Pollutant removal device that can adjust the retention time of river water and the exchange rate of the subsurface flow zone

By installing a third-level artificial weir group and microbial reproduction space on the riverbed, combined with an anchoring mechanism, the shortcomings of the undercurrent belt repair device in the prior art are solved, and efficient repair of the undercurrent belt and pollutant removal are achieved. , suitable for large-area river section restoration.

CN118326878BActive Publication Date: 2024-12-03CHINA GEOLOGICAL SURVEY NATURAL RESOURCES COMPREHENSIVE SURVEY COMMAND CENT
View PDF 6 Cites 0 Cited by

Patent Information

Application Number
CN202410570526.7
Authority / Receiving Office
CN · China
Patent Type
Patents(China)
Current Assignee / Owner
Filing Date
2024-05-09
Publication Date
2024-12-03
Estimated Expiration
2044-05-09

AI Technical Summary

Technical Problem

The existing underflow belt repair device cannot effectively adjust the retention time of the river water body and the exchange volume of underflow belt. It is complex in operation and is not suitable for large-area repairs, and the device cannot be recycled, which increases the repair cost.

Method used

An adjustable device including an artificial weir group and a weir connecting mechanism is designed. By installing a three-stage artificial weir group on the riverbed, a steep ridge of different heights is formed, the exchange flux of the undercurrent belt and the retention time of the water body are adjusted, and through microorganisms The breeding space and anchoring mechanism improve the stability and repair efficiency of the device.

Benefits of technology

It realizes flexible regulation of the exchange flux of the undercurrent belt and the retention time of the water body, improves the efficiency of pollutant removal, simplifies the operation process, reduces the repair cost, and is suitable for long-term river section restoration.

✦ Generated by Eureka AI based on patent content.

Smart Images

  • Figure CN118326878B_ABST
    Figure CN118326878B_ABST
Patent Text Reader

Abstract

The present invention relates to the field of hyporheic zone restoration, and provides a pollutant removal device capable of adjusting the retention time of river water and the exchange volume of hyporheic zone, comprising a plurality of artificial weirs and a weir body connection mechanism, wherein the plurality of artificial weirs are installed inside the river, a counterweight cavity is provided inside the artificial weir, and an anchoring mechanism is provided inside the counterweight cavity. The present invention has the following beneficial effects: the first-level artificial weir, the second-level artificial weir and the third-level artificial weir and the stones placed on the top of the first-level artificial weir and the third-level artificial weir in the present invention can promote the succession of the riverbed to form a stable three-level steep slope with different heights, which is used to increase the exchange flux of the hyporheic zone, form different levels of hyporheic zone exchange water flow and corresponding different levels of river water retention time, and the placement depth of each level of artificial weir in the river can be artificially controlled by adjusting the amount of counterweight material placed in the counterweight cavity, so as to further adjust the exchange flux of the hyporheic zone and the retention time of the water body, and help pollutants with different degradation rates to be efficiently removed in the river.
Need to check novelty before this filing date? Find Prior Art

Description

Technical Field

[0001] The invention relates to a pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone, and belongs to the field of hyporheic zone restoration. Background Art

[0002] The hyporheic zone is the central location between the permeable sediment buffer zone under the surface water and river channel, the lateral riparian zone and the groundwater. It is an important part of the connection between surface water bodies such as rivers and lakes and groundwater bodies. This area effectively connects the flow of land, surface water bodies and groundwater bodies, and the transfer of water, materials and energy.

[0003] The undercurrent zone is an important area for the exchange of matter and energy between surface water and groundwater, and plays an important role in purifying river water quality and maintaining river ecology.

[0004] Increasing the exchange flux of the hyporheic zone is one of the most important measures in the process of river restoration. Recent studies have shown that simply increasing the hyporheic exchange flux cannot effectively improve water quality at the basin scale. Strengthening the matching of the residence time of the hyporheic zone with the reaction time scale of the target pollutants to promote the appropriate biogeochemical conditions required for the degradation of the target substances is the key to the ecological restoration of hyporheic zones. However, there is currently no river ecological restoration device that clearly controls the residence time of the hyporheic zone. In addition, previous hyporheic zone restoration studies have poor controllability, the operation steps are too complicated, and are only suitable for operation in the laboratory. The experimental cycle is long and is not suitable for the restoration of hyporheic zones in longer river sections.

[0005] Most of the existing hyporheic zone repair devices are disposable products and cannot be recycled, which will increase the cost of repair and is not conducive to the implementation and development of hyporheic zone repair work. Summary of the invention

[0006] In view of the deficiencies in the prior art, the object of the present invention is to provide a pollutant removal device that can adjust the retention time of river water and the exchange volume of the subsurface flow zone.

[0007] In order to achieve the above object, the present invention is implemented through the following technical solutions:

[0008] A pollutant removal device capable of adjusting the retention time of water in a river channel and the exchange volume of a hyporheic zone comprises an artificial weir group and a weir body connection mechanism, wherein the artificial weir group is installed in a river channel, the artificial weir group comprises a primary artificial weir, a secondary artificial weir and a tertiary artificial weir, the primary artificial weir, the secondary artificial weir and the tertiary artificial weir are all installed on the riverbed, two secondary artificial weirs are symmetrically installed on both sides of the tertiary artificial weir, and two primary artificial weirs are symmetrically installed on the outside of the secondary artificial weir, the primary artificial weir, the secondary artificial weir and the tertiary artificial weir are all provided with a counterweight cavity inside, an anchoring mechanism is provided in the counterweight cavity, discharge holes are provided in the bottom of both sides of the counterweight cavity, a placement box is fixed on the top side of the artificial weir group, a placement groove is provided at the top center of the placement box, stones are placed in the placement groove, a blocking mechanism matched with the discharge hole is provided inside the placement box, the blocking mechanism is connected to the anchoring mechanism, two weir body lifting ears are symmetrically provided on the top of the artificial weir group, and a bottom water passage is provided at the bottom center of the artificial weir group.

[0009] Furthermore, the weir body connecting mechanism includes two frame plates, both ends of the frame plates are connected and fixed to the two adjacent artificial weir groups, a plurality of movable shafts are evenly spaced on opposite sides of the two frame plates, a movable plate is provided on the movable shaft, a connecting plate 2 is fixed between the two movable plates, a plurality of limit rods are evenly spaced and fixed on the outer surface of the connecting plate 2, a limit piece 1 is provided on the end of the limit rod, a limit piece 2 is provided on the outer surface of the limit piece 1, a microbial solution box is provided on the side of the connecting plate 2 away from the limit rod, and a plurality of drippers are provided at the bottom of the microbial solution box.

[0010] Furthermore, an upper limit block and a lower limit block are provided on the frame plate and located on the side of the movable plate, and the positions of the upper limit block and the lower limit block correspond to the top end and the bottom end of the movable plate.

[0011] Furthermore, a microbial breeding space is formed between two adjacent connecting plates 2, and a microbial breeding rack is placed in the microbial breeding space. The microbial breeding rack is one of wood or biological activated carbon sheets.

[0012] Furthermore, the first-level artificial weir, the second-level artificial weir and the third-level artificial weir, together with the stones and the microbial breeding racks on their tops, respectively form a number of steep slopes of different heights, and the several steep slopes of different heights form different levels of undercurrent zones for exchanging water flows.

[0013] Furthermore, the anchoring mechanism includes a movable plate slidably connected to the inside of the counterweight cavity, a connecting plate 1 is provided at the top center of the movable plate, a cover plate is fixed to the top of the connecting plate 1, the cover plate is clamped in the inlet and outlet holes, the inlet and outlet holes connect the top of the artificial weir group and the counterweight cavity, a cover plate lifting ear is fixed at the top center of the cover plate, the cover plate and the artificial weir group are connected and fixed by a connecting chain, a number of anchor rods are fixed on both sides of the bottom of the movable plate, and the bottom ends of the anchor rods penetrate the artificial weir group and extend to the inside of the river channel.

[0014] Furthermore, vertical material guiding slopes are provided on both sides of the outer surface of the connecting plate 1, and transverse material guiding slopes are provided on both sides of the top of the movable plate. A through hole matching the anchor rod is opened at the bottom of the artificial weir group, and the through hole connects the counterweight cavity and the outer surface of the bottom of the artificial weir group.

[0015] Furthermore, a sealing groove is provided inside the inlet and outlet hole, and a sealing block matching with the sealing groove is fixed to the side of the cover plate.

[0016] Furthermore, the blocking mechanism includes a side cavity opened in the inner side wall of the placement box, a plurality of rotating shafts are provided inside the side cavity, two groups of guide wheels are symmetrically provided on the rotating shaft, and a traction rope is provided on each of the two groups of guide wheels, one end of the traction rope is connected and fixed to the counterweight block, the counterweight block is vertically slidably connected to the inside of the placement box, a blocking plate is provided at the bottom center of the counterweight block, the bottom end of the blocking plate passes through the inside of the discharge hole and is stuck in the engaging groove, the engaging groove is provided at the inner bottom of the discharge hole, and the other end of the traction rope passes through the outside of the placement box and is connected and fixed to the top of the cover plate.

[0017] Furthermore, limiting slide blocks are fixed on both sides of the outer surface of the counterweight block, and limiting sliding grooves matching with the limiting slide blocks are opened on the inner wall of the placement box.

[0018] The beneficial effects of the present invention are:

[0019] The first-level artificial weir, the second-level artificial weir and the third-level artificial weir constituting the artificial weir group in the present invention are symmetrically distributed on the riverbed from the longitudinal direction, and are arranged in an inverted "V" shape from the vertical direction. The first-level artificial weir, the second-level artificial weir, the third-level artificial weir and the stones placed on the top of the weir can promote the succession of the riverbed to form a stable three-level steep slope with different heights, which is used to increase the exchange flux of the hyporheic zone, form different levels of hyporheic zone exchange water flow and corresponding different levels of river water retention time. At the same time, the placement depth of the artificial weirs at each level in the river channel can be artificially controlled by adjusting the amount of counterweight material placed in the counterweight cavity, so as to further adjust the exchange flux of the hyporheic zone and the water retention time, which is conducive to the efficient removal of pollutants with different degradation rates in the river channel.

[0020] Through the design of the weir body connecting mechanism, the two frame plates on the weir body connecting mechanism are installed on two adjacent artificial weirs, thereby determining the positions of several microbial breeding spaces on the weir body connecting mechanism, and then placing the wood in the microbial breeding space to ensure the stable progress of the microbial breeding work on the wood. At the same time, an appropriate amount of microbial solution is injected into the microbial solution box.

[0021] Through the design of the anchoring mechanism, the artificial weir is hoisted on the riverbed of the target river, and then the bottom of the artificial weir is pressed on the riverbed. At this time, the cover plate is still lifted by the crane and has not fallen into the inlet and outlet holes. Then, the counterweight material is placed into the counterweight cavity through the gap between the connecting plate 1 and the inlet and outlet holes. After the corresponding amount of counterweight material is placed, the cover plate is lowered so that the cover plate can fall into the inlet and outlet holes, and the inlet and outlet holes are blocked by sealing blocks and sealing grooves, so that the debris in the river will not enter the counterweight cavity. Under the downward pressure of the counterweight material, the counterweight material will press the movable plate down, and the descent of the movable plate will drive several anchor rods to be inserted from the through hole into the riverbed soil layer, thereby improving the stability of the artificial weir, making the artificial weir and the riverbed bite together, so that the long-term impact of the water flow will not cause the movement of the artificial weir.

[0022] Through the design of the blocking mechanism, after the repair of this section of water area is completed, the artificial weir needs to be lifted away and transported to the next repair area for use. At this time, first connect the crane hook with the cover plate lifting ear, and then lift the cover plate. As the cover plate rises, the cover plate will drive the moving plate to rise through the connecting plate, and the bottom of the moving plate will drive the anchor rod to rise, so that the anchor rod will break away from the riverbed and enter the through hole. Synchronously, as the moving plate rises, the moving plate will drive the counterweight material to rise, so that the counterweight material can gradually rise to the unloading hole. Because the connection end of the traction rope and the cover plate has an extra section that falls on the cover plate, the cover plate In the early stage of rising, the cover plate will only drive the movable plate and the counterweight material to rise, and will not pull the traction rope. When the movable plate rises to near the unloading hole, the leaked part of the traction rope is in a taut state. After that, the rise of the cover plate will drive the movable plate and the counterweight material to rise while pulling the traction rope. The other end of the traction rope pulls the counterweight block to rise, and the counterweight block pulls the blocking plate to rise. The blocking plate detaches from the unloading hole and gradually enters the side cavity. Moreover, the action of the blocking plate to open the unloading hole and the moving plate driving the counterweight material to rise, the counterweight material gradually flows from the inclined opening of the unloading hole to the outside of the artificial weir.

[0023] Through the design of the connecting chain, when the counterweight material is unloaded, the crane continues to pull up the cover plate lifting lugs. During this process, the connecting chain is gradually tightened, and the connecting chain connects the cover plate and the artificial weir into a whole. After that, the lifting of the crane will drive the artificial weir out of the river channel and store it on the transport vehicle;

[0024] Through the design of the first and second limiting members, the microbial breeding rack located in the microbial breeding space can be prevented from leaving the microbial breeding space under the impact of the water flow;

[0025] Through the design of the microbial solution tank and the dripper, the reproduction of microorganisms can be accelerated in the early stage of the restoration work. The microbial solution gradually drips into the river surface through the dripper. The water flow on the river surface carries the microbial solution and gradually enters several microbial reproduction spaces to contact and adhere to the microbial reproduction racks.

[0026] Through the design of the transverse material guiding slope and the vertical material guiding slope, the counterweight material between the moving plate and the connecting plate can flow quickly to the discharge hole under the guidance of the slopes of both, thereby accelerating the discharge action of the counterweight material. BRIEF DESCRIPTION OF THE DRAWINGS

[0027] In order to more clearly illustrate the embodiments of the present invention or the technical solutions in the prior art, the drawings required for use in the embodiments will be briefly introduced below. Obviously, the drawings described below are only some embodiments of the present invention. For ordinary technicians in this field, other drawings can be obtained based on these drawings without paying creative work.

[0028] Figure 1 It is a schematic cross-sectional view of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention;

[0029] Figure 2 It is a schematic diagram of the top view of the structure of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention;

[0030] Figure 3 A schematic diagram of the three-dimensional structure of an artificial weir of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention;

[0031] Figure 4 The local structure diagram of the weir connection mechanism of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention is shown in FIG. Figure 1 ;

[0032] Figure 5 The local structure diagram of the weir connection mechanism of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention is shown in FIG. Figure 2 ;

[0033] Figure 6 The local structure diagram of the weir connection mechanism of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention is shown in FIG. Figure 3 ;

[0034] Figure 7 It is a schematic diagram of the structure of the anchoring mechanism of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention;

[0035] Figure 8 It is a schematic diagram of the top view of the structure of the artificial weir of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention;

[0036] Fig. 9 A schematic diagram of the internal structure of an artificial weir of a pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention;

[0037] Fig.10 A schematic diagram of the structure of an artificial weir of a pollutant removal device capable of adjusting the retention time of water in a river channel and the exchange volume of a hyporheic zone according to the present invention;

[0038] Fig.11 The local structure diagram of the anchoring mechanism of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention is shown in FIG. Figure 1 ;

[0039] Fig.12 The local structure diagram of the anchoring mechanism of the pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone of the present invention is shown in FIG. Figure 2 .

[0040] In the figure, 1, river channel; 2, artificial weir group; 3, counterweight cavity; 4, moving plate; 5, connecting plate 1; 6, transverse guide slope; 7, cover plate; 8, cover plate lifting ear; 9, unloading hole; 10, placement box; 11, rotating shaft; 12, guide wheel; 13, traction rope; 14, counterweight block; 15, blocking plate; 16, fitting groove; 17, limiting slider; 18, limiting slide groove; 19, anchor rod; 20, through hole; 21, inlet and outlet hole; 22, sealing groove; 23, sealing block; 24, connecting chain; 25, weir body lifting ear; 26, frame plate ; 27. movable shaft; 28. movable plate; 29. ​​upper limit block; 30. lower limit block; 31. connecting plate 2; 32. limit rod; 33. placement groove; 34. bottom water passage; 35. microbial breeding rack; 36. side cavity; 37. limit piece 1; 38. limit piece 2; 39. microbial solution tank; 40. exchange water flow in the undercurrent zone; 41. stone; 42. steep slope; 43. first-level artificial weir; 44. second-level artificial weir; 45. third-level artificial weir; 46. riverbed; 47. river surface; 48. river flow direction. DETAILED DESCRIPTION

[0041] The following will be combined with the drawings in the embodiments of the present invention to clearly and completely describe the technical solutions in the embodiments of the present invention. Obviously, the described embodiments are only part of the embodiments of the present invention, not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by ordinary technicians in this field without creative work are within the scope of protection of the present invention.

[0042] Please refer to Figures 1-12. The present invention provides a technical solution for a pollutant removal device capable of adjusting the retention time of a river water body and the exchange volume of a hyporheic zone. The pollutant removal device capable of adjusting the retention time of a river water body and the exchange volume of a hyporheic zone comprises an artificial weir group 2 and a weir body connection mechanism. The artificial weir group 2 is installed in a river channel 1. The artificial weir group 2 comprises a primary artificial weir 43, a secondary artificial weir 44 and a tertiary artificial weir 45. The primary artificial weir 43, the secondary artificial weir 44 and the tertiary artificial weir 45 are all installed on the riverbed. Two secondary artificial weirs 44 are symmetrically installed on both sides of the tertiary artificial weir 45. The two The first-level artificial weir 43 is symmetrically installed on the outside of the second-level artificial weir 44. The first-level artificial weir 43, the second-level artificial weir 44 and the third-level artificial weir 45 are all provided with a counterweight cavity 3, and an anchoring mechanism is provided in the counterweight cavity 3. Discharge holes 9 are provided in the bottom of both sides of the counterweight cavity 3. A placement box 10 is fixed to the top side of the artificial weir group 2. A placement groove 33 is provided at the top center of the placement box 10. Stones 41 are placed in the placement groove 33. A blocking mechanism that cooperates with the discharge hole 9 is provided inside the placement box 10. The blocking mechanism and the anchoring mechanism The artificial weir group 2 is connected, two weir body lifting ears 25 are symmetrically arranged on the top, a bottom water passage 34 is arranged at the center of the bottom of the artificial weir group 2, the first-level artificial weir 43, the second-level artificial weir 44 and the third-level artificial weir 45 form a plurality of steep slopes 42 of different heights with the stones 41 and the microorganism breeding rack 35 on their tops, and the plurality of steep slopes 42 of different heights form different cascade undercurrent zones for exchanging water flows 40; the first-level artificial weir 43, the second-level artificial weir 44 and the third-level artificial weir 45 constituting the artificial weir group 2 are symmetrically distributed on the riverbed in the longitudinal direction, and are symmetrically distributed on the riverbed in the vertical direction. The first-level artificial weir 43, the second-level artificial weir 44, the third-level artificial weir 45 and the stones 41 placed thereon are arranged in an inverted "V" shape, which can promote the riverbed evolution to form a stable three-level steep slope 42 with different heights, which is used to increase the exchange flux of the hyporheic zone, form different levels of hyporheic zone exchange water flow 40 and corresponding different levels of river water retention time. At the same time, the placement depth of the artificial weirs at each level in the river channel 1 can be artificially controlled by adjusting the amount of counterweight material placed in the counterweight cavity 3, so as to further adjust the exchange flux of the hyporheic zone and the water retention time, which is conducive to the efficient removal of pollutants with different degradation rates in the river channel 1.

[0043] Referring to Figures 4-6, the weir body connection mechanism includes two frame plates 26, the two ends of the frame plates 26 are connected and fixed to the two adjacent artificial weir groups 2, a plurality of movable shafts 27 are evenly spaced on the opposite sides of the two frame plates 26, a movable plate 28 is provided on the movable shaft 27, a connecting plate 21 is fixed between the two movable plates 28, a plurality of limit rods 32 are evenly spaced and fixed on the outer surface of the connecting plate 21, a limit piece 1 37 is provided at the end of the limit rod 32, a limit piece 2 38 is provided on the outer surface of the limit piece 1 37, a microorganism solution box 39 is provided on the side of the connecting plate 21 away from the limit rod 32, a plurality of drippers are provided on the bottom of the microorganism solution box 39, and an upper The upper limit block 29 and the lower limit block 30, the positions of the upper limit block 29 and the lower limit block 30 correspond to the top and bottom ends of the movable plate 28, and a microbial breeding space is formed between the two adjacent connecting plates 31, and a microbial breeding rack 35 is placed in the microbial breeding space, and the microbial breeding rack 35 is one of wood or biological activated carbon sheets; through the design of the weir body connecting mechanism, the two frame plates 26 on the weir body connecting mechanism are installed on two adjacent artificial weir groups 2, and then the positions of several microbial breeding spaces on the weir body connecting mechanism are determined, and then the wood is placed in the microbial breeding space, so as to ensure the stable progress of the microbial breeding work on the wood, and at the same time, an appropriate amount of microbial solution is injected into the microbial solution box 39.

[0044] See Figures 7, 9, 11 and Fig.12The anchoring mechanism comprises a movable plate 4 slidably connected to the inside of the counterweight cavity 3, a connecting plate 5 is provided at the top center of the movable plate 4, a cover plate 7 is fixed to the top of the connecting plate 5, the cover plate 7 is clamped in the inlet and outlet hole 21, the inlet and outlet hole 21 connects the top of the artificial weir group 2 and the counterweight cavity 3, a cover plate lifting ear 8 is fixed at the top center of the cover plate 7, the cover plate 7 and the artificial weir group 2 are connected and fixed by a connecting chain 24, a plurality of anchor rods 19 are fixed on both sides of the bottom of the movable plate 4, the bottom ends of the anchor rods 19 penetrate the artificial weir group 2 and extend to the inside of the river channel 1, vertical guide slopes are provided on both sides of the outer surface of the connecting plate 5, transverse guide slopes 6 are provided on both sides of the top of the movable plate 4, a through hole 20 matched with the anchor rod 19 is provided at the bottom of the artificial weir group 2, the through hole 20 connects the counterweight cavity 3 and the outer surface of the bottom of the artificial weir group 2, a sealing groove 22 is provided inside the inlet and outlet hole 21, The side of the cover plate 7 is fixed with a sealing block 23 that matches the sealing groove 22; through the design of the anchoring mechanism, after the artificial weir group 2 is hoisted on the riverbed of the target river, the bottom of the artificial weir group 2 is pressed on the riverbed. At this time, the cover plate 7 is still lifted by the belt crane and has not yet fallen into the inlet and outlet hole 21. Then, the counterweight material is placed into the counterweight cavity 3 through the gap between the connecting plate 1 5 and the inlet and outlet hole 21. After the corresponding amount of counterweight material is placed, the cover plate 7 is lowered so that the cover plate 7 can fall. The sealing block 23 and the sealing groove 22 are used to seal the inlet and outlet holes 21, so that the debris in the river will not enter the counterweight cavity 3. Under the downward pressure of the counterweight material, the counterweight material will press the movable plate 4 down, and the descent of the movable plate 4 will drive several anchor rods 19 to be inserted from the through hole 20 into the riverbed soil layer, thereby improving the stability of the artificial weir group 2, so that the artificial weir group 2 and the riverbed are bitten together, so that the long-term impact of the water flow will not cause the movement of the artificial weir group 2.

[0045] Referring to FIG. 9 , the blocking mechanism includes a side cavity 36 opened in the inner side wall of the placement box 10, and a plurality of rotating shafts 11 are arranged inside the side cavity 36. Two sets of guide wheels 12 are symmetrically arranged on the rotating shaft 11, and a traction rope 13 is respectively arranged on the two sets of guide wheels 12. One end of the traction rope 13 is connected and fixed to a counterweight block 14. The counterweight block 14 is vertically slidably connected to the inside of the placement box 10. A blocking plate 15 is arranged at the bottom center of the counterweight block 14. The bottom end of the blocking plate 15 penetrates into the inside of the discharge hole 9 and is stuck in the fitting groove 16. The engaging groove 16 is provided at the inner bottom of the discharge hole 9, the other end of the traction rope 13 passes through the outer side of the placement box 10 and is connected and fixed to the top of the cover plate 7, and the limiting sliders 17 are fixed on both sides of the outer surface of the counterweight block 14. The limiting slide groove 18 matched with the limiting slider 17 is provided on the inner wall of the placement box 10. Through the design of the blocking mechanism, after the repair of this section of water area is completed, the artificial weir group 2 needs to be lifted and transported to the next repair area for use. At this time, the hook of the crane is first connected to the cover plate lifting ear 8, and then the lifting device 2 is lifted. The cover plate 7 is lifted. As the cover plate 7 rises, the cover plate 7 will drive the movable plate 4 to rise through the connecting plate 5. The bottom of the movable plate 4 drives the anchor rod 19 to rise, so that the anchor rod 19 is separated from the riverbed and enters the through hole 20. Synchronously, as the movable plate 4 rises, the movable plate 4 will drive the counterweight material to rise, so that the counterweight material can gradually rise to the discharge hole 9. Because the connection end of the traction rope 13 and the cover plate 7 has an extra section falling on the cover plate 7, the cover plate 7 will only drive the movable plate 4 and the counterweight material to rise in the early stage of the rise, and will not pull the traction rope 13. When the plate 4 rises to near the discharge hole 9, the leaked part of the traction rope 13 is in a taut state. After that, the rise of the cover plate 7 will drive the movable plate 4 and the counterweight material to rise while pulling the traction rope 13. The other end of the traction rope 13 pulls the counterweight block 14 to rise, and the counterweight block 14 pulls the blocking plate 15 to rise. The blocking plate 15 detaches from the discharge hole 9 and gradually enters the side cavity 36. In addition, the action of the blocking plate 15 to open the discharge hole 9 and the action of the movable plate 4 to drive the counterweight material to rise, the counterweight material gradually flows from the inclined opening of the discharge hole 9 to the outside of the artificial weir group 2.

[0046] When in use, the width of the target river is determined to determine the placement distance and number of the artificial weir groups 2. The installation positions of the artificial weirs at various levels are distributed along the longitudinal direction of the river channel 1, and are symmetrically distributed in the order of the first-level artificial weir 43, the second-level artificial weir 44, the third-level artificial weir 45, the second-level artificial weir 44, and the first-level artificial weir 43. The artificial weir groups 2 at various levels are vertically distributed in the river channel in an inverted "V" shape. The artificial weirs at various levels in the artificial weir group 2 are hoisted on the riverbed of the target river, and then the bottoms of the artificial weirs at various levels are pressed on the riverbed. At this time, the cover plate 7 is still lifted by the belt crane and has not fallen into the inlet and outlet hole 21. Then, the counterweight material is placed into the counterweight cavity 3 through the gap between the connecting plate 1 5 and the inlet and outlet hole 21. After the corresponding amount of counterweight material is placed, the cover plate 7 is lowered so that the cover plate 7 can fall into the inlet and outlet hole 21, and the inlet and outlet hole 21 is blocked by the sealing block 23 and the sealing groove 22, so that the debris in the river will not enter the counterweight cavity 3.

[0047] Under the downward pressure of the counterweight material, the counterweight material will press the movable plate 4 downward, and the downward movement of the movable plate 4 will drive a plurality of anchor rods 19 to be inserted from the through holes 20 into the inner part of the riverbed soil layer, thereby improving the stability of the artificial weir group 2, so that the artificial weir group 2 and the riverbed are engaged together, so that the long-term impact of the water flow will not cause the movement of the artificial weir group 2;

[0048] Then, the weir body connection mechanism is installed between two adjacent artificial weir groups 2, that is, the two frame plates 26 on the weir body connection mechanism are installed on the two adjacent artificial weir groups 2, and then the positions of several microorganism breeding spaces on the weir body connection mechanism are determined, and then the microorganism breeding rack 35 (wood) is placed in the microorganism breeding space, so as to ensure the stable progress of the microorganism breeding work on the wood, and at the same time, an appropriate amount of microorganism solution is injected into the microorganism solution box 39;

[0049] During the restoration process, the placement depth of each level of artificial weirs in the river channel can be controlled by adjusting the amount of counterweight material placed in the counterweight chamber 3. The depths of each level of artificial weirs in different river sections can also be set to different depths to further adjust the exchange flux of the subsurface flow zone and the water retention time, which is conducive to the efficient removal of pollutants with different degradation rates in the river channel.

[0050] After the repair of this section of water area is completed, it is necessary to lift the artificial weir group 2 and transport it to the next repair area for use. Through the design of the blocking mechanism, at this time, the hook of the crane is first connected with the cover plate lifting ear 8, and then the cover plate 7 is lifted. As the cover plate 7 rises, the cover plate 7 will drive the movable plate 4 to rise through the connecting plate 15, and the bottom of the movable plate 4 will drive the anchor rod 19 to rise, so that the anchor rod 19 is separated from the riverbed and enters the through hole 20. Synchronously, as the movable plate 4 rises, the movable plate 4 will drive the counterweight material to rise, so that the counterweight material can gradually rise to the unloading hole 9. Because the connection end of the traction rope 13 and the cover plate 7 has an extra section falling on the cover plate 7, the early stage of the cover plate 7 When the cover plate 7 rises, it will only drive the movable plate 4 and the counterweight material to rise, but will not pull the traction rope 13. When the movable plate 4 rises to near the discharge hole 9, at this time, the leaked part of the traction rope 13 is in a taut state. After that, the rise of the cover plate 7 will drive the movable plate 4 and the counterweight material to rise while pulling the traction rope 13. The other end of the traction rope 13 pulls the counterweight block 14 to rise, and the counterweight block 14 pulls the blocking plate 15 to rise. The blocking plate 15 is separated from the discharge hole 9 and gradually enters the side cavity 36. In addition, the action of the blocking plate 15 opening the discharge hole 9 and the action of the movable plate 4 driving the counterweight material to rise, the counterweight material gradually flows from the inclined opening of the discharge hole 9 to the outside of the artificial weir group 2.

[0051] The first-level artificial weir 43, the second-level artificial weir 44 and the third-level artificial weir 45 constituting the artificial weir group 2 are symmetrically distributed on the riverbed in the longitudinal direction and are arranged in an inverted "V" shape from the vertical direction. The first-level artificial weir 43, the second-level artificial weir 44, the third-level artificial weir 45 and the stones 41 placed thereon can promote the succession of the riverbed to form a stable three-level steep slope 42 with different heights, which is used to increase the exchange flux of the hyporheic zone, form different levels of hyporheic zone exchange water flow 40 and corresponding different levels of river water retention time. At the same time, the placement depth of the artificial weir group 2 at each level in the river channel can be artificially controlled by adjusting the amount of counterweight material placed in the counterweight cavity 3, so as to further adjust the exchange flux of the hyporheic zone and the water retention time, which is conducive to the efficient removal of pollutants with different degradation rates in the river channel;

[0052] Through the design of the transverse material guide slope 6 and the vertical material guide slope, the counterweight material between the moving plate 4 and the connecting plate 5 can flow quickly to the discharge hole 9 under the guidance of the two slopes, thereby accelerating the discharge action of the counterweight material;

[0053] When the counterweight material is unloaded, the crane continues to pull up the cover plate lifting lug 8. During this process, the connecting chain 24 is gradually tightened, and the connecting chain 24 connects the cover plate 7 and the artificial weir group 2 into a whole. After that, the lifting of the crane will drive the artificial weir group 2 to leave the river channel 1 and store it on the transport vehicle.

[0054] By designing the first limiting member 37 and the second limiting member 38, the microorganism breeding rack 35 located in the microorganism breeding space will not be separated from the microorganism breeding space under the impact of the water flow;

[0055] Through the design of the microbial solution box 39 and the dripper, the reproduction of microorganisms can be accelerated in the early stage of the repair work. The microbial solution gradually drips into the river surface through the dripper. The water flow on the river surface carries the microbial solution and gradually enters into several microbial reproduction spaces and contacts and adheres to the microbial reproduction rack 35.

[0056] Although this specification is described according to implementation modes, not every implementation mode includes only one independent technical solution. This description of the specification is only for the sake of clarity. Those skilled in the art should regard the specification as a whole. The technical solutions in each embodiment may also be appropriately combined to form other implementation modes that can be understood by those skilled in the art.

Claims

1. A pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone, characterized in that: The invention comprises an artificial weir group (2) and a weir body connection mechanism, wherein the artificial weir group (2) is installed in a river channel (1), wherein the artificial weir group (2) comprises a first-level artificial weir (43), a second-level artificial weir (44) and a third-level artificial weir (45), wherein the first-level artificial weir (43), the second-level artificial weir (44) and the third-level artificial weir (45) are all installed on the river bed, wherein two second-level artificial weirs (44) are symmetrically installed on both sides of the third-level artificial weir (45), and two first-level artificial weirs (43) are symmetrically installed on the outside of the second-level artificial weir (44), and wherein the first-level artificial weir (43), the second-level artificial weir (44) and the third-level artificial weir (45) are all provided with a counterweight cavity (3), wherein the counterweight cavity (3) is provided with an anchoring mechanism, the inner bottom of both sides of the counterweight cavity (3) is provided with a discharge hole (9), a placement box (10) is fixed to the top side of the artificial weir group (2), a placement groove (33) is provided at the top center of the placement box (10), a stone (41) is placed in the placement groove (33), a blocking mechanism matched with the discharge hole (9) is provided inside the placement box (10), the blocking mechanism is connected to the anchoring mechanism, two weir body lifting ears (25) are symmetrically provided at the top of the artificial weir group (2), a bottom water passage (34) is provided at the bottom center of the artificial weir group (2), and the weir body connecting mechanism includes two frame plates (26), the two ends of the frame plate (26) and the adjacent two The artificial weir group (2) is connected and fixed, a plurality of movable shafts (27) are evenly spaced on opposite sides of the two frame plates (26), a movable plate (28) is provided on the movable shaft (27), a second connecting plate (31) is fixed between the two movable plates (28), a microbial breeding space is formed between two adjacent second connecting plates (31), a microbial breeding rack (35) is placed in the microbial breeding space, a plurality of limit rods (32) are evenly spaced and fixed on the outer surface of the second connecting plate (31), a limit piece 1 (37) is provided at the end of the limit rod (32), a limit piece 2 (38) is provided on the outer surface of the limit piece 1 (37), a microbial breeding rack (35) is provided on the outer surface of the second connecting plate (31), and a microbial breeding rack (35) is provided on the side of the second connecting plate (31) away from the limit rod (32). A biological solution tank (39), wherein a plurality of drippers are provided at the bottom of the microbial solution tank (39), wherein the first-level artificial weir (43), the second-level artificial weir (44) and the third-level artificial weir (45) and the stone (41) on their tops and the microbial breeding rack (35) respectively form a plurality of steep slopes (42) of different heights, wherein the plurality of steep slopes (42) of different heights form different levels of subsurface flow exchange water flows (40), wherein the anchoring mechanism comprises a movable plate (4) slidably connected to the inside of the counterweight cavity (3), wherein a connecting plate 1 (5) is provided at the top center of the movable plate (4), wherein a cover plate (7) is fixed to the top of the connecting plate 1 (5), and wherein the cover plate (7) is snap-fitted into the inlet and outlet hole (21),The inlet and outlet holes (21) are connected to the top of the artificial weir group (2) and the counterweight chamber (3); a cover plate lifting lug (8) is fixed at the top center of the cover plate (7); the cover plate (7) and the artificial weir group (2) are connected and fixed via a connecting chain (24); a plurality of anchor rods (19) are fixed to both sides of the bottom of the movable plate (4); the bottom ends of the anchor rods (19) penetrate the artificial weir group (2) and extend to the inside of the river channel (1); the blocking mechanism comprises a side chamber (36) provided in the inner side wall of the placement box (10); a plurality of rotating shafts (11) are provided inside the side chamber (36); and the rotating shafts (11) are symmetrically provided with Two groups of guide wheels (12), each of the two groups of guide wheels (12) is provided with a traction rope (13), one end of the traction rope (13) is connected and fixed to a counterweight (14), the counterweight (14) is vertically slidably connected to the inside of the placement box (10), a blocking plate (15) is provided at the bottom center of the counterweight (14), the bottom end of the blocking plate (15) penetrates into the inside of the discharge hole (9) and is stuck in the fitting groove (16), the fitting groove (16) is provided at the inner bottom of the discharge hole (9), the other end of the traction rope (13) penetrates to the outside of the placement box (10) and is connected and fixed to the top of the cover plate (7).

2. The pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone according to claim 1 is characterized in that: An upper stop block (29) and a lower stop block (30) are provided on the frame plate (26) and located on the side of the movable plate (28); the positions of the upper stop block (29) and the lower stop block (30) correspond to the top end and the bottom end of the movable plate (28).

3. The pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone according to claim 2 is characterized in that: The microorganism breeding rack (35) is one of wood or a bio-activated carbon sheet.

4. The pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone according to claim 3 is characterized in that: The outer surface of the connecting plate 1 (5) is provided with vertical material guiding slopes on both sides, the top of the movable plate (4) is provided with transverse material guiding slopes (6) on both sides, and the bottom of the artificial weir group (2) is provided with a through hole (20) that matches the anchor rod (19), and the through hole (20) connects the counterweight cavity (3) and the outer surface of the bottom of the artificial weir group (2).

5. The pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone according to claim 4 is characterized in that: A sealing groove (22) is provided inside the inlet and outlet hole (21), and a sealing block (23) matching the sealing groove (22) is fixed to the side of the cover plate (7).

6. The pollutant removal device capable of adjusting the retention time of river water and the exchange volume of the hyporheic zone according to claim 5 is characterized in that: Limiting slide blocks (17) are fixed on both sides of the outer surface of the counterweight block (14), and limiting sliding grooves (18) matching with the limiting slide blocks (17) are provided on the inner wall of the placement box (10).

Citation Information

Patent Citations

  • Ecological restoration structure of double-layer arc-shaped riverbed

    CN108824365A

  • Ecological remediation structure enhancing phreatic zone exchanging

    CN108951527A

  • Device for enhancing water course undercurrent exchange

    CN110468776A

  • Subsurface zone in-situ remediation system and method

    CN115305861A

  • Ecological restoration structure and method for enhancing undercurrent exchange

    CN117604965A