation and drainage process of soil. The mechanism that causes the consolidation of soft soil foundation is divided into two parts: one is the vertical pressure difference between vacuum load and soil; the other is the horizontal pressure difference between vertical drainage board and surrounding soil due to vacuum pressure.

[0005] When conventional vacuum preloading is used to treat soft foundations, soil particles gather on the outside of the drainage board filter membrane to form a relatively dense siltation layer, which makes it difficult for the vacuum negative pressure to be transmitted to the soil outside the siltation layer, and it is difficult for water in the soil to pass through the siltation layer into the drainage board for discharge, forming a "grape bunch"-shaped soil column around the drainage board.

[0006] The improved vacuum preloading method mainly uses the drainage board as a vertical drainage system. Although it can enhance the reinforcement effect of soft foundation to some extent, it has not yet considered the influence of vacuum attenuation caused by horizontal drainage and drainage board clogging on the foundation reinforcement effect. At present, the inventor has proved that horizontal drainage can improve the reinforcement effect by 10-20% compared with vertical drainage. Summary of the invention

[0007] In view of the above problems, the purpose of the present invention is to overcome the shortcomings of the prior art and the lack of devices, and to provide a new type of bamboo-jointed vacuum preloaded drainage board in combination with the specific requirements of on-site construction. The vertical drainage pipe is connected by a horizontal drainage board, which is simple to manufacture but highly practical. It can solve the horizontal drainage during on-site construction and effectively overcome the vacuum attenuation problem caused by the clogging of the drainage board, and achieve a good drainage consolidation effect. To achieve the above purpose, the present invention adopts the following technical solutions:

[0008] A bamboo-joint drain board comprises a drain pipe 6, a drain board single plate 7, a hand-shaped joint 8 and a connecting nut 9. Holes matching the connecting nut 9 are opened at different positions on the side of the drain pipe 6. The drain board single plate 7 is fixedly connected to the drain pipe 6 through the hand-shaped joint 8 and the connecting nut 9; the connecting nut 9 is hollow and connected to one end of the hand-shaped joint 8.

[0009] Furthermore, the drain board sheets are arranged in pairs on the sides of the drain pipe, and each pair of drain board sheets are arranged on opposite sides of the drain pipe.

[0010] Furthermore, the drainage board sheets are arranged in a staggered manner on the side of the drainage pipe.

[0011] Furthermore, the drain board sheets are arranged on different planes around the drain board tubes.

[0012] The invention provides a construction accessory for the bamboo-joint type drainage board, comprising a casing and a casing base, and the casing can be detachably connected to the casing base.

[0013] Furthermore, the casing base is conical, and its height is greater than the height of the drainage pipe.

[0014] Furthermore, a base drainage pipe connection interface is provided on the casing base.

[0015] The construction method of the bamboo-joint type drainage board of the present invention comprises the following steps:

[0016] (1) manufacturing a construction kit, including a casing and a casing base, wherein the casing can be detachably connected to the casing base;

[0017] (2) Bend each drain board, use a casing to cover the outside of the bamboo-shaped drain board, and install the casing base so that the casing base and the casing are connected;

[0018] (3) Pressing the casing containing the bamboo drainage board into the super soft soil;

[0019] (4) After the bamboo-jointed drainage board is pressed into the predetermined position, the casing is removed;

[0020] (5) Connect the upper part of the drainage board pipe to the main pipeline to form a vacuum radiation drainage system.

[0021] The present invention has considerable applicable value, and its popularization and use can generate great social value, and also provides a new type of drainage board device for construction and scientific research institutes to study vacuum preloading. The present invention has the following advantages:

[0022] (1) The new bamboo-joint drainage board is formed by connecting the horizontal drainage board on the basis of the vertical vacuum drainage pipe. It is simple to make, practical and does not require complicated processing. Although it is easy to install, it can effectively overcome the vacuum attenuation problem caused by siltation of the drainage board on deep and ultra-soft soil foundation.

[0023] (2) The new bamboo-joint drainage board has a simple structure and good overall performance. During the construction process, it can ensure the vacuum degree in the vacuum drainage pipe. The vacuum degree attenuation is transferred from the traditional vacuum preloaded vertical drainage board to the horizontal drainage board, and the reinforcement effect is obvious. BRIEF DESCRIPTION OF THE DRAWINGS

[0024] Figure 1 It is a schematic diagram of the overall structure of the bamboo-joint drainage board of Example 1 of the present invention.

[0025] Figure 2 This is a schematic diagram of the structure of the bamboo-jointed drainage board of Example 2 of the present invention.

[0026] Figure 3 Bamboo drainage board connection diagram

[0027] Figure 4 Casing base structure diagram

[0028] Figure 5 It is an enlarged view of the hand-shaped connector 8 and the connecting nut 9.

[0029] Explanation of the numbers in the figure: 1 thin-walled casing; 2 casing base; 3 bamboo-jointed drainage board; 4 base groove; 5 base drainage pipe connection interface; 6 drainage board pipe; 7 drainage board single board; 8 hand-shaped joint; 9 connection nut DETAILED DESCRIPTION

[0030] The present invention is described below in conjunction with the accompanying drawings and embodiments.

[0031] Example 1

[0032] See also Figure 1 and Figure 3The present invention provides a new type of bamboo-joint drainage board, and the specific connection includes a drainage board single plate 7, a hand-shaped joint 8, a connecting nut 9, and a drainage pipe 6. When the foundation is vacuum preloaded, it is necessary to connect the drainage board single plate 7 with one side of the hand-shaped joint 8 in advance, and the other side of the hand-shaped joint 8 is inserted into the reserved hole in the drainage pipe 6 through the connecting nut 9 to form a bamboo-joint drainage board. The connecting nut 9 is hollow and is used to connect the drainage board single plate 7 and the drainage pipe 6.

[0033] See also Figure 1 , Figure 4 and Figure 5 In order to ensure that the bamboo-jointed drain board is smoothly put into the ground, it is necessary to bend the drain board single plate 7 along a certain direction, use the thin-walled casing 1 to cover the outside of the bamboo-jointed drain board 3, install the casing base 2, respectively connect the base drainage pipe connection interface 5 with the drain board pipe 6, the base groove 4 and the thin-walled casing 1, and use the pile-pressing mechanical equipment to press the bamboo-jointed drain board into the super-soft soil. After the bamboo-jointed drain board is pressed into the predetermined position, the casing is taken out by rotating in the opposite direction. Finally, the upper part of the drain board pipe 6 is connected to the main pipeline in the circuit to form a vacuum radiation drainage system. The bamboo-jointed drain board of the present invention has the same material as the drain board on the market. It also uses plastic material, has a certain flexibility, can be curled by external force, and can also stretch naturally when the external force is removed.

[0034] Due to the simplicity of the structure and the standard universality of all components, the reinforcement effect and other mechanical effects of the device can be easily analyzed and demonstrated through existing commercial finite element calculation software, so that engineering and technical personnel can flexibly set the position of the connecting nut 9 to optimize the design of the bamboo-section vacuum preloaded drainage board according to different actual engineering needs.

[0035] Example 2

[0036] Example 2 Figure 2 As shown, the only difference from Example 1 is that the arrangement of the drain board single plate 7 on the drain board tube 6 is different in Example 1. In Example 1, a pair of drain board single plates 7 are connected to two opposite sides of the drain board tube 6, while the drain board single plates 7 of Example 2 are staggered, but the connection method at the connection part is the same.

[0037] Example 3

[0038] Embodiment 3 is not drawn. Unlike Embodiment 1 or Embodiment 2, the individual drain board panels of Embodiment 3 are no longer distributed on one plane, but are arranged on different planes around the drain board pipe. However, the connection method at the connection parts is still the same.

Claims

1. A construction method of a bamboo-joint drain board, wherein the bamboo-joint drain board comprises a drain pipe, a drain board single board, a hand-shaped joint, a connecting nut and a construction accessory, holes matching the connecting nut are opened at different positions on the side of the drain pipe, and the drain board single board is fixedly connected to the drain pipe through the hand-shaped joint and the connecting nut; the connecting nut is hollow and connected to one end of the hand-shaped joint; the construction accessory comprises a casing and a casing base, and the casing can be detachably connected to the casing base; the casing base is conical, and its height is greater than the height of the drain pipe; a base drain pipe connection interface is provided on the casing base; the construction method comprises the following steps: (1) Bend each drain board, use the casing to cover the outside of the bamboo-shaped drain board, and install the casing base so that the casing base and the casing are connected; (2) Press the casing containing the bamboo drainage board into the super-soft soil; (3) After the bamboo-jointed drainage board is pressed into the predetermined position, the casing is removed; (4) Connect the upper part of the drainage board pipe to the main pipeline to form a vacuum radiation drainage system.

2. The construction method of the bamboo-joint drainage board according to claim 1, characterized in that: The drain board sheets are arranged in pairs on the sides of the drain pipe, and each pair of drain board sheets is arranged on opposite sides of the drain pipe.

3. The construction method of the bamboo-joint drainage board according to claim 1, characterized in that: The drainage board single plates are arranged in a staggered manner on the side of the drainage pipe.

4. The construction method of the bamboo-joint drainage board according to claim 1, characterized in that: The drain board sheets are arranged on different planes around the drain board pipes.