An assembly type high-rise building steel frame structure installation device and control method

By using devices such as vertical rails, lifting guide rails, and laser calibrators in the installation of high-rise building steel frame structures, the automated and precise installation of steel frames is realized, solving the problems of verticality deviation and waste of human resources during the installation process, and improving construction efficiency. Efficiency and safety.

CN116084712BActive Publication Date: 2024-10-11POWERCHINA MUNICIPAL CONSTR GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202310334371.2
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-03-31
Publication Date
2024-10-11
Estimated Expiration
2043-03-31

AI Technical Summary

Technical Problem

Steel frame structures of high-rise buildings are prone to vertical deviations during the installation process. The hoisting process consumes a lot of manpower and material resources, and poses safety risks to workers below. How to control the quality of steel frame installation projects has become key.

Method used

A prefabricated high-rise building steel frame structure installation device is designed, including vertical rails, lifting guide rails, lifting devices, consoles, laser calibrators and winches. The laser calibrator is used to achieve precise docking and automatic lifting of the steel frames. Reduce human errors and improve installation efficiency.

Benefits of technology

The steel frame docking error is reduced, manpower and material resources are saved, construction costs and difficulties are reduced, construction efficiency and installation speed are improved, and project quality is ensured.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116084712B_ABST
    Figure CN116084712B_ABST
Patent Text Reader

Abstract

The present invention proposes an installation device and a control method for an assembled high-rise building steel frame structure. The device includes vertical steel rails, a first-grade steel frame, a second-grade steel frame, a lifting guide rail, a lifting device, a control console, a first winch and a second winch. The present invention combines vertical steel rails fixed on both sides of the steel frame to form a basic structure of the lifting device. The steel frames are transported to specified positions one by one by using the winch, the lifting guide rail and the lifting device. The steel frames are accurately calibrated by a laser calibrator to achieve precise docking between the steel frames. The present invention realizes the automated and precise installation of assembled high-rise frames, reduces frame docking errors, saves a lot of manpower and material resources, and at the same time improves the installation efficiency of the steel frame structure to ensure the quality of engineering construction and the safety of personnel.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to the technical field of high-rise building steel frame structure installation, and in particular to an assembled high-rise building steel frame structure installation device. Background Art

[0002] In recent years, high-rise and super-high-rise buildings have sprung up in my country like bamboo shoots after rain. Since the steel frame structure system has high strength, rigidity and seismic resistance, it is increasingly used in high-rise and super-high-rise building structures. However, the steel frame structure needs to be hoisted to the specified height and position by a crane, and then manually corrected and welded. The verticality is very easy to deviate, and the hoisting process takes up a lot of manpower and material resources, and may cause harm to the lower staff. It can be seen that the quality of the installation of the assembled high-rise steel frame determines the success or failure of the assembled high-rise building project. How to control the quality of the steel frame installation project is the key to the stability and safety of the steel frame structure. To this end, this patent develops a precise installation device and control method for the steel frame structure of an assembled high-rise building to achieve automatic hoisting of the steel frame structure, save a lot of manpower and material resources, accurately dock, reduce the verticality error, and ensure the quality of engineering construction. Summary of the invention

[0003] In order to solve the problems existing in the background technology, the present invention proposes an assembly type high-rise building steel frame structure installation device, comprising a vertical steel rail, a first-grade steel frame, a second-grade steel frame, a lifting guide rail, a lifting device, a control console, a first hoist and a second hoist, wherein the first-grade steel frame is installed on a foundation, the vertical steel rail is installed on both sides of the first-grade steel frame, and the bottom end of the vertical steel rail is inserted into the foundation, the lifting guide rail comprises a sliding section and a rotating section, the sliding section is slidably connected to the vertical steel rail on one side of the first-grade steel frame, and the rotating section is rotatably connected to the upper end of the sliding section through a steering device;

[0004] The top of the lifting device is hoisted on the top of the lifting rail through a first cable, the bottom of the lifting device is rotatably connected to a sliding member, the sliding member is slidably connected to the side of the lifting rail away from the vertical rail, a first lifting pulley is installed on the top of the lifting rail, one end of the first cable is connected to the top of the lifting device, and the other end of the first cable is connected to the first winch through the first lifting pulley;

[0005] A second lifting pulley is installed at the top of the vertical rail on which the lifting guide rail is installed, and the lifting guide rail is slidably connected to the vertical rail through a second cable and a second hoisting machine, one end of the second cable is connected to the top of the sliding section of the lifting guide rail, and the other end of the second cable is connected to the second hoisting machine through a second lifting pulley;

[0006] The second grade steel frame is mounted on the lifting device through a calibration adjustment mechanism;

[0007] Laser calibrators are installed on the top side of the first steel frame and the bottom side of the second steel frame. The laser calibrators on the two steel frames are used to calibrate the docking accuracy of the two steels.

[0008] The control console is respectively connected with the first hoist, the second hoist, the laser calibrator, the steering device and the calibration adjustment mechanism.

[0009] Preferably, the calibration adjustment mechanism includes a fixing plate and an adjusting plate, a first screw is fixed to the top of the lifting device for rotation in the left-right direction, the first screw is driven by a first motor, a first sliding rod is fixed to the bottom of the lifting device for rotation in the left-right direction, a first screw hole matching the first screw is provided on the top of the adjusting plate for rotation in the left-right direction, the first screw is threadedly connected in the first screw hole, a first sliding hole matching the first sliding rod is provided on the bottom of the adjusting plate for rotation in the left-right direction, and the first sliding rod is slidably connected in the first sliding hole;

[0010] A second screw is fixed on the top of the adjustment plate for rotation along the front-to-back direction, and the second screw is driven by a second motor. A second sliding rod is fixed on the bottom of the adjustment plate for rotation along the front-to-back direction, and a sliding portion is provided at the top and bottom of the fixed plate. The size of the sliding portion in the front-to-back direction is smaller than the size of the fixed plate in the front-to-back direction. A second screw hole matching the second screw is provided on the sliding portion at the top of the fixed plate along the front-to-back direction, and the second screw is threadedly connected in the second screw hole. A second sliding hole matching the second sliding rod is provided on the sliding portion at the bottom of the fixed plate along the front-to-back direction, and the second sliding rod is slidably connected in the second sliding hole.

[0011] Preferably, a track pulley is rotatably fixed on one side of the lifting guide rail sliding section close to the vertical rail, a slide rail matching the track pulley is provided on the vertical rail, and the track pulley is embedded in the slide rail of the vertical rail.

[0012] Preferably, a sliding wheel is provided on the side of the lifting device close to the lifting guide rail.

[0013] Preferably, three laser calibrators are installed on each of the first-grade steel frame and the second-grade steel frame. The three laser calibrators on the first-grade steel frame are respectively located in the middle of the front, left and right sides of the top of the first-grade steel frame, and the three laser calibrators on the second-grade steel frame are respectively located in the middle of the front, left and right sides of the bottom of the second-grade steel frame.

[0014] A control method for an assembly type high-rise building steel frame structure installation device comprises the following steps:

[0015] S1, assemble the installation device, connect the first steel frame with the foundation 1, install vertical rails on both sides of the first steel frame after the connection is completed, and the vertical rails are inserted into the foundation 1, install a laser calibration instrument on the top side of the first steel frame, slide the lifting rails with the vertical rails, connect the lifting rails and the second hoisting pulley with the second cable, connect the lifting device with the lifting rails, connect the lifting device with the first hoisting pulley with the first cable and the first hoisting pulley, and then install the calibration adjustment mechanism on the lifting device;

[0016] S2. In the initial state, the lifting device is close to the foundation 1. The lifting device is made parallel to the surface of the foundation 1 by lowering the first cable. The second steel frame is installed on the calibration adjustment mechanism, and a laser calibration instrument is installed on the side of the bottom end of the second steel frame.

[0017] S3, starting the first hoist, and the first hoist lifts the lifting device through the first cable until the second steel frame on the lifting device is in a vertical state;

[0018] S4, the first winch continues to hoist the lifting device, so that the lifting device moves up along the lifting guide rail until the lifting device reaches the rotating section of the lifting guide rail; the second winch is started, and the second winch hoists the lifting guide rail through the second cable, so that the lifting guide rail slides along the vertical rail;

[0019] S5, after the hoisting device reaches the rotating section of the hoisting guide rail, the first hoisting machine is stopped, and the steering device is started to rotate the rotating section of the hoisting guide rail by 180 degrees, so that the second steel frame and the first steel frame are located on the same side;

[0020] S6, start the first winch, so that the first winch lowers the second steel frame through the first cable, and at the same time start all the laser aligners to accurately align the second steel frame with the first steel frame. When the laser aligner detects that the second steel frame is offset from the first steel frame, the control console controls the calibration adjustment mechanism to start, and adjusts the position of the second steel frame until the first and second steel frames are aligned;

[0021] S7. After the second-grade steel frame is precisely connected with the first-grade steel frame, the first-grade steel frame and the second-grade steel frame are welded to complete the installation of the second-grade steel frame;

[0022] S8, disassemble the second steel frame and the calibration adjustment mechanism, remove all laser calibration instruments on the first steel frame and the second steel frame, and connect the second cable to the lifting rail and the second winch through the second lifting wheels on the vertical rails on both sides of the second steel frame;

[0023] S9. Install vertical rails on both sides of the second steel frame, and install a laser alignment device in the middle of the front, left and right sides of the top of the second steel frame;

[0024] S10, starting the steering device to rotate the rotating section of the lifting guide rail 180 degrees, and lowering the lifting device through the first hoisting machine until the lifting device is in the initial state;

[0025] S11, install the third steel frame on the lifting device, repeat steps S3 and S4, start the second hoist, use the second hoist to lift the lifting guide rail up along the vertical rail until the third steel frame reaches the space above the second steel frame, and repeat steps S5-S7;

[0026] S12, starting from step S8 and looping until all steel frames are installed.

[0027] Preferably, the vertical rail is inserted 2m into the foundation.

[0028] Preferably, the first steel frame is connected to the vertical rails through a plurality of first steel plates, both ends of the first steel plates are respectively bolted to the vertical rails on both sides of the first steel frame, and the plurality of first steel plates and the vertical rails tightly embrace the first steel frame;

[0029] The second steel frame is connected to the calibration adjustment mechanism through a plurality of second steel plates, both ends of the second steel plates are respectively connected to the calibration adjustment mechanism with bolts, and the plurality of second steel plates and the calibration adjustment mechanism tightly embrace the second steel frame.

[0030] Preferably, the thickness of the first steel plate is 1 cm, the width is 5 cm, and the distance between two adjacent first steel plates is 2 m; the thickness of the second steel plate is 1 cm, the width is 5 cm, and the distance between two adjacent second steel plates is 2 m.

[0031] Preferably, the operating speeds of the first hoist and the second hoist are both controlled at 50 cm / min-100 cm / min.

[0032] The beneficial effects of the present invention are:

[0033] 1. The present invention can reduce the docking error of the steel frame. By docking the steel frames with three laser calibrators (three points determine a plane) to accurately calibrate the installation process, it can not only reduce human errors but also improve the installation speed of the steel frame.

[0034] 2. Compared with the traditional crane hoisting method, the present invention saves manpower and material resources, and also saves construction costs. At the same time, it reduces the construction difficulty, improves the construction efficiency, and the construction progress is easy to grasp and the construction process is simple.

[0035] 3. The present invention transforms the installation of assembled high-rise steel frames into automated and precise installation, which plays an important role in reducing the docking error of steel frames and improving the installation efficiency of steel frames. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 This is a schematic diagram of the structure of the initial state of the installation device of the present invention;

[0037] Figure 2 It is a schematic diagram of the structure when the lifting device of the present invention reaches the rotating section of the lifting guide rail;

[0038] Figure 3 This is a structural schematic diagram of the first steel frame and the second steel frame of the present invention when they are butt-jointed;

[0039] Figure 4 It is a structural schematic diagram of the sliding part of the present invention;

[0040] Figure 5 It is an exploded schematic diagram of the calibration adjustment mechanism of the present invention.

[0041] Numbers in the figure: 1-foundation, 2-control console, 3-second winch, 4-first winch, 5-vertical rail, 6-second steel frame, 7-hoisting device, 8-first cable, 9-steering device, 10-hoisting guide rail, 101-rotating section, 102-sliding section, 103-track pulley, 104-track, 11-laser calibrator, 12-first steel frame, 13-second cable, 14-second lifting pulley, 15-first lifting pulley, 16-sliding member, 17-sliding wheel, 171-first screw, 172-first sliding rod, 18-calibration adjustment mechanism, 181-fixed plate, 1811-sliding part, 182-adjusting plate, 1821-second screw, 1822-second sliding rod, 19-first steel plate, 20-second steel plate. DETAILED DESCRIPTION

[0042] In order to make the present invention clearer and more understandable, the technical solution of the present invention is further described in detail below in conjunction with the accompanying drawings and embodiments. It should be understood that the given embodiment is only one implementation method and does not represent all embodiments.

[0043] In this article, the terms "left, right, up, down" and the like are established based on the positional relationships shown in the drawings. Depending on the different drawings, the corresponding positional relationships may also change accordingly. Therefore, they cannot be understood as absolute limitations on the scope of protection.

[0044] Combined with Figure 1-5, An assembled high-rise building steel frame structure installation device, comprising a vertical steel rail 5, a first steel frame 12, a second steel frame 6, a hoisting guide rail 10, a hoisting device 7, a control console 2, a first hoist 4 and a second hoist 3, the first steel frame 12 is installed on a foundation 1, the vertical steel rail 5 is installed on both sides of the first steel frame 12, the bottom end of the vertical steel rail 5 is inserted into the foundation 1, the hoisting guide rail 10 comprises a sliding section 102 and a rotating section 101, the sliding section 102 is slidably connected to the vertical steel rail 5 on one side of the first steel frame 12, and the rotating section 101 is rotatably connected to the upper end of the sliding section 102 through a steering device 9;

[0045] The top of the lifting device 7 is hoisted on the top of the lifting rail 10 through the first cable 8, and the bottom of the lifting device 7 is rotatably connected with a sliding member 16. The sliding member 16 can be used as a fulcrum for connecting the lifting device 7 with the lifting rail 10, and at the same time, the lifting device 7 can slide along the lifting rail 10. The sliding member 16 is slidably connected to the side of the lifting rail 10 away from the vertical rail 5. A first lifting pulley 15 is installed on the top of the lifting rail 10. One end of the first cable 8 is connected to the top of the lifting device 7, and the other end of the first cable 8 is connected to the first winch 4 through the first lifting pulley 15;

[0046] A second hoisting pulley 14 is installed at the top of the vertical rail 5 on which the hoisting rail 10 is installed. The hoisting rail 10 is slidably connected to the vertical rail 5 through a second cable 13 and a second hoisting machine 3. One end of the second cable 13 is connected to the top of the sliding section 102 of the hoisting rail 10, and the other end of the second cable 13 is connected to the second hoisting machine 3 through the second hoisting pulley 14.

[0047] The second steel frame 6 is mounted on the lifting device 7 through a calibration adjustment mechanism 18;

[0048] The top side of the first steel frame 12 and the bottom side of the second steel frame 6 are both equipped with laser calibrators 11, and the laser calibrators 11 on the two steel frames are used to calibrate the docking accuracy of the two steels;

[0049] The control console 2 is respectively connected to the first winch 4, the second winch 3, the laser calibrator 11, the steering device 9 and the calibration adjustment mechanism 18, and the start, stop and movement stroke of the first winch 4, the second winch 3, the laser calibrator 11, the steering device 9 and the calibration adjustment mechanism 18 are controlled by the control console 2.

[0050] Specifically, the calibration adjustment mechanism 18 includes a fixing plate 181 and an adjusting plate 182. A first screw rod 171 is fixed to the top of the lifting device 7 for rotation along the left-right direction. The first screw rod 171 is driven by a first motor. A first slide rod 172 is fixed to the bottom of the lifting device 7 for rotation along the left-right direction. A first screw hole matching the first screw rod 171 is provided on the top of the adjusting plate 182 for rotation along the left-right direction. The first screw rod 171 is threadedly connected in the first screw hole. A first slide hole matching the first slide rod 172 is provided on the bottom of the adjusting plate 182 for rotation along the left-right direction. The first slide rod 172 is slidably connected in the first slide hole.

[0051] A second screw rod 1821 is fixed to the top of the adjustment plate 182 for rotation along the front-to-back direction, and the second screw rod 1821 is driven by a second motor. A second slide bar 1822 is fixed to the bottom of the adjustment plate 182 for rotation along the front-to-back direction. A sliding portion 1811 is provided at the top and bottom of the fixed plate 181. The dimension of the sliding portion 1811 in the front-to-back direction is smaller than that of the fixed plate 181 in the front-to-back direction to ensure that the fixed plate 181 has movement space. A second screw hole matching the second screw rod 1821 is provided on the top sliding portion 1811 of the fixed plate 181 in the front-to-back direction, and the second screw rod 1821 is threadedly connected in the second screw hole. A second slide hole matching the second slide bar 1822 is provided on the bottom sliding portion 1811 of the fixed plate 181 in the front-to-back direction, and the second slide bar 1822 is slidably connected in the second slide hole.

[0052] When the first motor is started, the first screw 171 rotates, and the adjustment plate 182 slides left-right along the first screw 171 and the first slide bar 172 driven by the first screw 171. When the second motor is started, the second screw 1821 rotates, and the fixed plate 181 slides front-back along the second screw 1821 and the second slide bar 1822 driven by the second screw 1821. Therefore, when the laser calibrator 11 detects that the first and second steel frames are not aligned, the first motor and the second motor can be started to adjust the second steel frame 6 front-to-back and left-to-right until the first and second steel frames are aligned.

[0053] Specifically, a track pulley 103 is rotatably fixed on one side of the sliding section 102 of the lifting guide rail 10 close to the vertical rail 5 , a slide rail matching the track pulley 103 is provided on the vertical rail 5 , and the track pulley 103 is embedded in the slide rail of the vertical rail 5 .

[0054] Specifically, a sliding wheel 17 is provided on the side of the lifting device 7 close to the lifting rail 10, and a track 104 is provided on the side of the lifting rail 10 close to the lifting device 7, so that the lifting device 7 can move along the track 104 through the sliding wheel 17 after being vertically erected, thereby improving the stability of the movement of the lifting device 7.

[0055] Specifically, three laser calibrators 11 are respectively installed on the first steel frame 12 and the second steel frame 6. The three laser calibrators 11 on the first steel frame 12 are respectively located in the middle of the front, left and right sides of the top of the first steel frame 12, and the three laser calibrators 11 on the second steel frame 6 are respectively located in the middle of the front, left and right sides of the bottom of the second steel frame 6. Three points can determine a plane, and the three laser calibrators 11 can also be installed in the middle of the back, left and right sides of one steel frame, and the side selected when installing the laser calibrator 11 on the other steel frame can correspond to the steel frame on which the laser calibrator 11 has been installed.

[0056] A control method for an assembly type high-rise building steel frame structure installation device comprises the following steps:

[0057] S1, assemble the installation device, connect the first steel frame 12 with the foundation, install vertical rails 5 on both sides of the first steel frame 12 after the connection is completed, and the vertical rails 5 are inserted into the foundation 1, install the laser calibration instrument 11 on the top side of the first steel frame 12, slide the lifting rail 10 with the vertical rail 5, connect the lifting rail 10 and the second hoisting machine 3 with the second cable 13 and the second lifting pulley 14, connect the lifting device 7 with the lifting rail 10, connect the lifting device 7 with the first hoisting machine 4 with the first cable 8 and the first lifting pulley 15, and then install the calibration adjustment mechanism 18 on the lifting device 7;

[0058] S2, in the initial state, the lifting device 7 is close to the foundation, and the first cable 8 is lowered to make the lifting device 7 parallel to the surface of the foundation, the second steel frame 6 is installed on the calibration adjustment mechanism 18, and the laser calibration instrument 11 is installed on the side of the bottom end of the second steel frame 6;

[0059] S3, start the first hoist 4, and the first hoist 4 lifts the lifting device 7 through the first cable 8 until the second steel frame 6 on the lifting device 7 is in a vertical state;

[0060] S4, the first hoisting machine 4 continues to hoist the lifting device 7, so that the lifting device 7 moves up along the lifting guide rail 10, until the lifting device 7 reaches the rotating section 101 of the lifting guide rail 10; the second hoisting machine 3 is started, and the second hoisting machine 3 hoists the lifting guide rail 10 through the second cable 13, so that the lifting guide rail 10 slides along the vertical rail 5;

[0061] S5, after the hoisting device 7 reaches the rotating section 101 of the hoisting guide rail 10, the first hoisting machine 4 is stopped, and the steering device 9 is started to rotate the rotating section 101 of the hoisting guide rail 10 by 180°, so that the second steel frame 6 and the first steel frame 12 are located on the same side;

[0062] S6, start the first hoist 4, so that the first hoist 4 lowers the second steel frame 6 through the first cable 8, and at the same time start all the laser aligners 11, so that the second steel frame 6 and the first steel frame 12 are accurately docked, when the laser aligner 11 detects that the second steel frame 6 and the first steel frame 12 are offset, the control console controls the calibration adjustment mechanism 18 to start, and adjusts the position of the second steel frame 6 until the first and second steel frames 6 are aligned;

[0063] S7, after the second steel frame 6 is precisely butted against the first steel frame 12, the first steel frame 12 and the second steel frame 6 are welded to complete the installation of the second steel frame 6;

[0064] S8, disassemble the second steel frame 6 and the calibration adjustment mechanism 18, remove all laser calibration instruments 11 on the first steel frame 12 and the second steel frame 6, and connect the second cable 13 to the lifting rail 10 and the second winch 3 through the second lifting wheels on the vertical rails 5 on both sides of the second steel frame 6;

[0065] S9, install vertical rails 5 on both sides of the second steel frame 6, and install a laser alignment device 11 in the middle of the front, left and right sides of the top of the second steel frame 6;

[0066] S10, start the steering device 9 to rotate the rotating section 101 of the lifting guide rail 10 by 180 degrees, and lower the lifting device 7 through the first hoisting machine 4 until the lifting device 7 is in the initial state;

[0067] S11, install the third steel frame on the lifting device 7, repeat steps S3 and S4, start the second hoist 3, and use the second hoist 3 to lift the lifting guide rail 10 and move it upward along the vertical rail 5 until the third steel frame reaches the space above the second steel frame, and repeat steps S5-S7;

[0068] S12, starting from step S8 and looping until all steel frames are installed.

[0069] Specifically, the vertical rail 5 is inserted into the foundation 2m.

[0070] Specifically, the first steel frame 12 is connected to the vertical steel rail 5 through a plurality of first steel plates 19, and both ends of the first steel plates 19 are respectively bolted to the vertical steel rails 5 on both sides of the first steel frame 12, and the plurality of first steel plates 19 and the vertical steel rails 5 tightly embrace the first steel frame 12;

[0071] The second steel frame 6 is connected to the calibration adjustment mechanism 18 through a plurality of second steel plates 20. Both ends of the second steel plates 20 are respectively connected to the calibration adjustment mechanism 18 with bolts. The plurality of second steel plates 20 and the calibration adjustment mechanism 18 tightly embrace the second steel frame 6. The first steel plate 19 and the second steel plate 20 are removed by removing the bolts, so that the vertical rail 5 can be removed from the first steel frame 12, and the second steel frame 6 can also be removed from the calibration adjustment mechanism 18, which is convenient for construction.

[0072] Specifically, the first steel plate 19 has a thickness of 1 cm and a width of 5 cm, and a distance between two adjacent first steel plates 19 is 2 m; the second steel plate 20 has a thickness of 1 cm and a width of 5 cm, and a distance between two adjacent second steel plates 20 is 2 m.

[0073] Specifically, the operating speeds of the first hoist 4 and the second hoist 3 are both controlled at 50 cm / min-100 cm / min.

[0074] The above embodiments are only to illustrate the basic principles and characteristics of the present invention, but are not limited to the above embodiments. It should be understood that for ordinary technicians in this field, various changes and modifications can be made to the present invention without departing from the spirit and scope of the present invention, and these changes and modifications fall within the scope of the present invention to be protected. The scope of protection of the present invention is defined by the attached claims and their equivalents.

Claims

1. An assembly type high-rise building steel frame structure installation device, characterized in that: The invention comprises a vertical steel rail (5), a first steel frame (12), a second steel frame (6), a lifting guide rail (10), a lifting device (7), a control console (2), a first hoist (4) and a second hoist (3), wherein the first steel frame (12) is installed on a foundation (1), the vertical steel rail (5) is installed on both sides of the first steel frame (12), and the bottom end of the vertical steel rail (5) is inserted into the foundation (1), and the lifting guide rail (10) comprises a sliding section (102) and a rotating section (101), wherein the sliding section (102) is slidably connected to the vertical steel rail (5) on one side of the first steel frame (12), and the rotating section (101) is rotatably connected to the upper end of the sliding section (102) through a steering device (9); The top of the lifting device (7) is hoisted to the top of the lifting rail (10) via a first cable (8); the bottom of the lifting device (7) is rotatably connected to a sliding member (16); the sliding member (16) is slidably connected to the side of the lifting rail (10) away from the vertical rail (5); a first lifting pulley (15) is installed at the top of the lifting rail (10); one end of the first cable (8) is connected to the top of the lifting device (7); the other end of the first cable (8) is connected to the first winch (4) via the first lifting pulley (15); A second lifting pulley (14) is installed at the top of the vertical steel rail (5) on which the lifting guide rail (10) is installed. The lifting guide rail (10) is slidably connected to the vertical steel rail (5) via a second cable (13) and a second hoisting machine (3). One end of the second cable (13) is connected to the top of the sliding section (102) of the lifting guide rail (10), and the other end of the second cable (13) is connected to the second hoisting machine (3) via the second lifting pulley (14). The second steel frame (6) is mounted on the lifting device (7) via a calibration adjustment mechanism (18); A laser calibrator (11) is installed on the top side of the first steel frame (12) and the bottom side of the second steel frame (6), and the laser calibrators (11) on the two steel frames are used to calibrate the docking accuracy of the two steels; The control console (2) is respectively connected to the first hoist (4), the second hoist (3), the laser calibration instrument (11), the steering device (9) and the calibration adjustment mechanism (18).

2. The assembly type high-rise building steel frame structure installation device according to claim 1, characterized in that: The calibration adjustment mechanism (18) comprises a fixing plate (181) and an adjusting plate (182); a first screw rod (171) is fixed to the top of the lifting device (7) for rotation in the left-right direction; the first screw rod (171) is driven by a first motor; a first sliding rod (172) is fixed to the bottom of the lifting device (7) for rotation in the left-right direction; a first screw hole matching the first screw rod (171) is provided at the top of the adjusting plate (182) in the left-right direction; the first screw rod (171) is threadedly connected in the first screw hole; a first sliding hole matching the first sliding rod (172) is provided at the bottom of the adjusting plate (182) in the left-right direction; the first sliding rod (172) is slidably connected in the first sliding hole; A second screw rod (1821) is fixed to the top of the adjustment plate (182) for rotation in the front-to-rear direction, and the second screw rod (1821) is driven by a second motor. A second sliding rod (1822) is fixed to the bottom of the adjustment plate (182) for rotation in the front-to-rear direction. A sliding portion (1811) is provided at the top and bottom of the fixed plate (181). The dimension of the sliding portion (1811) in the front-to-rear direction is smaller than the dimension of the fixed plate (181) in the front-to-rear direction. A second screw hole matching the second screw rod (1821) is provided on the top sliding portion (1811) of the fixed plate (181) in the front-to-rear direction, and the second screw rod (1821) is threadedly connected in the second screw hole. A second sliding hole matching the second sliding rod (1822) is provided on the bottom sliding portion (1811) of the fixed plate (181) in the front-to-rear direction, and the second sliding rod (1822) is slidably connected in the second sliding hole.

3. The assembly type high-rise building steel frame structure installation device according to claim 1 is characterized by: A track pulley (103) is rotatably fixed on one side of the sliding section (102) of the lifting guide rail (10) close to the vertical steel rail (5); a slide rail matching the track pulley (103) is provided on the vertical steel rail (5); and the track pulley (103) is embedded in the slide rail of the vertical steel rail (5).

4. The assembly type high-rise building steel frame structure installation device according to claim 1, characterized in that: A sliding wheel (17) is provided on one side of the lifting device (7) close to the lifting guide rail (10).

5. The assembly type high-rise building steel frame structure installation device according to claim 1, characterized in that: The first steel frame (12) and the second steel frame (6) are each equipped with three laser alignment instruments (11). The three laser alignment instruments (11) on the first steel frame (12) are respectively located at the middle positions of the front, left and right sides of the top of the first steel frame (12), and the three laser alignment instruments (11) on the second steel frame (6) are respectively located at the middle positions of the front, left and right sides of the bottom of the second steel frame (6).

6. A control method for installing a prefabricated high-rise building steel frame structure according to claim 1 or 2 or 3 or 4 or 5, characterized in that: The following steps are involved: S1, assembling the installation device, connecting the first steel frame (12) with the foundation (1), after the connection is completed, installing vertical steel rails (5) on both sides of the first steel frame (12), and the vertical steel rails (5) are inserted into the foundation (1), installing a laser calibration instrument (11) on the top side of the first steel frame (12), slidingly connecting the lifting rail (10) with the vertical steel rail (5), connecting the lifting rail (10) with the second hoisting machine (3) by using a second cable (13) and a second lifting pulley (14), connecting the lifting device (7) with the lifting rail (10), connecting the lifting device (7) with the first hoisting machine (4) by using a first cable (8) and a first lifting pulley (15), and then installing the calibration adjustment mechanism (18) on the lifting device (7); S2, in the initial state, the lifting device (7) is close to the foundation (1), and the lifting device (7) is parallel to the surface of the foundation (1) by lowering the first cable (8), the second steel frame (6) is installed on the calibration adjustment mechanism (18), and a laser calibration instrument (11) is installed on the side of the bottom end of the second steel frame (6); S3, starting the first hoist (4), the first hoist (4) hoists the lifting device (7) through the first cable (8) until the second steel frame (6) on the lifting device (7) is in a vertical state; S4, the first hoist (4) continues to hoist the lifting device (7), so that the lifting device (7) moves upward along the lifting guide rail (10), until the lifting device (7) reaches the rotating section (101) of the lifting guide rail (10); the second hoist (3) is started, and the second hoist (3) hoists the lifting guide rail (10) through the second cable (13), so that the lifting guide rail (10) slides along the vertical rail (5); S5, after the hoisting device (7) reaches the rotating section (101) of the hoisting guide rail (10), the first hoist (4) is stopped, and the steering device (9) is started to rotate the rotating section (101) of the hoisting guide rail (10) by 180 degrees, so that the second steel frame (6) and the first steel frame (12) are located on the same side; S6, start the first winch (4), so that the first winch (4) lowers the second steel frame (6) through the first cable (8), and at the same time start all the laser alignment devices (11) so that the second steel frame (6) and the first steel frame (12) are accurately docked. When the laser alignment device (11) detects that the second steel frame (6) and the first steel frame (12) are offset, the control console controls the calibration adjustment mechanism (18) to start, and adjusts the position of the second steel frame (6) until the first and second steel frames (6) are aligned; S7, after the second steel frame (6) is accurately butted against the first steel frame (12), the first steel frame (12) and the second steel frame (6) are welded to complete the installation of the second steel frame (6); S8, disassemble the second steel frame (6) and the calibration adjustment mechanism (18), remove all laser calibration instruments (11) on the first steel frame (12) and the second steel frame (6), and connect the second cable (13) to the lifting guide rail (10) and the second winch (3) through the second lifting wheels on the vertical rails (5) on both sides of the second steel frame (6); S9, installing vertical rails (5) on both sides of the second steel frame (6), and installing a laser alignment device (11) at the middle position of the front, left and right sides of the top of the second steel frame (6); S10, starting the steering device (9) to rotate the rotating section (101) of the lifting guide rail (10) by 180 degrees, and lowering the lifting device (7) by means of the first hoisting machine (4) until the lifting device (7) is in an initial state; S11, installing the third steel frame onto the lifting device (7), repeating steps S3 and S4, starting the second hoist (3), and using the second hoist (3) to lift the lifting guide rail (10) upward along the vertical steel rail (5) until the third steel frame reaches the spatial position above the second steel frame, and repeating steps S5-S7; S12, starting from step S8 and looping until all steel frames are installed.

7. A control method for installing a prefabricated high-rise building steel frame structure according to claim 6, characterized in that: The vertical steel rail (5) is inserted into the foundation 2m.

8. A control method for installing a prefabricated high-rise building steel frame structure according to claim 6, characterized in that: The first steel frame (12) is connected to the vertical steel rail (5) via a plurality of first steel plates (19), the two ends of the first steel plates (19) are respectively bolted to the vertical steel rails (5) on both sides of the first steel frame (12), and the plurality of first steel plates (19) and the vertical steel rails (5) tightly embrace the first steel frame (12); The second steel frame (6) is connected to the calibration adjustment mechanism (18) via a plurality of second steel plates (20); both ends of the second steel plates (20) are respectively bolted to the calibration adjustment mechanism (18); and the plurality of second steel plates (20) and the calibration adjustment mechanism (18) tightly embrace the second steel frame (6).

9. A control method for installing a prefabricated high-rise building steel frame structure according to claim 8, characterized in that: The first steel plate (19) has a thickness of 1 cm and a width of 5 cm, and the distance between two adjacent first steel plates (19) is 2 m; the second steel plate (20) has a thickness of 1 cm and a width of 5 cm, and the distance between two adjacent second steel plates (20) is 2 m.

10. A control method for installing a prefabricated high-rise building steel frame structure according to claim 6, characterized in that: The operating speeds of the first hoist (4) and the second hoist (3) are both controlled within a range of 50 cm / min-100 cm / min.