Pumping type dewatering well, construction method of dewatering well and reconstruction method
Through the design of closed tube wells and telescopic drainage pipes, the problem of foundation pit dewatering wells causing damage to the foundation cushion and waterproofing is solved, effective dewatering below the foundation cushion is achieved, ensuring the integrity and waterproofing of the building, and Saves construction time and cost.
Patent Information
- Application Number
- CN202310720953.4
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2023-06-16
- Publication Date
- 2024-10-01
- Estimated Expiration
- 2043-06-16
AI Technical Summary
When the excavation depth of the foundation pit exceeds the groundwater level, the existing dewatering well design can easily destroy the integrity and waterproofness of the foundation cushion, affecting the integrity and waterproofing effect of the building.
Use closed tube wells and telescopic drainage pipes. The closed tube wells are buried under the foundation cushion. The groundwater is pumped out through the telescopic drainage pipes to ensure that the entire precipitation and drainage process is completed below the foundation cushion to avoid damage to the foundation cushion and waterproof membrane. .
It achieves effective precipitation without damaging the integrity and waterproofness of the building foundation, reduces construction difficulty and cost, and saves construction period and resources.
Smart Images

Figure CN117947803B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the field of foundation pit dewatering technology, and in particular to a pumping dewatering well, a construction method of the dewatering well, and a modification method thereof. Background Art
[0002] When the excavation depth of the foundation pit exceeds the groundwater level, precipitation treatment is required during the excavation and construction of the foundation pit. Common precipitation measures are to dig a precipitation well connected to the groundwater from the bottom of the foundation pit to balance the water pressure and pump water out through the precipitation well to prevent groundwater from surging after rain. When the building load meets the anti-floating requirements, the groundwater level drops, and the precipitation well within the building foundation slab is then filled and sealed.
[0003] However, in order to facilitate the pumping of water from the top of the precipitation well, the top of the precipitation well will be higher than the design elevation of the foundation cushion layer, so that the precipitation well protrudes from the bottom wall of the foundation pit. When the foundation cushion layer is constructed later and the waterproof membrane is laid, the protruding precipitation well will interrupt the cushion layer and destroy the integrity of the cushion layer, or even puncture the waterproof membrane, thus affecting the foundation waterproofing. The sealing sleeve protruding from the foundation cushion layer will also interfere with the arrangement of the through-length reinforcement of the foundation bottom plate. Summary of the invention
[0004] In order to enable the precipitation well to achieve effective precipitation without destroying the integrity and waterproofness of the building foundation, the present application provides a pumping precipitation well, a precipitation well construction method and a precipitation well renovation method.
[0005] In the first aspect, the present application provides a pumping type precipitation well, which adopts the following technical solution:
[0006] A pumping type precipitation well, comprising:
[0007] A closed pipe well, comprising a well body and a sealing cover, wherein the sealing cover is covered at the well mouth of the well body, the sealing cover is buried in the soil below the elevation of the foundation cushion layer, and a drainage hole is opened on the closed pipe well;
[0008] The drainage device includes a telescopic drainage pipe and a pumping device. One end of the telescopic drainage pipe extends into the closed pipe well through the drainage hole, and the other end of the telescopic drainage pipe is connected to the pumping device for draining water from the closed pipe well to the outside. The telescopic drainage pipe is buried in the soil below the elevation of the foundation cushion layer. When filling the closed pipe well, the telescopic drainage pipe can be extended and serve as a grouting pipe.
[0009] By adopting the above technical solution, a closed pipe well with drainage holes is buried in the soil below the design elevation of the foundation cushion layer, and the telescopic drainage pipe of the drainage device is extended into the closed pipe well through the drainage hole, and the telescopic drainage pipe is also buried in the soil below the design elevation of the foundation cushion layer, and then the water is drained out using a pumping device. The groundwater in the closed pipe well is horizontally discharged from the soil layer to the outside of the foundation bottom plate, and the entire precipitation and drainage process is completed below the design elevation of the foundation cushion layer, so that effective precipitation can be achieved without destroying the integrity and waterproofness of the building foundation.
[0010] The telescopic drain pipe is used as a drainage pipe. When filling the closed pipe well, the telescopic drain pipe can also serve as a grouting pipe. The telescopic drain pipe is extended to a position where the pipe mouth is close to the bottom of the closed pipe well. During the grouting process, the telescopic drain pipe gradually contracts upward, which can make the concrete slurry poured into the closed pipe well more compact.
[0011] Optionally, the drainage hole is opened on the sealing cover, and the telescopic drainage pipe includes a water absorption section and a water guiding section which are sealed and connected to each other, the water absorption section is inserted into the drainage hole, and the water guiding section extends to the outside of the foundation bottom plate and is connected to the pumping device.
[0012] By adopting the above technical solution, the integrity of the well body can be improved by opening the drainage hole on the sealing cover. There is no need to reserve drainage holes when constructing the well body, thereby reducing the difficulty of well body construction; the water guide section is extended to the outside of the foundation bottom plate and then connected to the pumping device, which can facilitate the placement of the pumping device in the fertilizer tank of the foundation pit. When draining water, the groundwater is sucked out of the closed pipe well through the water suction section, and then drained to the outside of the foundation bottom plate by the water guide section, so that the groundwater level within the foundation bottom plate is maintained at the height required for construction.
[0013] Optionally, the portion of the water suction section below the sealing cover is a bellows, and a water baffle is provided at the mouth of the bellows. When water is pumped upward, the water pressure acts on the water baffle to shrink the bellows.
[0014] By adopting the above technical solution, when pumping water outwards, the water flow impacts the water retaining plate upwards to make the bellows retract as much as possible, so that the mouth of the bellows is separated from the water surface in time after the water level drops, thereby reducing excess drainage; and when grouting inwards, the concrete slurry flows downwards to impact the water retaining plate, so that the bellows stretches, thereby making the mouth of the bellows closer to the bottom of the well body. Starting grouting from the bottom of the well body can make the concrete slurry more compact.
[0015] Optionally, the water baffle is hinged to the inner wall of the bellows, and the bellows is provided with a limiting member for preventing the water baffle from rotating downward.
[0016] By adopting the above technical scheme, the water retaining plate is hinged to the inner wall of the corrugated pipe, and a limiter is arranged on the corrugated pipe to prevent the water retaining plate from rotating downward. When pumping, the water retaining plate rotates upward under the action of water pressure to expand the pumping area, improve the pumping efficiency, and achieve the effect of accelerating the precipitation speed; when grouting, the water retaining plate is blocked by the limiter and cannot rotate downward under the action of the gravity of the slurry, which can make the water retaining plate surface more effectively withstand the impact force of concrete during the grouting stage so that the corrugated pipe can extend.
[0017] Optionally, a guide member is provided between the bellows and the well body, the guide member is fixedly connected to the bellows and slidably connected to the well body, and a sliding groove for the guide member to slide is provided on the inner wall of the well body.
[0018] By adopting the above technical solution, a slide groove is opened on the inner wall of the well body, and a guide member is set between the well body and the bellows. The guide member slides along the slide groove to guide the expansion and contraction of the bellows, thereby avoiding friction between the extended bellows and the inner wall of the well body, resulting in poor expansion and contraction.
[0019] Optionally, the guide member is a guide plate, a slider is provided on the edge of the guide plate, the slider is slidably inserted in the slide groove, and the guide plate is connected between the well body and the bellows to block the gap between the well body and the bellows.
[0020] By adopting the above technical solution, the guide is set as a guide plate with a slider on the edge. The guide plate blocks the gap between the well body and the corrugated pipe, which can prevent the aggregate with larger particle size in the concrete from getting stuck in the gap and hindering the expansion and contraction of the corrugated pipe during grouting.
[0021] Optionally, a reset member is connected between the sealing cover and the guide member, and the reset member is used to retract and reset the bellows.
[0022] By adopting the above technical solution, a reset piece is connected between the sealing cover and the guide piece, and the reset piece plays a role of assisting the contraction of the bellows during the grouting process. The bellows can automatically retract and reset under the action of the reset piece.
[0023] Optionally, the reset member includes a fixedly connected winding wheel and a pull rope, the winding wheel is rotatably connected to the sealing cover, the pull rope is wound on the winding wheel, one end of the pull rope away from the winding wheel is connected to the guide member, and a coil spring is installed on the winding wheel.
[0024] By adopting the above technical solution, the reset member is set in the form of a combination of a reel, a coil spring and a pull rope. When grouting and sealing the well, the elastic force of the coil spring drives the reel to reel in the pull rope, thereby driving the guide member to slide upward along the slide groove, and the corrugated tube gradually retracts, and grouting from bottom to top makes the concrete pouring more dense. Winding the pull rope on the reel can also save space.
[0025] In the second aspect, the present application provides a method for constructing a pumping type precipitation well, which adopts the following technical solution:
[0026] A construction method of a pumping type precipitation well, used to construct the above-mentioned pumping type precipitation well, comprises the following steps:
[0027] S1 Dewatering: digging soil from the ground downward until it connects to groundwater to form a well hole, and pumping water out of the well hole to reduce the water level in the well hole to below the design elevation of the foundation cushion layer;
[0028] S2 Foundation pit excavation: excavate the foundation pit to lower the bottom elevation of the foundation pit to the design elevation of the foundation cushion layer;
[0029] S3 Well construction: providing a sealing cover, supporting a formwork in the well hole and pouring concrete to below the design elevation of the foundation cushion layer to form a well body, closing the sealing cover on the top of the well body to form a closed pipe well, and reserving a drainage hole on the closed pipe well;
[0030] S4 buried pipe: provide telescopic drainage pipe and pumping device, bury the telescopic drainage pipe in the soil below the design elevation of the foundation cushion, insert one end of the telescopic drainage pipe into the drainage hole, and connect the other end to the pumping device;
[0031] S5 Sealing the well: After the building is constructed to meet the anti-floating requirements, the pumping device is removed, and the telescopic drainage pipe is continued to be used as a grouting pipe to pour concrete into the closed pipe well and fill the closed pipe well.
[0032] By adopting the above technical solution, the groundwater is first lowered to below the construction surface, and then the foundation pit is excavated and the closed pipe well and telescopic drainage pipe are buried in the soil below the design elevation of the foundation cushion layer. The entire precipitation and drainage process can be completed below the design elevation of the foundation cushion layer; a pumping device is then set up to cope with the rising water level, and water is pumped out in time to prevent groundwater from suddenly surging, thereby achieving effective precipitation without destroying the integrity and waterproofness of the building foundation.
[0033] In a third aspect, the present application provides a method for transforming a precipitation well, which adopts the following technical solution:
[0034] A method for transforming a precipitation well, used to transform an existing precipitation well into the above-mentioned pumping precipitation well, comprises the following steps:
[0035] S1 Cutting: Provide a sealing cover with drainage holes, cut the existing drainage well, make the wellhead height lower than the design elevation of the foundation cushion layer, and cover the sealing cover at the wellhead of the drainage well to form a closed pipe well;
[0036] S2 buried pipe: provide telescopic drainage pipe and pumping device, bury the telescopic drainage pipe in the soil below the design elevation of the foundation cushion, insert one end of the telescopic drainage pipe into the drainage hole, and connect the other end to the pumping device;
[0037] S3 Well Sealing: After the building is constructed to meet the anti-floating requirements, the pumping device is removed, and the telescopic drainage pipe continues to be used as a grouting pipe to pour concrete into the closed pipe well and fill the closed pipe well.
[0038] By adopting the above technical solution, the existing old-style precipitation wells can be transformed into pumping precipitation wells that will not damage the integrity and waterproofness of the foundation slab, so that the entire precipitation and drainage process can be completed below the design elevation of the foundation cushion. Using the original precipitation wells for transformation can save time for early precipitation and well casting and maintenance, shortening the construction period, reducing waste, and saving costs.
[0039] In summary, the present application includes at least one of the following beneficial technical effects:
[0040] 1. By burying the closed pipe well and the telescopic drainage pipe in the soil below the design elevation of the foundation cushion layer, the entire precipitation and drainage process can be completed below the design elevation of the foundation cushion layer. Then a pumping device is set up to pump water out in time to prevent groundwater from surging, thereby achieving effective precipitation without destroying the integrity and waterproofness of the building foundation slab.
[0041] 2. By transforming the original old-style precipitation wells into pumping precipitation wells that will not damage the integrity and waterproofness of the foundation slab, the entire precipitation and drainage process can be completed below the design elevation of the foundation cushion layer, which can save time for early precipitation and well casting and maintenance, shortening the construction period, reducing waste and saving costs. BRIEF DESCRIPTION OF THE DRAWINGS
[0042] Figure 1 It is a schematic diagram of the structure of the pumping precipitation well in Example 1 of the present application.
[0043] Figure 2 It is a schematic diagram of the internal structure of the closed pipe well in Example 1 of the present application.
[0044] Figure 3 It is a schematic diagram of the guide plate structure of Example 1 of the present application.
[0045] Figure 4 It is a schematic diagram of the reset component structure of Example 1 of the present application.
[0046] Figure 5 This is a flow chart of the construction method of the pumping-type precipitation well in Example 2 of the present application.
[0047] Figure 6This is a flow chart of the transformation method of the precipitation well in Example 3 of the present application.
[0048] Description of reference numerals:
[0049] 10. Foundation pit; 20. Foundation; 201. Cushion; 202. Waterproof membrane; 203. Bottom plate; 1. Closed pipe well; 11. Well body; 111. Slide; 12. Sealing cover; 13. Drain hole; 2. Telescopic drain pipe; 21. Water suction section; 211. Bellows; 22. Water guide section; 3. Pumping device; 4. Water baffle; 5. Limiting member; 6. Guide plate; 61. Sliding block; 7. Resetting member; 71. Winding wheel; 72. Pull rope; 73. Coil spring. DETAILED DESCRIPTION
[0050] The following is combined with Figure 1-6 This application is described in further detail.
[0051] Example 1
[0052] The embodiment of the present application discloses a pumping type precipitation well.
[0053] Reference Figure 1 The pumping type precipitation well includes a closed pipe well 1 and a drainage device, and the closed pipe well 1 is buried in the soil below the foundation pit 10. The top of the closed pipe well 1 is located below the elevation of the cushion layer 201 of the foundation 20, and the excess groundwater in the closed pipe well 1 is pumped out through the drainage device, and is laterally discharged from the soil layer below the foundation pit 10 to the outside of the bottom plate 203 of the foundation 20, thereby avoiding the cushion layer 201, the bottom plate 203 and the waterproof membrane 202 of the foundation 20, and achieving effective precipitation without destroying the integrity and waterproofness of the building foundation 20.
[0054] The common method of dewatering the existing foundation pit 10 is to first set up a circle of dewatering wells around the perimeter of the foundation pit 10 on the ground to balance the water pressure, first lower the groundwater level within the scope of the foundation pit 10 as a whole, and then set up another dewatering well at the bottom of the foundation pit 10 for local dewatering, and dewatering is carried out by cooperating with the dewatering wells inside and outside the foundation pit 10. The drainage device generates power to actively pump water outward, and there is no need to set up dewatering wells around the periphery of the foundation pit 10 in advance, so that effective dewatering can be achieved within the scope of the foundation 20 without adding dewatering wells outside the foundation pit 10, reducing the construction cost of dewatering wells.
[0055] Reference Figure 1 , Figure 2, a closed pipe well 1 includes a well body 11 and a sealing cover 12, the sealing cover 12 covers the wellhead of the well body 11 and the top of the sealing cover 12 is located below the elevation of the cushion layer 201 of the foundation 20. In this embodiment, considering that circular steel pipes are often used for digging wells, in order to facilitate construction, the cross section of the well body 11 is preferably made into a circular shape, and the sealing cover 12 matched with the well body 11 is also preferably made into a circular shape. A drainage hole 13 is opened on the closed pipe well 1, the well body 11 is cast with concrete, and the surrounding wall of the well body 11 is an arc surface. During construction, reserving the drainage hole 13 on the well body 11 will increase the construction difficulty, so the drainage hole 13 is selected to be opened in the center of the sealing cover 12. You can choose to directly purchase a finished flange with holes as the sealing cover 12. In other embodiments, the well body 11 and the sealing cover 12 can also be selected in other shapes according to needs; if you need to save the space at the top of the sealing cover 12, you can also choose to open the drainage hole 13 on the surrounding wall of the well body 11 near one end of the sealing cover 12.
[0056] The drainage device includes a telescopic drainage pipe 2 and a pumping device 3. The telescopic drainage pipe 2 is divided into a water absorption section 21 and a water guide section 22. The water guide section 22 is horizontally buried below the elevation of the cushion layer 201 of the foundation 20, extending from the closed pipe well 1 to the outside of the bottom plate 203 of the foundation 20, and is connected to the pumping device 3 placed in the fertilizer tank of the foundation pit 10. The water guide section 22 is sealed with the water absorption section 21, and the water absorption section 21 is bent downward and inserted into the drainage hole 13 of the sealing cover 12. The pumping device 3 can select a self-priming water pump to provide power for precipitation. In addition to being used for early precipitation, the pumping device 3 can also be used as a defensive drainage measure during the construction process to deal with the sudden rise in water levels caused by excessive rainfall in summer. When the pipe mouth of the telescopic drainage pipe 2 is below the water surface, the pumping device 3 can pump water out in time to maintain the groundwater level below the construction operation surface to prevent groundwater from surging.
[0057] Reference Figure 2 The water guide section 22 and the water absorption section 21 located above the sealing cover 12 are preferably steel pipes with corrosion-resistant paint, while the water absorption section 21 located below the sealing cover 12 can be selected to use a bellows 211, so as to realize the telescopic function of the telescopic drainage pipe 2. In addition to precipitation in the early stage of construction, when the closed pipe well 1 is buried at the end of construction, the telescopic drainage pipe 2 can be extended and used as a grouting pipe. The use state can be switched by extending or contracting the bellows 211, so that one pipe can be used for multiple purposes, thereby greatly improving the utilization rate of the telescopic drainage pipe 2.
[0058] Since excessive extraction of groundwater will damage the ecological environment and cause serious problems such as soil collapse, the ideal state of foundation pit 10 dewatering is to drain as little groundwater as possible so that the groundwater level is maintained below the construction working surface.
[0059] Reference Figure 2, a water retaining plate 4 is installed at the mouth of the bellows 211, so that the telescopic drainage pipe 2 can automatically extend and shorten according to the use requirements. The water flow hits the water retaining plate 4 upward to make the bellows 211 retract as much as possible, so that the mouth of the bellows 211 can be separated from the water surface in time after the water level drops, reducing the excess drainage. The bottom mouth of the bellows 211 can be selected to be slightly lower than the groundwater level limit allowed for construction to avoid the sudden rise of groundwater affecting the construction. When grouting inward, the concrete slurry flows downward to hit the water retaining plate 4, and the bellows 211 is extended, so that the mouth of the bellows 211 is closer to the bottom of the well body 11. As the amount of concrete in the well body 11 gradually increases, the concrete at the bottom of the well body 11 pushes the water retaining plate 4 upward, causing the bellows 211 to gradually retract, and the well body 11 is gradually grouting from bottom to top, so that the concrete slurry is more compact.
[0060] Reference Figure 3 The water baffle 4 is in the shape of a ring sector and is composed of two parts spliced together. The water baffle 4 is hinged to the inner wall of the bellows 211, and the two parts of the water baffle 4 are symmetrically distributed on both sides of the rotating shaft. When pumping water upward, the water pressure drives the water baffle 4 to rotate, expanding the pumping area and improving the pumping efficiency. In order to prevent the water baffle 4 from rotating downward and keep the water baffle 4 in a horizontal position, a limiter 5 fixedly connected to the bellows 211 is provided at the bottom of the water baffle 4.
[0061] Reference Figure 3 Since the bellows 211 is flexible, a guide piece can be provided at the bottom of the bellows 211 to guide the expansion and contraction of the bellows 211, and a slide groove 111 for the guide piece to slide vertically can be provided on the inner wall of the well body 11. Avoid the bellows 211 after extension from rubbing against the inner wall of the well body 11, which may cause poor expansion and contraction. In order to reduce the deadweight, the guide piece is preferably made into a guide plate 6. The guide plate 6 is in the shape of a ring sector and a slider 61 is convexly provided along the outer edge, and the slider 61 is slidably inserted in the slide groove 111. The guide plate 6 is fixedly connected to the bellows 211 by hot melting, welding or gluing, which can play a sealing role. Making the outer edge of the guide plate 6 as close as possible to the inner wall of the well body 11 can block the gap between the well body 11 and the bellows 211, and avoid the aggregate in the concrete from getting stuck in the gap to hinder the expansion and contraction of the bellows 211 during grouting.
[0062] In this embodiment, in order to keep the guide plate 6 receiving balanced, four sliders 61 are evenly distributed along the outer periphery of the guide plate 6, and the slide grooves 111 on the well body 11 are arranged one by one with the sliders 61. In other embodiments, the number of the sliders 61 can also be three, five, etc.
[0063] Reference Figure 2 , Figure 4A reset member 7 is connected between the sealing cover 12 and the guide member to retract and reset the bellows 211. The reset member 7 includes a reel 71 and a pull rope 72. A rotating shaft is fixedly connected to the bottom of the sealing cover 12. The reel 71 is sleeved on the rotating shaft. A coil spring 73 is installed on the reel 71. The coil spring 73 is sleeved on the rotating shaft, and the two ends are respectively connected to the rotating shaft and the reel 71. One end of the pull rope 72 is fixedly connected to the reel 71 and wound on the reel 71. The end of the pull rope 72 away from the reel 71 is fixedly connected to the guide member. During the grouting process, the elastic force of the coil spring 73 drives the reel 71 to reel the pull rope 72, and cooperates with the concrete accumulated at the bottom of the well body 11 to make the guide plate 6 slide upward along the slide groove 111, so that the bellows 211 gradually retracts upward, making the grouting more compact. Winding the pull rope 72 on the reel 71 can also save space. In order to balance the force on the guide plate 6 , two groups of reset members 7 may be symmetrically arranged along the central axis of the guide plate 6 .
[0064] The implementation principle of a pumping type dewatering well in the embodiment of the present application is as follows: before the building meets the anti-floating requirements, the bellows 211 is in a contracted state. When the water level in the well body 11 is higher than the mouth of the bellows 211, the pumping device 3 is started to pump water outward; in the later stage of construction, after the building structure itself can meet the anti-floating requirements, grouting is injected into the well body 11 to seal the well, the pumping device 3 is removed, and the telescopic drainage pipe 2 is continued to be used to pour concrete slurry into the well body 11, and the concrete impacts the water retaining plate 4 downward, and the water retaining plate 4 presses against the limiter 5, driving the guide member to slide downward, driving the bellows 211 to extend, so that the concrete falls to the bottom of the well body 11; the coil spring 73 elastic force drives the winding wheel 71 to rotate the winding rope 72, driving the guide member to slide upward to retract and reset the bellows 211.
[0065] Example 2
[0066] The embodiment of the present application discloses a construction method of a pumping type precipitation well.
[0067] Reference Figure 1 The construction method of the pumping type precipitation well includes the following steps:
[0068] S1 Dewatering: Use drilling equipment to dig the soil from the ground downward until it connects to the groundwater to form a wellbore, and pump water out of the wellbore to lower the water level in the wellbore to below the design elevation of the foundation 20 cushion layer 201.
[0069] S2 Excavation of foundation pit 10: Use excavation equipment to excavate foundation pit 10, so that the bottom elevation of foundation pit 10 is reduced to the design elevation of foundation 20 cushion layer 201.
[0070] S3 Well construction: Support formwork in the well hole and pour concrete to below the designed elevation of the foundation 20 cushion layer 201 to form a well body 11, cover the sealing cover 12 on the top of the well body 11 to form a closed pipe well 1, and reserve a drainage hole 13 on the closed pipe well 1.
[0071] S4 buried pipe: bury the telescopic drainage pipe 2 in the soil below the design elevation of the foundation 20 cushion layer 201, insert one end of the telescopic drainage pipe 2 into the drainage hole 13, and connect the other end to the pumping device 3, so that the groundwater level is kept below the working surface during the construction process.
[0072] A foundation 20 cushion layer 201 is constructed at the bottom of the foundation pit 10, and a waterproofing membrane 202 is laid on the cushion layer 201. Then, the bound bottom plate 203 steel bars are placed on the waterproofing membrane 202, and the bottom plate 203 concrete is poured.
[0073] S5 Well sealing: After the building construction meets the anti-floating requirements, remove the pumping device 3, continue to use the telescopic drainage pipe 2 as a grouting pipe, pour concrete into the closed pipe well 1, and fill the closed pipe well 1.
[0074] The social benefits brought by the construction method of a pumping type precipitation well in the embodiment of the present application are: precipitation is first performed, and then the closed pipe well 1 and the drainage device are buried below the design elevation of the cushion layer 201, so that the entire precipitation and drainage process is completed below the design elevation of the cushion layer 201 of the foundation 20. This enables the subsequent construction of the foundation 20 to proceed smoothly, ensures the integrity and waterproofness of the building foundation 20, and can also effectively precipitate water.
[0075] Example 3
[0076] The embodiment of the present application discloses a method for modifying a precipitation well.
[0077] Reference Figure 1 , the transformation method of the precipitation well includes the following steps:
[0078] S1 Cutting: Cut the existing precipitation well so that the wellhead height is lower than the design elevation of the foundation 20 cushion layer 201, and cover the sealing cover 12 at the wellhead of the precipitation well to form a closed pipe well 1.
[0079] S2 buried pipe: bury the telescopic drainage pipe 2 in the soil below the design elevation of the foundation 20 cushion layer 201, insert one end of the telescopic drainage pipe 2 into the drainage hole 13, and connect the other end to the pumping device 3, so that the groundwater level is kept below the working surface during the construction process.
[0080] A foundation 20 cushion layer 201 is constructed at the bottom of the foundation pit 10, and a waterproofing membrane 202 is laid on the cushion layer 201. Then, the bound bottom plate 203 steel bars are placed on the waterproofing membrane 202, and the bottom plate 203 concrete is poured.
[0081] S3 Well Sealing: After the building construction meets the anti-floating requirements, remove the pumping device 3, continue to use the telescopic drainage pipe 2 as a grouting pipe, pour concrete into the closed pipe well 1, and fill the closed pipe well 1.
[0082] The social benefits brought about by the renovation method of a precipitation well in an embodiment of the present application are: it can transform the existing old-style precipitation well into a pumping precipitation well that will not damage the integrity and waterproofness of the bottom plate 203 of the foundation 20, so that the entire precipitation and drainage process can be completed below the design elevation of the cushion layer 201 of the foundation 20, thereby saving the time for early precipitation and pouring and curing of the well body 11, which shortens the construction period, reduces waste, and saves costs.
[0083] The above are all preferred embodiments of the present application, and the protection scope of the present application is not limited thereto. Therefore, any equivalent changes made according to the structure, shape, and principle of the present application should be included in the protection scope of the present application.
Claims
1. A pumping type precipitation well, characterized in that: include: A closed pipe well (1), comprising a well body (11) and a sealing cover (12), wherein the sealing cover (12) covers the well mouth of the well body (11), the sealing cover (12) is buried in soil below the elevation of a cushion layer (201) of a foundation (20), and a drainage hole (13) is provided on the closed pipe well (1); a drainage device, comprising a telescopic drainage pipe (2) and a pumping device (3), wherein one end of the telescopic drainage pipe (2) extends into the closed pipe well (1) through the drainage hole (13), and the other end of the telescopic drainage pipe (2) is connected to the pumping device (3) and is used to drain water from the closed pipe well (1) to the outside, the telescopic drainage pipe (2) is buried in soil below the elevation of a cushion layer (201) of a foundation (20), and when the closed pipe well (1) is filled, the telescopic drainage pipe (2) can be extended to serve as a grouting pipe; The drainage hole (13) is formed on the sealing cover (12); the telescopic drainage pipe (2) comprises a water absorption section (21) and a water guide section (22) which are sealed and connected to each other; the water absorption section (21) is inserted into the drainage hole (13); the water guide section (22) extends to the outside of the bottom plate (203) of the foundation (20) and is connected to the water pumping device (3); The portion of the water absorption section (21) located below the sealing cover (12) is a bellows (211), and a water baffle (4) is provided at the mouth of the bellows (211). When water is pumped upward, water pressure acts on the water baffle (4) to cause the bellows (211) to contract. The water baffle plate (4) is hinged to the inner wall of the bellows (211), and a stopper (5) for preventing the water baffle plate (4) from rotating downward is provided on the bellows (211); A guide member is provided between the bellows (211) and the well body (11); the guide member is fixedly connected to the bellows (211) and slidably connected to the well body (11); and a sliding groove (111) for the guide member to slide is provided on the inner wall of the well body (11); A reset member (7) is connected between the sealing cover (12) and the guide member, and the reset member (7) is used to retract and reset the bellows (211); When grouting inwards, the concrete slurry flows downwards to impact the water retaining plate (4), thereby extending the corrugated pipe (211); when pumping water, the water retaining plate (4) rotates upwards under the action of water pressure to expand the pumping area.
2. The pumping type precipitation well according to claim 1 is characterized in that: The guide member is a guide plate (6), and a slider (61) is provided on the edge of the guide plate (6). The slider (61) is slidably inserted in the slide groove (111). The guide plate (6) is connected between the well body (11) and the bellows (211) to block the gap between the well body (11) and the bellows (211).
3. The pumping type precipitation well according to claim 2 is characterized in that: The reset member (7) comprises a fixedly connected reel (71) and a pull rope (72); the reel (71) is rotatably connected to the sealing cover (12); the pull rope (72) is wound on the reel (71); one end of the pull rope (72) away from the reel (71) is connected to the guide member; and a coil spring (73) is installed on the reel (71).
4. A method for constructing a pumping type precipitation well, characterized in that: Used to construct a pumping type precipitation well as described in any one of claims 1 to 3, The method comprises the following steps: S1: dewatering: digging soil from the ground downward until the groundwater is connected to form a well hole, and pumping water out of the well hole to reduce the water level in the well hole to below the design elevation of the foundation (20) cushion layer (201); S2: excavating the foundation pit (10) to reduce the bottom elevation of the foundation pit (10) to the design elevation of the foundation (20) cushion layer (201); S3: building a well: supporting a formwork in the well hole and pouring concrete to below the design elevation of the foundation (20) cushion layer (201) to form a well body (11), and covering the sealing cover (12) on the well body (11) at the top, forming a closed pipe well (1), and reserving a drainage hole (13) on the closed pipe well (1); S4 pipe burying: burying the telescopic drainage pipe (2) in the soil below the design elevation of the foundation (20) cushion layer (201), inserting one end of the telescopic drainage pipe (2) into the drainage hole (13), and connecting the other end to the pumping device (3); S5 well sealing: after the building is constructed to meet the anti-floating requirements, dismantling the pumping device (3), continuing to use the telescopic drainage pipe (2) as a grouting pipe, pouring concrete into the closed pipe well (1), and filling the closed pipe well (1).
5. A method for transforming a precipitation well, characterized in that: Used to transform an existing precipitation well into a pumping precipitation well as described in any one of claims 1 to 3, The method comprises the following steps: S1 cutting: cutting an existing precipitation well so that the wellhead height is lower than the design elevation of the foundation (20) cushion layer (201), and covering the wellhead with the sealing cover (12) to form a closed pipe well (1); S2 pipe burying: burying a telescopic drainage pipe (2) in the soil below the design elevation of the foundation (20) cushion layer (201), inserting one end of the telescopic drainage pipe (2) into a drainage hole (13), and connecting the other end to a pumping device (3); S3 well sealing: after the building is constructed to meet the anti-floating requirements, dismantling the pumping device (3), continuing to use the telescopic drainage pipe (2) as a grouting pipe, pouring concrete into the closed pipe well (1), and filling the closed pipe well (1).