A cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge

By real-time monitoring and adjustment of cable force in a cable-stayed bridge with a large span curve T structure, the problems of high cost and low efficiency of cable force monitoring in the existing technology are solved, and the uniformity of cable force and structural safety are improved, and the simplification of cable force is achieved. The construction process was completed.

CN118294060BActive Publication Date: 2024-11-26CHINA RAILWAY SEVENTH GRP CO LTD +1
View PDF 0 Cites 0 Cited by

Patent Information

Application Number
CN202410537702.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-04-30
Publication Date
2024-11-26
Estimated Expiration
2044-04-30

AI Technical Summary

Technical Problem

The prior art cannot meet the long-term, uninterruptible and efficient cable-stayed bridge cable-stranded bridge cable-stranded bridge cable-stranded bridge cable-stranded bridge cable-stranded bridge cable-stranded bridge cable-stranded needs to be high cost and cannot take into account the demand for reasonable stresses of ideal bridge linear shape and cable-strand tension.

Method used

The cable force monitoring method of cable-stayed bridge of a large-span curve T-structure low tower is used to determine the number of cables and anchor points, and the tension force of each cable is estimated, and the cable force is monitored in real time during the construction process, using a penetrating type The cable force sensor is measured and adjusted to ensure cable force uniformity and structural safety.

Benefits of technology

The ideal high-quality bridge linear shape and cable tensioning are achieved, which improves cable force safety and structural safety, reduces monitoring costs, simplifies the construction process, and improves the overall structural quality of the bridge.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118294060B_ABST
    Figure CN118294060B_ABST
Patent Text Reader

Abstract

The present invention discloses a cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge, comprising the following steps: 1. determining the number of cables of the long-span curved T-structure low-tower cable-stayed bridge and the anchor point position of each cable; 2. estimating the tensioning force of each cable and performing simulated positive calculation on the entire construction process; 3. tensioning and cable force monitoring of the first and second cables; 4. tensioning and cable force monitoring of the third cable; 5. tensioning and cable force monitoring of the i-th cable; 6. supplementary tensioning and cable force monitoring of the first and second cables; 7. measuring and obtaining the bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge; 8. replacing sensors and monitoring the cable force of the long-span curved T-structure low-tower cable-stayed bridge in the operation stage. The present invention takes the high-quality ideal bridge alignment and the reasonable force of cable tensioning as monitoring targets, so as to achieve the purpose of comprehensively improving the cable force safety and structural safety, thereby improving the overall structural quality of the bridge.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention belongs to the technical field of bridge detection, and in particular relates to a cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge. Background Art

[0002] During the long-term service of bridges, structural fatigue will occur, and the health problems of bridge structures continue to emerge. Cables, as important load-bearing components of cable-stayed bridges, directly affect the health, safety and stability of cable-stayed bridge structures. Therefore, cable force monitoring has become an important monitoring parameter for bridge structure safety monitoring. Especially for large-span cable-stayed bridges, in addition to bearing most of the structural load, they are also an important part of the entire structural stiffness. The cable force is an important parameter in the design. The size of the cable force directly affects the linear shape of the main beam, the internal force distribution of the main beam, and the displacement and torsion of the main tower. Therefore, during the construction process, accurately measuring the cable force value and adjusting it to within the range of design requirements is the key to ensuring the safety of the cable-stayed bridge structure and construction.

[0003] At present, the measurement of bridge cable tension can be carried out by string vibration theory, oil gauge, elongation value dual control method, etc. The string vibration theory, oil gauge, elongation value dual control method and EM magnetic flux method require repeated manual operation to measure cable tension, which does not meet the long-term and uninterrupted monitoring nature of cable tension monitoring, and the labor cost is high, and it is impossible to take into account the monitoring of the ideal bridge line shape and the reasonable tension of the cable tension. Summary of the invention

[0004] The technical problem to be solved by the present invention is to provide a cable force monitoring method for a large-span curved T-structure low-tower cable-stayed bridge in view of the deficiencies in the above-mentioned prior art, taking the high-quality ideal bridge line shape and the reasonable force of the cable tensioning as the monitoring targets, so as to achieve the purpose of comprehensively improving the cable force safety and structural safety, thereby improving the overall structural quality of the bridge and facilitating its popularization and use.

[0005] In order to solve the above technical problems, the technical solution adopted by the present invention is: a cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge, characterized in that the method comprises the following steps:

[0006] Step 1: determine the number of cables and the anchor point position of each cable of the long-span curved T-structure low-tower cable-stayed bridge;

[0007] Step 2: Estimate the tension of each cable and simulate the whole construction process;

[0008] Step 3: Tensioning and cable force monitoring of the first and second cables. The process is as follows:

[0009] Step 301, pre-elevation of the first and second cables: on the basis of the design elevations of the anchor points corresponding to the first and second cables on the short tower, a plurality of first pre-elevation parameters are superimposed, wherein the plurality of first pre-elevation parameters respectively include the loading test deformation of the beam sections corresponding to the first and second cables, the deformation generated during the construction of the beam sections corresponding to the first and second cables, the deformation generated during the operation stage of the beam sections corresponding to the first and second cables, the deformation generated by the shrinkage creep of the beam sections corresponding to the first and second cables, and a first adjustment value for later adjustment;

[0010] Step 302, installation and tensioning of the first and second cables: the first and second cables are installed according to the anchor point control positions of the first and second cables, and through-type cable force sensors are installed on the first and second cables, and the tensioning force of the first and second cables only needs to meet the deadweight of the casing;

[0011] Step 303: using the through-type cable force sensors installed on the first and second cables to monitor the cable forces of the first and second cables in real time during the construction phase;

[0012] Step 4: Tensioning and cable force monitoring of the third cable. The process is as follows:

[0013] Step 401, pre-elevation of the third cable: on the basis of the design elevation of the anchor point corresponding to the third cable on the short tower, a plurality of second pre-elevation parameters are superimposed, wherein the plurality of second pre-elevation parameters respectively include the loading test deformation of the hanging blue on the beam section corresponding to the third cable, the deformation generated during the construction of the beam section corresponding to the third cable, the deformation generated during the operation stage of the beam section corresponding to the third cable, the deformation generated by the shrinkage creep of the beam section corresponding to the third cable, and a second adjustment value for later adjustment;

[0014] Step 402, installation and tensioning of the third cable: installing the third cable according to the anchor point control position of the third cable, and installing a through-type cable force sensor on the third cable;

[0015] According to the formula Obtain the tension force T3 of the third cable, and tension the third cable according to T3, where N is the overall tension control force of the cable, N 12 is the tension of the first and second cables in step 302, n is the total number of cables of the long-span curved T-structure low-tower cable-stayed bridge, E c is the elastic modulus of the cable, A is the cross-sectional area of ​​the cable, δ is the change in cable length caused by the change of the tower and the main beam during cable installation, c is the retraction of the clip, and l is the calculated cable length of the cable;

[0016] Step 403: using a through-type cable force sensor installed on the third cable to monitor the cable force of the third cable in real time during the construction phase;

[0017] Step 5: Tensioning and cable force monitoring of the i-th cable. The process is as follows:

[0018] Step 501, pre-elevation of the ith cable: on the basis of the design elevation of the anchor point corresponding to the ith cable on the short tower, a plurality of third pre-elevation parameters are superimposed, the plurality of third pre-elevation parameters respectively including the loading test deformation of the beam section corresponding to the ith cable, the deformation generated during the construction of the beam section corresponding to the ith cable, the deformation generated during the operation stage of the beam section corresponding to the ith cable, the deformation generated by the shrinkage creep of the beam section corresponding to the ith cable, and a third adjustment value for later adjustment, wherein i is a positive integer and 3≤i≤n;

[0019] Step 502, installation and tensioning of the i-th cable: installing the i-th cable according to the anchor point control position of the i-th cable, and installing a through-type cable force sensor on the i-th cable;

[0020] According to the formula T i =T i-1 -Δ i , obtain the tension T of the i-th cable i , according to T i The i-th cable is tensioned, where T i-1 is the tension of the i-1th cable, Δ i is the sensor change value when the i-th cable is installed;

[0021] Step 503: using a through-type cable force sensor installed on the i-th cable to monitor the cable force of the i-th cable in real time during the construction phase;

[0022] Step 6: Re-tensioning and cable force monitoring of the first and second cables: After the tensioning of the last cable is completed, re-tensioning is performed on the first and second cables to ensure that the uniformity of the cable force values ​​of all cables is controlled within the range that the cable force discrete error of each cable is no more than ±2% of the theoretical cable force value;

[0023] Step seven, measure and obtain the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge. When the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge meets the ideal completed bridge alignment standard, the cable force monitoring of the long-span curved T-structure low-tower cable-stayed bridge during the construction phase is completed; when the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge does not meet the ideal completed bridge alignment standard, adjust the first adjustment value, the second adjustment value and / or the third adjustment value, and perform supplementary tensioning on all cables until the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge meets the ideal completed bridge alignment standard, and the cable force monitoring of the long-span curved T-structure low-tower cable-stayed bridge during the construction phase is completed;

[0024] Step 8. Replace sensors and monitor the cable tension of the large-span curved T-structure low-tower cable-stayed bridge during the operation phase: remove the through-type cable tension sensors on all cables and replace them with string-vibration cable tension meters to monitor the cable tension of the large-span curved T-structure low-tower cable-stayed bridge during the operation phase.

[0025] The above-mentioned cable force monitoring method for a large-span curved T-structure low-tower cable-stayed bridge is characterized in that: in step two, based on the vertical component of the beam of each cable being equal to the deadweight of the corresponding main beam block and the force margin, the tensioning force of each cable is estimated and the entire construction process is simulated and analyzed for positive calculation to obtain a predicted bridge line shape, which is compared with the predetermined ideal bridge line shape, the tensioning force at each stage is corrected, and then a new round of positive calculation is performed; after multiple iterations, the ideal bridge line shape is obtained.

[0026] The above-mentioned cable force monitoring method for a large-span curved T-structure low-tower cable-stayed bridge is characterized in that: in step 302, during the installation and tensioning process of the first and second cables, the installation positions of the first and second cables are measured in real time as the cable-stayed bridge is constructed, and the measurement work is completed when the temperature of the structural member is in a stable period, that is, the measurement work is completed from 3 pm to before sunrise, and the measurement work includes measuring the installation positioning coordinates and anchor point coordinates of the cable-stayed cable anchor at the tower column end.

[0027] The above-mentioned cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge is characterized in that: in step 6, the theoretical cable force value is calculated according to the formula get.

[0028] The above-mentioned cable force monitoring method for a large-span curved T-structure low-tower cable-stayed bridge is characterized in that the deformation generated during the construction of the corresponding beam section of each cable is determined by interference parameters, and the interference parameters include the deadweight of the box girder, tensioning disturbance and hanging blue walking disturbance.

[0029] The above-mentioned cable force monitoring method for a large-span curved T-structure low-tower cable-stayed bridge is characterized in that: in step seven, the measurement of the bridge line shape of the large-span curved T-structure low-tower cable-stayed bridge is completed when the temperature of the structural components is in a stable period, that is, the measurement work is completed from 3 pm to before sunrise.

[0030] Compared with the prior art, the present invention has the following advantages:

[0031] 1. During the tensioning and cable force monitoring process of each cable, the present invention comprehensively considers the deformation of the hanging blue during loading and pressure testing, the deformation generated during the construction of the beam section, the deformation generated during the operation stage, the deformation generated by the shrinkage creep of the beam section, and the adjustment value for the later adjustment of the bridge body line shape, so as to take the high-quality ideal bridge line shape and the reasonable force of the cable tensioning as the monitoring target, so as to achieve the purpose of comprehensively improving the cable force safety and structural safety, and facilitate popularization and use.

[0032] 2. In the process of tensioning the cables of the present invention, when the latter cable is tensioned, as the cable force value of the latter cable increases, the cable force value of the first tensioned cable gradually decreases. When the cable force values ​​of the two cables are equal, the cable force value at this time is the tensioning cable force value of the latter cable, and so on. The uniformity of the cable force in the cables can be ensured, which is reliable, stable and has a good use effect.

[0033] 3. The method of the present invention has simple steps. After tensioning and supplementing all the cables, the completed bridge line shape of the large-span curved T-structure low-tower cable-stayed bridge is measured and obtained, and the line shape is adjusted in time. When the completed bridge line shape of the large-span curved T-structure low-tower cable-stayed bridge meets the ideal completed bridge line shape standard, the cable force monitoring of the large-span curved T-structure low-tower cable-stayed bridge during the construction phase is completed, thereby improving the overall structural quality of the bridge and facilitating its popularization and use.

[0034] In summary, the present invention takes high-quality ideal bridge alignment and reasonable cable tensioning stress as monitoring targets, so as to achieve the purpose of comprehensively improving cable safety and structural safety, thereby improving the overall structural quality of the bridge and facilitating popularization and use.

[0035] The technical solution of the present invention is further described in detail below through the accompanying drawings and embodiments. BRIEF DESCRIPTION OF THE DRAWINGS

[0036] Figure 1 The figure is a flowchart of the method of the present invention. DETAILED DESCRIPTION

[0037] like Figure 1 As shown, a cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge of the present invention comprises the following steps:

[0038] Step 1: determine the number of cables and the anchor point position of each cable of the long-span curved T-structure low-tower cable-stayed bridge;

[0039] Step 2: Estimate the tension of each cable and simulate the whole construction process;

[0040] Step 3: Tensioning and cable force monitoring of the first and second cables. The process is as follows:

[0041] Step 301, pre-elevation of the first and second cables: on the basis of the design elevations of the anchor points corresponding to the first and second cables on the short tower, a plurality of first pre-elevation parameters are superimposed, wherein the plurality of first pre-elevation parameters respectively include the loading test deformation of the beam sections corresponding to the first and second cables, the deformation generated during the construction of the beam sections corresponding to the first and second cables, the deformation generated during the operation stage of the beam sections corresponding to the first and second cables, the deformation generated by the shrinkage creep of the beam sections corresponding to the first and second cables, and a first adjustment value for later adjustment;

[0042] Step 302, installation and tensioning of the first and second cables: the first and second cables are installed according to the anchor point control positions of the first and second cables, and through-type cable force sensors are installed on the first and second cables, and the tensioning force of the first and second cables only needs to meet the deadweight of the casing;

[0043] Step 303: using the through-type cable force sensors installed on the first and second cables to monitor the cable forces of the first and second cables in real time during the construction phase;

[0044] Step 4: Tensioning and cable force monitoring of the third cable. The process is as follows:

[0045] Step 401, pre-elevation of the third cable: on the basis of the design elevation of the anchor point corresponding to the third cable on the short tower, a plurality of second pre-elevation parameters are superimposed, wherein the plurality of second pre-elevation parameters respectively include the loading test deformation of the hanging blue on the beam section corresponding to the third cable, the deformation generated during the construction of the beam section corresponding to the third cable, the deformation generated during the operation stage of the beam section corresponding to the third cable, the deformation generated by the shrinkage creep of the beam section corresponding to the third cable, and a second adjustment value for later adjustment;

[0046] Step 402, installation and tensioning of the third cable: installing the third cable according to the anchor point control position of the third cable, and installing a through-type cable force sensor on the third cable;

[0047] According to the formula Obtain the tension force T3 of the third cable, and tension the third cable according to T3, where N is the overall tension control force of the cable, N 12 is the tension of the first and second cables in step 302, n is the total number of cables of the long-span curved T-structure low-tower cable-stayed bridge, E c is the elastic modulus of the cable, A is the cross-sectional area of ​​the cable, δ is the change in cable length caused by the change of the tower and the main beam during cable installation, c is the retraction of the clip, and l is the calculated cable length of the cable;

[0048] Step 403: using a through-type cable force sensor installed on the third cable to monitor the cable force of the third cable in real time during the construction phase;

[0049] Step 5: Tensioning and cable force monitoring of the i-th cable. The process is as follows:

[0050] Step 501, pre-elevation of the ith cable: on the basis of the design elevation of the anchor point corresponding to the ith cable on the short tower, a plurality of third pre-elevation parameters are superimposed, the plurality of third pre-elevation parameters respectively including the loading test deformation of the beam section corresponding to the ith cable, the deformation generated during the construction of the beam section corresponding to the ith cable, the deformation generated during the operation stage of the beam section corresponding to the ith cable, the deformation generated by the shrinkage creep of the beam section corresponding to the ith cable, and a third adjustment value for later adjustment, wherein i is a positive integer and 3≤i≤n;

[0051] Step 502, installation and tensioning of the i-th cable: installing the i-th cable according to the anchor point control position of the i-th cable, and installing a through-type cable force sensor on the i-th cable;

[0052] According to the formula T i =T i-1 -Δ i , obtain the tension T of the i-th cable i , according to T i The i-th cable is tensioned, where T i-1 is the tension of the i-1th cable, Δ i is the sensor change value when the i-th cable is installed;

[0053] Step 503: using a through-type cable force sensor installed on the i-th cable to monitor the cable force of the i-th cable in real time during the construction phase;

[0054] Step 6: Re-tensioning and cable force monitoring of the first and second cables: After the tensioning of the last cable is completed, re-tensioning is performed on the first and second cables to ensure that the uniformity of the cable force values ​​of all cables is controlled within the range that the cable force discrete error of each cable is no more than ±2% of the theoretical cable force value;

[0055] Step seven, measure and obtain the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge. When the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge meets the ideal completed bridge alignment standard, the cable force monitoring of the long-span curved T-structure low-tower cable-stayed bridge during the construction phase is completed; when the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge does not meet the ideal completed bridge alignment standard, adjust the first adjustment value, the second adjustment value and / or the third adjustment value, and perform supplementary tensioning on all cables until the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge meets the ideal completed bridge alignment standard, and the cable force monitoring of the long-span curved T-structure low-tower cable-stayed bridge during the construction phase is completed;

[0056] Step 8. Replace sensors and monitor the cable tension of the large-span curved T-structure low-tower cable-stayed bridge during the operation phase: remove the through-type cable tension sensors on all cables and replace them with string-vibration cable tension meters to monitor the cable tension of the large-span curved T-structure low-tower cable-stayed bridge during the operation phase.

[0057] It should be noted that the cables are installed in order from bottom to top on the long-span curved T-structure dwarf tower. The first cable refers to the lowest and innermost cable, the second cable refers to the cable located above and outside the first cable, and so on.

[0058] In actual implementation, the cable tension is one of the most important monitoring indicators during the construction of cable-stayed bridges. The through-type sensor has the advantages of high accuracy, fast testing speed and little environmental interference, and is used to measure the tension of the tensioned cable; the string-vibration cable force meter is used to measure the tension of the tensioned cable and the tensioned cable.

[0059] In this embodiment, in step two, based on the vertical component of each cable on the beam being equal to the deadweight of the corresponding main beam block and the force margin, the tensioning force of each cable is estimated and the entire construction process is simulated and analyzed by positive calculation to obtain a predicted bridge line shape, which is compared with the predetermined ideal bridge line shape, the tensioning force at each stage is corrected, and then a new round of positive calculation is performed; after multiple iterations, the ideal bridge line shape is obtained.

[0060] In this embodiment, in step 302, during the installation and tensioning of the first and second cables, the installation positions of the first and second cables are measured in real time as the cable-stayed bridge is constructed. The measurement work is completed when the temperature of the structural components is stable, that is, from 3 pm to before sunrise. The measurement work includes measuring the installation positioning coordinates and anchor point coordinates of the cable-stayed cable anchor at the tower end.

[0061] It should be noted that the coordinates of the cable anchor point and the inclination angle of the cable sleeve have a great influence on the main beam line shape and force, and are the focus of tower column construction control. In addition, the tower deviation can also be understood through the detection of the anchor point coordinates.

[0062] In this embodiment, in step 6, the theoretical cable force value is calculated according to the formula get.

[0063] In this embodiment, the deformation amount generated when each cable corresponds to the beam section during construction is determined by interference parameters, and the interference parameters include the deadweight of the box beam, tensioning disturbance and hanging blue walking disturbance.

[0064] In this embodiment, in step seven, the measurement of the completed bridge line shape of the long-span curved T-structure low-tower cable-stayed bridge is completed when the temperature of the structural components is stable, that is, the measurement work is completed from 3 pm to before sunrise.

[0065] If the tensile stress of the top and bottom slab concrete exceeds the allowable range during the calculation process implemented by the present invention, the tension cable force values ​​of these construction stages are adjusted in a targeted manner, and the calculation is performed again after the adjustment. Repeated trial calculations will eventually result in a set of tension cable force values, so that the structural stress during the construction process is always within a safe range throughout the construction process and meets the verification calculation requirements of the bridge operation stage.

[0066] The above description is only a preferred embodiment of the present invention and does not limit the present invention in any way. Any simple modification, change and equivalent structural change made to the above embodiment based on the technical essence of the present invention still falls within the protection scope of the technical solution of the present invention.

Claims

1. A cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge, characterized in that: The method comprises the following steps: Step 1: determine the number of cables and the anchor point position of each cable of the long-span curved T-structure low-tower cable-stayed bridge; Step 2: Estimate the tension of each cable and simulate the whole construction process; Step 3: Tensioning and cable force monitoring of the first and second cables. The process is as follows: Step 301, pre-elevation of the first and second cables: on the basis of the design elevations of the anchor points corresponding to the first and second cables on the short tower, a plurality of first pre-elevation parameters are superimposed, wherein the plurality of first pre-elevation parameters respectively include the loading test deformation of the beam sections corresponding to the first and second cables, the deformation generated during the construction of the beam sections corresponding to the first and second cables, the deformation generated during the operation stage of the beam sections corresponding to the first and second cables, the deformation generated by the shrinkage creep of the beam sections corresponding to the first and second cables, and a first adjustment value for later adjustment; Step 302, installation and tensioning of the first and second cables: the first and second cables are installed according to the anchor point control positions of the first and second cables, and through-type cable force sensors are installed on the first and second cables, and the tensioning force of the first and second cables only needs to meet the deadweight of the casing; Step 303: using the through-type cable force sensors installed on the first and second cables to monitor the cable forces of the first and second cables in real time during the construction phase; Step 4: Tensioning and cable force monitoring of the third cable. The process is as follows: Step 401, pre-elevation of the third cable: on the basis of the design elevation of the anchor point corresponding to the third cable on the short tower, a plurality of second pre-elevation parameters are superimposed, wherein the plurality of second pre-elevation parameters respectively include the loading test deformation of the hanging blue on the beam section corresponding to the third cable, the deformation generated during the construction of the beam section corresponding to the third cable, the deformation generated during the operation stage of the beam section corresponding to the third cable, the deformation generated by the shrinkage creep of the beam section corresponding to the third cable, and a second adjustment value for later adjustment; Step 402, installation and tensioning of the third cable: installing the third cable according to the anchor point control position of the third cable, and installing a through-type cable force sensor on the third cable; According to the formula Obtain the tension force T3 of the third cable, and tension the third cable according to T3, where N is the overall tension control force of the cable, N 12 is the tension of the first and second cables in step 302, n is the total number of cables of the long-span curved T-structure low-tower cable-stayed bridge, E c is the elastic modulus of the cable, A is the cross-sectional area of ​​the cable, δ is the change in cable length caused by the change of the tower and the main beam during cable installation, c is the retraction of the clip, and l is the calculated cable length of the cable; Step 403: using a through-type cable force sensor installed on the third cable to monitor the cable force of the third cable in real time during the construction phase; Step 5: Tensioning and cable force monitoring of the i-th cable. The process is as follows: Step 501, pre-elevation of the ith cable: on the basis of the design elevation of the anchor point corresponding to the ith cable on the short tower, a plurality of third pre-elevation parameters are superimposed, the plurality of third pre-elevation parameters respectively including the loading test deformation of the beam section corresponding to the ith cable, the deformation generated during the construction of the beam section corresponding to the ith cable, the deformation generated during the operation stage of the beam section corresponding to the ith cable, the deformation generated by the shrinkage creep of the beam section corresponding to the ith cable, and a third adjustment value for later adjustment, wherein i is a positive integer and 3≤i≤n; Step 502, installation and tensioning of the i-th cable: installing the i-th cable according to the anchor point control position of the i-th cable, and installing a through-type cable force sensor on the i-th cable; According to the formula T i =T i-1 -Δ i , obtain the tension T of the i-th cable i , according to T i The i-th cable is tensioned, where T i-1 is the tension of the i-1th cable, Δ i is the sensor change value when the i-th cable is installed; Step 503: using a through-type cable force sensor installed on the i-th cable to monitor the cable force of the i-th cable in real time during the construction phase; Step 6: Re-tensioning and cable force monitoring of the first and second cables: After the tensioning of the last cable is completed, re-tensioning is performed on the first and second cables to ensure that the uniformity of the cable force values ​​of all cables is controlled within the range that the cable force discrete error of each cable is no more than ±2% of the theoretical cable force value; Step seven, measure and obtain the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge. When the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge meets the ideal completed bridge alignment standard, the cable force monitoring of the long-span curved T-structure low-tower cable-stayed bridge during the construction phase is completed; when the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge does not meet the ideal completed bridge alignment standard, adjust the first adjustment value, the second adjustment value and / or the third adjustment value, and perform supplementary tensioning on all cables until the completed bridge alignment of the long-span curved T-structure low-tower cable-stayed bridge meets the ideal completed bridge alignment standard, and the cable force monitoring of the long-span curved T-structure low-tower cable-stayed bridge during the construction phase is completed; Step 8. Replace sensors and monitor the cable tension of the large-span curved T-structure low-tower cable-stayed bridge during the operation phase: remove the through-type cable tension sensors on all cables and replace them with string-vibration cable tension meters to monitor the cable tension of the large-span curved T-structure low-tower cable-stayed bridge during the operation phase.

2. A cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge according to claim 1, characterized in that: In step 2, based on the vertical force component on the beam of each cable being equal to the deadweight of the corresponding main beam block and the force margin, the tension of each cable is estimated and the entire construction process is simulated and analyzed to obtain a predicted bridge alignment. The predicted bridge alignment is compared with the predetermined ideal bridge alignment, the tension at each stage is corrected, and a new round of alignment calculation is performed; After multiple iterations, the ideal bridge line shape is obtained.

3. A cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge according to claim 1, characterized in that: In step 302, during the installation and tensioning of the first and second cables, the installation positions of the first and second cables are measured in real time as the cable-stayed bridge is constructed. The measurement work is completed when the temperature of the structural components is stable, that is, from 3 pm to before sunrise. The measurement work includes measuring the installation positioning coordinates and anchor point coordinates of the cable-stayed cable anchor at the tower end.

4. A cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge according to claim 1, characterized in that: In step 6, the theoretical cable force value is calculated according to the formula get.

5. A cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge according to claim 1, characterized in that: The deformation amount generated when each cable corresponds to the beam section during construction is determined by interference parameters, which include the deadweight of the box beam, tension disturbance and hanging blue walking disturbance.

6. A cable force monitoring method for a long-span curved T-structure low-tower cable-stayed bridge according to claim 1, characterized in that: In step seven, the measurement of the completed bridge line shape of the long-span curved T-structure low-tower cable-stayed bridge is completed during the period when the temperature of the structural components is stable, that is, the measurement work is completed from 3 pm to before sunrise.