A shield tunnel lining segment reinforcement auxiliary installation method
Through space function and projection equipment technology, the problems of long drilling time and difficulty in ensuring hole position in convergence deformation of shield tunnels are solved, the precise installation and construction efficiency of reinforcement are achieved, and the safety and operation of the tunnel structure are ensured. stability.
Patent Information
- Application Number
- CN202410644260.6
- Authority / Receiving Office
- CN · China
- Patent Type
- Patents(China)
- Current Assignee / Owner
- Filing Date
- 2024-05-23
- Publication Date
- 2024-11-15
- Estimated Expiration
- 2044-05-23
AI Technical Summary
During the operation of the shield tunnel, convergence deformation caused by external soil and water loads and construction disturbances, resulting in structural safety hazards and unstable operation. The existing reinforcement methods have long drilling time, difficulty in ensuring the hole position, and the reinforcement assembly cannot be operated in parallel. Problems affect construction efficiency and accuracy.
By obtaining the contour information of the shield pipe sheet and reinforcement, use a spatial function to characterize the hole position to be drilled and the drilled restriction area, perform error determination and conflict inspection, adjust the reinforcement and tunnel attachments, select the alignment basis points, and use projection to The equipment projectes the hole to be drilled and the drilling restricted area onto the pipe sheet to achieve precise drilling and reinforcement installation.
It improves the accuracy and efficiency of construction, reduces rework and adjustment time, ensures the matching of the reinforcement and tunnel pipe sheets, realizes parallel operation of drilling and installation, and significantly improves construction efficiency and accuracy.
Smart Images

Figure CN118223910B_ABST
Abstract
Description
Technical Field
[0001] The invention relates to the technical field of shield tunnel maintenance, in particular to the inspection and reinforcement technology of operating tunnel lining segments, and specifically to an auxiliary installation method for a shield tunnel lining segment reinforcement body. Background Art
[0002] In urban areas with limited ground resources, subway tunnels are usually built using the shield method. During the service life of shield tunnels, under the long-term action of external water and soil loads or the disturbance of nearby construction, convergence deformation is usually inevitable. Convergence deformation not only affects the stress state of the tunnel, bringing structural safety hazards, but also may cause problems such as intrusion limits, affecting the normal operation of trains.
[0003] At present, in the treatment of convergence deformation of shield tunnels, various reinforcement bodies are often installed in the tunnel to improve the tunnel's deformation resistance, such as steel rings, corrugated steel rings, composite cavities, etc. Taking the most widely used steel ring reinforcement as an example, the steel ring is generally composed of 5-16 pieces of 20mm thick arc-shaped steel plates. During construction, each arc-shaped steel plate is first fixed to the shield segment to be reinforced with 4-6 stainless steel expansion bolts or chemical anchors, and then all the arc-shaped steel plates are connected into a whole by welding. Finally, epoxy resin is injected between the arc-shaped steel plate and the shield segment for bonding to complete the installation. The construction method of other reinforcement bodies is similar to this, and is completed through three steps: fixing components, connecting into rings, and injecting glue in the gap.
[0004] However, the window time available for maintenance work in an operating subway is generally only a few hours, and the time available for reinforcement work is very limited. The above existing process faces the following problems when used to solve the tunnel convergence deformation problem:
[0005] (1) The drilling time is long and the hole position is difficult to guarantee. In the process of fixing the reinforcement body to the shield segment, the bolt holes on the segment need to be drilled on site. When there are no prefabricated holes on the reinforcement body, the reinforcement body must be placed at the specified position by a mechanical arm at the construction site, and then the reinforcement body must be drilled through first, and then the bolt depth inside the segment is drilled. This takes a long time, and due to the obstruction of the steel plate, it is not easy to drill the hole perpendicular to the segment surface, so the fixing effect is difficult to guarantee. When there are prefabricated holes on the reinforcement body, it is necessary to measure the relative position of the bolt holes on the reinforcement body and drill holes in the corresponding positions of the segment in sequence. However, if the hole position on one of the segments does not meet the requirements, such as the internal steel bars of the segment are exposed after drilling, or there are existing pipelines blocking the hole position, etc., so that the hole position on the segment cannot be drilled, then the other previously completed holes will be invalid and cannot be used, which not only destroys the original structure but also increases the rework time.
[0006] (2) During the assembly of reinforcement bodies, parallel operations cannot be performed and secondary processing is often required. Reinforcements are usually assembled from the bottom of both sides of the shield tunnel to the tunnel vault in sequence. Each reinforcement body can only be fixed and the specific location where the next reinforcement body should be placed can be determined after multiple drilling and bolting. If the previous reinforcement bodies have been installed and a subsequent reinforcement body cannot be installed due to size error or tunnel fit problems, it is necessary to cut the reinforcement body on site to adapt, which will generate additional work and risks and have a huge impact on the construction progress. Summary of the invention
[0007] In view of the shortcomings of the prior art, the present invention proposes a shield tunnel lining segment reinforcement auxiliary installation method to improve construction accuracy and enhance work efficiency.
[0008] To achieve the above objectives, the present invention is implemented through the following technical solutions:
[0009] A method for auxiliary installation of a reinforcement body for a shield tunnel lining segment, comprising: obtaining information on the inner contour of a shield segment and the contour of a reinforcement body, wherein the reinforcement body is preset with a mounting hole for mounting and fixing the reinforcement body to the segment, and the mounting hole corresponds one-to-one to a position to be drilled on the shield segment; judging whether an assembly error after the reinforcement body is mounted and fixed to the segment meets the requirement, and if not, adjusting the reinforcement body; collecting segment structure information and information on appendages in the tunnel, and determining a drilling restriction area; judging whether the position to be drilled on the shield segment conflicts with the drilling restriction area, and if so, adjusting the reinforcement body or relocating the appendages in the tunnel, and if not, selecting an alignment base point on the segment; based on the alignment base point, arranging qualified positions to be drilled and the drilling restriction area on the segment; drilling construction is performed on the segment with reference to the positions to be drilled and the drilling restriction area, and the reinforcement body is installed and fixed.
[0010] In some embodiments, the obtaining of the inner contour information of the shield segment and the contour information of the reinforcement body includes: determining the spatial function of each structure.
[0011] In some embodiments, determining each structure space function includes:
[0012] In the spatial coordinate system, the center of a ring of segments on the cross section and the midpoint of the longitudinal section are taken as the origin O, the x and z axes are the horizontal and vertical directions of the tunnel cross section, and the y axis is the longitudinal direction of the tunnel. The inner surface of the segment can be expressed as a cylindrical surface with the center as the Y axis, that is:
[0013]
[0014] Where: R t is the inner diameter of the tunnel, w t is the longitudinal width of the segment;
[0015] The reinforcement is similar to the segment, which is a part of the cylindrical surface with the Y axis as the center. The first reinforcement is at the lower left of the tunnel cross section, and the numbers increase in clockwise direction. The i-th reinforcement R i The spatial function of can be characterized as:
[0016]
[0017] Where: R r w is the outer or inner diameter of the reinforcement body; 1,i 、w 2,i are the starting and ending points of the reinforcement in the Y-axis direction, θ 1,i ,θ 2,i They represent the angle between the line connecting the arc starting point and the origin of the i-th reinforcement and the X-axis, and the angle between the line connecting the arc end point and the origin and the X-axis in the XOZ plane.
[0018] In some embodiments, determining each structure space function further comprises:
[0019] For the mounting holes pre-arranged on the reinforcement body, its spatial function can be regarded as a cylindrical surface extended along the direction of its normal vector of a spatial circle. Then the spatial function of the jth mounting hole on the i-th reinforcement body can be expressed as:
[0020]
[0021] Among them: x0, y0, z0 are the coordinates of the center of the mounting hole, r is the radius of the mounting hole, l, m, n are the direction vectors of the center axis of the cylinder;
[0022] The positions of the holes to be drilled on the shield segment are the same as the positions of the installation holes on the reinforcement body, so they can be characterized by the same spatial function.
[0023] In some embodiments, the step of determining whether the assembly error after the reinforcement body is installed and fixed to the pipe segment meets the requirements includes:
[0024] A series of coordinates (x i , y i , z i ) as the judgment points, and calculate the spatial function R of the outer surface of the reinforcement body according to the x and y coordinates of these judgment points i The z coordinate value in (x, y, z) is compared with the z coordinate value of the discriminant point. i Compare the coordinate values;
[0025] When the cumulative error does not exceed the limit, the assembly error is considered to meet the requirements.
[0026] In some embodiments, collecting the segment structure information and the appendage information in the tunnel and determining the drilling restriction area includes:
[0027] Collect the segment structure reinforcement diagram and the layout diagram of the tunnel accessories to determine the spatial function of the drilling restriction area.
[0028] In some embodiments, determining the spatial function of the drilling restriction area includes:
[0029] The drilling restriction area is represented by the projection of the steel bars and the appendages in the tunnel on the inner surface of the segment;
[0030] In the spatial coordinate system, the center of a ring of segments on the cross section and the midpoint of the longitudinal section are taken as the origin O, the x and z axes are taken as the horizontal and vertical directions of the tunnel cross section, and the y axis is taken as the longitudinal direction of the tunnel. The spatial function of the projection area of the restriction on the inner surface of the segment is consistent or basically consistent with the spatial function of the outer surface of the reinforcement. The spatial function of the projection surface of the i-th restriction can be expressed as:
[0031]
[0032] Where: w s1,i 、w s2,i are the starting point and end point of the projection surface of the i-th restriction in the Y-axis direction, θ s1,i ,θ s2,i They represent the angle between the line connecting the starting point of the arc and the origin of the projection surface of the i-th steel bar and the X-axis, as well as the angle between the line connecting the end point of the arc and the origin and the X-axis in the XOZ plane.
[0033] In some embodiments, the determining whether the position of the hole to be drilled on the shield segment conflicts with the drilling restriction area includes:
[0034] The spatial function of the hole to be drilled on the shield segment and the spatial function of the drilling restriction area are solved simultaneously. If there is an intersection point between the two spatial functions, there is a hole to be drilled in the drilling restriction area.
[0035] In some embodiments, selecting an alignment base point on the segment includes:
[0036] Areas on the shield segment that are easy to identify or measure on site are selected as alignment base points, including lifting holes, grouting holes, and hand holes, to facilitate subsequent on-site projection layout.
[0037] In some embodiments, the step of arranging qualified holes to be drilled and drilling restriction areas on the segment based on the alignment base point includes:
[0038] The information of the alignment base point, the hole position to be drilled and the drilling restriction area is imported into the projection device, and the qualified hole position to be drilled and the drilling restriction area are projected onto the pipe segment by the projection device.
[0039] In some embodiments, projecting the qualified holes to be drilled and the drilling restriction areas onto the pipe segment by a projection device includes:
[0040] Setting an alignment base point in the projection device;
[0041] Turn on the projection device and only display the alignment cardinal points;
[0042] Adjust the projection zoom ratio and angle to make all alignment base points match the alignment base points on the on-site segments one by one;
[0043] Display all the holes to be drilled and the drilling restriction areas in the area;
[0044] Check one by one whether the projection graphics are consistent with the on-site conditions. If they are consistent, prepare for drilling construction at the designated locations of the segments.
[0045] The beneficial effects of the present invention compared to the prior art are as follows: the present invention provides a shield tunnel lining segment reinforcement auxiliary installation method, which aims to solve the problem of low efficiency and poor precision in the assembly of reinforcement bodies of shield tunnel lining segments. It is intended to use a bolt hole auxiliary positioning system to determine in advance the corresponding positions of the reinforcement body bolt holes on the shield segment, so that each reinforcement body can be accurately installed, thereby improving construction accuracy. At the same time, through spatial algorithms, avoidance rules and other means, the full ring of hole positions is pre-arranged before construction, so that time-consuming drilling operations can be carried out in parallel, greatly improving work efficiency. The specific advantages include at least one or more of the following:
[0046] (1) The method proposed in the present invention greatly improves the feasibility of construction. Through error judgment and conflict inspection, the present invention completes the adjustment and decision-making work that was originally required in the tunnel in advance, preventing the occurrence of situations such as the mismatch between the reinforcement and the tunnel segment and the inability to implement the drilling plan.
[0047] (2) The method proposed in the present invention improves the accuracy of installation. The present invention can accurately arrange the construction points in the digital space into the physical space by aligning the base point setting and construction projection, thereby improving the accuracy of construction and making it easier to achieve the expected installation requirements.
[0048] (3) The method proposed in the present invention significantly improves construction efficiency. Compared with the traditional construction method, the present invention can complete the two links of drilling holes and anchor bolt construction in the reinforcement body construction in parallel. At the same time, the drilling work can be completed by relying on spatial projection without lifting the heavy reinforcement body, which greatly improves the construction efficiency.
[0049] (4) The method proposed in the present invention has a small amount of algorithmic calculation and a light device. By using spatial functions, the present invention greatly reduces the high amount of calculation generated by directly using three-dimensional models. At the same time, the additional functions only need to be stored in a relatively light projection device, which is easy to use and worthy of promotion and use.
[0050] It should be understood that the implementation of any embodiment of the present invention does not mean that multiple or all of the above-mentioned beneficial effects must be possessed or achieved at the same time. BRIEF DESCRIPTION OF THE DRAWINGS
[0051] In order to more clearly illustrate the implementation methods of the present invention or the technical solutions in the prior art, the following briefly introduces the drawings required for the implementation methods or the description of the prior art. Obviously, the drawings in the following description are only exemplary, and for ordinary technicians in this field, other implementation drawings can be derived from the provided drawings without creative work.
[0052] The structures, proportions, sizes, etc. illustrated in this specification are only used to match the contents disclosed in the specification so as to facilitate understanding and reading by persons familiar with the technology. They are not used to limit the conditions under which the present invention can be implemented, and therefore have no substantial technical significance. Any structural modification, change in proportion or adjustment in size shall still fall within the scope of the technical contents disclosed in the present invention without affecting the effects and purposes that can be achieved by the present invention.
[0053] Figure 1 A schematic diagram showing an overall flow chart of an auxiliary installation method according to an embodiment of the present invention;
[0054] Figure 2 Schematic diagrams of the spatial functions of various structures in an embodiment of the present invention are exemplarily shown, wherein (a) represents the spatial function of the inner surface of the tunnel, and (b) represents the spatial function of the reinforcement body and the bolt hole;
[0055] Figure 3 A schematic diagram of a cross-section of a projection operation tunnel according to an embodiment of the present invention is exemplified;
[0056] Figure 4 A schematic diagram of a longitudinal section of a projection working tunnel according to an embodiment of the present invention is exemplarily shown.
[0057] In the figure: 1-segment; 2-reinforcement body; 3-projection equipment; 4-alignment base point; 5-bolt hole; B-area where bolt holes are to be drilled on the tunnel surface; S-drilling restriction area.
[0058] In the various drawings, the same or corresponding reference numerals represent the same or corresponding parts. DETAILED DESCRIPTION
[0059] In order to make the purpose, technical solution and advantages of the embodiments of the present invention more clearly understood, the embodiments of the present invention are further described in detail below in conjunction with the embodiments and drawings. Here, the illustrative embodiments of the present invention and their description are used to explain the present invention, but are not intended to limit the present invention.
[0060] In the present invention, unless otherwise clearly specified and limited, the terms "installed", "connected", "connected", "fixed" and the like should be understood in a broad sense, for example, it can be a fixed connection, a detachable connection, or an integral connection; it can be a mechanical connection or an electrical connection; it can be a direct connection or an indirect connection through an intermediate medium, it can be the internal connection of two elements or the interaction relationship between two elements. For ordinary technicians in this field, the specific meanings of the above terms in the present invention can be understood according to specific circumstances.
[0061] It should be understood that the terms "include / comprise", "consist of..." or any other variations are intended to cover non-exclusive inclusion, so that a product, device, process or method that includes a series of elements includes not only those elements, but also may include other elements not explicitly listed when necessary, or also includes elements inherent to such product, device, process or method. In the absence of more restrictions, the elements defined by the sentence "include / comprise...", "consist of..." do not exclude the presence of other identical elements in the product, device, process or method that includes the elements.
[0062] It is also necessary to understand that terms such as "upper", "lower", "front", "back", "left", "right", "top", "bottom", "inside" and "outside" to indicate directions or positional relationships are based on the directions or positional relationships shown in the accompanying drawings, and are only for the convenience of describing the present invention and simplifying the description, and do not indicate or imply that the referred device, component or structure must have a specific direction, be constructed or operate in a specific direction, and should not be understood as a limitation on the present invention.
[0063] In addition, the terms "first" and "second" are used for descriptive purposes only and should not be understood as indicating or implying relative importance or implicitly indicating the number of the indicated technical features. Therefore, the features defined as "first" and "second" may explicitly or implicitly include one or more of the features. In the description of the present invention, the meaning of "plurality" is two or more, unless otherwise clearly and specifically defined.
[0064] In order to better understand the above technical solution, the above technical solution will be described in detail below with reference to the accompanying drawings and specific implementation methods.
[0065] The present invention provides a shield tunnel lining segment reinforcement auxiliary installation method, comprising: obtaining the inner contour of the shield segment and the contour information of the reinforcement, wherein the reinforcement is preset with a mounting hole for mounting and fixing the reinforcement to the segment, and the mounting hole corresponds one-to-one to the position to be drilled on the shield segment; judging whether the assembly error after the reinforcement is mounted and fixed to the segment meets the requirement, and if not, adjusting the reinforcement; collecting the segment structure information and the information of the appendages in the tunnel, and determining the drilling restriction area; judging whether the position to be drilled on the shield segment conflicts with the drilling restriction area, and if so, adjusting the reinforcement or migrating the appendages in the tunnel, and if not, selecting an alignment base point on the segment; based on the alignment base point, arranging the qualified position to be drilled and the drilling restriction area on the segment; drilling construction is performed on the segment with reference to the position to be drilled and the drilling restriction area, and the reinforcement is installed and fixed. The auxiliary installation method for reinforcement bodies provided by the present invention can solve the problems of long drilling time for tunnel convergence and deformation, difficulty in ensuring the hole position, easy waste holes, or the inability to perform drilling and installation in parallel during the assembly of reinforcement bodies, which has a great impact on the construction progress. This effectively responds to the actual situation that the skylight time available for maintenance work in an operating subway is short and the time available for reinforcement work is very limited.
[0066] The specific implementation of the above auxiliary installation method is described in detail below in conjunction with a specific engineering example.
[0067] A subway shield tunnel has been in operation for many years. Through 3D laser scanning, it was found that several rings in the tunnel had lateral convergence deformation, and the deformation value exceeded the specification requirements. After expert evaluation, it was planned to use steel ring reinforcement to repair it and prevent the tunnel from continuing to deform. Figure 1 The method flow shown is used to design its construction.
[0068] (1) Obtain the inner contour information of the shield segment and the reinforcement body contour information.
[0069] Combination Figure 2 As shown, the reinforcement body 2 is made of an arc-shaped steel plate, and its shape is consistent or substantially consistent with the shape of the pipe segment 1 to be reinforced, and the arc-shaped steel plate is prefabricated with bolt holes 5 when it leaves the factory, and is installed and fixed to the pipe segment 1 to be reinforced by means of the bolt holes and bolts during reinforcement. During reinforcement, the bolt holes 5 need to correspond one-to-one to the positions to be drilled on the pipe segment 1, so the embodiment of the present invention needs to locate qualified positions to be drilled on the pipe segment 1 to be reinforced.
[0070] In this embodiment, a spatial model of the tunnel inner contour, that is, a spatial model of the segment, has been obtained through the early three-dimensional laser scanning. Figure 2The reinforcement body in this embodiment is composed of 5 pieces of Q345B arc-shaped steel plates with a thickness of 20 mm and a width of 850 mm. Several bolt holes 5 have been drilled on the steel plates at a spacing of 400 mm. According to the processing design drawing, the spatial model of the reinforcement body contour is obtained, as shown in FIG. Figure 2 As shown in (b) in .
[0071] In this embodiment, obtaining the inner contour information of the shield segment and the contour information of the reinforcement body preferably first includes: determining the spatial function of each structure.
[0072] Spatial function refers to the function that characterizes the geometric outline of an object. Figure 2 As shown in the figure, in the spatial coordinate system, the center of a ring of segments on the cross section and the midpoint of the longitudinal section are taken as the origin O, the x and z axes are taken as the horizontal and vertical directions of the tunnel cross section, and the y axis is taken as the longitudinal direction of the tunnel. The inner surface of the segment can be expressed as a cylindrical surface with the center of the cylinder as the Y axis, that is:
[0073]
[0074] Where: R t is the inner diameter of the tunnel, w t is the longitudinal width of the segment;
[0075] Reinforcement 2 is similar to segment 1, and is a unified partial cylindrical surface with the center of the column as the Y axis. The first reinforcement is located at the lower left of the tunnel cross section, and the numbers increase in clockwise direction. The i-th reinforcement R i The spatial function of can be characterized as:
[0076]
[0077] Where: R r w is the outer or inner diameter of the reinforcement body; 1,i 、w 2,i are the starting and ending points of the reinforcement in the Y-axis direction, θ 1,i ,θ 2,i They represent the angle between the line connecting the arc starting point and the origin of the i-th reinforcement and the X-axis, and the angle between the line connecting the arc end point and the origin and the X-axis in the XOZ plane.
[0078] For the bolt holes pre-arranged on the reinforcement body 2, their spatial function can be regarded as a cylindrical surface that is extended along the direction of its normal vector. Then the spatial function of the jth mounting hole on the i-th reinforcement body can be expressed as:
[0079]
[0080] Among them: x0, y0, z0 are the coordinates of the center of the mounting hole, r is the radius of the mounting hole, l, m, n are the direction vectors of the center axis of the cylinder;
[0081] The positions of the holes to be drilled on the shield segment are the same as the positions of the bolt holes on the reinforcement body, and therefore can be characterized by the same spatial function. In this embodiment, all areas where bolt holes are to be drilled on the tunnel surface are denoted as B.
[0082] The above spatial functions are simplified spatial functions for convenient calculation, which can meet the calculation accuracy of this embodiment. However, when the surface of a tunnel or a reinforced body is very rough, points on all surfaces of the structure can be obtained by scanning, and a set of functions containing several triangular faces can be obtained by confirming a plane using three adjacent points, so as to characterize the spatial function of the tunnel or reinforced body.
[0083] This part uses spatial functions to greatly reduce the high amount of calculations generated by directly using three-dimensional models. The algorithm has a small amount of calculations, and the additional functions only need to be stored in a relatively lightweight projection device. The device is lightweight and easy to use.
[0084] (2) Determine whether the assembly error after the reinforcement body is installed and fixed to the pipe segment meets the requirements. If not, adjust the reinforcement body.
[0085] The purpose of this step is to detect the degree of matching between the shape of the reinforcement and the contour inside the tunnel, avoiding time delays caused by secondary processing of the reinforcement at the construction site, thereby improving construction efficiency.
[0086] Theoretically, the spatial function of the outer surface of each reinforcement should be completely consistent with the inner surface of the tunnel. However, due to factors such as processing errors and irregular deformation of the inner surface of the tunnel, adhesives such as epoxy resin can usually be used to fill the gap between the two. Therefore, by judging the difference in the spatial functions of the two at specific points, the assembly error can be calculated.
[0087] In this embodiment, a series of coordinates (x i , y i , z i ) as the judgment points, and calculate the spatial function R of the outer surface of the reinforcement body according to the x and y coordinates of these judgment points i The z coordinate value in (x, y, z) is compared with the zi coordinate value of the judgment point. For example, in this embodiment, the root mean square error of the cumulative assembly error of the reinforcement body is:
[0088]
[0089] Among them, h m is the reinforcement body spatial function R i Substitute (x, y, z) into x i , y i The calculated value of z m Substitute x into the tunnel surface spatial function T(x, y, z)i , y i The calculated value of z after ; n is the number of decision points.
[0090] When the cumulative error does not exceed the limit, it can be considered that the assembly error meets the requirements. The number of judgment points and the cumulative error limit can be determined according to the construction level, tunnel deformation, specifications, etc. In this embodiment, 70 points per reinforcement body and a cumulative error limit of 15 mm are used for judgment. The calculated error does not exceed the limit, and there is no need to adjust the size of each reinforcement body.
[0091] If the assembly error requirements are not met, the reinforcement body needs to be adjusted, including adjusting the position of the reinforcement body, replacing the reinforcement body, etc.
[0092] Through error judgment, this link can complete the adjustment and decision-making work that was originally required in the tunnel in advance, prevent the occurrence of mismatch between the reinforcement body and the tunnel segment, and greatly improve the feasibility of construction.
[0093] (3) Collect information on the segment structure and the accessories in the tunnel to determine the drilling restriction area.
[0094] Since drilling operations cannot be carried out at the steel mesh inside the shield segment and at the accessories inside the tunnel, this link is mainly to collect the segment structure reinforcement diagram and the tunnel accessory layout diagram, and determine the spatial function of the drilling restriction area. The purpose is to quantitatively characterize the drilling restriction area in advance. This area will limit the drilling construction work later and should be excluded in advance.
[0095] The steel bars in the tunnel segments are generally arranged in layers, and the projection of each layer on the inner surface of the tunnel is consistent. Therefore, the projection surface of the steel bars on the inner surface of the tunnel segments can be used to represent the drilling restriction area. Similarly, the attachments in the tunnel can also be represented by the projection surface. For example, the attachments in the tunnel include pipelines, cables, equipment boxes, pantographs, lighting lamps, etc.
[0096] In the coordinate system mentioned above, the spatial function of the projection area of the restriction on the inner surface of the segment is consistent or basically consistent with the spatial function of the outer surface of the reinforcement. The spatial function of the projection surface of the i-th restriction can be expressed as:
[0097]
[0098] Where: w s1,i 、w s2,i are the starting point and end point of the projection surface of the i-th restriction in the Y-axis direction, θ s1,i ,θ s2,i They represent the angle between the line connecting the starting point of the arc and the origin of the projection surface of the i-th steel bar and the X-axis, as well as the angle between the line connecting the end point of the arc and the origin and the X-axis in the XOZ plane.
[0099] This embodiment uses the above-mentioned spatial function to characterize all the segment steel meshes and inner wall pipelines in the tunnel. The drilling restriction area composed of various restriction areas is recorded as S.
[0100] (4) Determine whether the position of the hole to be drilled on the shield segment conflicts with the drilling restriction area. If so, adjust the reinforcement or relocate the accessories in the tunnel. If not, select the alignment base point on the segment.
[0101] The purpose of this step is to prevent the segment area behind the prefabricated bolt holes on the reinforcement from being unable to be constructed.
[0102] In this embodiment, the area B where all bolt holes are to be drilled on the tunnel surface is obtained according to the above step (1) and the drilling restriction area S obtained in step (3), and the corresponding spatial functions are used for joint solution. When there is an intersection point between the two spatial functions after the joint solution, it means that there are bolt holes in the drilling restriction area, and it is necessary to adjust the construction restriction area or the bolt hole position. In this embodiment, 26 conflicts were found after inspection, of which 23 were overlapped with the appendages in the tunnel. After confirming that the relevant pipelines have the conditions for migration, only the pipeline migration can be carried out without adjusting the reinforcement body; there are 3 conflicts between the bolt hole position and the steel mesh of the pipe segment, and the bolt hole position of the reinforcement body must be adjusted.
[0103] After the pipeline migration design and secondary processing of some reinforcement bodies in this embodiment, it is confirmed again through steps (1) to (4) that there is no conflict. Therefore, the alignment base point can be selected on the pipe segment.
[0104] Areas on the existing shield segments that are easy to identify or measure on site, such as lifting holes, grouting holes, hand holes, etc., are selected as alignment base points 4 to facilitate subsequent on-site projection layout.
[0105] The alignment base points are used to ensure that the spatial model is consistent with the physical model. Selecting points that are easily identified on site can quickly and efficiently scale the geometric dimensions of the projection space, so that it can provide guidance for the physical model. Usually, within a projection range, at least 4 non-collinear base points should be set to ensure the effectiveness of the projection. In this embodiment, 8 hand holes on a ring of segments are selected as the alignment base points 4. Figure 3-4 shown.
[0106] This link uses conflict testing based on error judgment to complete the adjustments and decision-making work that was originally required in the tunnel in advance, preventing the tunnel segment drilling plan from being unable to be implemented, avoiding on-site rework and unnecessary damage to the segments, and greatly improving construction efficiency.
[0107] (5) Based on the alignment base point, the qualified holes to be drilled and the drilling restriction areas are arranged on the segment.
[0108] The purpose of this link is to facilitate on-site construction and enable drilling work to be carried out in parallel.
[0109] The spatial model that has been detected by conflict and set for the base point can be imported into the projection device, that is, the information of the base point, the position of the hole to be drilled and the drilling restriction area is imported into the projection device, and projected on the shield segment through the projection device. It is easy to understand that importing the projection device means converting the information of the above digital model into projectable picture information, which is convenient for the projection device to project.
[0110] Specifically can be divided into:
[0111] 5.1: Set the alignment base point in the projection device;
[0112] 5.2: Turn on the projection device and only display the alignment points;
[0113] 5.3: Adjust the projection scale and angle so that all the images are aligned with the base points (such as Figure 3-4 The small black triangles in the figure match the alignment base points on the on-site segments one by one;
[0114] 5.4: Display all the holes to be drilled and the drilling restriction areas in the area;
[0115] 5.5: Check whether the projection graphics are consistent with the on-site conditions one by one. If they are consistent, mark the designated parts of the pipe segments and prepare for drilling. On-site conditions include whether the construction restriction area is completely consistent with the site, whether the drilling position is in a position that is obviously not suitable for construction, and whether there are other situations on site that require adjustment of the plan.
[0116] The cross section of the working diagram of this link is as follows Figure 3 As shown, the longitudinal section is Figure 4 As shown, this embodiment uses a combined projection device 3 including multiple lenses, which can simultaneously project an area with a cross-section of 300° and a longitudinal width of 3m. After one alignment, it can satisfy the positioning of all points in the 2-ring segment.
[0117] (6) Drill holes on the segments according to the locations of holes to be drilled and the restricted areas for drilling, and install and fix the reinforcement bodies.
[0118] Finally, referring to the qualified holes to be drilled and the drilling restricted areas that have been laid out, drilling construction is carried out on the segments and the reinforcement bodies are installed and fixed, thus completing the reinforcement of the shield tunnel lining segments.
[0119] Due to the preparation of the previous work, the two steps of drilling and fixing the reinforcement body can be completed in parallel. In this embodiment, the drilling operation is performed according to the projection of 60 hole positions / rings, and the drilling is performed first, and then the steel plate that has been fully drilled is fixed. Usually, the drilling time for constructing a steel plate is less than the installation and fixing time. Therefore, the reinforcement method of this embodiment can be used by the relevant personnel to enter the next area with the projection equipment to perform drilling construction or complete the installation work in groups. Compared with the traditional construction method, this can significantly speed up the construction efficiency.
[0120] Although several specific implementation details are included in the above discussion, these should not be construed as limiting the scope of the present invention. Certain features described in the context of separate embodiments may also be implemented in a single implementation in combination. On the contrary, the various features described in the context of a single implementation may also be implemented in multiple implementations individually or in any suitable sub-combination.
[0121] The embodiments of the present invention have been described above, and the above description is exemplary, not exhaustive, and is not limited to the disclosed embodiments. Many modifications and variations will be apparent to those of ordinary skill in the art without departing from the scope and spirit of the described embodiments. The selection of terms used herein is intended to best explain the principles of the embodiments, practical applications, or technical improvements in the market, or to enable other persons of ordinary skill in the art to understand the embodiments disclosed herein.
Claims
1. A shield tunnel lining segment reinforcement auxiliary installation method, characterized in that: The steps include: Obtaining the inner contour of the shield segment and the contour information of the reinforcement body, and determining the spatial function of the shield segment and the reinforcement body, wherein the reinforcement body is preset with a mounting hole for fixing it to the segment, and the mounting hole corresponds one-to-one to the position of the hole to be drilled on the shield segment; Determine whether the assembly error after the reinforcement body is installed and fixed to the pipe segment meets the requirements. If not, adjust the reinforcement body; Collecting segment structure information and tunnel attachment information to determine the drilling restriction area; including: collecting segment structure reinforcement diagram and tunnel attachment layout diagram to determine the spatial function of the drilling restriction area; Determine whether the hole to be drilled on the shield segment conflicts with the drilling restriction area, including: performing simultaneous solution based on the spatial function of the hole to be drilled on the shield segment and the spatial function of the drilling restriction area, if there is an intersection point between the two spatial functions, then there is a hole to be drilled in the drilling restriction area; if there is a conflict, adjust the reinforcement or relocate the appendages in the tunnel; if there is no conflict, select an alignment base point on the segment; Based on the alignment base point, the qualified holes to be drilled and the drilling restriction areas are arranged on the pipe segment; Drill holes on the segments according to the locations of holes to be drilled and the restricted areas for drilling, and install and fix the reinforcement bodies.
2. The auxiliary installation method according to claim 1, characterized in that: Determining each structure space function includes: In the spatial coordinate system, the center of a ring of segments on the cross section and the midpoint of the longitudinal section are taken as the origin O, the x and z axes are the horizontal and vertical directions of the tunnel cross section, and the y axis is the longitudinal direction of the tunnel. The inner surface of the segment can be expressed as a cylindrical surface with the center as the Y axis, that is: ; Where: R t is the inner diameter of the tunnel, w t is the longitudinal width of the segment; The reinforcement is similar to the segment, which is a part of the cylindrical surface with the Y axis as the center. The first reinforcement is at the lower left of the tunnel cross section, and the numbers increase in clockwise direction. The i-th reinforcement R i The spatial function of can be characterized as: ; Where: R r w is the outer or inner diameter of the reinforcement body; 1,i 、w 2,i are the starting and ending points of the reinforcement in the Y-axis direction, θ 1,i ,θ 2,i They represent the angle between the line connecting the arc starting point and the origin of the i-th reinforcement and the X-axis, and the angle between the line connecting the arc end point and the origin and the X-axis in the XOZ plane.
3. The auxiliary installation method according to claim 2, characterized in that: Determining the spatial functions of each structure also includes: For the mounting holes pre-arranged on the reinforcement body, its spatial function can be regarded as a cylindrical surface extended along the direction of its normal vector of a spatial circle. Then the spatial function of the jth mounting hole on the i-th reinforcement body can be expressed as: ; Among them: x0, y0, z0 are the coordinates of the center of the mounting hole, r is the radius of the mounting hole, l, m, n are the direction vectors of the center axis of the cylinder; The positions of the holes to be drilled on the shield segment are the same as the positions of the installation holes on the reinforcement body, so they can be characterized by the same spatial function.
4. The auxiliary installation method according to claim 1, characterized in that: The step of judging whether the assembly error after the reinforcement body is installed and fixed to the pipe segment meets the requirements includes: A series of coordinates (x i , y i , z i ) as the judgment points, and calculate the spatial function R of the outer surface of the reinforcement body according to the x and y coordinates of these judgment points i The z coordinate value in (x, y, z) is compared with the z coordinate value of the discriminant point. i Compare the coordinate values; When the cumulative error does not exceed the limit, the assembly error is considered to meet the requirements.
5. The auxiliary installation method according to claim 1, characterized in that: The spatial function for determining the drilling restriction area includes: The drilling restriction area is represented by the projection of the steel bars and the appendages in the tunnel on the inner surface of the segment; In the spatial coordinate system, the center of a ring of segments on the cross section and the midpoint of the longitudinal section are taken as the origin O, the x and z axes are taken as the horizontal and vertical directions of the tunnel cross section, and the y axis is taken as the longitudinal direction of the tunnel. The spatial function of the projection area of the restriction on the inner surface of the segment is consistent or basically consistent with the spatial function of the outer surface of the reinforcement. The spatial function of the projection surface of the i-th restriction can be expressed as: ; Where: w s1,i 、w s2,i are the starting point and end point of the projection surface of the i-th restriction in the Y-axis direction, θ s1,i ,θ s2,i They represent the angle between the line connecting the starting point of the arc and the origin of the projection surface of the i-th steel bar and the X-axis, as well as the angle between the line connecting the end point of the arc and the origin and the X-axis in the XOZ plane.
6. The auxiliary installation method according to claim 1, characterized in that: The step of arranging the qualified holes to be drilled and the drilling restriction areas on the segments based on the alignment base point includes: The information of the alignment base point, the hole position to be drilled and the drilling restriction area is imported into the projection device, and the qualified hole position to be drilled and the drilling restriction area are projected onto the pipe segment by the projection device.
7. The auxiliary installation method according to claim 6, characterized in that: The projecting of the qualified holes to be drilled and the drilling restriction areas onto the pipe segment by the projection device includes: Setting an alignment base point in the projection device; Turn on the projection device and only display the alignment cardinal points; Adjust the projection zoom ratio and angle to make all alignment base points match the alignment base points on the on-site segments one by one; Display all the holes to be drilled and the drilling restriction areas in the area; Check one by one whether the projection graphics are consistent with the on-site conditions. If they are consistent, prepare for drilling construction at the designated locations of the segments.
Citation Information
Patent Citations
Shield tunnel lining segment and reinforcing method thereof
CN107620598A
Lining reinforcing part and shield tunnel lining reinforcing method
CN116517598A
Shield tunnel lining reinforcing structure
CN220621871U
Complete device for repairing and reinforcing shield tunnel segments, and repair and reinforcement process
WO2022253243A1