3D Visual Construction Management System

Through the three-dimensional visual construction management system, real-time data acquisition and three-dimensional modeling technology are used to solve the problems of low construction management efficiency and insufficient safety in traditional bridge construction, and real-time monitoring and optimization of construction progress and structural safety are achieved.

CN118194409BActive Publication Date: 2024-11-15中路高科交通检测检验认证有限公司 +1
View PDF 5 Cites 0 Cited by

Patent Information

Application Number
CN202410398384.0
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-03
Publication Date
2024-11-15
Estimated Expiration
2044-04-03

AI Technical Summary

Technical Problem

During the construction process of traditional bridges, construction management faces difficulties in real-time monitoring, insufficient adaptability to complex environments, inaccurate structural safety assessment, and lack of effective tools for material use and quality control, resulting in low construction efficiency, safety and reliability.

Method used

Adopt a three-dimensional visual construction management system, including data acquisition module, progress management module, quality control module and bridge dynamic load response simulation module. Through real-time data acquisition and three-dimensional modeling technology, a three-dimensional model at the construction site is built to realize construction progress monitoring and structure. Integrity check and load response analysis.

Benefits of technology

It improves the efficiency and accuracy of construction management, optimizes structural safety and response prediction, ensures construction quality, and improves the success rate and safety of bridge construction projects.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118194409B_ABST
    Figure CN118194409B_ABST
Patent Text Reader

Abstract

The present invention belongs to the technical field of construction management, and relates to a three-dimensional visualization construction management system, including a data acquisition module for collecting real-time data of a bridge construction site, a three-dimensional visualization module for building a three-dimensional model of a bridge, a progress management module for monitoring the progress of the bridge project and timely adjusting the construction plan, a quality control module for checking structural integrity and material applicability, and a bridge dynamic load response simulation module for simulating and analyzing the effects of various dynamic loads on the bridge during construction and / or use. The present invention can improve management efficiency, accurately monitor the construction status of the construction site, and effectively predict and evaluate the response and stability of the bridge structure.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The present invention belongs to the technical field of construction management, and relates to a three-dimensional visualized construction management system, and in particular to a three-dimensional visualized construction management system applied to bridge construction. Background Art

[0002] In the traditional bridge construction process, construction management usually faces many challenges. These challenges include but are not limited to the difficulty of real-time monitoring of construction progress, lack of adaptability to complex construction environments, and accurate assessment of structural safety. Traditional methods rely on manual supervision and static construction plans, which often lead to untimely information updates and difficulty in responding to immediate changes and potential risks during the construction process.

[0003] In addition, traditional construction management methods often lack effective tools and technical support when dealing with the response of bridge structures to dynamic loads (such as traffic flow, wind loads) and natural disasters such as earthquakes. This limitation not only affects the safety and efficiency during construction, but may also affect the long-term performance and reliability of bridges.

[0004] At the same time, traditional management methods also present challenges in terms of material use and quality control. Due to the lack of accurate real-time data and efficient analysis tools, it is difficult for engineering teams to identify and resolve construction quality issues in a timely manner, which may lead to later structural problems and increased maintenance costs.

[0005] Therefore, in the face of these challenges, there is an urgent need for a comprehensive construction management system that can integrate real-time data acquisition, 3D visualization technology and structural analysis tools. Such a system can not only improve the efficiency and accuracy of construction management, but also optimize structural safety and response prediction, ensure construction quality, and thus improve the success rate and safety of bridge construction projects. Summary of the invention

[0006] In order to solve the above-mentioned technical problems existing in the background technology, the present invention provides a three-dimensional visual construction management system that can improve the efficiency and accuracy of construction management, monitor the status of the construction site in real time, and effectively predict and evaluate the response and stability of the bridge structure.

[0007] In order to achieve the above object, the present invention adopts the following technical solution:

[0008] A three-dimensional visualization construction management system, characterized in that: the three-dimensional visualization construction management system includes a data acquisition module, a three-dimensional visualization module, a progress management module, a quality control module and a bridge dynamic load response simulation module;

[0009] The data acquisition module is responsible for collecting real-time data of the bridge construction site, which includes bridge structural parameters, environmental parameters, raw material status, worker distribution and traffic flow; the bridge structural parameters include the size, shape, angle, connection relationship and position relationship of the constructed bridge; the environmental parameters include wind load and earthquake factors; the raw material status includes the quantity, quality and type of raw materials;

[0010] The 3D visualization module uses the real-time data collected by the data acquisition module to construct a 3D model of the construction site, the core of which is the 3D model of the bridge, to achieve real-time visualization of the construction process, including real-time bridge construction progress, construction scenes, raw material distribution, and personnel allocation;

[0011] The progress management module is based on the three-dimensional model of the construction site constructed by the three-dimensional visualization module, which monitors the progress of bridge construction in real time and adjusts the construction plan in time;

[0012] The quality control module is based on the three-dimensional model of the construction site constructed by the three-dimensional visualization module to check the integrity of the bridge structure and the applicability of the raw materials;

[0013] The bridge dynamic load response simulation module is used to simulate and analyze the impact of various dynamic loads on the bridge during the construction process. It uses real-time data such as environmental parameters and traffic flow collected by the data acquisition module, combined with the three-dimensional model of the construction site constructed by the three-dimensional visualization module, to simulate and evaluate the real-time impact of traffic flow, wind load, earthquake factors, etc. on the bridge structure.

[0014] Preferably, the specific method of the three-dimensional visualization module used in the present invention to construct the three-dimensional model of the construction site using the real-time data collected by the data acquisition module is:

[0015] The real-time data collected by the data acquisition module is transmitted to the three-dimensional visualization module, which processes and integrates the input real-time data. Based on the processed and integrated data, the three-dimensional visualization module uses the building information model (BIM) to construct a three-dimensional model of the construction site including a three-dimensional model of the bridge and a three-dimensional model of the bridge surrounding environment. The three-dimensional model of the construction site includes the structure of the bridge, construction equipment, material distribution, and worker configuration, and the core of the model is the three-dimensional model of the bridge.

[0016] More preferably, the specific steps of constructing the three-dimensional model of the construction site are:

[0017] a) Import basic data and define basic information of the project: the imported basic data includes terrain data, geological information, existing transportation and infrastructure data; the basic information includes unit system and coordinate system;

[0018] b) Preliminary creation of the geometric shape of the bridge: determine the length, width, height and appearance of the bridge, and use CAD tools to draw the basic outline of the bridge in the building information model;

[0019] c) Build a three-dimensional bridge model: define the thickness, raw materials and loading conditions of the bridge deck, determine the size and raw materials of the bridge piers according to the structural load calculation formula, and use structural analysis software to perform stress analysis and deflection analysis;

[0020] d) Import or draw the 3D model of the bridge surroundings, and align the 3D model of the bridge surroundings with the 3D model of the bridge in the same coordinate system, match the corresponding raw materials for each component of the bridge, and define the cross-sectional dimensions and prestressing level of the components;

[0021] e) Feedback the analysis results of the structural analysis software into the building information model (BIM) of the 3D visualization module;

[0022] f) Construction site simulation: Use the construction simulation function in the BIM software to simulate the construction process, and adjust the construction plan according to the simulation results. The simulated construction process includes the transportation of raw materials and the order of component installation.

[0023] Preferably, the progress management module used in the present invention includes a progress tracking unit and a progress analysis and adjustment unit;

[0024] The progress tracking unit is used to display the comparison between the current construction status and the planned progress, and use color coding or other visual markings to highlight the areas that are behind schedule or ahead of schedule in the three-dimensional model of the bridge;

[0025] The progress analysis and adjustment unit uses the integrated data and the three-dimensional model of the bridge to perform regular progress analysis, detect any deviation from the predetermined construction plan, and adjust the construction plan and resource allocation in a timely manner based on the analysis results.

[0026] Preferably, the specific working mode of the progress tracking unit adopted by the present invention is:

[0027] 1) Integrate the real-time data from the data acquisition module, upload the real-time data to the system database regularly, and reflect it to the bridge 3D model synchronously;

[0028] 2) Progress mapping: In the 3D bridge model, each construction component is assigned a progress status mark, which is automatically updated according to real-time data to reflect the current construction status of each component;

[0029] 3) Visual display: Use color coding in the 3D bridge model, using different colors to mark different parts of the model according to different stages of construction progress;

[0030] The specific working method of the progress analysis and adjustment unit is:

[0031] 1) Define the construction plan baseline and, for each construction phase, define the expected completion time point;

[0032] 2) Collecting real-time construction data: Regularly collect real-time construction data, including the amount of work completed, the amount of raw materials used, and the number of working hours used;

[0033] Calculate schedule deviation: ;

[0034] in, is the current amount of work completed obtained from real-time construction data, According to the planned workload, the calculated progress deviation is associated with the corresponding construction part in the 3D bridge model. , indicating that the work at this stage is ahead of schedule; if , indicating that the work is behind schedule; in the 3D model of the bridge, different colors or marks are used to indicate different progress deviations.

[0035] Preferably, the specific operation mode of the quality control module adopted by the present invention is:

[0036] Step 1) In the 3D model of the bridge, ensure that each structural component of the bridge is modeled according to the design drawings, including specific dimensions, properties of the selected raw materials and connection methods; use the 3D model of the bridge to conduct structural analysis, including stress testing, deflection analysis and vibration analysis to evaluate the structural integrity of the bridge, and conduct finite element analysis based on the data of the 3D model of the bridge to determine whether the stress and deformation of the structure are within the safe range;

[0037] Step 2) Material suitability verification: In the 3D bridge model, check the properties of all raw materials, including strength, durability and compatibility;

[0038] Step 3) Visually check each construction stage in the 3D model of the bridge to ensure that the installation and connection methods of all components meet the design requirements, and compare the data of the 3D model of the construction site with the actual situation on the construction site.

[0039] More preferably, the specific implementation method of the finite element analysis in step 1) is:

[0040] Step 1.1) Extract the geometric information of the components from the 3D bridge model, including the size, shape and boundary conditions, and determine the properties of the raw materials, including the elastic modulus , Poisson's ratio and density;

[0041] Step 1.2) Meshing: Divide the 3D bridge model into elements; define the loads applied to the model and the applied boundary conditions, including gravity, live loads and wind loads, and the applied boundary conditions including the type and location of supports;

[0042] Step 1.3) Use finite element analysis software to analyze and calculate the stress and deformation of each element. The calculation formula is expressed as:

[0043] ;in, is stress, It is strain;

[0044] Preferably, the simulation steps of the bridge dynamic load response simulation module adopted by the present invention include:

[0045] S1) Data integration: Integrate the environmental data and traffic flow data collected by the data acquisition module into the bridge dynamic load response simulation module, and update the 3D model of the construction site in the 3D visualization module to ensure that the model reflects the current status and construction stage of the bridge in real time;

[0046] S2) Dynamic load simulation:

[0047] S21) Using the collected traffic flow data, generate corresponding dynamic loads to simulate the impact of vehicles on the bridge structure when traveling on the bridge;

[0048] S22) Use the collected environmental data to apply wind loads in the 3D model of the construction site to simulate the effects of wind on the bridge structure;

[0049] S23) Combine historical earthquake data and analysis to simulate the impact of potential earthquakes on bridge structures;

[0050] S3) Response Analysis: Run dynamic analysis to evaluate the response of the bridge structure under various loading conditions, including vibration, displacement, and stress distribution;

[0051] S4) adjusting the model parameters according to the current state of the bridge and the real-time construction status;

[0052] S5) Risk Assessment and Reporting: Based on the simulation results, the safety and stability of the bridge structure under various loading conditions are assessed and an analysis report is generated, which includes potential risk areas and recommended reinforcement measures.

[0053] Preferably, the specific implementation of step S21) adopted in the present invention is:

[0054] S211) Collect traffic flow data, which includes the type, weight, speed and passing frequency of vehicles. For each type of vehicle, calculate its standard load on the bridge deck. Calculated using the following formula: ,in, is the acceleration due to gravity;

[0055] S212) Consider the dynamic effects of vehicle movement and apply dynamic load factors Add static load, determined according to vehicle type and speed: ;in, is the load;

[0056] S213) Load distribution simulation: Based on the size and driving trajectory of the vehicle, the load distribution is simulated in the three-dimensional bridge model, including the contact point of the wheel on the bridge deck and the load distribution;

[0057] Consider the changing load effect of vehicles driving on the bridge, and calculate the load changes with time and space; establish a dynamic model based on the vehicle type and the corresponding weight of each type of vehicle, simulate the vehicle as a series of mass points, each mass point represents a part of the vehicle, and for each vehicle, establish a load-time function to describe how its load changes over time, which is calculated based on vehicle speed and bridge length; the finite element analysis method is used to calculate the response of the bridge to dynamic loads, dividing the bridge into a series of elements and calculating the stress and deformation of each element, applying the load-time function to the corresponding elements and calculate the response of the bridge using the dynamic equation, which is expressed as: ,in, is the mass matrix, is the damping matrix, is the stiffness matrix, is the displacement vector, and are the velocity and acceleration vectors, respectively, and the dynamic equations are solved using the central difference method;

[0058] S214) Overall Structural Response Analysis: Apply the calculated dynamic loads to the 3D model of the bridge and run a structural analysis to evaluate the response and analyze the long-term performance and fatigue life cycle of the bridge under continuous traffic flow conditions.

[0059] Preferably, the specific implementation of step S22) adopted in the present invention is:

[0060] S221) Collect environmental data, including wind speed and wind direction, and calculate wind load based on the collected wind speed : ;in, is the air density, is the wind-exposed area of ​​the bridge, is the wind speed, is the drag coefficient;

[0061] S222) In the three-dimensional bridge model, determine the geometric shape and structural characteristics of the bridge to ensure that the three-dimensional bridge model can reflect the response of the bridge to wind loads;

[0062] S223) Apply the calculated wind load to the three-dimensional model of the bridge, and the wind load is distributed over the entire length and height of the bridge according to the actual wind direction; for complex bridge structures, fluid dynamics is used to simulate the wind load distribution, and finite element analysis is used to analyze and evaluate the response of the bridge under wind load;

[0063] S224) Analyze the calculation results, focus on the maximum stress and displacement of key structural components, evaluate the structural safety of the bridge based on the results, and adjust the design if necessary.

[0064] Preferably, step S23) adopted in the present invention specifically includes:

[0065] S231) collecting earthquake historical data, including the intensity, frequency, focal depth and magnitude of earthquakes, and determining earthquake motion parameters for defining earthquake loads and simulating earthquake motions based on the earthquake historical data and relevant specifications, wherein the earthquake motion parameters include earthquake motion acceleration spectrum, duration and repetition interval;

[0066] S232) In the three-dimensional model of the bridge, ensure that the bridge structure model accurately reflects the actual structural characteristics, including material properties, geometric dimensions and structural details, and use finite element analysis methods to apply seismic parameters to the three-dimensional model of the bridge;

[0067] S233) Perform dynamic analysis on the three-dimensional bridge model to calculate the bridge's response under earthquake action, including displacement, velocity, acceleration and internal force distribution;

[0068] S234) Analyze the simulation results to determine the maximum stress and displacement of the bridge structure during an earthquake, as well as the possible failure mode. Based on the simulation results, evaluate the seismic performance and safety of the bridge and optimize the design.

[0069] Compared with the prior art, the advantages and beneficial effects of the present invention are:

[0070] 1. In the present invention, the data acquisition module is responsible for collecting real-time data from the bridge construction site; the three-dimensional visualization module uses the collected data to build a three-dimensional bridge model to achieve intuitive visualization of the construction process; the progress management module monitors the progress of the bridge project based on the three-dimensional model and real-time data, and adjusts the construction plan in a timely manner; the quality control module uses the three-dimensional model to check the structural integrity and material applicability; the bridge dynamic load response simulation module is used to simulate and analyze the impact of various dynamic loads on the bridge during construction and / or use. It strengthens the control of the construction process, improves the efficiency and quality of decision-making, and can effectively predict and evaluate the response and stability of the bridge structure.

[0071] 2. This invention significantly improves the efficiency and accuracy of construction management during bridge construction by integrating real-time data collection and 3D modeling technology; using real-time data such as staff distribution, raw material usage and construction progress, combined with detailed 3D models, enables the project management team to quickly and accurately monitor the status of the construction site. This not only strengthens control over the construction process, but also improves the efficiency and quality of decision-making.

[0072] 3. In the present invention, the bridge dynamic load response simulation module includes an earthquake impact analysis function, which provides an in-depth understanding of the behavior of bridges under various loads and environmental conditions, and effectively predicts and evaluates the response and stability of bridge structures by simulating the impact of factors such as traffic flow, wind loads and earthquakes. This prediction capability is crucial for guiding improvements in bridge design, determining safety thresholds and formulating emergency response measures.

[0073] 4. The present invention adopts a quality control module that can conduct detailed inspections of structural integrity and raw material applicability to ensure that the construction quality meets design and safety standards, which helps to improve the overall performance and durability of the bridge, reduce maintenance costs, and improve public safety. BRIEF DESCRIPTION OF THE DRAWINGS

[0074] Figure 1 It is a schematic diagram of the framework of the three-dimensional visual construction management system provided by the present invention. DETAILED DESCRIPTION

[0075] like Figure 1 As shown, the present invention provides a three-dimensional visual construction management system, including the following modules:

[0076] Data acquisition module: responsible for collecting real-time data of the bridge construction site, including environmental parameters, environmental parameters, raw material status, worker distribution, and traffic flow; bridge structure parameters include the size, shape, angle, connection relationship, and position relationship of the constructed bridge; environmental parameters include wind load and earthquake factors;

[0077] 3D visualization module: Use the collected real-time data to build a 3D model of the construction site. The core is the 3D model of the bridge, which enables real-time visualization of the construction process, including real-time bridge construction progress, construction scenes, raw material distribution, and personnel allocation.

[0078] Progress management module: Based on the 3D model of the construction site constructed by the 3D visualization module, the progress of the bridge project construction can be monitored in real time. According to the design requirements, the construction plan can be adjusted in time to ensure that the project is completed on time;

[0079] Quality control module: Based on the 3D model of the construction site constructed by the 3D visualization module, check the integrity of the bridge structure and the applicability of the raw materials to ensure that the construction quality meets the standards;

[0080] Bridge dynamic load response simulation module: used to simulate and analyze the impact of various dynamic loads on bridges during the construction process. It uses real-time data such as environmental parameters and traffic flow data collected by the data acquisition module, combined with the three-dimensional model of the construction site built by the three-dimensional visualization module, to evaluate and simulate the impact of traffic flow, wind load, and earthquake factors on the bridge structure. This module provides an in-depth understanding of the dynamic load conditions that occur during the bridge construction process, helping to formulate more accurate and safe construction plans.

[0081] The specific steps of constructing the 3D model of the construction site include:

[0082] The real-time data collected by the data acquisition module is transmitted to the 3D visualization module. The 3D visualization module processes and integrates the input real-time data. Based on the processed and integrated data, the 3D visualization module uses the building information model (BIM) to construct a 3D model of the construction site including a 3D model of the bridge and a 3D model of the bridge's surrounding environment. The 3D model of the construction site includes the structure of the bridge, construction equipment, raw material distribution, and worker configuration. The core of the model is the 3D model of the bridge. The specific steps of constructing the 3D model of the construction site include:

[0083] Step 1: Import basic data and define basic information of the project: Import basic data including terrain data, geological information, existing transportation and infrastructure data; basic information includes unit system and coordinate system;

[0084] Step 2: Preliminary creation of the geometric shape of the bridge: determine the length, width, height and appearance of the bridge, and use CAD tools to draw the basic outline of the bridge in the building information model;

[0085] Step 3: Build a 3D bridge model: define the thickness, raw materials and loading conditions of the bridge deck, determine the size and raw materials of the bridge piers according to the structural load calculation formula, and use structural analysis software to perform stress analysis and deflection analysis to ensure the stability and safety of the bridge structure;

[0086] Step 4: Import or draw a 3D model of the bridge surroundings, and correctly align the 3D model of the bridge surroundings with the 3D model of the bridge in the same coordinate system, match corresponding raw materials for each component of the bridge, and define the cross-sectional dimensions and prestress level of the components;

[0087] Step 5: Feedback the analysis results of the structural analysis software into the building information model (BIM) of the 3D visualization module;

[0088] Step 6. Construction site simulation: Use the construction simulation function of BIM software to simulate the construction process, including the transportation of raw materials and the order of component installation, to ensure the feasibility of the construction simulation, and adjust the construction plan according to the simulation results.

[0089] Step 7. Document and report generation: Generate detailed project reports including design calculations, analysis results and construction plans; prepare construction drawings and related documents for use by the construction team.

[0090] The building information model receives new live data and updates in real time to reflect real-time changes on the construction site.

[0091] The progress management module includes a progress tracking unit and a progress analysis and adjustment unit, specifically:

[0092] 1) Progress monitoring and visualization: A progress tracking unit is preset in the 3D model of the construction site. The progress tracking unit can show the comparison between the current construction progress and the planned progress, and use color coding or other visual markers to highlight the areas behind or ahead of schedule in the model;

[0093] 2) Progress Analysis and Adjustment Unit: Use integrated real-time data and the 3D model of the bridge to conduct regular progress analysis to detect any deviations from the scheduled construction plan. Based on the analysis results, timely adjust the construction plan and resource allocation;

[0094] Establish a feedback loop to feed back the analysis results of progress analysis using real-time data of construction progress and 3D bridge model to the project management team, so as to ensure that the project management team can make timely decisions based on the feedback information and notify the construction team to make corresponding adjustments.

[0095] The progress tracking unit operates in the following ways:

[0096] 1) Integrate real-time data from the data acquisition module, including raw material consumption, worker configuration, use of construction equipment, and completed workload. The real-time data is uploaded to the system database regularly and reflected in the 3D bridge model simultaneously;

[0097] 2) Progress mapping: In the 3D bridge model, each construction component is assigned a progress status mark, which is automatically updated based on real-time data to reflect the current construction status of each component. For example, if the construction progress of a pier is behind schedule, the part will be displayed in red in the model;

[0098] 3) Visual display: Use color coding in the 3D bridge model, using different colors to mark different parts of the model according to different stages of construction progress;

[0099] The specific operation mode of the progress analysis and adjustment unit includes:

[0100] 1) Define the construction plan baseline and, for each construction phase, define the expected completion time point;

[0101] 2) Collect real-time construction data: Regularly collect real-time construction data, including the amount of work completed, the amount of materials used, and the number of working hours used;

[0102] Calculate schedule deviation: ;

[0103] in, is the current amount of work completed obtained from real-time construction data, According to the planned workload, the calculated progress deviation is associated with the corresponding construction part in the 3D bridge model. , indicating that the work at this stage is ahead of schedule; if , indicating that the work is behind schedule; in the 3D model of the bridge, different colors or marks are used to indicate different progress deviations.

[0104] Steps to adjust construction schedule and resource allocation:

[0105] Use the above-mentioned progress deviation formula to calculate the progress deviation and conduct progress analysis based on it; assuming that for a key construction stage, such as bridge pier construction, the calculation result is , indicating that the current construction progress is behind schedule. At the same time, analyzing other construction stages, such as bridge deck paving, the calculation results are , indicating that the current construction progress is ahead of schedule;

[0106] 1) Reallocate resources: For lagging construction stages, such as the aforementioned bridge pier construction, increase resource input, including increasing work shifts and deploying additional construction personnel and equipment to the construction site of this stage. For advanced construction stages, such as the aforementioned bridge deck paving, consider temporarily reducing resource input and prioritizing resources to lagging construction stages such as bridge pier construction.

[0107] 2) Adjust the construction plan:

[0108] For delayed construction phases, such as the aforementioned pier construction, reschedule subsequent construction activities based on the delayed construction progress. If the pier construction is delayed by one week, the construction plans of advanced construction phases such as the aforementioned bridge deck paving and other subsequent activities need to be postponed accordingly, the construction time points need to be updated, and ensure that all team members are aware of the updated schedule.

[0109] 3) Supply Chain Management:

[0110] Rearrange the supply and transportation of raw materials according to the adjusted construction plan. Speed ​​up the progress of lagging construction stages such as the aforementioned bridge pier construction, ensure that sufficient construction materials such as concrete and steel bars arrive on site in a timely manner, and communicate with suppliers about the needs after the updated construction plan to avoid shortages or surpluses of raw materials.

[0111] The specific operation mode of the quality control module includes:

[0112] Step 1) In the 3D model of the bridge, ensure that each structural component of the bridge is modeled according to the design drawings, including specific dimensions, the properties of the selected raw materials and the connection methods. Use the 3D model of the bridge to perform structural analysis, including stress testing, deflection analysis and vibration analysis to evaluate the structural integrity of the bridge. Use the data in the 3D model of the bridge to perform finite element analysis to determine whether the stress and deformation of the structure are within the safe range. The finite element analysis is as follows:

[0113] Step 1.1) Extract the geometric information of the components from the 3D bridge model, including size, shape and boundary conditions, and determine the properties of the raw materials, including the elastic modulus , Poisson's ratio ,density;

[0114] Step 1.2) Meshing: Divide the 3D bridge model into a finite number of elements (such as tetrahedrons or hexahedrons) to ensure mesh refinement and improve analysis accuracy; define the loads and boundary conditions applied to the model. The loads include gravity, live loads, and wind loads. The boundary conditions include the type and location of supports.

[0115] Step 1.3) Use finite element analysis software to analyze and apply mechanical equations and material equations to calculate the stress and deformation of each element. The calculation formula is expressed as: ;in, is stress, It is strain;

[0116] Evaluate the stress and deformation results to ensure they are within safe limits, comparing the results with design standards and safety requirements, such as stress should not exceed the ultimate stress of the material to use;

[0117] Step 2) Material suitability verification: In the 3D bridge model, check the properties of all raw materials, including strength, durability and compatibility;

[0118] Step 3) Visually check each construction stage in the 3D model of the bridge to ensure that the installation and connection methods of all components meet the design requirements, and compare the data of the 3D model of the construction site with the actual situation on the construction site.

[0119] The simulation steps of the bridge dynamic load response simulation module include:

[0120] S1, data integration: Integrate the environmental data (such as wind speed, wind direction, temperature and humidity) and traffic flow data (such as vehicle type, weight, speed and frequency) collected by the data acquisition module into the bridge dynamic load response simulation module, and update the 3D model of the construction site in the 3D visualization module to ensure that the model accurately reflects the current status and construction stage of the bridge;

[0121] S2, dynamic load simulation:

[0122] S21, using the collected traffic flow data, generates corresponding dynamic loads to simulate the impact of vehicles on the structure when driving on the bridge;

[0123] S22, using the collected environmental data to apply wind loads in the 3D model of the construction site to simulate the effects of wind on the bridge structure;

[0124] S23, combining historical earthquake data and analysis to simulate the impact of potential earthquakes on bridge structures;

[0125] S3, Response Analysis: Run dynamic analysis to evaluate the response of the bridge structure under various loading conditions, including vibration, displacement, and stress distribution;

[0126] S4, adjust the model parameters according to the current construction status and real-time construction status of the bridge to ensure the accuracy of the analysis results;

[0127] S5, Risk Assessment and Reporting: Based on the simulation results, the safety and stability of the bridge structure under various loading conditions are evaluated and an analysis report is generated, including potential risk areas and recommended reinforcement measures.

[0128] Through these steps, the bridge dynamic load response simulation module can effectively use real-time data and bridge 3D models to evaluate and simulate the response of the bridge under different load conditions, helping the project team to understand the dynamic behavior of the bridge in a timely manner and take corresponding measures to ensure the safety and stability of the bridge structure.

[0129] The specific implementation methods of S21 include:

[0130] S21) Collect traffic flow data, including vehicle type, weight, speed and frequency of passing. For each vehicle type, calculate its standard load on the bridge deck. Calculated using the following formula: ,in, is the acceleration due to gravity (approximately );

[0131] S22) Consider the dynamic effects of vehicle movement and apply dynamic load factors Add static load, determined according to vehicle type and speed: ;in, is the load;

[0132] S23) Load distribution simulation: Based on the size and driving trajectory of the vehicle, the load distribution is simulated in the three-dimensional bridge model, including the contact point of the wheel on the bridge deck and the load distribution;

[0133] Consider the changing load effects of vehicle movement on the bridge, calculate the load changes over time and space, establish a dynamic model based on various vehicle types and their corresponding weights, simulate the vehicle as a series of mass points, each mass point represents a part of the vehicle, and for each vehicle, establish a load-time function To describe the variation of its load over time, the function is calculated based on the vehicle speed and the length of the bridge. For example, if the vehicle is traveling at a constant speed, then the load-time function can be expressed as a function that changes significantly when the vehicle enters and leaves the bridge. The finite element analysis method is used to calculate the response of the bridge to dynamic loads. The bridge is divided into a series of elements and the stress and deformation of each element are calculated. The load-time function is applied to the corresponding elements and calculate the response of the bridge using the dynamic equation, which is expressed as: ,in, is the mass matrix, is the damping matrix, is the stiffness matrix, is the displacement vector, and are velocity and acceleration vectors, respectively, and the dynamic equations are solved using the central difference method. The calculation results are analyzed, especially the maximum stress and displacement at key points (such as supports and structural connections);

[0134] S24) Overall Structural Response Analysis, applies the calculated dynamic loads to a 3D model of the bridge structure, runs a structural analysis to evaluate the response and analyzes the long-term performance and fatigue life cycle of the bridge under continuous traffic flow conditions.

[0135] The specific implementation of S22 includes:

[0136] S221) Collect environmental data, including wind speed and wind direction, and calculate wind load based on the collected wind speed : ;in, is the air density, is the wind-exposed area of ​​the bridge, is the wind speed, is the drag coefficient;

[0137] S222) In the three-dimensional bridge model, determine the geometric shape and structural characteristics of the bridge to ensure that the three-dimensional bridge model can reflect the response of the bridge to wind loads;

[0138] S223) The calculated wind load is applied to the three-dimensional model of the bridge. The wind load is distributed over the entire length and height of the bridge according to the actual wind direction. For complex bridge structures, fluid dynamics simulation is used to simulate the wind load distribution. The finite element analysis method (same as the above traffic factors) is used for structural analysis to evaluate the response of the bridge under wind load, focusing on the vibration, displacement and stress distribution of the bridge. For long-span bridges, special attention is paid to the flutter stability and aeroelastic effect of the bridge.

[0139] S224) Analyze the calculation results, focus on the maximum stress and displacement of key structural components, evaluate the structural safety of the bridge based on the results, and adjust the design accordingly, such as adding dampers or adjusting the geometry of the bridge to reduce the impact of wind loads.

[0140] The specific implementation methods of S23 include:

[0141] S231) Collect historical earthquake data, including the intensity, frequency, focal depth and magnitude of earthquakes, and determine earthquake vibration parameters, including earthquake vibration acceleration spectrum, duration and repetition interval, based on the historical earthquake data and relevant specifications. The parameters are used to define earthquake loads and simulate ground motions;

[0142] S232) In the three-dimensional model of the bridge, ensure that the bridge structure model accurately reflects the actual structural characteristics, including the properties of the raw materials, geometric dimensions and structural details, and apply the seismic vibration parameters to the bridge structure model using the finite element analysis method (same as the above traffic factors);

[0143] S233) Perform dynamic analysis on the 3D model to calculate the bridge response under earthquake action, including displacement, velocity, acceleration and internal force distribution, focusing on key parts of the bridge, such as piers, abutments and supporting structures;

[0144] S234) Analyze the simulation results to determine the maximum stress and displacement of the bridge structure during an earthquake, as well as the possible failure mode. Based on the simulation results, evaluate the seismic performance and safety of the bridge and optimize the design, such as adding dampers, improving support design, or strengthening structural connections.

Claims

1. A three-dimensional visual construction management system, characterized by: The three-dimensional visualization construction management system includes a data acquisition module, a three-dimensional visualization module, a progress management module, a quality control module and a bridge dynamic load response simulation module; The data acquisition module is responsible for collecting real-time data of the bridge construction site, which includes bridge structural parameters, environmental parameters, raw material status, worker distribution and traffic flow; the bridge structural parameters include the size, shape, angle, connection relationship and position relationship of the constructed bridge; the environmental parameters include wind load and earthquake factors; the raw material status includes the quantity, quality and type of raw materials; The 3D visualization module uses the real-time data collected by the data acquisition module to construct a 3D model of the construction site, the core of which is the 3D model of the bridge, to achieve real-time visualization of the construction process, including real-time bridge construction progress, construction scenes, raw material distribution, and personnel allocation; The progress management module is based on the three-dimensional model of the construction site constructed by the three-dimensional visualization module, which monitors the progress of bridge construction in real time and adjusts the construction plan in time; The quality control module is based on the three-dimensional model of the construction site constructed by the three-dimensional visualization module to check the integrity of the bridge structure and the applicability of the raw materials; The bridge dynamic load response simulation module is used to simulate and analyze the impact of various dynamic loads on the bridge during the construction process. It uses real-time data such as environmental parameters and traffic flow collected by the data acquisition module, combined with the three-dimensional model of the construction site constructed by the three-dimensional visualization module, to simulate and evaluate the real-time impact of traffic flow, wind load, earthquake factors, etc. on the bridge structure.

2. The three-dimensional visual construction management system according to claim 1, characterized in that: The specific method in which the three-dimensional visualization module uses the real-time data collected by the data acquisition module to construct a three-dimensional model of the construction site is: The real-time data collected by the data acquisition module is transmitted to the three-dimensional visualization module, which processes and integrates the input real-time data. Based on the processed and integrated data, the three-dimensional visualization module uses the building information model (BIM) to construct a three-dimensional model of the construction site including a three-dimensional model of the bridge and a three-dimensional model of the bridge surrounding environment. The three-dimensional model of the construction site includes the structure of the bridge, construction equipment, material distribution, and worker configuration, and the core of the model is the three-dimensional model of the bridge. Preferably, the specific steps of constructing the three-dimensional model of the construction site are: a) Import basic data and define basic information of the project: the imported basic data includes terrain data, geological information, existing transportation and infrastructure data; the basic information includes unit system and coordinate system; b) Preliminary creation of the geometric shape of the bridge: determine the length, width, height and appearance of the bridge, and use CAD tools to draw the basic outline of the bridge in the building information model; c) Build a three-dimensional bridge model: define the thickness, raw materials and loading conditions of the bridge deck, determine the size and raw materials of the bridge piers according to the structural load calculation formula, and use structural analysis software to perform stress analysis and deflection analysis; d) Import or draw the 3D model of the bridge surroundings, and align the 3D model of the bridge surroundings with the 3D model of the bridge in the same coordinate system, match the corresponding raw materials for each component of the bridge, and define the cross-sectional dimensions and prestressing level of the components; e) Feedback the analysis results of the structural analysis software into the building information model (BIM) of the 3D visualization module; f) Construction site simulation: Use the construction simulation function in the BIM software to simulate the construction process, and adjust the construction plan according to the simulation results. The simulated construction process includes the transportation of raw materials and the order of component installation.

3. The three-dimensional visual construction management system according to claim 2, characterized in that: The progress management module includes a progress tracking unit and a progress analysis and adjustment unit; The progress tracking unit is used to display the comparison between the current construction status and the planned progress, and use color coding or other visual markings to highlight the areas that are behind schedule or ahead of schedule in the three-dimensional model of the bridge; The progress analysis and adjustment unit uses the integrated data and the three-dimensional model of the bridge to perform regular progress analysis, detect any deviation from the predetermined construction plan, and adjust the construction plan and resource allocation in a timely manner based on the analysis results.

4. The three-dimensional visual construction management system according to claim 3, characterized in that: Said The specific working method of the progress tracking unit is: 1) Integrate the real-time data from the data acquisition module, upload the real-time data to the system database regularly, and reflect it to the bridge 3D model synchronously; 2) Progress mapping: In the 3D bridge model, each construction component is assigned a progress status mark, which is automatically updated according to real-time data to reflect the current construction status of each component; 3) Visual display: Use color coding in the 3D bridge model, using different colors to mark different parts of the model according to different stages of construction progress; The specific working method of the progress analysis and adjustment unit is: 1) Define the construction plan baseline and, for each construction phase, define the expected completion time point; 2) Collecting real-time construction data: Regularly collect real-time construction data, including the amount of work completed, the amount of raw materials used, and the number of working hours used; Calculate schedule deviation: ; in, is the current amount of work completed obtained from real-time construction data, According to the planned workload, the calculated progress deviation is associated with the corresponding construction part in the 3D bridge model. , indicating that the work at this stage is ahead of schedule; if , indicating that the work is behind schedule; in the 3D model of the bridge, different colors or marks are used to indicate different progress deviations.

5. The three-dimensional visual construction management system according to claim 4, characterized in that: The specific method of the quality control module is: Step 1) In the 3D model of the bridge, ensure that each structural component of the bridge is modeled according to the design drawings, including specific dimensions, properties of the selected raw materials and connection methods; Use the 3D model of the bridge to conduct structural analysis, including stress testing, deflection analysis, and vibration analysis, to assess the structural integrity of the bridge. Perform finite element analysis based on the data from the 3D model of the bridge to determine whether the stress and deformation of the structure are within a safe range. Step 2) Material suitability verification: In the 3D bridge model, check the properties of all raw materials, including strength, durability and compatibility; Step 3) Visually check each construction stage in the 3D model of the bridge to ensure that the installation and connection methods of all components meet the design requirements, and compare the data of the 3D model of the construction site with the actual situation on the construction site.

6. The three-dimensional visual construction management system according to claim 5, characterized in that: The specific implementation method of the finite element analysis in step 1) is: Step 1.1) Extract the geometric information of the components from the 3D bridge model, including the size, shape and boundary conditions, and determine the properties of the raw materials, including the elastic modulus , Poisson's ratio and density; Step 1.2) Meshing: Divide the 3D bridge model into elements; define the loads applied to the model and the applied boundary conditions, including gravity, live loads and wind loads, and the applied boundary conditions including the type and location of supports; Step 1.3) Use finite element analysis software to analyze and calculate the stress and deformation of each element. The calculation formula is expressed as: ;in, is stress, It's strain.

7. The three-dimensional visual construction management system according to claim 6, characterized in that: The simulation steps of the bridge dynamic load response simulation module include: S1) Data integration: Integrate the environmental data and traffic flow data collected by the data acquisition module into the bridge dynamic load response simulation module, and update the 3D model of the construction site in the 3D visualization module to ensure that the model reflects the current status and construction stage of the bridge in real time; S2) Dynamic load simulation: S21) Using the collected traffic flow data, generate corresponding dynamic loads to simulate the impact of vehicles on the bridge structure when traveling on the bridge; S22) Use the collected environmental data to apply wind loads in the 3D model of the construction site to simulate the effects of wind on the bridge structure; S23) Combine historical earthquake data and analysis to simulate the impact of potential earthquakes on bridge structures; S3) Response Analysis: Run dynamic analysis to evaluate the response of the bridge structure under various loading conditions, including vibration, displacement, and stress distribution; S4) adjusting the model parameters according to the current state of the bridge and the real-time construction status; S5) Risk Assessment and Reporting: Based on the simulation results, the safety and stability of the bridge structure under various loading conditions are assessed and an analysis report is generated, which includes potential risk areas and recommended reinforcement measures.

8. The three-dimensional visual construction management system according to claim 7, characterized in that: The specific implementation of step S21) is: S211) Collect traffic flow data, which includes the type, weight, speed and passing frequency of vehicles. For each type of vehicle, calculate its standard load on the bridge deck. Calculated using the following formula: ,in, is the acceleration due to gravity; S212) Consider the dynamic effects of vehicle movement and apply dynamic load factors Add static load, determined according to vehicle type and speed: ;in, is the load; S213) Load distribution simulation: Based on the size and driving trajectory of the vehicle, the load distribution is simulated in the three-dimensional bridge model, including the contact point of the wheel on the bridge deck and the load distribution; Consider the changing load effect of vehicles driving on the bridge, and calculate the load changes with time and space; establish a dynamic model based on the vehicle type and the corresponding weight of each type of vehicle, simulate the vehicle as a series of mass points, each mass point represents a part of the vehicle, and for each vehicle, establish a load-time function to describe how its load changes over time, which is calculated based on vehicle speed and bridge length; the finite element analysis method is used to calculate the response of the bridge to dynamic loads, dividing the bridge into a series of elements and calculating the stress and deformation of each element, applying the load-time function to the corresponding elements and calculate the response of the bridge using the dynamic equation, which is expressed as: ,in, is the mass matrix, is the damping matrix, is the stiffness matrix, is the displacement vector, and are the velocity and acceleration vectors, respectively, and the dynamic equations are solved using the central difference method; S214) Overall Structural Response Analysis: Apply the calculated dynamic loads to the 3D model of the bridge and run a structural analysis to evaluate the response and analyze the long-term performance and fatigue life cycle of the bridge under continuous traffic flow conditions.

9. The three-dimensional visual construction management system according to claim 8, characterized in that: The specific implementation of step S22) is: S221) Collect environmental data, including wind speed and wind direction, and calculate wind load based on the collected wind speed : ;in, is the air density, is the wind-exposed area of ​​the bridge, is the wind speed, is the drag coefficient; S222) In the three-dimensional bridge model, determine the geometric shape and structural characteristics of the bridge to ensure that the three-dimensional bridge model can reflect the response of the bridge to wind loads; S223) Apply the calculated wind load to the three-dimensional model of the bridge, and the wind load is distributed over the entire length and height of the bridge according to the actual wind direction; for complex bridge structures, fluid dynamics is used to simulate the wind load distribution, and finite element analysis is used to analyze and evaluate the response of the bridge under wind load; S224) Analyze the calculation results, focus on the maximum stress and displacement of key structural components, evaluate the structural safety of the bridge based on the results, and adjust the design if necessary.

10. The three-dimensional visual construction management system according to claim 9, characterized in that: The step S23) specifically includes: S231) collecting earthquake historical data, including the intensity, frequency, focal depth and magnitude of earthquakes, and determining earthquake motion parameters for defining earthquake loads and simulating earthquake motions based on the earthquake historical data and relevant specifications, wherein the earthquake motion parameters include earthquake motion acceleration spectrum, duration and repetition interval; S232) In the three-dimensional model of the bridge, ensure that the bridge structure model accurately reflects the actual structural characteristics, including material properties, geometric dimensions and structural details, and use finite element analysis methods to apply seismic parameters to the three-dimensional model of the bridge; S233) Perform dynamic analysis on the three-dimensional bridge model to calculate the bridge's response under earthquake action, including displacement, velocity, acceleration and internal force distribution; S234) Analyze the simulation results to determine the maximum stress and displacement of the bridge structure during an earthquake, as well as the possible failure mode. Based on the simulation results, evaluate the seismic performance and safety of the bridge and optimize the design.

Citation Information

Patent Citations

  • Method for viewing tunnel monitoring and measurement data on BIM (Building Information Modeling) construction management platform

    CN105631154A

  • Method for establishing and analyzing template support model based on finite element analysis and BIM

    CN112163256A

  • BIM-FEM-based bridge structure digital twinborn body and method

    CN113806978A

  • Creeping formwork construction monitoring method and system and computer readable storage medium

    CN114547759A

  • Urban slow bridge health monitoring and digital twinning system

    CN117171842A