A water hammer test device
By designing detachable assembly and power drive parts, the rapid disassembly and assembly and replacement of the water hammer test device is achieved, solving the problem of low testing efficiency in the prior art and improving the testing efficiency and efficiency.
Patent Information
- Application Number
- CN202410230415.1
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-02-29
- Publication Date
- 2024-11-29
- Estimated Expiration
- 2044-02-29
AI Technical Summary
The existing water hammer test device takes a lot of time to disassemble and install when replacing pipe workpieces, resulting in less testing efficiency.
A water hammer test device is designed, using detachable disassembly and power drive parts to pump water into the water source box through the power drive parts, so that the water flows through the first connecting pipe, pipeline workpiece, disassembly and second connecting pipe , use the cut-off valve to close the water flow to form a water hammer effect. After the test, the assembly can be quickly removed and replaced with a new pipe workpiece.
It realizes rapid disassembly and assembly and replacement of pipeline workpieces, improves testing efficiency, simplifies the testing process, and reduces manpower consumption.
Smart Images

Figure CN118090471B_ABST
Abstract
Description
Technical Field
[0001] The present application relates to the technical field of pipeline testing, and in particular to a water hammer testing device. Background Art
[0002] Water hammer test refers to a test in water hammer equipment. During the test, fill the pump with water, start the water supply pump, supply water to the water tower through the test check valve, and the water in the water tower flows back to the pool through the overflow pipe, forming an open cycle. When the pump runs stably, suddenly disconnect the power supply of the water pump, the water pump stops supplying water to the water tower, and the water flow transitions from forward flow to reverse flow in a very short time. At this time, the check valve closes automatically and quickly due to the pressure difference, and the water pressure in front of the valve body rises rapidly in an instant, thus generating water hammer phenomenon.
[0003] The existing water hammer test installs the pipeline workpiece on the water hammer test equipment, and observes the pressure changes of the pipeline workpiece during the water hammer test, so as to test the strength and performance of the pipeline workpiece, and at the same time test the stability and pressure resistance of the pipeline. During the test, the installation method of the pipeline is very firm, resulting in a lot of time spent on disassembling and replacing the pipeline workpiece for a new test after the test, which reduces the test efficiency. Summary of the invention
[0004] In order to improve the efficiency of water hammer testing, the present application provides a water hammer testing device.
[0005] The present application provides a water hammer test device, which adopts the following technical solution:
[0006] A water hammer test device comprises a test bench, a water source box is arranged on one side of the test bench, a power drive component is arranged at the bottom of the test bench, an input end of the power drive component is communicated with the water source box, a first pipe rack is arranged on the top of the test bench, a first connecting pipe for connecting a pipeline workpiece is connected to the first pipe rack, an output end of the power drive component is communicated with the first connecting pipe, a second pipe rack is arranged on the first pipe rack, a second connecting pipe is connected to the second pipe rack, a cavity is arranged inside the second pipe rack, a cut-off valve is connected to the second pipe rack, a disassembly component for connecting the pipeline workpiece is detachably connected to the second connecting pipe, and the second pipe rack is communicated with the water source box.
[0007] By adopting the above technical solution, when the pipeline workpiece needs to be tested for quality, the disassembly part can be removed from the second connecting pipe, the two ends of the pipeline workpiece are respectively connected to the first connecting pipe and the disassembly part, and then the disassembly part is installed on the second connecting pipe, and the water source box is pumped by the power drive part to make water flow through the first connecting pipe, the pipeline workpiece, the disassembly part, the second connecting pipe and the water pipe in sequence. During the flow, the cut-off valve can be closed to make the water flow form an impact in the pipeline workpiece, so as to perform a water hammer test on the pipeline workpiece to test whether the quality of the pipeline workpiece is qualified. After the test, the disassembly part can be removed from the second connecting pipe, and then the disassembly part and the first connecting pipe are detached from the pipeline workpiece, and a new pipeline workpiece can be replaced for testing, which is convenient for disassembly and assembly and improves the test efficiency.
[0008] Optionally, the disassembly part includes a disassembly pipe and a special-shaped block, the disassembly pipe is detachably connected to the second connecting pipe, the special-shaped block is connected to the disassembly pipe, one end of the disassembly pipe is provided with a connecting pipe sleeve for connecting a pipeline workpiece, and the connecting pipe sleeve is provided with a thread.
[0009] By adopting the above technical solution, when the disassembly part needs to be installed on the pipeline workpiece, the disassembly part can be removed from the second connecting pipe, the pipeline workpiece is connected to the connecting pipe sleeve, and the pipeline workpiece and the connecting pipe sleeve are threadedly connected, thereby completing the installation of the disassembly part and the pipeline workpiece.
[0010] Optionally, a fixing seat is provided on the top of the test bench, a clamping block is provided at the end of the first connecting pipe, a mounting sleeve is provided on the clamping block, a thread is provided on the mounting sleeve, a clamping groove for inserting the clamping block is provided on the fixing seat, a lifting and lowering driving member is provided on the test bench, a disassembly driving member is provided at the driving end of the lifting and lowering driving member, and a disassembly driving member is connected to the driving end of the disassembly driving member for clamping with the special-shaped block.
[0011] By adopting the above technical solution, before the disassembly and assembly part is installed on the pipeline workpiece, the pipeline workpiece can be connected to the installation pipe sleeve, the clamping block is inserted into the clamping groove, and then the disassembly and assembly part is connected to the pipeline workpiece, and the special-shaped blocks of the disassembly and assembly clamping part are clamped together through the lifting and lowering driving part and the disassembly and assembly driving part, and the installation pipe sleeve and the connecting pipe sleeve are installed on the pipeline workpiece, thereby improving the disassembly and assembly efficiency.
[0012] Optionally, the end of the second connecting pipe is plugged into the disassembly connecting pipe, a moving part is slidably connected to the second connecting pipe, a moving driving part for driving the moving part to slide is provided on the second pipe rack, a moving hook is movably connected to the moving part, and the moving hook is hooked with the special-shaped block.
[0013] By adopting the above technical solution, when the disassembly pipe is installed on the second connecting pipe, the movable hook can be hooked on the special-shaped block, and the movable driving member is driven to slide, so that the movable hook presses the special-shaped block against the fixed plate.
[0014] Optionally, a branch pipe is connected to the second pipe rack, one end of the branch pipe away from the second pipe rack is connected to the output end of the power drive component, and a branch valve is provided on the branch pipe.
[0015] By adopting the above technical solution, the branch pipe can relieve the pressure of the pipeline.
[0016] Optionally, the output end of the power driving member is connected to a rewinding tube group, and one end of the rewinding tube group away from the power driving member is connected to the first tube rack.
[0017] By adopting the above technical solution, the rewinding pipe group can reduce the severe impact of the pipeline during the water hammer test, thereby protecting the entire pipeline.
[0018] Optionally, the return winding tube group includes a first winding tube and a second winding tube, the first winding tube and the second winding tube are connected to each other, the first winding tube is symmetrically arranged, the second winding tube is arranged between the symmetrically arranged first winding tubes, a first circulation assembly is arranged between the first winding tubes, and a second circulation assembly is arranged at the ends of the symmetrical first winding tubes that are away from each other.
[0019] By adopting the above technical solution, the impact force of the water flow in the pipeline can be adjusted through the first flow-through component and the second flow-through component, thereby improving the test accuracy.
[0020] Optionally, an opening is provided on the top of the water source box, a filter is provided inside the water source box, the connection between the power drive element and the water source box is located below the filter element, the outer wall of the filter element abuts against the inner wall of the water source box, a silt collecting element is provided on the filter element, and a lifting and lowering drive element for driving the filter element to rise and fall is provided on the water source box, and the driving end of the lifting and lowering drive element is connected to the filter element.
[0021] By adopting the above technical solution, the lifting and lowering drive component can make the filter element move up and down, and the dirt on the inner wall of the water source box can be scraped off by the silt collecting component and collected by the filter element, thereby reducing the blockage of the pipeline and reducing the impact on the test.
[0022] Optionally, the water source tank is provided with a lifting drive member, and the driving end of the lifting drive member is provided with a silt sweeping component for sweeping the inner wall of the water source tank. The silt sweeping component is diagonally distributed in the water source tank, and the silt sweeping component is used to clean two adjacent inner walls of the water source tank.
[0023] By adopting the above technical solution, the silt sweeping assembly can be used to clean the two adjacent inner walls of the water source box, and the lifting drive member drives the silt sweeping assembly to move up and down, so that the inner wall of the water source box is cleaned before the silt collecting member scrapes it.
[0024] Optionally, the silt sweeping assembly includes a lifting frame, a silt sweeping driving member, a transmission wheel group and a silt sweeping frame, the lifting frame is connected to the driving end of the lifting driving member, the silt sweeping driving member is arranged on the lifting frame, the transmission wheel group is rotatably connected to the lifting frame, the driving end of the silt sweeping driving member is connected to the transmission wheel group, the silt sweeping frame is slidingly connected to the bottom end of the lifting frame, the silt sweeping frame is transmission-connected to the transmission wheel group, and the silt sweeping frame is provided with a sweeping hair.
[0025] By adopting the above technical solution, when cleaning, the silt sweeping driving component can drive the transmission wheel group to rotate, driving the silt sweeping frame to move, so that the sweeping hair can clean the inner wall of the water source box, and cooperate with the lifting driving component to drive the lifting frame to rise and fall, so as to perform multi-directional cleaning, thereby improving the cleaning effect of the water source box.
[0026] In summary, the present application includes at least one of the following beneficial technical effects:
[0027] 1. When the pipeline workpiece needs to be tested for quality, the disassembly part can be removed from the second connecting pipe, and the two ends of the pipeline workpiece are respectively connected to the first connecting pipe and the disassembly part, and then the disassembly part is installed on the second connecting pipe. The water source box is pumped by the power drive part to make water flow through the first connecting pipe, the pipeline workpiece, the disassembly part, the second connecting pipe and the water pipe in sequence. During the flow process, the cut-off valve can be closed to make the water flow form an impact in the pipeline workpiece, so as to perform a water hammer test on the pipeline workpiece to test whether the quality of the pipeline workpiece is qualified. After the test, the disassembly part can be removed from the second connecting pipe, and then the disassembly part and the first connecting pipe are separated from the pipeline workpiece, and a new pipeline workpiece can be replaced for testing. The disassembly and assembly are convenient, and the test efficiency is improved;
[0028] 2. When the disassembly component needs to be installed on the pipeline workpiece, the disassembly component can be removed from the second connecting pipe, and the pipeline workpiece can be connected to the connecting pipe sleeve so that the pipeline workpiece and the connecting pipe sleeve are threadedly connected, thereby completing the installation of the disassembly component and the pipeline workpiece;
[0029] 3. Before installing the disassembly part on the pipeline workpiece, the pipeline workpiece can be connected to the installation pipe sleeve, the clamping block can be inserted into the clamping groove, and then the disassembly part can be connected to the pipeline workpiece. The special-shaped blocks of the disassembly clamping part can be clamped together through the lifting and lowering driving part and the disassembly driving part, and the installation pipe sleeve and the connecting pipe sleeve can be installed on the pipeline workpiece to improve the disassembly efficiency. BRIEF DESCRIPTION OF THE DRAWINGS
[0030] Figure 1 It is a schematic diagram of the overall structure in the embodiment of the present application.
[0031] Figure 2 It is a schematic diagram of the top structure of the test bench in the embodiment of the present application.
[0032] Figure 3 It is a schematic diagram of the structure of the mounting pipe in the embodiment of the present application.
[0033] Figure 4 It is a partial cross-sectional view of the water shield in the embodiment of the present application.
[0034] Figure 5 It is a partial cross-sectional view of the disassembly and assembly of the card parts in the embodiment of the present application.
[0035] Figure 6 It is a schematic diagram of the structure of the rewinding tube group in the embodiment of the present application.
[0036] Figure 7 It is a partial cross-sectional view of the water source box in the embodiment of the present application.
[0037] Figure 8 It is a structural schematic diagram of the installation frame in the embodiment of the present application.
[0038] Fig. 9 It is a partial cross-sectional view of the installation frame in the embodiment of the present application.
[0039] Fig.10 It is a schematic diagram of the silt sweeping component in an embodiment of the present application.
[0040] Fig.11 It is a schematic diagram of the structure of the transmission wheel group in the embodiment of the present application.
[0041] Description of reference numerals:
[0042] 1. Test bench; 11. Power drive; 111. Output pipe; 12. Fixed seat; 121. Snap-in slot; 13. Support frame; 14. Lifting and lowering drive; 141. Lifting and lowering seat; 15. Disassembly and assembly drive; 16. Disassembly and assembly card; 161. Disassembly and assembly slot; 17. Water collecting tank; 18. Water collecting pipe; 2. Water source box; 21. Filter; 22. Silt collecting part; 23. Fixed frame; 24. Lifting and lowering drive; 25. Installation frame; 251. Placement slot; 26. Plug rod; 27. Limit block; 271. Spring; 3. First pipe rack; 31. First connecting pipe; 32. Snap-in block; 33. Installing pipe sleeve; 34. Extension pipe; 4. Second pipe rack; 41. Second connecting pipe; 42. Cut-off valve ;43. water pipe;431. branch pipe;432. branch valve;44. moving part;45. moving driving part;451. moving screw rod;452. water shield;46. moving hook;47. fixing plate;471. sealing rubber pad;5. mounting tube;51. special-shaped block;52. connecting pipe sleeve;61. first winding tube;62. second winding tube;63. first connecting valve;64. first straight tube;65. second connecting valve;66. second straight tube;7. lifting driving part;71. lifting frame;711. transverse slide rail;72. silt sweeping driving part;721. rotating rod;73. inclined bracket;74. silt sweeping frame;741. hair sweeping;75. rotating wheel;76. eccentric shaft;77. transmission rod. DETAILED DESCRIPTION
[0043] The following is combined with Figure 1-11 This application is described in further detail.
[0044] The embodiment of the present application discloses a water hammer testing device.
[0045] Reference Figure 1 and Figure 2A water hammer test device comprises a test bench 1, a water source box 2 is arranged on one side of the test bench 1, and clean water is contained in the water source box 2. A power driving member 11 is installed at the bottom of the test bench 1, and the power driving member 11 is a water pump. The input end of the power driving member 11 is connected to the inside of the water source box 2. A first pipe rack 3 is arranged on the top of the test bench 1, and the top of the first pipe rack 3 extends in the horizontal direction. A plurality of first connecting pipes 31 for connecting pipeline workpieces are connected to the first pipe rack 3. In this embodiment, the number of the first connecting pipes 31 is four. A cavity is opened inside the first pipe rack 3. One end of the first connecting pipe 31 close to the first pipe rack 3 is connected to the inside of the first pipe rack 3. The output end of the power driving member 11 is connected to the inside of the first pipe rack 3. The top of the first pipe rack 3 is connected to the second The pipe rack 4, a cavity is opened inside the second pipe rack 4, and a plurality of second connecting pipes 41 are connected to one side of the second pipe rack 4. In this embodiment, the number of the second connecting pipes 41 is four, and the number of the second connecting pipes 41 is consistent with the number of the first connecting pipes 31. The second connecting pipes 41 are connected to the second pipe rack 4, and a cut-off valve 42 and a water pipe 43 are connected to the side of the second pipe rack 4 away from the second connecting pipe 41. One end of the water pipe 43 is connected to the second pipe rack 4, and the water pipe 43 is connected to the inside of the second pipe rack 4. The cut-off valve 42 is installed at one end of the water pipe 43 close to the second pipe rack 4, and the end of the water pipe 43 away from the second pipe rack 4 is connected to the inside of the water source box 2. The end of the second connecting pipe 41 away from the second pipe rack 4 is detachably connected with a disassembly component for connecting a pipeline workpiece.
[0046] When the pipeline workpiece needs to be tested for quality, one end of the pipeline workpiece can be connected to the end of the first connecting pipe 31, and the other end of the pipeline workpiece can be connected to the disassembly component, and then the disassembly component is installed on the end of the second connecting pipe 41 away from the second pipe rack 4, and the water source tank 2 is pumped by the power drive 11 to pump the water in the water source tank 2 into the first pipe rack 3 and the first connecting pipe 31, so that the water flows through the pipeline workpiece, the disassembly component, the second connecting pipe 41 and the water pipe 43 in sequence, and then returns to the water source tank 2 through the water pipe 43, so that A circulating pipeline is formed. When water is flowing, the shut-off valve 42 can be closed to form a water hammer effect in the pipeline workpiece, so that the inside of the pipeline workpiece is impacted by the water flow, thereby performing a water hammer test on the pipeline workpiece to test whether the quality of the pipeline workpiece is qualified. After the test, the shut-off valve 42 can be closed, and then the drive of the power drive component 11 is stopped. The disassembly component can be removed from the second connecting pipe 41, and then the disassembly component and the first connecting pipe 31 are detached from the pipeline workpiece, and a new pipeline workpiece can be replaced for testing, which is convenient for disassembly and assembly.
[0047] Reference Figure 3 and Figure 4The disassembly and assembly parts include a disassembly and assembly pipe 5 and a special-shaped block 51. The disassembly and assembly pipe 5 is detachably connected to the end of the second connecting pipe 41 away from the second pipe rack 4. The special-shaped block 51 is in a hexagonal block shape. The special-shaped block 51 is installed on the outer wall of the disassembly and assembly pipe 5. The special-shaped block 51 is close to the end of the disassembly and assembly pipe 5 close to the second connecting pipe 41. One end of the disassembly and assembly pipe 5 is provided with a connecting pipe sleeve 52 for connecting the interface of the pipeline workpiece, and the inner side wall of the connecting pipe sleeve 52 is provided with an internal thread for cooperating with the interface of the pipeline workpiece.
[0048] When the disassembly part and the pipeline workpiece need to be installed with each other, the interface of the pipeline workpiece can be inserted into the connecting pipe sleeve 52, and the disassembly pipe 5 can be rotated to make the connecting pipe sleeve 52 and the pipeline workpiece threadedly connected. The disassembly part can be installed on the pipeline workpiece, and then the disassembly part can be installed on the second connecting pipe 41 for testing, which is convenient for installation.
[0049] Reference Figure 2 and Figure 5 A fixing seat 12 is provided on the top of the test bench 1. A clamping block 32 is connected to one end of the first connecting pipe 31 away from the power driving member 11. The clamping block 32 is in a hexagonal block shape. A mounting sleeve 33 for accessing the interface of the pipeline workpiece is provided on the clamping block 32. The inner side wall of the mounting sleeve 33 is provided with an internal thread for matching with the interface of the pipeline workpiece. A clamping groove 121 for inserting the clamping block 32 in a horizontal or vertical direction is provided on the top and side wall of the fixing seat 12. A supporting frame 13 is provided on the top of the test bench 1. A lifting and lowering driving member 14 is installed on the supporting frame 13. The lifting and lowering driving member 14 is a cylinder. The lifting and lowering driving member 14 Located above the fixed seat 12, the driving end of the lifting and lowering driving member 14 faces the top of the fixed seat 12, the driving end of the lifting and lowering driving member 14 is connected to the landing seat 141, the lifting and lowering driving member 14 can drive the landing seat 141 to move up and down, and the bottom of the landing seat 141 is connected to the disassembly and assembly driving member 15, the disassembly and assembly driving member 15 is a motor, and the driving end of the disassembly and assembly driving member 15 is connected to a disassembly and assembly card 16 for clamping with the special-shaped block 51, the disassembly and assembly card 16 is block-shaped, and a disassembly and assembly slot 161 is provided on the side of the disassembly and assembly card 16 away from the disassembly and assembly driving member 15, and the shape of the disassembly and assembly slot 161 is adapted to the shape of the special-shaped block 51.
[0050] When it is necessary to install the pipeline workpiece for testing, the clamping block 32 can be inserted into the clamping groove 121, one end interface of the pipeline workpiece can be inserted into the installation sleeve 33, and the disassembly and assembly pipe 5 and the other end interface of the pipeline workpiece can be plugged into each other, so that the lifting and lowering driving member 14 drives the lifting and lowering seat 141 to descend, and the special-shaped block 51 is inserted into the disassembly and assembly clamping groove 161, and the disassembly and assembly driving member 15 drives the disassembly and assembly clamping member 16 to rotate, thereby driving the disassembly and assembly pipe 5 and the connecting sleeve 52 to rotate, so that the connecting sleeve 52 is threadedly connected to the pipeline workpiece, and then driving the pipeline workpiece to rotate, so that the pipeline workpiece is threadedly connected to the installation sleeve 33, thereby completing the connection between the pipeline workpiece and the first connecting pipe 31 and the disassembly and assembly parts. When disassembling, it is only necessary to rotate the disassembly and assembly clamping member 16 in the same way in the opposite direction to separate the pipeline workpiece, the first connecting pipe 31 and the disassembly and assembly parts from each other, which is convenient for disassembly and assembly, saves manpower, and improves disassembly and assembly efficiency.
[0051] Reference Figure 2 and Figure 4 The end of the second connecting pipe 41 away from the second pipe rack 4 is plugged into the disassembly pipe 5, and the outer wall of the second connecting pipe 41 is slidably connected with a moving member 44, which is annular and slides along the extension direction of the second connecting pipe 41. The second pipe rack 4 is provided with a moving driving member 45 for driving the moving member 44 to slide, and the moving driving member 45 is a motor. The driving end of the moving driving member 45 is connected to a moving screw rod 451, which passes through the moving member 44, and the moving screw rod 451 is threadedly connected to the moving member 44. The outer wall cover is provided with a water-blocking cover 452, and the outer side of the moving part 44 is rotatably connected with a moving hook part 46, the moving hook part 46 is hook-shaped, and the moving hook part 46 is circumferentially distributed on the outer peripheral side of the moving part 44, and the extension direction of the rotation axis of the moving hook part 46 is perpendicular to the sliding direction of the moving hook part 46, and the end of the moving hook part 46 away from the moving part 44 is hooked with the side of the special-shaped block 51 away from the second connecting tube 41, and the outer wall of the second connecting tube 41 is provided with a fixed plate 47, and the end of the moving screw rod 451 away from the moving driving part 45 is rotatably connected to the fixed plate 47.
[0052] When it is necessary to install the disassembly tube 5 on the second connecting tube 41, the second connecting tube 41 can be inserted into the port of the disassembly tube 5 close to the special-shaped block 51, so that the fixed plate 47 is close to the special-shaped block 51, and the movable hook 46 can be rotated to hook the movable hook 46 on the special-shaped block 51, and then the movable driving member 45 can drive the movable screw rod 451 to rotate, driving the movable member 44 to slide on the second connecting tube 41, thereby moving away from the fixed plate 47, so that the movable hook 46 presses the special-shaped block 51 and the fixed plate 47 against each other, thereby completing the installation of the disassembly tube 5 and the second connecting tube 41.
[0053] A sealing rubber pad 471 is provided on the side of the fixed plate 47 facing away from the moving part 44. When the disassembly pipe 5 is installed on the second connecting pipe 41, the sealing rubber pad 471 can improve the sealing between the fixed plate 47 and the special-shaped block 51, and can play a buffering role between the fixed plate 47 and the special-shaped block 51.
[0054] Reference Figure 1 A branch pipe 431 is connected to the water pipe 43. One end of the branch pipe 431 away from the water pipe 43 is connected to the output end of the power drive member 11. Both ends of the branch pipe 431 are provided with branch valves 432, which are existing switch valves.
[0055] When the water pressure in the pipeline is too high, the branch valve 432 can be opened to allow a portion of the water drawn by the power drive component 11 to flow into the branch pipe 431, and then this portion of water flows into the water pipe 43 and directly returns to the water source box 2, thereby relieving pressure, reducing the situation where the water pressure in the water pipeline is too high and causes the pipeline to rupture, and reducing the impact force on the pipeline workpiece during the water hammer test.
[0056] Reference Figure 1 and Figure 6 The output end of the power driving member 11 is connected to a rewinding tube group, which is located between the driving end of the power driving member 11 and the first connecting tube 31, and one end of the rewinding tube group away from the power driving member 11 is connected to a side of the first pipe rack 3 away from the first connecting tube 31.
[0057] When the water pumped out by the power drive member 11 flows into the rewinding pipe group, the flow direction can be changed, thereby reducing the severe impact on the pipeline during the water hammer test and protecting the pipeline. In addition, the rewinding pipe group can also be used to reduce the pressure of the fluid by increasing the length of the pipeline and the curvature of the curve, so that the fluid can be slowly decelerated when passing through the rewinding pipe group.
[0058] An extension tube 34 is connected to a side of the first pipe rack 3 away from the first connecting tube 31. The return winding tube group includes a first winding tube 61 and a second winding tube 62. The first winding tube 61 and the second winding tube 62 are both S-shaped tubes. The first winding tube 61 and the second winding tube 62 are connected to each other. The distance between the straight tube parts of the first winding bending points is greater than the distance between the straight tube parts of the second winding bending points. There are two first winding tubes 61. The first winding tubes 61 are symmetrically arranged, wherein one first winding tube 61 is connected to the extension tube 34, and the other first winding tube 61 is connected to the output end of the power drive member 11. The second winding tube 62 is arranged between the two symmetrically arranged first winding tubes 61. The two symmetrical first winding tubes 61 The ends close to each other are respectively connected to the two ends of the second winding pipe 62, and a first circulation assembly is arranged between the two first winding pipes 61. The first circulation assembly includes a first connecting valve 63 and a first straight pipe 64. The first connecting valve 63 is a three-way valve. There are two first connecting valves 63. The two first connecting valves 63 are distributed at the ends of the two first winding pipes 61. The ends of the two first winding pipes 61 away from the second winding pipe 62 are respectively on the two first connecting valves 63. The first straight pipe 64 is located between the two first connecting valves 63. The two ends of the first straight pipe 64 are respectively connected to the ports of the two first connecting valves 63. The ends of the two symmetrical first winding pipes 61 away from each other are provided with a second circulation assembly.
[0059] When the water in the pipeline flows slowly and the impact force of the water hammer needs to be increased, the first connecting valve 63 can switch the water path so that the water between the two first winding pipes 61 flows through the first straight pipe 64 and no longer flows through the second winding pipe 62, thereby speeding up the flow rate of the water flow, increasing the impact force of the water hammer test, and further testing the quality of the pipeline workpiece.
[0060] The driving end of the power drive member 11 is connected to the output pipe 111, the branch pipe 431 is connected to the output pipe 111, and the branch pipe 431 is connected to the output pipe 111. One of the first connecting valves 63 is located between the output pipe 111 and one of the first winding pipes 61, and the end of the output pipe 111 and the end of the first winding pipe 61 are respectively connected to two interfaces of the first connecting valve 63; another first connecting valve 63 is located between the extension pipe 34 and another first winding pipe 61, and the end of the extension pipe 34 away from the first pipe rack 3 and the end of the first winding pipe 61 are respectively connected to one of the interfaces of the first connecting valve 63. Two interfaces; the second transfer flow assembly includes a second connecting valve 65 and a second straight pipe 66, the second connecting valve 65 is a three-way valve, the number of the second connecting valves 65 is two, the two second connecting valves 65 are located between the two first winding pipes 61, the ends of the two first winding pipes 61 away from the first connecting valve 63 are respectively connected to the ends of the two second connecting valves 65 away from each other, the two ends of the second winding pipe 62 are respectively connected to the interfaces of the two second connecting valves 65, the second straight pipe 66 is located between the two second connecting valves 65, and the two ends of the second straight pipe 66 are respectively connected to the third interfaces of the two second connecting valves 65.
[0061] When it is necessary to further increase the flow rate and water pressure, the second connecting valve 65 can switch the water path so that the water flow between the output pipe 111 and the extension pipe 34 flows directly through the second straight pipe 66 without flowing into the second winding pipe 62 for deceleration. This can speed up the flow rate of water, increase the water pressure, and enhance the impact force of water hammer. Different impact environments can be changed to perform quality tests on the valve body, thereby improving the accuracy of the test.
[0062] A water collecting tank 17 is provided on the top of the test bench 1, and the water collecting tank 17 is located below the first pipe rack 3. A water collecting pipe 18 is connected to the bottom of the test bench 1, and the water collecting pipe 18 is connected to the water collecting tank 17. One end of the water collecting pipe 18 away from the water collecting tank 17 is connected to the water source box 2. When the pipeline workpiece is disassembled for replacement, the water in the pipeline workpiece and the pipeline flows onto the test bench 1, and then flows into the water collecting tank 17, and can flow into the water source box 2 through the water collecting pipe 18, thereby reducing waste.
[0063] Reference Figure 1 and Figure 7The water source box 2 is in the shape of a rectangular box, and an opening is provided on the top of the water source box 2. A filter 21 is provided inside the water source box 2. The filter 21 is located at the inner bottom of the water source box 2. The connection between the power driving member 11 and the water source box 2 is located below the filter 21. The filter 21 is in the shape of a filter plate. A sludge collecting member 22 is provided on the top of the filter 21. The sludge collecting member 22 is in the shape of a frame horizontally arranged along the inner side wall of the water source box 2. The vertical section of the sludge collecting member 22 is inclined inward from top to bottom. The top outer wall of the filter element 22 is in contact with the inner wall of the water source box 2. A fixing frame 23 is provided on the top of the water source box 2. A lifting and lowering driving member 24 for driving the filter element 21 to rise and fall is connected to the top of the fixing frame 23. The lifting and lowering driving member 24 is a cylinder. The driving end of the lifting and lowering driving member 24 is connected to a mounting frame 25. A placement groove 251 for placing the filter element 21 is provided on the top of the mounting frame 25. The filter element 21 is located in the placement groove 251. The silt collecting member 22 is installed on the mounting frame 25. Figure 7 and Figure 8 A plug-in rod 26 is inserted into one side of the mounting frame 25, and the plug-in rod 26 is inserted into the side wall of the filter element 21. Figure 8 and Fig. 9 The side walls at both ends of the plug-in rod 26 are slidably connected to the limit blocks 27, the sliding direction of the limit blocks 27 is perpendicular to the extension direction of the plug-in rod 26, the limit blocks 27 are plugged into the side walls of the plug-in rod 26, and the side walls of the plug-in rod 26 are provided with grooves for accommodating the limit blocks 27. The side walls of the limit blocks 27 are connected to springs 271, and one end of the spring 271 away from the plug-in rod 26 is connected to the groove wall of the groove.
[0064] After a certain number of water hammer tests, scale and solid waste are easily accumulated on the inner wall of the water source tank 2. The lifting and lowering drive member 24 can drive the mounting frame 25 to move upward, thereby driving the filter element 21 to move upward and out of the water surface of the water source tank 2. During the movement, the sludge collecting member 22 can scrape off the scale and solid waste on the inner wall of the water source tank 2, and the scale and solid waste can be concentrated along the sludge collecting member 22 to the filter element 21 and fall on the filter mesh part of the filter element 21, thereby completing the cleaning of the inner wall of the water source tank 2 and the collection of dirt and waste, reducing the possibility of blockage in the pipeline and reducing the impact on the water hammer test.
[0065] Reference Figure 7 and Fig.10 The outer wall of the water source box 2 is connected with a lifting drive member 7, and the lifting drive member 7 is a cylinder. The driving end of the lifting drive member 7 is provided with a silt sweeping component for sweeping the inner wall of the water source box 2. There are two groups of silt sweeping components, and the silt sweeping components are diagonally distributed in the water source box 2. The silt sweeping components are used to clean the two adjacent inner walls of the water source box 2, and the silt sweeping components are located above the silt collecting component 22.
[0066] Before driving the filter element 21 to rise, the two groups of silt-clearing components can be respectively used to clean the two adjacent inner walls of the water source box 2. At the same time, the lifting drive 7 drives the silt-clearing components to rise and fall, thereby cleaning the inner wall of the water source box 2 in the vertical direction, making it easier for scale and solid waste to be collected by the filter element 21, thereby improving the cleaning effect.
[0067] The driving end of the lifting drive member 7 is away from the water source tank 2. The silt sweeping assembly includes a lifting frame 71, a silt sweeping drive member 72, a transmission wheel group and a silt sweeping frame 74. The lifting frame 71 is connected to the driving end of the lifting drive member 7. The silt sweeping drive member 72 is a motor. The silt sweeping drive member 72 is installed on the top of the lifting frame 71. The transmission wheel group is rotatably connected to the lifting frame 71, and the transmission wheel group is close to the bottom of the lifting frame 71. The driving end of the silt sweeping drive member 72 is connected with a rotating rod 721, and the bottom end of the rotating rod 721 is connected to the top of the transmission wheel group. The silt sweeping frame 74 is slidably connected to the bottom end of the lifting frame 71, and the silt sweeping frame 74 is transmission-connected to the transmission wheel group. A sweeping hair 741 is provided on the side of the silt sweeping frame 74 close to the inner wall of the water source tank 2. The end of the sweeping hair 741 close to the inner wall of the water source tank 2 is scattered. Fig.10 and Fig.11 The transmission wheel group includes rotating wheels 75 arranged in the vertical direction. There are three rotating wheels 75 in each transmission wheel group. The central axis of the rotating wheel 75 coincides with the rotation axis of the rotating rod 721. The top rotating wheel 75 is connected to the bottom end of the rotating rod 721. The bottom rotating wheel 75 is rotatably connected to the inner bottom wall of the lifting frame 71. Eccentric shafts 76 are provided between the top rotating wheel 75 and the middle rotating wheel 75, and between the middle rotating wheel 75 and the bottom rotating wheel 75. Adjacent rotating wheels 75 are fixed in pairs by eccentric shafts 76. There is one eccentric shaft 76 between adjacent rotating wheels 75. The extension direction of the rotation axis of the eccentric shaft 76 is parallel to the extension direction of the rotation axis of the rotating rod 721. The rotation axis of one eccentric shaft 76 is parallel to the rotation axis of the rotating rod 721. The plane formed by the axis is perpendicular to the plane formed by the rotation axis of the other eccentric shaft 76 and the rotation axis of the rotating rod 721. The side wall of the eccentric shaft 76 is rotatably connected to a transmission rod 77. The end of the transmission rod 77 away from the eccentric shaft 76 is rotatably connected to the silt sweeping frame 74. An inclined bracket 73 is fixed to the side wall of the lifting frame 71. The end of the inclined bracket 73 away from the lifting frame 71 is fixedly connected to a transverse slide rail 711. The silt sweeping frame 74 is slidably connected to the transverse slide rail 711. The transverse slide rail 711 extends in a horizontal direction. The extension direction of the transverse slide rail 711 is parallel to the inner wall of the water source box 2. There are two transverse slide rails 711 in each set of transmission wheel groups. The two sets of transverse slide rails 711 are perpendicular to each other. The silt sweeping frame 74 can slide along the extension direction of the transverse slide rail 711.
[0068] When it is necessary to clean the inner wall of the water source box 2, the silt-sweeping driving component 72 can drive the rotating rod 721 to rotate, driving the rotating wheel 75 to rotate, and driving the transmission rod 77 and the silt-sweeping frame 74 to move through the eccentric shaft 76, so that the inner wall of the water source box 2 is cleaned horizontally through the sweeping hair 741. At the same time, the lifting driving component 7 can drive the lifting frame 71 to be lifted and lowered, so that the inner wall of the water source box 2 is cleaned vertically, thereby improving the cleaning efficiency of the water source box 2.
[0069] The implementation principle of a water hammer testing device in an embodiment of the present application is as follows: when a pipeline workpiece needs to be tested for quality, the disassembly component can be removed from the second connecting pipe 41, and the two ends of the pipeline workpiece are respectively connected to the first connecting pipe 31 and the disassembly component, and then the disassembly component is installed on the second connecting pipe 41. The water source box 2 is pumped by the power drive component 11 to make water flow through the first connecting pipe 31, the pipeline workpiece, the disassembly component, the second connecting pipe 41 and the water pipe 43 in sequence. During the flow of water, the cut-off valve 42 can be closed to make the water flow form a water hammer effect in the pipeline workpiece, thereby performing a water hammer test on the pipeline workpiece to test whether the quality of the pipeline workpiece is qualified. After the test, the disassembly component can be removed from the second connecting pipe 41, and then the disassembly component and the first connecting pipe 31 are detached from the pipeline workpiece, and a new pipeline workpiece can be replaced for testing. The disassembly and assembly are convenient, and the replacement efficiency and testing efficiency are improved.
[0070] The above are all preferred embodiments of the present application. The embodiments are only explanations of the present application and do not limit the protection scope of the present application in turn. Therefore, all equivalent changes made according to the structure, shape, and principle of the present application should be covered within the protection scope of the present application.
Claims
1. A water hammer test device, It is characterized in that The invention comprises a test bench (1), wherein a water source box (2) is provided on one side of the test bench (1), a power drive component (11) is provided at the bottom of the test bench (1), an input end of the power drive component (11) is connected to the water source box (2), a first pipe rack (3) is provided on the top of the test bench (1), a first connecting pipe (31) for connecting a pipeline workpiece is connected to the first pipe rack (3), an output end of the power drive component (11) is connected to the first connecting pipe (31), a second pipe rack (4) is provided on the first pipe rack (3), a second connecting pipe (41) is connected to the second pipe rack (4), a cavity is provided inside the second pipe rack (4), a cut-off valve (42) is connected to the second pipe rack (4), a disassembly component for connecting a pipeline workpiece is detachably connected to the second connecting pipe (41), and the second pipe rack (4) is connected to the water source box (2).
2. A water hammer test device according to claim 1, It is characterized in that The disassembly component comprises a disassembly pipe (5) and a special-shaped block (51); the disassembly pipe (5) is detachably connected to the second connecting pipe (41); the special-shaped block (51) is connected to the disassembly pipe (5); one end of the disassembly pipe (5) is provided with a connecting pipe sleeve (52) for connecting a pipeline workpiece; the connecting pipe sleeve (52) is provided with a thread.
3. A water hammer testing device according to claim 2, It is characterized in that The top of the test bench (1) is provided with a fixing seat (12), the end of the first connecting pipe (31) is provided with a clamping block (32), the clamping block (32) is provided with a mounting sleeve (33), the mounting sleeve (33) is provided with a thread, the fixing seat (12) is provided with a clamping groove (121) for inserting the clamping block (32), the test bench (1) is provided with a lifting and lowering driving member (14), the driving end of the lifting and lowering driving member (14) is provided with a disassembly driving member (15), and the driving end of the disassembly driving member (15) is connected to a disassembly clamp (16) for clamping with the special-shaped block (51).
4. A water hammer testing device according to claim 2, It is characterized in that The end of the second connecting pipe (41) is plugged into the disassembly connecting pipe (5); a moving member (44) is slidably connected to the second connecting pipe (41); a moving driving member (45) for driving the moving member (44) to slide is provided on the second pipe rack (4); a moving hook member (46) is movably connected to the moving member (44); and the moving hook member (46) is hooked to the special-shaped block (51).
5. A water hammer testing device according to claim 1, It is characterized in that The second pipe rack (4) is connected to a branch pipe (431), one end of the branch pipe (431) away from the second pipe rack (4) is connected to an output end of the power drive member (11), and a branch valve (432) is provided on the branch pipe (431).
6. A water hammer testing device according to claim 1, It is characterized in that The output end of the power driving member (11) is connected to a rewinding tube group, and one end of the rewinding tube group away from the power driving member (11) is connected to the first tube rack (3).
7. A water hammer testing device according to claim 6, It is characterized in that The return winding tube group comprises a first winding tube (61) and a second winding tube (62), the first winding tube (61) and the second winding tube (62) being connected to each other, the first winding tube (61) being symmetrically arranged, the second winding tube (62) being arranged between the symmetrically arranged first winding tubes (61), a first circulation assembly being arranged between the first winding tubes (61), and a second circulation assembly being arranged at ends of the symmetrical first winding tubes (61) that are away from each other.
8. A water hammer testing device according to claim 1, It is characterized in that The water source box (2) is provided with an opening at the top, a filter element (21) is provided inside the water source box (2), a connection between the power drive element (11) and the water source box (2) is located below the filter element (21), an outer wall of the filter element (21) is in contact with an inner wall of the water source box (2), a silt collecting element (22) is provided on the filter element (21), and a lifting and lowering drive element (24) for driving the filter element (21) to rise and fall is provided on the water source box (2), a driving end of the lifting and lowering drive element (24) is connected to the filter element (21).
9. A water hammer testing device according to claim 8, It is characterized in that The water source box (2) is provided with a lifting drive member (7), and a silt-sweeping assembly for sweeping the inner wall of the water source box (2) is provided at the driving end of the lifting drive member (7), the silt-sweeping assembly being diagonally distributed in the water source box (2), and the silt-sweeping assembly being used to clean two adjacent inner walls of the water source box (2).
10. A water hammer testing device according to claim 9, It is characterized in that The silt sweeping assembly comprises a lifting frame (71), a silt sweeping driving member (72), a transmission wheel group and a silt sweeping frame (74); the lifting frame (71) is connected to the driving end of the lifting driving member (7); the silt sweeping driving member (72) is arranged on the lifting frame (71); the transmission wheel group is rotationally connected to the lifting frame (71); the driving end of the silt sweeping driving member (72) is connected to the transmission wheel group; the silt sweeping frame (74) is slidably connected to the bottom end of the lifting frame (71); the silt sweeping frame (74) is transmission-connected to the transmission wheel group; and a sweeping bristle (741) is arranged on the silt sweeping frame (74).
Citation Information
Patent Citations
Stainless steel tube compression resistance detection device
CN115165600A
Conduit bending fatigue test device and equipment
CN213181088U