Offshore wind power pile foundation anti-scour pit system

By designing an annular sand-fixing cover and a diversion sand-proof cover on the foundation of offshore wind power piles, combined with a multi-layer mesh cover and a flow-blocking structure, the problem of protection and repair of scour pits in offshore wind power pile foundations has been solved, achieving stronger protection effects and Economy.

CN116677020BActive Publication Date: 2024-10-29CHINA THREE GORGES CORPORATION

Patent Information

Application Number
CN202310804649.8
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2023-06-30
Publication Date
2024-10-29
Estimated Expiration
2043-06-30

AI Technical Summary

Technical Problem

Existing technology cannot effectively prevent and repair scour pits in offshore wind turbine pile foundations, leading to reduced bearing capacity and the risk of wind turbine tilting or collapse.

Method used

An anti-scouring pit system for offshore wind power pile foundations is designed, including a sand-fixing cover and a sand-proof cover. The sand-fixing cover has an annular structure and is sleeved on the offshore wind power pile foundation to form sand penetration holes and gaps. The positioning part is plugged into the seabed. The anti-sand cover has a flow guide surface to change the direction of water flow, and a multi-layer mesh cover and flow blocking structure to reduce the flow speed.

Benefits of technology

By reducing the flow rate and keeping the sediment within the gap, the protection of offshore wind power pile foundations and the self-repair of scour pits are achieved, which enhances the protection effect, and the system can be disassembled and reused, improving economy.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN116677020B_ABST
    Figure CN116677020B_ABST
Patent Text Reader

Abstract

The present application provides an offshore wind power pile foundation anti-scour pit system, including: a sand fixation cover, which is annular in structure and is sleeved on the offshore wind power pile foundation, the sand fixation cover is formed with sand penetration holes, the sand fixation cover is inclined from the center position of the offshore wind power pile foundation to the edge, so that a gap can be formed between the sand fixation cover and the seabed in the use state, and the edge of the sand fixation cover is sequentially provided with a plurality of positioning parts along the circumferential direction, and the positioning parts are suitable for being inserted on the seabed to fix the sand fixation cover; a sand prevention cover, which has an annular shell, is connected to the top of the sand fixation cover, and is sleeved on the offshore wind power pile foundation; wherein the sand fixation cover is provided with a plurality of sand penetration holes, and the lower surface of the sand fixation cover has a reverse osmosis microstructure to prevent silt from seeping out of the gap through the sand penetration holes. The sand fixation cover can reduce the flow rate, and the silt entering the gap can be retained in the gap through the sand penetration holes and the reverse osmosis microstructure, so that the sand fixation cover can perform anti-scour protection on the offshore wind power pile foundation.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention relates to the technical field of offshore wind power pile foundation protection, and in particular to an offshore wind power pile foundation anti-scour pit system. Background Art

[0002] The diameter of the steel pipe pile foundation of offshore wind power is relatively large. Under the combined effect of factors such as ocean currents, it will cause flow phenomena such as vortices and downwelling currents in the water around the pile foundation. These flow phenomena will wash away the sediment near the pile foundation, and then form obvious scour pits around the pile foundation. The appearance of scour pits reduces the buried depth of the pile foundation, thereby weakening its bearing capacity, causing the risk of wind turbines tilting or even collapsing.

[0003] In the relevant existing technologies, in order to avoid or suppress the problem of scouring of pile foundations, there are currently the following methods: the dumping method, that is, throwing sand bags, stones, concrete components, etc. around the pile foundation to protect the nearby seabed; the geotextile compaction method, which is to cover the pile foundation with sand blankets or interlocking rows to cover the surrounding seabed to prevent the original sand and gravel from being scoured away; the bionic water grass method, which is to anchor the bionic water grass at a predetermined position on the seabed around the pile foundation, and use the water grass's hindering effect on flow to cause the sediment in the seawater to settle; the reserved scouring depth method, which is to increase the buried depth of the wind turbine, and the increased depth is determined based on the situation where the scouring pit depth reaches the maximum.

[0004] Although the above methods can protect the offshore wind power pile foundation to a certain extent, the protective effect is not good. Summary of the invention

[0005] Therefore, the technical problem to be solved by the present invention is to overcome the defect that the protection method of offshore wind power pile foundation in the prior art can only avoid the formation of scour pits to a certain extent, but cannot complete self-repair of the scour pits that have already been formed, thereby providing an offshore wind power pile foundation anti-scour pit system that can both avoid the formation of scour pits and complete self-repair of scour pits.

[0006] In order to solve the above technical problems, the present invention provides an offshore wind power pile foundation anti-scour pit system, including: a sand fixation cover, which is annular in structure and is sleeved on the offshore wind power pile foundation, the sand fixation cover is formed with sand penetration holes, the sand fixation cover is inclined from the center position where it is sleeved on the offshore wind power pile foundation to the edge, so that a gap can be formed between the sand fixation cover and the seabed when in use, and the edge of the sand fixation cover is provided with a plurality of positioning portions spaced apart from each other in the circumferential direction, and the positioning portions are suitable for being plugged into the seabed to fix the sand fixation cover; a sand prevention cover, which has an annular shell, the sand prevention cover is connected to the top of the sand fixation cover, and the sand prevention cover is sleeved on the offshore wind power pile foundation.

[0007] Optionally, the annular structure of the sand fixation cover includes two semi-annular cover body structures, and the two semi-annular cover body structures are detachably connected to enclose the annular structure of the sand fixation cover.

[0008] Optionally, the sand fixation cover includes a fixing ring and a multi-layer mesh cover, the fixing ring is suitable for being sleeved on an offshore wind power pile foundation, the fixing ring has an axis, the multi-layer mesh covers are ring-shaped and respectively connected to the fixing ring, and are arranged in sequence and spaced apart from each other along the extension direction of the axis of the fixing ring; wherein the positioning portion passes through the multi-layer mesh covers in sequence.

[0009] Optionally, the mesh cover includes a frame and a protective net, the frame is connected to the fixing ring, and the protective net is connected to the frame, and in use, the structural strength of the frame located at the top of the mesh cover is greater than the structural strength of the frame of other mesh covers.

[0010] Optionally, the skeleton includes: an inner ring suitable for being sleeved on the fixed ring; a radial support structure, one end of which is connected to the inner ring, and a plurality of the radial support structures are arranged in a ring direction; an outer ring, which is connected to the other end of the radial support structure, and the outer ring is provided with a plurality of connecting holes in a ring direction for cooperating with the positioning portion; wherein the radial support structure is inclined from the inner ring to the outer ring, the positioning portion is provided on the outer ring, and the protective net is connected to two adjacent radial support structures, the inner ring and the outer ring, and a plurality of the protective nets are connected to form a ring.

[0011] Optionally, in use, the inner ring of the skeleton of the mesh cover close to the sand-proof cover and the radial support structure are respectively composed of a corrosion-resistant metal material and a glass fiber structure coated on the outside of the corrosion-resistant metal material.

[0012] Optionally, a flow-blocking structure is provided on the upper surface of the protective net, and the flow-blocking structure is arranged perpendicular to the upper surface of the protective net.

[0013] Optionally, the fixing ring includes two semi-ring bodies, and the ends of the semi-ring bodies are provided with slots, so that the two semi-ring bodies are connected into a ring structure through the slots.

[0014] Optionally, the outer wall of the middle portion of the positioning portion is concave to form an annular groove, and the multiple layers of the mesh covers are sequentially sleeved on the annular groove.

[0015] Optionally, the positioning portion includes: a connecting portion; a clamping portion, arranged above the connecting portion; a wedge-shaped portion, arranged below the connecting portion; a fastener, passing through the clamping portion and the connecting portion and connecting the wedge-shaped portion; wherein the clamping portion, the connecting portion and the wedge-shaped portion together constitute an annular groove.

[0016] Optionally, the sand fixation cover is provided with a plurality of sand penetration holes, and the lower surface of the sand fixation cover has a reverse osmosis microstructure to prevent silt from seeping out of the sand penetration holes from the gaps.

[0017] Optionally, the outer wall of the sand-proof cover has a guide surface, and the guide surface extends from top to bottom to the outside to form an arc shape for horizontal guidance.

[0018] The technical solution of the present invention has the following advantages:

[0019] 1. The offshore wind power pile foundation anti-scour pit system provided by the present invention can reduce the flow velocity by utilizing the inclined setting of the sand fixation cover, and the silt entering the gap can be retained in the gap through the sand penetration hole, so that the silt entering the gap can protect the offshore wind power pile foundation.

[0020] 2. The offshore wind power pile foundation anti-scour pit system provided by the present invention provides a guide surface on the outer wall of the sand-proof cover, and the guide surface extends from the top to the bottom to the outside to form an arc to perform horizontal diversion, so that the water flow impacting the sand-proof cover can change direction and finally flow out in a horizontal direction, thereby reducing the water flow flowing along the outer wall of the sand-proof cover to the sand-fixing cover, avoiding the flow phenomenon that causes scour.

[0021] 3. The offshore wind power pile foundation anti-scour pit system provided by the present invention has a better protection effect through multi-layer mesh covers.

[0022] 4. The offshore wind power pile foundation anti-scour pit system provided by the present invention can further reduce the flow velocity by arranging a flow-blocking structure on the upper surface of the mesh cover, so that the sand-fixing cover has a better protective effect.

[0023] 5. The offshore wind power pile foundation anti-scour pit system provided by the present invention has a sand fixation cover which is configured as two semi-ring cover structures. The two semi-ring cover structures are detachably connected to enclose an annular structure of the sand fixation cover. When installing the sand fixation cover, the two semi-ring cover structures can be respectively clamped on the offshore wind power pile foundation from two opposite sides of the offshore wind power pile foundation, and then the two semi-ring cover structures can be fixed, thereby realizing the installation and fixation of the sand fixation cover, which is more convenient.

[0024] 6. The offshore wind power pile foundation anti-scour pit system provided by the present invention increases the adaptability of the positioning part by configuring the positioning part into a connecting part, a pressing part and a wedge-shaped part, and connecting them through fasteners, so that the number of mesh covers that can be fixed by the positioning part can be adjusted by increasing or decreasing the connecting part.

[0025] 7. The offshore wind power pile foundation anti-scour pit system provided by the present invention can lift and recycle the sand-fixing cover and the sand-proof cover, thereby improving the economic efficiency. BRIEF DESCRIPTION OF THE DRAWINGS

[0026] In order to more clearly illustrate the specific implementation methods of the present invention or the technical solutions in the prior art, the drawings required for use in the specific implementation methods or the description of the prior art will be briefly introduced below. Obviously, the drawings described below are some implementation methods of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0027] Figure 1 A schematic structural diagram of an offshore wind power pile foundation anti-scour pit system provided in an embodiment of the present invention;

[0028] Figure 2 A schematic structural diagram of an offshore wind power pile foundation anti-scour pit system provided in another embodiment of the present invention;

[0029] Figure 3 It is a schematic diagram of the upward structural view of a mesh cover of an offshore wind power pile foundation anti-scour pit system provided in one embodiment of the present invention;

[0030] Figure 4 A schematic diagram of the structure of a mesh cover of an offshore wind power pile foundation anti-scour pit system provided in another embodiment of the present invention, viewed from above;

[0031] Figure 5 It is a schematic diagram of a partially enlarged structure of a protective net of an offshore wind power pile foundation anti-scour pit system provided in one embodiment of the present invention;

[0032] Figure 6 It is a schematic diagram of the top view of the structure of the fixing ring of the anti-scour pit system of the offshore wind power pile foundation provided in one embodiment of the present invention before installation;

[0033] Figure 7 It is a schematic diagram of the top view of the structure of the fixing ring of the offshore wind power pile foundation anti-scour pit system after installation provided in one embodiment of the present invention;

[0034] Figure 8 A schematic cross-sectional view of a fixing ring of an offshore wind power pile foundation anti-scour pit system provided in one embodiment of the present invention;

[0035] Fig. 9 It is a schematic cross-sectional structure diagram of a positioning part of an offshore wind power pile foundation anti-scour pit system provided in one embodiment of the present invention.

[0036] Description of reference numerals:

[0037] 1-sand fixation cover; 2-sand cover; 3-offshore wind power pile foundation; 4-seabed; 5-gap; 6-elastic pad;

[0038] 11-fixing ring; 12-net cover; 13-positioning part;

[0039] 111-semi-ring body; 112-slot; 113-shock-absorbing layer;

[0040] 121-frame; 122-protective net; 123-fixing ring;

[0041] 1211-inner ring; 1212-radial support structure; 1213-outer ring;

[0042] 1221- flow blocking structure;

[0043] 131-connecting portion; 132-pressing portion; 133-wedge-shaped portion; 134-fastening member;

[0044] 1301- Annular groove;

[0045] 21- Guide surface. DETAILED DESCRIPTION

[0046] The technical solution of the present invention will be described clearly and completely below in conjunction with the accompanying drawings. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0047] In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicating the orientation or positional relationship, are based on the orientation or positional relationship shown in the drawings, and are only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the device or element referred to must have a specific orientation, be constructed and operated in a specific orientation, and therefore cannot be understood as limiting the present invention. In addition, the terms "first", "second", and "third" are used for descriptive purposes only, and cannot be understood as indicating or implying relative importance.

[0048] In the description of the present invention, it should be noted that, unless otherwise clearly specified and limited, the terms "installed", "connected", and "connected" should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection, or it can be indirectly connected through an intermediate medium, or it can be the internal communication of two components. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.

[0049] In addition, the technical features involved in the different embodiments of the present invention described below can be combined with each other as long as they do not conflict with each other.

[0050] Application Overview

[0051] The steel pipe pile foundation of offshore wind power faces the problem of seawater scouring, which affects the normal operation of wind turbines. The existing methods for suppressing seawater scouring are mostly passive suppression methods, and there are different problems.

[0052] For offshore wind turbines buried at a greater depth, the dumping and filling method has poor filling accuracy, and there are problems such as fill loss and poor protective layer forming effect. In addition, this method is more suitable for sea areas with clear water quality, and it is difficult to observe the dumping and filling effect in sea areas with low visibility;

[0053] Geotextile method: the sand used in this method will suffer great loss during repeated washing by seawater, so the long-term reliability of this method is low;

[0054] Bionic water grass method: The sedimentation effect of bionic water grass on the sediment in the seawater makes it suitable for sea areas with high sediment content. However, it will not be able to form an effective sediment cover layer in sea areas with fast seabed flow, low sediment content and small sand particle size.

[0055] The reserved scour depth method increases the length of the wind turbine, which will increase the construction cost of the offshore wind turbine to a certain extent. In addition, this method allows the formation of scour pits, which will have a negative impact on the fixation of the submarine cables connected to the wind turbine.

[0056] The above method has its own shortcomings such as difficulty in implementation, low reliability and high cost. In addition, its main purpose is to avoid the formation of scour pits, but it has no effect on repairing scour pits that have already been formed.

[0057] Example 1

[0058] like Figure 1 and Figure 2 A specific implementation of an anti-scour pit system for an offshore wind power pile foundation is shown, and the anti-scour pit system for an offshore wind power pile foundation includes: a sand fixation cover 1 and a sand prevention cover 2. The sand fixation cover 1 is annular and is sleeved on the offshore wind power pile foundation 3. The sand fixation cover 1 is formed with sand penetration holes. The sand fixation cover 1 is inclined from the center position where it is sleeved on the offshore wind power pile foundation 3 to the edge, so that a gap 5 can be formed between the sand fixation cover 1 and the seabed 4 when in use. A plurality of positioning portions 13 are sequentially spaced from each other along the circumferential direction along the edge of the sand fixation cover 1, and the positioning portions 13 are suitable for being plugged into the seabed 4 to fix the sand fixation cover 1. The sand prevention cover 2 has an annular shell, and the sand prevention cover 2 is connected to the top of the sand fixation cover 1, and the sand prevention cover 2 is sleeved on the offshore wind power pile foundation 3.

[0059] The above-mentioned sand fixation cover 1 is connected with the offshore wind power pile foundation 3 to form an umbrella-shaped structure, so that the sand fixation cover 1 can reduce the flow rate. When there is seawater impact, the seawater flows downward along the slope of the sand fixation cover 1, which can reduce the flow rate, so that the silt can flow down from the sand penetration holes and enter the gap 5 between the sand fixation cover 1 and the seabed 4. For the units that have not formed scour pits, anti-scour protection is provided. For the units that have formed scour pits, it can also be used to settle the silt in the surrounding seawater and fill and repair the scour pits.

[0060] The lower surface of the sand-fixing cover 1 has a reverse osmosis microstructure to prevent silt from seeping out of the sand-penetrating holes from the gap 5. By using the reverse osmosis microstructure on the lower surface of the sand-fixing cover 1, for example, the reverse osmosis membrane has such a reverse osmosis microstructure, so that the silt entering the gap 5 can remain in the gap 5 instead of flowing out from the sand-penetrating holes, so that the silt entering the gap 5 can fill the scour pit that has been formed and complete self-repair. The anti-sand cover 2 is sleeved on the wind turbine unit and hoisted on the sand-fixing cover 1 to prevent the silt in the seawater from settling into the gap between the sand-fixing cover 1 and the wind turbine unit. An elastic pad 6 is provided between the sand-fixing cover 1 and the anti-sand cover 2 to form a better sealing effect.

[0061] Furthermore, since the sand fixing cover 1 needs to be hoisted from above when it is set up as a whole, so as to install the sand fixing cover 1 on the offshore wind power pile foundation 3, which makes the installation inconvenient. Therefore, the annular structure of the sand fixing cover 1 includes two semi-annular cover body structures, and the two semi-annular cover body structures are detachably connected to enclose the annular structure of the sand fixing cover 1. When installing the sand fixing cover 1, the two semi-annular cover body structures can be respectively clamped on the offshore wind power pile foundation 3 from two opposite sides of the offshore wind power pile foundation 3, and then the two semi-annular cover body structures are fixed, so that the installation and fixation of the sand fixing cover 1 can be realized, which is more convenient.

[0062] Furthermore, if Figure 2 As shown, the sand fixation cover 1 includes a fixing ring 11 and a multi-layer mesh cover 12. The fixing ring 11 is suitable for being sleeved on the offshore wind power pile foundation 3. The fixing ring 11 has an axis. The multi-layer mesh cover 12 is annular and respectively connected to the fixing ring 11, and is arranged in sequence and spaced apart from each other along the extension direction of the axis of the fixing ring 11; wherein the positioning portion 13 passes through the multi-layer mesh cover 12 in sequence.

[0063] The sand fixation cover 1 may include a fixing ring 11 and a mesh cover 12, and the mesh cover 12 is connected to the fixing ring 11. The fixing ring 11 may play a role in strengthening the structure, and it can be understood that the fixing ring 11 may also be divided into two half rings, and the mesh cover 12 may also be divided into half rings.

[0064] When multiple layers of mesh covers 12 are arranged at a vertical height, the ability to slow down the flow velocity of the seawater around the offshore wind power pile foundation 3 is stronger, and the requirements of adapting to the seabed conditions of different flow states can be met.

[0065] Furthermore, in order to increase the structural strength of the mesh cover 12, the mesh cover 12 includes a frame 121 and a protective net 122, the frame 121 is connected to the fixing ring 11, and the protective net 122 is connected to the frame 121. In the use state, the structural strength of the frame 121 of the mesh cover 12 close to the sand cover 2 is greater than the structural strength of the frame 121 of other mesh covers 12, so that the upper frame 121 can play the role of supporting the entire sand fixation cover 1, playing the role of an "umbrella frame". The protective net 122 includes a polyurethane mesh film, and the membrane-like polyurethane net can retain the reverse osmosis microstructure, which can prevent the silt entering the gap 5 from flowing out of the sand fixation cover 1, so that the silt entering the gap 5 can also form an anti-corrosion layer, which can further protect the seabed 4 around the offshore wind power pile foundation 3 and reduce the sand pit from being washed out.

[0066] like Figure 5 As shown, in order to further reduce the flow rate of water and accelerate the sedimentation, the upper surface of the protective net 122 is provided with a plurality of flow-blocking structures 1221, which are arranged vertically with the upper surface of the protective net 122, and can increase the flow resistance of seawater and reduce the flow rate of seawater. When the flow rate is low, the sand in the seawater will separate from the seawater and no longer flow with the seawater, thereby settling. Among them, the flow-blocking structure 1221 can be a short cilia structure, so as to further increase the resistance of water.

[0067] When the mesh cover 12 is configured to be multi-layered, the protective net 122 uses a low-cost fiber net, which itself has a low manufacturing cost, and the multi-layer fiber net structure arranged at a vertical height has a stronger ability to slow down the flow rate of seawater around the pile foundation and can adapt to seabed conditions with different flow patterns.

[0068] Furthermore, if Figure 3 and Figure 4 As shown, in order to further ensure the structural strength of the sand fixation cover 1, the skeleton 121 includes: an inner ring 1211, a radial support structure 1212 and an outer ring 1213. The inner ring 1211 is suitable for being sleeved on the fixing ring 11 to facilitate fixing the protective net 122. The radial support structure 1212 is connected to the inner ring 1211 at one end, and multiple radial support structures 1212 are arranged circumferentially. The outer ring 1213 is connected to the other end of the radial support structure 1212. The outer ring 1213 is circumferentially provided with multiple connecting holes 1214 that are plugged in with the positioning part 13, wherein the radial support structure 1212 is inclined from the inner ring 1211 to the outer ring 1213, and the positioning part 13 is arranged on the outer ring 1213. The protective net 122 is connected to two adjacent radial support structures 1212, the inner ring 1211 and the outer ring 1213, and multiple protective nets 122 are connected to form a ring. The mesh holes of the protective net 122 form sand-permeable holes, and the reverse osmosis microstructure is arranged on the lower surface of the protective net 122 .

[0069] The inner ring 1211, radial support structure 1212 and outer ring 1213 can be made of materials with a certain hardness, so as to ensure the rigidity requirements of the sand fixation cover 1, and enable the sand fixation cover 1 to be more firmly fixed on the seabed 4, so as to prevent the sand fixation cover 1 from being invalidated by the impact of seawater, and the mesh of the protective net 122 forms sand penetration holes. Among them, the radial support structure 1212 adopts a rod-shaped structure, which can form the main skeleton of the sand fixation cover 1, the inner ring 1211 is mainly used to be fixed on the offshore wind power pile foundation 3, and the positioning part 13 is arranged on the outer ring 1213, which can ensure that the positioning part 13 can be firmly inserted into the seabed 4.

[0070] like Figure 3 As shown, the frame 121 of the mesh cover 12 near the sand-proof cover 2 can be circumferentially provided with a plurality of radial support structures 1212 to ensure that the frame 121 on the upper part of the sand-fixing cover 1 can play a supporting role for the entire sand-fixing cover 1. Figure 3 As shown, the skeleton 121 of the lower multi-layer mesh cover 12 can be provided with at least two radial support structures 1212 to simplify the structure of the lower mesh cover 12. Of course, the skeleton 121 of the lower mesh cover 12 can also be provided with multiple radial support structures 1212. Among them, the inner ring 1211 and the outer ring 1213 can both support the semi-ring structure, which will not be repeated here.

[0071] When installing the sand fixation cover 1, take the hoisting method as an example, the inner ring 1211 of the sand fixation cover 1 is installed on the wind power pile foundation. When the sand fixation cover 1 includes a multi-layer mesh cover 12, the fixing ring 11 is installed on the pile foundation, and then the multi-layer mesh cover 12 is sequentially installed on the fixing ring 11. The hoisting pile foundation is placed in the seawater, and the inner ring 1211 is lifted by a cable to slowly fall. When it is close to the seabed 4, the cable is released to make the sand fixation cover 1 fall. By using the effect of gravity, the sand fixation cover 1 has a certain landing speed, so that the positioning part 13 can be inserted into the seabed 4 to a certain depth, so that the sand fixation cover 1 is firmly positioned on the seabed 4.

[0072] Furthermore, in the use state, the inner ring 1211 and the radial support structure 1212 of the skeleton 121 of the mesh cover 12 close to the anti-sand cover 2 are respectively composed of a corrosion-resistant metal material and a glass fiber structure coated on the outside of the corrosion-resistant metal material. Among them, the corrosion-resistant metal material can include a glass fiber structure of corrosion-resistant steel, and the protective net 122 is a fiber net. The fiber net only plays the role of reducing the flow rate of seawater. The glass fiber structure lined with corrosion-resistant steel is used as the material of the inner ring 1211 and the radial support structure 1212 of the top skeleton 121, which can ensure the structural strength of the sand fixation cover 1. The inner ring 1211 and the radial support structure 1212 of the lower skeleton 121 can be made of polymer materials such as polyurethane with reduced density. The protective net 122 can be a mesh membrane made of materials such as polyurethane, and the outer ring 1213 can be made of polymer materials such as polyurethane, and there are round holes on the outer ring 1213 for connecting with the positioning solid 13.

[0073] Furthermore, if Figure 6 and Figure 7 As shown, the fixing ring 11 includes two semi-ring bodies 111, and the ends of the semi-ring bodies 111 are provided with a slot 112, so that the two semi-ring bodies 111 are connected into a ring structure through the slot 112. Among them, the two semi-ring bodies 111 are snap-fitted and connected through the slot 112 set at the ends, which is convenient for installing the fixing ring 11 on the offshore wind power pile foundation 3, and is also convenient for disassembly. Among them, the slot 112 includes a groove and a protruding structure, and when the two semi-ring bodies 111 are connected, the groove of the slot 112 of one semi-ring body 111 is matched with the protruding structure of the slot 112 of the other semi-ring body 111, and the protruding structure of the slot 112 of one semi-ring body 111 is matched with the groove of the slot 112 of the other semi-ring body 111, thereby forming a mutually engaged connection structure. A shock-absorbing layer 113 is also provided on the inner side of each semi-ring body 111 to reduce the adverse effects of the offshore wind power pile foundation 3 on the sand fixation cover 1 when vibrating.

[0074] like Figure 8 As shown, an annular snap-fit ​​groove is provided on the outer periphery of the fixing ring 11, and the snap-fit ​​groove can be used to install the inner ring 1211, so that the inner ring 1211 is nested on the fixing ring 11, and the inner ring 1211 can be more firmly positioned. When the fixing ring 11 can be divided into two parts, the inner ring 1211 can also be divided into two parts, wherein the two inner rings 1211 of the frame 121 of the mesh cover 12 at the top can be connected by bolts, and the two inner rings 1211 of the frame 121 of the mesh cover 12 at the bottom can be made of polyurethane with lower density, so they can be fastened by tying. The bottom of the fixing ring 11 is provided with a nested fixing ring sleeve 123, and the fixing ring sleeve 123 can also be divided into two parts. The structure of the fixing ring sleeve 123 is made of a material with high structural strength and can also be fastened by bolts.

[0075] Furthermore, if Fig. 9 As shown, the outer wall of the middle part of the positioning part 13 is concave to form an annular groove 1301, and the multi-layer mesh cover 12 is sequentially sleeved on the annular groove 1301. The annular groove 1301 can limit the mesh cover 12 sleeved on the positioning part 13, so that the mesh cover 12 is not easy to be separated from the positioning part 13. Among them, a gasket 135 is provided between the multi-layer mesh covers 12 below the top mesh cover 12, and the gasket 135 can play the role of isolating two adjacent mesh covers 12.

[0076] In order to ensure that the positioning portion 13 can be inserted into a deeper depth of the seabed 4 , the positioning portion 13 has a wedge-shaped structure.

[0077] Among them, the multiple positioning parts 13 can be arranged in a one-to-one correspondence with the multiple radial support structures 1212 , and the radial support structures 1212 are connected to the positioning parts 13 .

[0078] The above-mentioned positioning part 13 can be a fixed wedge made of corrosion-resistant steel. The bottom of the wedge-shaped structure of the positioning part 13 can be an inverted cone with a pointed bottom. When the sand fixation cover 1 falls, the positioning part 13 with a wedge-shaped structure can be more easily inserted into the seabed 4 and inserted to a certain depth.

[0079] Further, continue to combine Fig. 9 As shown, in order to adjust the number of layers of the mesh cover 12, the positioning part 13 includes: a connecting part 131, a pressing part 132, a wedge-shaped part 133 and a fastener 134, the pressing part 132 is arranged above the connecting part 131, the wedge-shaped part 133 is arranged below the connecting part 131, and the fastener 134 penetrates the pressing part 132 and the connecting part 131 and connects the wedge-shaped part 133, wherein the pressing part 132, the connecting part 131 and the wedge-shaped part 133 together constitute an annular groove 1301. If it is necessary to increase the number of layers of the mesh cover 12, it can be achieved by adding a connecting part 131. The fastener 134 can be a bolt. Specifically, the circular holes of the multi-layer outer ring 1213 can be sleeved on the annular groove 1301, and the top of the wedge-shaped part 133 and the bottom of the pressing part 132 can form a step to form a limit for the outer ring 1213. The outer ring 1213 of the first layer of mesh cover 12 at the top has a relatively large thickness, which can increase the structural strength of the overall structure.

[0080] Further, continue to combine Figure 2 As shown, since the sand-proof cover 2 is arranged on the upper part of the sand-fixing cover 1, when the water flow hits the sand-proof cover 2, it will flow downward along the outer wall of the sand-proof cover 2 and hit the sand-fixing cover 1. Therefore, the outer wall of the sand-proof cover 2 has a guide surface 21, and the guide surface 21 extends from the top to the bottom to the outside to form an arc for horizontal diversion, so that the water flow hitting the sand-proof cover 2 can change direction and finally flow out in a horizontal direction, thereby reducing the water flow flowing along the outer wall of the sand-proof cover 2 to the sand-fixing cover 1, avoiding the occurrence of flow phenomena that cause scouring.

[0081] Specifically, the bottom of the sand-proof cover 2 is cylindrical, and the outer wall of the upper portion of the sand-proof cover 2 has an inwardly concave arc-shaped structure, which naturally transitions to the cylindrical structure of the bottom.

[0082] The above-mentioned offshore wind power pile foundation anti-scour pit system can have two functions of suppressing the formation of scour pits and providing scour pit modification, which can be achieved by a sand fixation cover 1 with a single mesh cover structure or a multi-layer mesh cover structure.

[0083] The sand fixation cover 1 is composed of a steel frame structure, a polyurethane net and a fixed wedge covering it. A wedge-shaped space, i.e., a gap 5, is left between the polyurethane net and the seabed 4. The sediment settled in the seawater flowing through it can fall into the wedge-shaped space through the mesh, which helps the sediment to settle, fill the existing scour pits, or form an anti-corrosion layer.

[0084] The existing methods are limited by the seabed environment, resulting in poor scour pit suppression effect and inability to be reused. The present application enables the sand fixation cover and the sand prevention cover to be hoisted and recovered, thereby being reused and improving economic efficiency.

[0085] In another embodiment, when the system is installed, the sand fixation cover 1 and the sand control cover 2 are installed in sequence from bottom to top. The central support rings of the sand control cover 2 and the sand fixation cover 1 are both hollow ring structures, and the inner ring diameter is larger than the offshore wind power pile foundation 3. When installed, the above two structures are sequentially placed on the offshore wind power pile foundation 3, and slowly sunk to the seabed by means of a crane or by bundling floating objects such as air bags.

[0086] The main function of the sand-fixing cover 1 is to protect the seabed sediment under the cover and prevent it from being washed away by seawater. In addition, there is a wedge-shaped space between the multi-layer fiber net of the sand-fixing cover 1 and the seabed, and the settled sediment can further fall into the wedge-shaped space. Due to the structure of the sand-fixing cover fiber net of the sand-fixing cover 1, the settled sediment is difficult to flow out, so a protective layer can be formed.

[0087] The cover structure of the sand-fixing cover 1 includes a multi-layer fiber net and a cover net structure, that is, the multi-layer net cover is divided into a cover net structure and a multi-layer fiber net. The cover net structure is located at the top, and the support structure of the cover net structure needs to bear the weight of the overall sand-fixing cover 1. The support structure of the cover net structure adopts a glass fiber structure lined with corrosion-resistant steel, while the multi-layer fiber net only plays the role of reducing the flow rate of seawater, and its support structure is a polymer material such as polyurethane with reduced density. The multi-layer fiber net structure arranged at a vertical height has a stronger ability to slow down the flow rate of seawater around the pile foundation and can adapt to the seabed conditions of different flow states. The inner ring of the cover net structure is also made of a glass fiber material lined with corrosion-resistant steel, and the inner ring of the fiber net is a polymer material such as polyurethane. The outer ring structure is made of a polymer material such as polyurethane, and there are round holes on it for connection with a fixed wedge. Both the fiber net and the cover net structure are structures spliced ​​by two upper and lower semicircular nets. When installed, the two parts are spliced ​​and fastened on the wind turbine tower for use.

[0088] The fiber net surface of the sand-fixing cover 1 and the cover net structure has a short cilia structure, which can increase the flow rate of seawater flowing through it, so that the sediment therein slows down and settles.

[0089] The outer circular holes of the fiber net and the cover net structure are aligned, and the fixing wedges pass through the circular holes to fix them. When more layers of fiber net need to be installed, the number of the middle parts of the fixing wedges can be increased. The bottom of the fixing wedge has a pointed cone bottom end for inserting into the seabed to fix the entire system.

[0090] The fiber net and cover net structure are both installed on the center ring, which is also a two-part connected structure. When the system is installed at sea, the two center ring halves, one fixed and the other from top to bottom, allow the installation slots to be inserted into each other and form a complete center ring structure.

[0091] After the central ring structure is connected, the two parts of each layer of the multi-layer fiber net and the cover net structure are connected and nested in the outer groove. The inner ring sleeve of the cover net and the fixed ring sleeve are fastened by reliable means such as bolt connection, and the inner ring sleeve of the fiber net can be fastened by binding or the like.

[0092] It can be seen that the sand-fixing cover 1 and the anti-sand cover 2 can be hoisted, recovered, and reused, with good economic benefits.

[0093] Obviously, the above embodiments are only examples for clear explanation, and are not intended to limit the implementation methods. For those skilled in the art, other different forms of changes or modifications can be made based on the above description. It is not necessary and impossible to list all the implementation methods here. The obvious changes or modifications derived from this are still within the protection scope of the invention.

Claims

1. An offshore wind power pile foundation anti-scour pit system, characterized in that: include: A sand fixation cover (1) is annular in structure and is sleeved on an offshore wind power pile foundation (3). The sand fixation cover (1) is formed with sand penetration holes. The sand fixation cover (1) is inclined from the center position where it is sleeved on the offshore wind power pile foundation (3) to the edge, so that a gap (5) can be formed between the sand fixation cover (1) and the seabed (4) in a use state. The edge of the sand fixation cover (1) is provided with a plurality of positioning parts (13) spaced from each other in sequence along the circumferential direction. The positioning parts (13) are suitable for being inserted on the seabed (4) to fix the sand fixation cover (1). The sand fixation cover (1) comprises a fixing ring (11) and a multi-layer mesh cover (12). The fixing ring (11) is suitable for being sleeved on the offshore wind power pile foundation (3). The fixing ring (11) has an axis. The multi-layer mesh covers (12) are annularly connected to the fixing ring (11) and extend along the axis of the fixing ring (11). The plurality of mesh covers (12) are arranged in sequence and spaced apart from each other; wherein the positioning portion (13) passes through the plurality of layers of the mesh covers (12) in sequence; the outer wall of the middle portion of the positioning portion (13) is concave inward to form an annular groove (1301); the plurality of layers of the mesh covers (12) are sleeved on the annular groove (1301) in sequence; the positioning portion (13) comprises a connecting portion (131), a pressing portion (132), a wedge-shaped portion (133) and a fastener (134); the pressing portion (132) is arranged above the connecting portion (131); the wedge-shaped portion (133) is arranged below the connecting portion (131); the fastener (134) passes through the pressing portion (132) and the connecting portion (131) and connects the wedge-shaped portion (133); wherein the pressing portion (132), the connecting portion (131) and the wedge-shaped portion (133) together constitute the annular groove (1301); The sand-proof cover (2) has an annular shell, the sand-proof cover (2) is connected to the top of the sand-fixing cover (1), and the sand-proof cover (2) is sleeved on the offshore wind power pile foundation (3).

2. The offshore wind power pile foundation anti-scour pit system according to claim 1, characterized in that: The annular structure of the sand fixation cover (1) comprises two semi-annular cover body structures, and the two semi-annular cover body structures are detachably connected to enclose the annular structure of the sand fixation cover (1).

3. The offshore wind power pile foundation anti-scour pit system according to claim 1, characterized in that: The mesh cover (12) comprises a frame (121) and a protective net (122); the frame (121) is connected to the fixing ring (11), and the protective net (122) is connected to the frame (121); in a use state, the structural strength of the frame (121) located at the top of the mesh cover (12) is greater than the structural strength of the frame (121) of other mesh covers (12).

4. The offshore wind power pile foundation anti-scour pit system according to claim 3, characterized in that: The skeleton (121) comprises: An inner ring (1211) adapted to be sleeved on the fixing ring (11); A radial support structure (1212), one end of which is connected to the inner ring (1211), and a plurality of radial support structures (1212) are arranged in an annular direction; An outer ring (1213) connected to the other end of the radial support structure (1212), the outer ring (1213) being provided with a plurality of connection holes (1214) in an annular direction and being plugged in and matched with the positioning portion (13); Wherein, the radial support structure (1212) is inclined from the inner ring (1211) to the outer ring (1213), the positioning portion (13) is arranged on the outer ring (1213), the protective net (122) is connected to two adjacent radial support structures (1212), the inner ring (1211) and the outer ring (1213), and a plurality of the protective nets (122) are connected to form a ring.

5. The offshore wind power pile foundation anti-scour pit system according to claim 4, characterized in that: In use, the inner ring (1211) of the skeleton (121) of the mesh cover (12) close to the sand-proof cover (2) and the radial support structure (1212) are respectively composed of a corrosion-resistant metal material and a glass fiber structure coated on the outside of the corrosion-resistant metal material.

6. The offshore wind power pile foundation anti-scour pit system according to claim 3, characterized in that: The upper surface of the protective net (122) is provided with a flow-blocking structure, and the flow-blocking structure is arranged perpendicular to the upper surface of the protective net (122).

7. The offshore wind power pile foundation anti-scour pit system according to any one of claims 1 to 6, characterized in that: The fixing ring (11) comprises two semi-ring bodies (111), and the ends of the semi-ring bodies (111) are provided with clamping grooves (112), so that the two semi-ring bodies (111) are connected to form a ring structure through the clamping grooves (112).

8. The offshore wind power pile foundation anti-scour pit system according to any one of claims 1 to 6, characterized in that: The sand fixation cover (1) is provided with a plurality of sand penetration holes, and the lower surface of the sand fixation cover (1) has a reverse osmosis microstructure to prevent silt from seeping out of the sand penetration holes from the gap (5).

9. The offshore wind power pile foundation anti-scour pit system according to any one of claims 1 to 6, characterized in that: The outer wall of the sand-proof cover (2) has a flow-guiding surface (21), and the flow-guiding surface (21) extends from top to bottom to form an arc shape for horizontal flow guidance.

Citation Information

Patent Citations

  • Anti-scouring system of offshore wind power pile foundation

    CN113152504A

  • Offshore foundation scouring multi-protection system

    CN114108706A

Cited By

  • Anti-scouring device for offshore wind power foundation

    CN120174910A